MRP Chapman Exercises
MRP Chapman Exercises
R 3 120 30
Yes 2 500 20
T 2 600 370
to. Complete the MRP explosion for product Y. Identify any problems
9 17
Planned Order Releases (Y)
Gross Requirement 27 51
Scheduled Receptions 0 0 0
Availability Projection 8 81 30
Net Requirement 19
Planned Order Releases 100 100 100
b. The Part S provider tells you that your delivery will be delayed for a week.
3 Lot size
Waiting time Availability 20 Program reception
Week -3 -2 -1 0
LPP of P - S (2) 40
LPP of Q - S (1) 100 100
LPP of R - S (2) 120 120
Gross Requirement 340 80 340
Scheduled Receptions 500
Availability Projection 20 180 100 260
Net Requirement 240
Planned Order Releases 500 500
onentes R.
50 Inv.
urity 0
Sec
ion 10
4 5 67 8 9 10
30 20 20 25 25 25 25
8 3 10 0 5 0
50 50 50 50
Inv. Security
Scheduled receptions
None 5
None None
None 8
None None
500, week 1 20
None 50
ma and analyze possible solutions
5 5 555 55
30 20 20 25 25 25 25
20 20 25 25 25 25
ar a single product of Y)
40 Inv. Security None
to None
2 3 456 789
20 30 20 20 25 25 25 25
20 30 20 20 25 25 25 25
9 19 39 19 34 9 24 39
21 16 16 1
40 40 40 40
60 90 60 60 75 75 75 75
0 0 0 0 0 0 0
70 80 20 60 85 10 35 60
30 20 40 15 65 40
100 100 100 100
34 40 60 40 40 50 50 50
98 58 118 78 38 108 58 8
22 2 12
120 120
What problems does this cause and what possible alternatives are there?
500 Inv. Security 20
gives 500
1 2 3 4 5 6 7 8
40 40 40 40 40
100 100 100 100 100
120 120
180 80 340 180 420 180
39
1
0
0
60
9 10
25 0
50 0
78 78
42
or product of Q
9 10
380 380
7 8 9 10
9 10
380 380
Product Y is manufactured from one component P, three components Q and two comp
P is manufactured from two parts of S.
Q is made from a part of S
R is made from two S parts and three T parts
R 3 120 30
Yes 2 500 20
T 2 600 0 370 0
a. Complete the MRP explosion for product Y. Identify any problems
b. The Part S provider tells you that your delivery will be delayed for a week.
Wait time 3 Lot size
Availability 20 Scheduled reception
Week -1 0 1
Gross Requirement 280
Scheduled Receptions 500
Availability Projection 20 20 20 260
Net Requirement
Planned Order Releases 500
onentes R.
50 Inv. Security 0
ion 10
4 5 6 7 8 9 10
30 20 20 25 25 25 25
8 3 1 0 0 5 0
33 13 43 18 43 18 43
39 49 45 50
50 50 50 50
Inv. Security
Scheduled receptions
None 5
None None
None 8
None None
500, week 1 20
None 50
ma and analyze possible solutions
50 50 50
ar a single product of Y)
0 0 0 0 0 0 0
20 20 10 10 0 0 30 30
20 30 40 50
40 40 80
100 0 0 20 20 40 40 60
100 80 60
120 120 120
16
0
60
0
What problems does this cause and what possible alternatives are there?
500 Inv. Security 20
to 500 weeks1
2 3 456 789
240 180 240 280 240 180 0 0
0 0 000 000
20 320 80 300 60 380 380 380
-140 -180 -100
500 500
10
0
60
10
0
0
380
Product “X” has the following product structure. Additionally, they present
themselves to. Complete the master schedule and generate the MRP records for
each of the
b. Suppose the supplier of the 600 “C” parts scheduled for the week implications
of this? Describe ALL possible options in this case.
Product "X"
Master Program for Y: 1
Y COMPONENT MRP (One P component is needed, three comp 2
P COMPONENT MRP (A P component is needed to manufacture 2
Q COMPONENT MRP (Three components of Q are needed to 2
MRP OF COMPONENT R (Two components of R are needed to 3
T COMPONENT MRP (Three T components are needed to 4
components Q and two components R to make a single product Y) 6
manufacture a single product of Y) 6
manufacture a single product of Y) 7
make a single product of P, a component of S to make a so 7
open a single product from R) 8
or product of Q 11
Y COMPONENT MRP (One P component is needed, three comp 14
P COMPONENT MRP (A P component is needed to manufacture 14
Q COMPONENT MRP (Three components of Q are needed to 14
MRP OF COMPONENT R (Two components of R are needed to 15
MRP OF COMPONENT S (Two components of S are needed for a single product of Q
and two components of S to manufacture a single product 15
T COMPONENT MRP (Three T components are needed to 15
components Q and two components R to make a single product Y) 18
manufacture a single product of Y) 18
manufacture a single product of Y) 19
manufacture a single product of P, a component of S to manufacture a product of R) 19
manufacture a single product of R) 19
MRP OF COMPONENT A 27
COMPONENT B MRP 27
COMPONENT C MRP 27
COMPONENT D MRP 28
COMPONENT E MRP 28
3) 30
MRP OF COMPONENT C (Three components of C are needed to 39
MRP OF COMPONENT D (2 components of D are needed for only product C) 39
MRP OF COMPONENT D (2 components of D are needed for only product C) 40
MRP OF COMPONENT E (Two components of E are needed to 40
enrich a single product A) 42
to manufacture a single product A) 43
manufacture a single product B and 1 single component of D to manufacture a 43
manufacture a single product B and 1 single component of D to manufacture a 200
to manufacture a single product C) 200
List of Materials to produce A 45
MRP OF COMPONENT A 45
COMPONENT B MRP 46
COMPONENT C MRP 46
COMPONENT D MRP 46
COMPONENT E MRP 47
D (1) E 54
(2) 58
List of Materials to produce A 60
*' 60
B (3) C (2) 60
E (2) D (1) E (1) D ( 60
MRP OF COMPONENT B (Three components are needed 60
MRP OF COMPONENT C (Two components are needed 61
MRP OF COMPONENT D (One component d is needed to manufacture a single product
of B) 61
MRP OF COMPONENT E (Two components are needed to make a single product of C) 61
MRP OF COMPONENT E (With 140 defective units 63
2) 64
of B to manufacture a single product A) 64
of C to manufacture a single product A) 65
e C to manufacture a single product of B and two components of C to 65
E to manufacture a single product of B and a component of E to 65
List of Materials to produce A 69
B (1) 69