EIA-ON Flour Industry Tsiyon Seyifu
EIA-ON Flour Industry Tsiyon Seyifu
REPORT
FOR
MAY, 2024
Hawasa, Ethiopia
አድራሻ፡- Shagar Siitii/ሸገር ሲቲ፣ K/M/Noonnoo ኖን ክ/ከተማ፣Ashawaa Meedaa/አሸዋ ሜዳ፣ Moolii Shaaqaa
Gamoo 3ffaa/ ሻቃ ሞል: 3 ኛ ፎቅ Bil/ስልክ፡-+251-965-04-12-99/913-841-057,
E-Mail/ኢ-ሜይል:- [email protected]
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Table of Contents
ACRONYMS vi
Figure viii
Tables ix
EXECUTIVE Summary 1
1. BACKROUND INFORMATION OF THE PROJECT 2
1.1 INTRODUCTION......................................................................................................................................... 2
1.2 AUTHOR PRESENTATION......................................................................................................................3
1.3 PROMOTER PRESENTATION & LOCATION............................................................................................3
1.4 PUBLIC PARTICIPATION AND SCOPING REPORT...................................................................................3
1.5 APPROACH TO THIS ENVIRONMENTAL IMPACT ASSESSMENT............................................................4
1.6 APPROACH TO THE ENVIRONMENTAL MANAGEMENT PLAN...................................................................5
1.7 TERMS OF REFERENCE (TOR).................................................................................................................... 5
1.8 METHODOLOGY................................................................................................................................... 5
1.10 OBJECTIVES OF THE STUDY..................................................................................................................... 6
2. THE PROJECT PROPOSAL 8
3. POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK 10
3.1 POLICY FRAMEWORK.............................................................................................................................. 10
3.1.1 CONSTITUTION OF THE FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA.........................................10
3.1.3 ENVIRONMENTAL POLICY OF ETHIOPIA...........................................................................................11
3.1.4 INDUSTRIAL POLICY AND STRATEGY OF ETHIOPIA...........................................................................11
3.2 LEGISLATIVE FRAMEWORK..................................................................................................................... 11
3.2.1 ENVIRONMENTAL POLLUTION CONTROL.........................................................................................11
3.2.2 PROCLAMATION 513/2007, SOLID WASTE MANAGEMENT.............................................................12
3.2.3 REGULATION 159/2008, PREVENTION OF INDUSTRIAL POLLUTION................................................12
3.3 INSTITUTIONAL FRAMEWORK.................................................................................................................13
3.3.1 THE ENVIRONMENTAL PROTECTION ORGANS.................................................................................13
3.3.2 ENVIRONMENTAL PROTECTION AUTHORITY...................................................................................13
3.3.3 REGIONAL ENVIRONMENTAL AGENCIES (REA)................................................................................13
ii
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
v
ACRONYMS
ARCCH Authority for Research and Conservation for Cultural Heritage
BOD ESIABiological
Report: - Tsiyon
Oxygen Seyifu Flour-Mill Factory
Demand 20
oC Degree Cellicious
EP Environmental Protection
ha Hectare
KM Kilo Meter
mm Millimeter
Figure
Figure 1: Location Project Area........................................................................................................................ 19
vii
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Tables
Table 1: Raw materials and Solid waste flows of flour processing Industry.......................................................8
Table 2: Environmental setting in 600m radius................................................................................................16
Table 3: Summary of Project Site Facilities.......................................................................................................21
Table 4: The Environmental Impact Assessment Criteria.................................................................................23
Table 5: Summary of Project Plan Modification...............................................................................................28
Table 6: Summary of Positive Impacts of the project.......................................................................................29
Table 7: Summary of water Bodies contamination Aspects and Significance...................................................30
Table 8: Summary of Solid Waste Contamination Aspects and Significance....................................................31
Table 9: Summary of Air Quality Contamination Aspects and Significance......................................................32
Table 10: Summary of NOISE AND VIBRATION Aspects and Significance.........................................................33
Table 11: Environmental Management Framework.........................................................................................37
Table 12: Soil and water management measures.............................................................................................38
Table 13: Noise and vibration management measures....................................................................................39
Table 14: Waste and Chemical Management Measures..................................................................................40
Table 15: Environmental Management and Monitoring Plan..........................................................................41
Table 16: Financial Requirement for Environmental Protection Costs.............................................................42
viii
EXECUTIVE SUMMARY
TSIYON SEYIFU FLOUR-MILL FACTORY plans to engage in a Wheat Flour Mill Project in the Sidama Regional
State, South Sidama Zone, Dara Woreda Machisho Town Millennium Kebele an area covering around
2,099m2. This document presents the Environmental and Social Impact Assessment (ESIA) of the proposed
Wheat Flour Mill Project as requested by the Sidama Regional State of Environment, Forest and Climate
Change Authority for the development permit.
The project area is bordered on the south by the South Asphalt Road, on the north by an all-weather road, on
the West by a resident, and on the east by an international Asphalt Road.
The project has been proposed in favor of the TSIYON SEYIFU FLOUR-MILL FACTORY. The project is
comprised of the establishment of a wheat flour mill Plant and adjacent wheat Flour production as shown in
Table 1. The machinery capacity is 36 tones per 24 hours and the annual requirement is 10,800 tons of wheat
at full production capacity three. The factory has 8 hours per day and 300 days per annum one shift working
scheduled
Article 3 of Proclamation no. 300/2002; determining the modalities of protection, conservation, and
promotion of the environment, and Article 4 of Proclamation n°513/2007 urban administration engaging in
the collection, transportation, use or disposal of solid waste, in Ethiopia stipulates that every development
project shall be required to undergo Environmental Impact Assessment before its commencement.
In this regard, TSIYON SEYIFU FLOUR-MILL FACTORY PROJECT hired the consultancy firm, Yoya Development
Consultancy and Training (PLC) to carry out the present Environmental& Social Impact Assessment (ESIA).
The proposed site for the development of the project is about 2,099m 2 of land under the government holding
far from any settlement area.
The significant environmental impacts identified by the ESIA are discussed briefly below:
Removal of vegetation covers;
Loss of soil micro-fauna and micro-flora;
Emission of dust and particulates into air;
Underground water contamination by wheat flour mill discharges;
Spilling and leakage of waste materials.
These potential impacts can also be mitigated as indicated in the ESIA report. Despite some predicted adverse
impacts, the proposed development project has positive impacts on the socio-economic environments of the
area.
The beneficial impacts (inceptive) for the local people associated with the project in due courses of its
inception to operation are:
Creation of employment, skills development, and long-term self-reliance opportunities;
Payment of government taxes to contribute to the national and regional development;
Reinstated land that can be used for forest and or agricultural production.
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Ethiopia is one of the largest wheat producers in Africa, there are still large pockets of food insecurity, and it
is a net importer of wheat. The principal wheat crops grown in Ethiopia are teff, wheat, and barley, which
are primarily cool-weather crops; and corn, sorghum, and millet, which are warm-weather wheat crops. All
wheat in Ethiopia is consumed as food, with crop residues and by-products commonly fed to livestock. It is
estimated that farmers hold about 10 percent of their wheat production for planting. Despite Ethiopia’s
large livestock population (the largest in Africa), the commercial feed industry is just beginning, mostly
located around Addis Ababa and slightly to the south. Feed is by far the biggest constraint to the livestock
sector. There are about 20 feed millers in the country, but most of them produce primarily for their
consumption. Only about half produce feed solely for sale.
Flour is a food item, which is a finely ground meal of cereals such as wheat, maize, sorghum, rice, etc.
obtained by milling and blending various streams of different quality. It mainly contains endosperm and a
certain quantity of bran. Wheat flour on average contains from 14% to 16.5% moisture. Based on its baking
quality and other quality indices such as gluten quality and content, colour, moisture content, granular size
of particles, and others, flour is divided into different grades. The basic application of flour is for bread
making, cakes and biscuits, and porridge at the household level. Semolina, a product obtained by milling
extra hard (durum) wheat, is also used in pasta and macaroni making. The byproduct bran is used for animal
feed and composite preparation for urban and rural agricultural inputs.
This project is new and under construction without an ESIA document. In line with this Sidama regional State
Environmental Protection Authority orders flour mill Processing Industry should prepare ESIA to operate the
mitigation measures of the industry waste.
The milling plants are characterized by unit operations that involve changes to the physical properties of the
wheats through cleaning and size reduction. The production process in these plants can be divided into three
general processing lines: Dry cleaning using cylinder or disc millers, Wet cleaning using cylinder or disc
millers, and Wet cleaning using stone millers.
Project industry processing activities have the potential to generate a wide range of waste that requires
proper planning from the outset to avoid resulting in impacts to human, biological, or other environmental
receptors. The Project seeks to proactively manage such potential wastes and to this effect has included
specific obligations regarding waste management in the bidding document drawn by the Authorized
organization.
To ensure the appropriate management and disposal of the project-related waste, Tsion Seyifu Flour Mill
Factory shall develop a framework for addressing waste management. This Environmental & Social Impact
2
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Assessment (ESIA) provides an overview of the framework and management practices applied by the owner
of W/r. Tsion Seyifu to avoid the waste generated around the project areas.
This Report has been produced by Yoya Development Consultancy and Training (PLC) which was hired by
the Project Promoter Tsion Seyifu Flour Mill Factory to carry out the study. The Consultancy firm is based in
Ethiopia (ESIA) regulation and has got strong background and knowledge in the area of Environmental
Assessment, and a track record of over 10 years of conducting studies of Environmental Impact Assessment
for Development Projects in Ethiopia in general and particularly in Sidama Regional State.
W/r Tsion Seyifu owns the Flour Mill Factory and has Ethiopian nationality. The stakeholder is owed by W/r.
Tsion Seyifu is fully capitalized and has reputable experience in other business management that helps with
flour production and marketing operations. The project manager is Mr. Belete Kebede, he has a Bachelor's
degree in accounting, and he has a responsibility in charge of business accounts and day-to-day
management.
3
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
report includes full details of the public participation activities and all the issues and concerns raised by the
Interested and Affected Parties. There was considerable support for the project, particularly from the people
of Mechiso town Municipality of Millennium Keble who were looking for employment opportunities. It was
apparent from the public participation that many of the public concerns stemmed from the legacy of the
New Flour Factory plant at Mechiso town Municipality, Millennium Keble, which had a medium record of
environmental management – especially in all aspects of construction, decommission, and operation phase
environmental effect. This influenced many people’s perceptions that did not have experience of a modern
Flour Factory. However, the Scoping Report was compiled in response to some inputs: -
the concerns of Interested and Affected Parties,
the initial site investigation,
consultations with specialists
professional experience, and
The TOR Checklist of Environmental Characteristics.
The Scoping Report should be read as an integral component of this ESIA as its content is not repeated here.
It outlined the key issues that would need to be assessed in the ESIA.
The Scoping Report was submitted to Sidama region State of EFCCA on Jun 7. The Scoping Report was made
available to the public through the Dara Woreda EFCC office, Mechiso town Millennium Kebele Council.
Registered Interested and Affected Parties were notified of its availability. No comments were received on
that report, suggesting that the Interested and Affected Parties were satisfied that it provided a
comprehensive record of their issues and concerns.
4
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
1.8 METHODOLOGY
Based on terms of reference (ToR) prepared by the YOYA Development Consultancy and Training PLC, the
methodology used during consultancy is paraphrased in the following:
5
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
b) Interviews: The consultant has interviewed people in the area of the project as well as in the woreda
institution and other governmental institutions related to this project.
c) Data collection: Through site visit of the site, required qualitative and quantitative data have been
collected
d) Stakeholders consultation: the consultant analyzed key partners/stakeholders including three sub-
village inhabitants in Mechisho town of Millennium Keble to find out their involvement, role,
suggestions, and responsibilities on this project.
e) Mapping and zoning of the site
f) Reporting: the data and information collected were organized and compiled in a report.
6
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
To detect the effects of the project on the neighboring environment such as the water bodies, the
soil, the people, the infrastructure, the fauna, the flora, and the atmosphere;
To detect the effect of the neighboring environment on the project, this means the effect on the
soil of the project and the surrounding activities;
To detect the effect of the project on the environment;
To propose alternative measures where it is noticed that adverse effects may occur;
To enable the proposal of mitigation measures where adverse effects may have occurred;
To carry out a diagnosis of the existing environment and activities in the area of the project;
To propose enforcement measures where beneficial effects from the project are detected;
To set up an environmental management plan that will govern all activities of the project for the
better protection of the environment.
7
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Table 1: Raw materials and Solid waste quantity of the flour processing industry
Primary process (wheat separation from waste, wheat milling & primary processing)
First Cleaning Process t/year %
Annual wheat Received 10,800 100
Ready (Clean) wheat 10,368 96
Solid wastes 432.00 4
Milling section (flour processing) t/year %
Secondary Processing
Ready (Cleaned) wheat for Flour Proses 10,368 100
Manufacturing Flour product (II) Flour 7,880 76
Solid wastes 415 4
Bran and Other by 2,074 20
Total solid wastes 2,920 27%
Whenever wheat is handled and strikes against each other it tends to rub off small particles of chaff and
fragment some kernels. In this manner, waste was continuously generated and the wheat was never
absolutely clean. Solid wastes were produced in two main sections of flour processing outlets.
Initially part of Elevator: The total amount of wheat 10,800 tonnes (100%) reached in the Elevator or
primary treatment section, 10,368 tones (96%) of clean wheat and 432 tonnes (4%) of solid wastes were
produced.
8
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
The second source of solid waste Wheat Milling section. Thus, at the milling department of the production
section, 7,880 tones (76%) of flour, 415 tones (4%) of solid waste, and 2,074 tons (20%) of bran and other
by-products and a total of 2,920 tons were generated and shown as above tabl-1.
9
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
The Constitution is the supreme law of the country, whose provisions guide all other policies, regulations,
and institutional frameworks. The Constitution of the FDRE has various provisions that are aimed at ensuring
the implementation of development projects in an environmentally sustainable manner.
The concepts of sustainable development and environmental rights are enshrined in the Constitution of the
FDRE through articles 43 and 44, which state among others the right to development and the right to live in
a clean and healthy environment. Article 44(2) of the Constitution states that all persons who have been
displaced, or whose livelihood has been adversely affected as a result of state programs have the right to
commensurate monetary or alternative means of compensation including relocation with adequate State
assistance. The government shall pay fair compensation for property found on the land but the amount of
compensation shall not take into account the value of land. Moreover, the Constitution states that, without
prejudice to the right to private property, the government may expropriate private property for public
purposes subject to payment in advance of compensation commensurate to the value of the property
(Article 40(8). Moreover, Article 43 (2) dealing with the rights to development states that nationals have the
right to participate in national development and, in particular, to be consulted for policies and projects
affecting the community.
Article 92 of the Constitution states that the design and implementation of any program and development
projects shall not damage or destroy the environment, and people have the right to be fully consulted and
express their views in the planning and implementation of environmental policies and project
To cope with the prevailing environmental problems such as land degradation, rainfall fluctuation, increasing
temperature, and flooding, and speed up its socio-economic development, the Government of Ethiopia has
planned a climate-resilient green economy as a development strategy. This development direction promotes
environmental protection, reducing fossil fuel consumption which releases greenhouse gases into the
atmosphere. With the demand for energy growing with the increasing population, industrialization, and
10
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
urbanization, the Government realized that harnessing clean and renewable energy sources such as wind,
solar, hydro and geothermal energy sources is critical.
The policy seeks to ensure the empowerment and participation of the people and their organizations at all
levels in environmental management activities, raise public awareness, and promote understanding of the
essential linkage between environment and development. In addition to its guiding principles, the policy
addresses sect-oral and cross-sect-oral environmental issues.
Ethiopia has set its industrial policy and strategy as of August 2002. The industry development strategy of
the country has put in place the principles that primarily focus on the promotion of agricultural-lead
industrialization, export-lead development, and expansion of labor-intensive industries these principles are
interdependent and interlinked to one another. The strategy has also set other principles that clearly state
the pivotal contribution of the private sector, the leadership role of the Government, and the integrated and
coordinated participation of the public at large in nurturing the strategy. This strategy refers to those
industries which are primarily involved in the production of manufactured foods.
The problem of improper handling of hazardous substances related to activities such as pests and insects,
crop diseases, fertilizer application management, and industrial development is becoming a serious
environmental concern. In association with this, the proclamation provides a basis from which the relevant
11
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
environmental standard applicable to Ethiopia can be developed while sanctioning the violation of these
standards as a criminally punishable offense.
For the sake of appropriate project implementation, environmental standards, and related requirements,
inspectors belonging to EPA or the relevant regional environmental agency are empowered by the
proclamation to enter, without prior notice or court order, land premises at any time, at their discretion.
Such wide power was driven by Ethiopia’s serious concern and commitment to protecting the environment
from pollution.
Therefore, Solid Waste Management Proclamation No. 513/2007 states (Article 5.1) that Urban
Administrations shall ensure the participation of the lowest administrative levels and their respective local
communities in designing and implementing their respective solid waste management plans. In Article 5.1
each Region or urban administration shall set its schedule and, based on that, prepare its solid waste
management plan and report of implementation. Measures related to waste handling and disposal:
Any person shall collect waste in an especially designated place and in a manner, which does not
affect the health of the society.
No person shall dispose of solid, liquid, or any other waste in a manner that contaminates the
environment or affects the health of the society.
This Regulation confers important obligations to industrial operators. A factory subject to the regulations is
obliged to prevent or minimize the generation and release of pollutants to a level not exceeding the
environmental standards. The regulation also obliges industrial operators to handle their equipment, inputs,
and products in a manner that prevents damage to the environment and human health. Moreover, the
regulations urge industrial operators to prepare and implement an emergency response system of their own.
On the other hand, industrial operators are required to prepare and implement internal environmental
monitoring systems and keep written records of the pollutants generated and the disposal mechanisms used
to get rid of the pollutants. To this factory are required by the regulation to submit annual compliance
reports with the provision of the regulations.
12
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
There are so many organizations involved in environmental management in the country. These organizations
include the Ministry of Environment and Mineral Resources, Regional Land and Protection and
Environmental, National Environment and Management Authority, Local Authorities, Ministry of Water and
Irrigation, etc. It also ensures coordination among sectorial ministries and agencies on environmental
matters.
The proclamation stipulates the mandatory need for the establishment of Environmental organs by regions.
The mandates of the regional environmental organs are to enable regions to coordinate environmental
activities, avoid duplication of efforts, and improve the dissemination of environmental information. This
proclamation also mandates the EPA to undertake studies and research, develop action plans, etc, in the
area of combating desertification.
13
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
This policy recognizes that the conservation of natural habitats is essential to safeguard their unique
biodiversity and to maintain environmental services and products for human society and long-term
sustainable development.
The proposed Industrial Zone Development Project activities will be implemented on agricultural land and
are not likely to adversely impact any of the Natural Habitats. This project is not therefore going to trigger
OP/BP 4.04.
The objective of this policy is to assist borrowers in harnessing the potential of forests to reduce poverty
sustainably, integrate forests effectively into sustainable economic development, and protect the vital local
and global environmental services and values of forests.
No forest or shrubs of major biodiversity significance will be cleared during the land preparation and
construction of the industrial zone development project and other ancillary development activities
associated with the provision of infrastructures and various utilities.
This policy under the sub-project will not therefore trigger OP/BP 4.36.
14
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
defined as movable or immovable objects, sites, structures, groups of structures, natural features, and
landscapes that have archaeological, paleontological,
The Occupational Safety and Health Act, of 2007 applies to all workplaces where any person is at work,
whether temporarily or permanently. The purpose of this Act is to: Secure the safety, health, and welfare of
persons at work; and Protect persons other than persons at work against risks to safety and health arising
out of, or in connection with, the activities of persons at work.
a) Safety
Workers must be trained on personal safety and how to handle waste emissions from flour mill plants. They
should be provided with Personal Protective equipment which should be worn at all times. There should be a
toxic acidic contamination risk preparedness plan spelled out and implemented. Adequate protection close
should be installed at every pump, in the office, an escape route marked, and an assembly point provided
and marked.
b) Health
Associated with wheat Flour industry are vector-borne diseases such as malaria. Conditions favoring the
proliferation of vectors include stagnant wastewater in disposal tanks, drains, reservoirs, and seepage sites.
Furthermore, the lack of sanitary and wastewater treatment facilities as well as the increased incidence of
human-water contact will exacerbate the problem of vector-borne diseases. Wastewater generated from
this process is acidic and rich in suspended dissolved and organic matter. This processing activity in the
project area could negatively affect public health and safety; because appropriate mitigation measures are
not implemented. Specific risks include:
Spinning sensation, eye, ear, and skin irritation, stomach pain, Nausea, and breathing problems among the
residents of nearby areas and risk of increase of water-related diseases from standing wastewater in
abandoned borrows areas and seepage.
c) Welfare
Every occupier shall be provided and maintain to be readily accessible, a first-aid box or cupboard of the
prescribed standard. The occupier of a workplace shall cause a thorough safety and health audit of his
workplace to be carried out at least once in every period of twelve months by a safety and health advisor,
who shall issue a report of such an audit containing the prescribed particulars to the occupier on payment of
a prescribed fee and shall send a copy of the report to the Regional and district EPA.
15
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
The project will be at the edge of ensuring sustainable development, delivering economically, socially, and
environmentally important values. It will contribute to the delivery of Ethiopia’s Sustainable Development
and Poverty Reduction Program by creating employment and export revenues whilst supporting social
development through a project community support plan.
The envisaged flour mill plant project has been designed to ensure sustainable development and deliver
economic, social, and environmental achieve the objectives of Ethiopia’s Sustainable development and
poverty reduction
17
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Skills and technology transfer: the project will be commercialized at high-technology processing
facilities. Best-in-class agricultural industry practices will be implemented and disseminated in the
region through technical support to growers;
building capacity: The management and technical capacity of local staff will be increased and is
planned for Ethiopian staff to follow in the international team's footsteps once the business is up and
running;
Sustainable employment: processing foods is labor intensive and the project will bring a high level of
employment and income potential to rural communities;
Minimized carbon footprint and waste operation: The Flour-Mill Plant factory will strive to
recycle the maximum amount of waste resulting from allots activities in the processing plant;
18
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
5. PROJECT DESCRIPTION
The specific feature of the project area in terms of temperature is from 28 to 24oC and a rainfall pattern
range is average 1200-1300 mm per annum. The specific location area of the flour industry is located about
8k from Woreda town of Kebado the administrative town of the district. The size of the flour plant is about
2,099 M2, which has one lagoon pit on the southeast side in front of the factory.
The shareholders of the project, Tsiyon Seyifu Flour-Mill Factory, recognize the enormous potential that the
newly established for developing a successful agro-processing business in Sidam Regional State South Sidam
Zone, Dara woreda Mechsio town, Millennium Kebele, and believes that it offers an excellent investment
opportunity which will provide good returns to investors.
In addition, the owner believes that the business offers the opportunity to be a model of genuine
commitment to sustainable development that can maximize valuable returns from economic, social, and
environmental perspectives.
In short, Tsiyon Seyifu Flour-Mill Factory project will offer a highly competitive position for the primary
production of quality flour that can be delivered throughout the year, reliable, quality, high yield, and
competitive flours. The project raw materials are (hard wheat and soft wheat), for the production of meal
and flour to be used to supply production lines. The production process of wheat flour consists of four major
operations Wheat Intake and Pre-Cleaning, Wheat Cleaning and preparation, Milling, and Packing and
Dispatching. Associated facilities include boilers (steam and hot water), air compressors (compressed air
production), refrigerators (cooling water production), and electric transformers (conversion of equipments’
voltages).
Annually the factory will receive 10,800 tons of wheat for flour production. Wheat is usually received in the
unclaimed state and contains a variety of different types and sizes of foreign material including wheat bran,
chaff, rust, weed seeds, various types of pollens, different mold spores, and pieces of wheat, dirt, and insect
parts.
Whenever wheat is handled and strikes against each other it tends to rub off small particles of chaff and
fragment some kernels. In this manner, waste was continuously generated and the wheat was never
absolutely clean. Solid wastes were produced into two main sections of flour processing departments.
Initially part of Elevator: The total amount of wheat 10,800 tones (100%) reached in the Elevator or primary
treatment section, 10,368 tones (96%) clean wheat, and 432 tones (4%) solid wastes were produced.
The second source of solid waste was the Milling section. Thus, at the milling department of the production
section, 10,368tone (76%) of flour, 415 tones (4%) of solid waste, and 2,074 tones (20%) of bran and other
by-products and a total of 2,920 tons were generated and shown as above tabl-1.
Thus, from this flour industry generated wastes are Solid wastes (cereals bran), Liquid wastes, and
Particulate Matter emission wastes, the Impact of accidents, Noise pollution, and Greenhouse gas
20
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
emissions. From those wastes Solid wastes (wheat bran) are economically important for the production of
composite and cattle feed for which there is a production unit.
Consequently, the ESIA including the project asset was described in the following list of Table. The ESIA of
the project report also includes information gathered from the project proponent, Values and Financial
Analysts, and details
21
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
22
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Firstly, in line with national practice in ESIAs, a broad definition of “Environment” is adopted, which
incorporates both bio-physical and socio-economic components. The EA Policy of Ethiopia seeks to achieve a
balance between negative and positive impacts and between biophysical impacts and social and economic
gains to society. Therefore, both negative and positive impacts on the environment will be considered
below. To the extent that it is practically possible, this report will recommend measures to mitigate negative
impacts and optimize (or enhance) positive impacts.
The assessments will include the Factory Plant, related assets, and related infrastructure such as roads,
power lines, and water pipelines. Normally, there is a two-way interaction between a project and its
environment. Not only does the project have impacts on its environment, but the environment also provides
opportunities and constraints on the project. For example, in Ethiopia water resources may pose a
constraint, while the impact of HIV/AIDS has implications for training and maintaining the skills base of the
workforce.
This assessment is made based on the current proposals. Should these proposals change in any material
way, then some of the assessments below may have to be reconsidered. In Section 8, for each activity with
the potential for environmental impacts, a discussion of the impact is presented. Where practically possible,
the discussion is followed by a table that summarizes the assessment according to specific criteria as follows.
Assessment Criteria
Nature of impact An explanation of how the environment will be affected by specific activities
Mitigation What measures could be applied to reduce negative impacts or enhance
positive impacts
Extent The geographical extent of the impact
Duration The length of time that the impact persists: -
Short term 0-5 years
Medium-term 5-15 years
Long-term – lifespan of the project
Permanent
23
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Intensity (or Low (natural, social, and cultural functions are not significantly affected)
magnitude) - Medium (natural, social, and cultural functions continue but are modified)
- High (natural, social, and cultural functions become altered to the degree that they become
dysfunctional
Probability The probability of the impact occurring: -
- Improbable (a low probability that the impact will occur)
- Probable (a distinct probability that the impact will occur)
- Highly probable (it is most likely that the impact will occur)
- Definite (where the impact will occur regardless of any mitigation measures)
Confidence The level of confidence that can be placed on this assessment: -
- Low (would indicate that further investigation is required if the impact could
potentially be significant)
- Medium (further investigation may be required if the impact could be
significant)
- High (The impact is well understood. However further investigation may be
required to determine the effectiveness of possible mitigation measures).
Significance The Significance of the impact is determined as a synthesis of the above
assessment criteria where: -
- Low significance means that the impact would not affect the decision to approve
the project (or a particular project alternative),
- Medium significance – the assessed impact should affect the decision unless it is
effectively mitigated,
- High significance – the decision would be influenced regardless of any mitigation
Further investigation A recommendation for further investigation (before the commencement of the
or monitoring activity) or monitoring (before commencement and/or during operations, or even
post-closure
Wheat Intake and Pre-Cleaning, Wheat Cleaning and preparation, Milling, and Packing and Dispatching.
wheat Intake and Pre-cleaning: - The major unit operations are dumping, conveying, weighing, pre-
cleaning, and conveying to storage silos or transferring to the working bins of the cleaning room.
Wheat Cleaning and Preparation: - The main unit operations involved are weighing, screening, destoning,
impurity separation, ferromagnetic separation, scouring, aspiration, dampening, tempering, and etiolating.
24
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Milling: - Major operations involved are weighing, breaking open, scalping, scratching, detaching, sifting,
purifying, milling (grounding), resifting and etiolating.
Packing and Dispatching: - The major operations involved are the collection of flour streams and bran,
mixing and aerating, resifting, etiolating, packing, sewing, loading, and dispatching. The process does not
release any pollutants to the environment.
In a flour processing company, raw materials are stored and cleaned in an elevator department. The
operation of elevator section equipment is based on the difference of wheat and the main features of
impurities. This section consists of technological refinement devices: aspirators, separators, spiral settlers,
machines for stone separation, and magnetic apparatuses.
Through this process, the project produces different wastes. Data collected from this flour industry is highly
aggregated and generally obtained a lot of information about industry processing performance. Therefore,
having this in mind, the flour industry found in Mechiso town, millennium Kebele by the name of Tsiyon
Seyifu Flour Industry Its processing outputs are;
Cleaned wheat is supplied to a flour processing department: Moisture is added by washing the wheat to
toughen the outside layer of bran so that it will come off in large flakes. Bran is undesirable in flour and is
difficult to separate in the powdered state.
Wheat is fed through several successively smoother rolls until it is reduced to its finished form. A screening
operation between each set of rolls helps control particle size and separates the bran. The bolters or sifters
are also gradually reduced in effective mesh sizes down to a fine silk sieve. The finished product includes
clear (rough) and pattern (fine) flour produced in a milling department. The working principle of the milling
equipment is based on pressing and shifting (rolls and millstones), striking (disk mills), and striking and
grinding (hammer mills) deformations. Rolls are used most frequently. Finally, ready flour is packed and
stored.
The most possible positive and negative impacts of the project were identified using a data collection
checklist and data obtained from the surrounding public participation opinion. From this flour project,
identified wastes are Solid wastes (cereals bran), Liquid wastes, Particulate Matter emission wastes, Impact
of accidents, Noise pollution, and greenhouse gas emission
The proposed Tsiyon Seyifu Flour Mill Factory would expect wastes are dust emissions, solid waste, liquid
waste, and fuel, oil, and lubricant, and the associated maximum predicted ground level concentrations
would still comply with the relevant environmental impact in all phases of construction, decommission and
operations. Consequently, it is considered that the proposed development would have a negligible impact
on particulate emissions and concentrations in the vicinity of the site.
25
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
7. CONSULTATION
7.1 INTRODUCTION
Proclamation (Art. 3(1)) of EPA, 2002; EPA, 1997 and subsequent (ESIA)/EA Regulations of 299/2002 requires
any project to carry out environmental impact assessments for development proposals. According to
(ESIA) /EA Regulations, 2003 such studies have to incorporate consultation and public participation (CPP)
process.
ESIA process is largely determined by effective consultation and public participation (CPP) which provides a
cornerstone for project planning and successful implementation. Consultation and Public participation help
to: Facilitate the involvement and participation of affected persons throughout the project cycle and ensure
a sense of responsibility and commitment towards implementing the proposed EMP.
CPP should be undertaken mainly during project construction, decommission, and operations phases. It
should involve the affected persons, lead agencies, private sector, among others. The methodology for CPP
may include; Meetings and technical workshops with affected communities, Questionnaires, Interviews, and
Notices. It is the responsibility of the project proponent to adequately ensure the effective distribution of
the information to the affected persons to militate against unnecessary delays in decision-making and
project implementation.
The intent of the Yoya Development Consultancy and Training (PLC) strategy has been to identify and
incorporate a range of community values to ensure that the project was appropriately adapted to the local
context. The steps in the local consultation program were designed to identify and address stakeholders
concerns about the project and to build positive, long-term relationships with the project community
neighbors’.
Consultation specific to the project was initiated by contacting the Environmental officer of Dara District Mr.
Ashenaf Loha who thereafter provided the consultant team with contact persons at the Woreda Sector. The
consultation process included to a large extent public consultation through Mechiso town Millennium Keble
with the local people and interested and affected parties.
26
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
(b) Whether the proposed project development project will cause negative impacts on the following area:
Local residents, Natural ecology of the area, the human environment, public health and safety, Effect on
water resources and quality, soil Quality in the local area, The areas of scenic beauty, Road transport and
related infrastructure, Drainage of the area, and any other comment.
Meeting with local This meeting was held for five days as from Tuesday, May 24 th to Jun 6th, 2024 at the site
after receiving detailed Terms of Reference from Dara woreda environmental protection office dated Jun
8th, 2024 and photos are provided at the end of this project report.
The proposed development project is accepted by the interested and the affected parties (i.e. almost
all of the respondents)
The proposed project will benefit the general population by providing much-needed jobs and in the
long run reduce dependency and poverty.
Other industries in the area hope to have good raw materials for food industries etc.
Participants Attending Result: The respondents however, did not object to the project and were in
agreement that it should be implemented but the proponent should consider employing people from the
local area for jobs that do not need specialized skills before he brings other people in. put in place measures
to curb insecurity. Members of the public who participated in this public participation were so passionate
about insecurity and how it needs to be addressed.
27
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Dust and fugitive emissions The project for the flour mill facility is planned to be portable and
partially enclosed to mitigate dust concerns
Noise The plant is planned to be partially enclosed, using closed material and
insulted cover to mitigate noise concerns and to achieve compliance with
the Ethiopian Environmental Law. This enclosure will also work in
mitigating dust emissions and potential health concerns.
Proximity to Road The factory will not extend beyond the site that is beside the road
Groundwater Constructed Waste collection damp pit with cement concrete downstream of the
entire site is expected to mitigate potential sedimentation of the groundwater
28
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
8. EVALUATION OF IMPACTS
8.1 EZEDIN MOHAMED FLOUR INDUSTRY SITES – POTENTIAL IMPACT
Data and information were collected when project site visits were conducted; we noted that the industry has
most important positive and some negative impacts on the surrounding environment.
Thus, the project has some definite negative impacts on the surrounding environment in both direct and
indirect ways, as there will be direct and indirect interactions between project activities and the
environment. In this chapter analysis was done to identify and classify according to its potential effect, the
impacts inference on the socioeconomic environment (health, security, economic activities, finances, etc)
and the biophysical environment (fauna, flora, water, air, soil, energy) activities. Those negative, direct, or
indirect impacts are described in detail as follows;
The most possible positive impact of the project is to create job opportunities for 34 skilled employees and
120 casual labour that enable them to generate income for their families. It also supplies 10,368 tons of
quality flour /year to its customers. Similarly, the project earns considerable profit for the proponent and
also it increases the revenue of the city administration through tax.
Impacts
1 Provision of 10,368 tons of quality flour /year to its customers
2 Job creation for 34 skilled and 110 casual labour were employed in different services of the factory
3 New opportunities for income generation for many individuals who has been supplied wheat to the
wheat mill
4 Increased economic activities directly or indirectly related to the project;
5 Possibility of savings for the local population and employees of the plant.
6 Payment of taxes to the local and central government
7 Create opportunities for the community to be exposed to modern gardening, recreation activities and
agricultural development practices.
8 Enhances cultural transformation through which women of the area who are under cultural pressure
can be benefited by encouraging them through employment opportunities.
9 Contributes to the realization of the development strategy, particularly in the area of industry sector
29
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Based on the project proposal production plan table-1 of analysis, annually 2,920 tones (8%) total solid
wastes were produced from raw materials and manufactured products. If we consider 5,530 tones (20%) of
Bran and Other by-products as solid waste, the number of solid wastes increased to 2,074 tons (28%) /year
above Table-1. This generated solid waste is containing with a very high potential of environmental
pollutants (effluent) when disposed the downstream of watercourses and other biodiversity with no
treatment. This type of waste nowadays has become a series problem in the receiving environment,
especially in water bodies. Summary of the associated environmental negative impacts are described in
detail as follows;
30
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
Nature of impact Potential contamination of groundwater by explosives, fuels, oils, hydraulic fluids
or domestic sewage
Mitigation Pump water from the dump pit for use
• Maintain all vehicles to prevent spills of oils, hydraulic fluids etc
• Re-use treated sewage water
• Pave vehicle parks and collect runoff
• Bund all hazardous liquid storage installations
• Ensure collection of liquid waste and recycling or legal disposal at an approved
disposal facility
Extent Since water will be abstracted from a few boreholes and probably the factory, the
dump of collection should be sufficient to limit any contamination to an area close
to the site.
Duration The potential for contamination will exist for as long as the operations phase
Intensity Low
Probability High, unless mitigation is effectively implemented
Confidence High
Significance Low – provided mitigation is effectively implemented
Further investigation Water quality tests should be undertaken to establish baseline water quality, and
or monitoring periodic water quality monitoring from abstraction boreholes is recommended
during operations
The process of construction using cement does not generate significant quantities of solid waste. Ash from
fuels used in the kiln becomes part of the cement product. However, solid waste will be generated in
workshops (e.g. used parts, scrap metal) and from offices (e.g. packaging, paper, kitchen waste).
Combustible material can probably be used in the kilns. Any other waste must be collected and removed to
an approved waste disposal facility in Dara Woreda. Littering must be forbidden and site staff must be disciplined in
this regard.
In Tsiyon Seyifu Four Milling Factory, air emissions from the raw material organized sources are supplied to
the solid parts treatment cyclones. In this factory, dust is generated at the transfer points of the enclosed
conveying equipment, carried through bucket elevators, and emitted at the discharge of the conveyed
materials.
Noise pollution represents the exposure of people or animals to levels of sound that are annoying, stressful,
or damaging to the ears. The maximum noise generated from this project flour factory is 43 db at its source
and the minimum is 32 db at the nearest settlement area.
According to EPA noise limits, 55 dba at the nearest residences is in the range of acceptable noise level for
rural districts an acceptable outdoor noise level is considered to be 65 dBA during the daytime and 45 dBA at
night. The project noise is low from the permissible noise level to guarantee minimal comfort to humans is
55 – 35 dba, noise problem is not an issue for the nearby residents.
Overall, it is considered that the impact of noise will be very limited because there are so few people living
near the site, and the nearest neighbors are more than 600m from the Flour Factory
service in case of accident are not available. This study concludes, that to avoid workers of safety
equipment ignorance, it is advisable to provide regular follow-up and training.
34
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
9. ANALYSIS OF ALTERNATIVES
This chapter analyzes the possible alternatives besides the methods and other parameters already
considered in the design of the project. Bearing in mind the critical need for the protection of environmental
ecosystems and the core role that the Tsiyon Seyifu Flour-Mill Factory site will play in the social and
economic development of the country, it’s imperative to analyze and balance the need for the planet,
people and profit in the context of the sustainable development.
In the scenario where Dara Woreda Environment, Forest Climate Change Office is not permitted to factory
in the site in question, soil erosion will still be evident given the fact that the site had already been quarried
before and no need for rehabilitation of the area was done.
35
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
All activities carried out on the site, and about the project, would comply with the relevant provisions of all
related relevant legislation and regulations, and would also comply with relevant policies and guidelines
relating to the construction, decommission phase, and operation phases of the project including, but not
limited to, those detailed. Summarizes the key recommendations for environmental management in the
form of an Environmental Management Plan. These recommendations are arranged according to the
relevant phase of the project.
36
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
All safeguard measures detailed in the Environmental Assessment would be applied to the project
Construction activities would be managed to comply with the premises’ Environment Protection
License noise limits, which range from 55–45 dB(A) when measured at the nearest residences
(dimensionless unit, decibel (dB))
Noisy construction activities would generally be undertaken during daylight hours, although some
construction activities would be undertaken outside these hours
Limits Environmental awareness training would be provided to all personnel (including all labourers/
plant operators/ supervisors and engineers), and would address, but not be limited to:
Sedimentation and erosion control;
Water quality control;
Pollution control; and
DEC requirements
The training would commence at the start of construction and would continue as new personnel
are engaged
A register of environmental awareness training would be established and maintained at the site.
The register would contain details of the type of training, personnel trained, training dates and
qualifications of the trainer
37
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
The location of the construction activities immediately adjacent to the banks of the Legedara River increases
the risk of potential impacts to the river occurring, although the site stormwater management system would
collect all runoff from the construction area and convey it to the environmental farm for treatment and
irrigation. However, additional environmental control measures have been developed to further minimize
the risk of discharges to the Legedara River, as detailed in Table 12. Acid Sulphate Soils (ASS) are not
expected to be encountered on site and consequently have not been considered further.
A site-specific Erosion and Sediment Control Plan (ESCP) has been developed for the project. The
ESCP identifies appropriate control measures and practices to prevent soil and erosion impacts,
and discharges of turbid site runoff to the Legedara River
All sediment control measures detailed in the ESCP would be implemented on-site prior to
construction commencing
All sediment and erosion controls would be inspected by the Contractor/Proponent at a minimum
of weekly intervals and within 24 hours of all rainfall events exceeding 10 mm in 24 hours. Routine
maintenance would be undertaken to desilt sediment basins and traps and replace damaged
sediment control fences and other structures.
Loss of suspended solids and sediment to the Legedara River would be prevented by using
temporary or reverse super elevation for any excavations, constructing berms along the edge of
the site to prevent runoff to the river, and installing silt fences along the property boundary with
the river.
A silt fence would be installed between the site and the Legedara River, along the entire perimeter
of the construction area, to prevent suspended solids from being transported offsite.
All site runoff would be collected and diverted to the site stormwater management system, which
would then convey it to the surrounding farm for treatment and irrigation, thereby preventing any
offsite impacts
In the event of a spillage of potentially harmful chemicals, fuels, oils or materials, would be
contacted immediately, and contaminants would be immediately control
An incident/emergency spill plan would be developed. This would include measures to avoid
spillages of fuels, chemicals, and fluids onto the floodplain and/or into any waterways. All
personnel would be made aware of these measures. An emergency spill kit would be kept onsite
at all times.
All fuels, chemicals, and liquids would be stored at least 50 m away from any waterways or
drainage lines within an impervious bunded area
Any wastewater generated from construction processes would be contained onsite and directed
to the site storm water management system for conveyance to the Environmental Farm for
treatment and irrigation. The discharge of water into waterways would be prohibited
The refueling of plant and maintenance of machinery would be undertaken within impervious
bunded areas within the compound sites.
38
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
The noise and vibration mitigation management measures would include the appropriate siting of plant,
equipment, compounds, and machinery to minimize noise impacts and construction noise monitoring to
monitor compliance with the noise limits specified in the premise’s Environment Protection License, as
detailed in Table 13.
Appropriate noise and vibration mitigation measures would be developed and implemented
throughout the construction process, including all commitments made in the EA, and required by
the Conditions of Approval.
Construction activities would be managed to comply with the premises’ Environment Protection
license noise limits, which range from 55 – 45 dB(A) when measured at the nearest residences.
Noisy construction activities in this project is not an issue.
Limits.
Plant and equipment would be selected and operated with appropriate mufflers and noise
controls and where practical work practices and plant selection would be considered so as to
minimize noise impacts
High efficiency mufflers would be used on all construction equipment and manufacturer’s noise
control equipment would remain intact. All construction equipment would be well maintained and
serviced
39
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
minimize the risk of such spillages occurring. In addition, appropriate waste management measures would
be implemented to ensure that waste is avoided, minimized, or recycled wherever possible, or responsibly
disposed of. Appropriate mitigation and management measures are detailed in Table 14.
An incident emergency spill plan would be developed and implemented as required. This would
include measures to avoid spillages of fuels, chemicals, and fluids into any waterways. All
personnel would be made aware of these measures. An emergency spill kit would be kept onsite
at all times.
Storage areas for fuels, oils and chemicals would be surrounded by impervious bund walls to
contain any spillage. Storage areas would not be located within 50 meters of any waterway, on
slopes above 10%, or near areas of native vegetation. All precautions would be taken to eliminate
fuel or other spills.
Storage areas for fuels, oils and chemicals used in construction would be surrounded by bund
walls to retain any spills. The bund would contain at least 110% of the volume of the largest
container
A schedule of all hazardous materials in use on the works would be maintained and recorded for
the duration of the construction.
Refueling operations would not be left unattended whilst refueling is in progress. Refueling of
plant and maintenance would not occur within 50m of waterways or sensitive areas.
The refueling of plant, and maintenance of machinery, would be undertaken within impervious
bunded areas.
Should any spillage of fuels, oils, chemicals or other potentially hazardous/polluting materials
occur during construction the Dara Woreda would be contacted immediately, and contaminants
would be immediately contained, removed, treated (if necessary), and disposed of by Dara
Woreda requirements.
All wastes would be transported by licensed waste management contractors and would be
disposed of to an appropriately licensed waste management facility
The construction site would be maintained in a clean and tidy condition. Covered bins would be
provided for waste disposal
The Resource Management Hierarchy principles the would-be adopted in this EWMP
40
11. ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN
Environmental monitoring involves the measurement of relevant parameters, at a level of detail accurate
enough, to distinguish the anticipated changes. Monitoring aims to determine the effectiveness of actions to
improve environmental quality. The environmental management and monitoring plans have been developed
and outlined to bring home the key findings of the Environmental Impact Assessment of the project in
mention, recommending necessary mitigation actions, defining roles, monitoring able indicators, and the
estimated cost.
These flour industry EWMPs outlined in tables hereafter address the potential negative impacts and
mitigation measures as well as roles, costs, and monitorable indicators that can help to determine the
effectiveness of actions to upgrade the quality of the environment; as regards to this flour Industry . The
detailed information is stated below in Table 15.
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 2018
Source of Mitigation measure Monitoring Indicators Monitoring and reporting Cost of Responsibility bodies
Potential Impact frequency mitigation/
enhancement
measure
Liquid and solid Constructions of waste disposal pit/tank Presence of well At the end of every work Part of the worked, Regional Environmental
waste Maintained month report operational cost Protection Forest and Climate Change
receptacles and Authority
central collection
point
Flour industry Flour by- products should be stored in a No contaminated husk Monitoring every two Part of the worked, Regional Environmental
waste separate site store and handled carefully. waste months or quarterly operation Protection Forest and Climate Change
An solid waste used for compost expense Authority
preparation
Office waste & building of toilet and solid waste pit healthy environment Monitoring every two part of operation worked, Regional Environmental
human extraction and workers from air months or quarterly expense Protection Forest and Climate Change
pollution Authority
Flour waste Fulfillment of facility for disposal and fully protected Monitoring every two part of operation worked, Regional Environmental
influxes treatment with EM environment from months or quarterly expense Protection Forest and Climate Change
noise, fire hazards & Authority
seeing dressed
workers
workers Health Provide Personal Protective Equipment Workers using Monitoring every two part of operation worked, Regional Environmental
and Safety Train workers on personal safety and Protective Equipment months or quarterly expense Protection Forest and Climate Change
how to handle flour waste Presence of a First Aid Authority
Box
41
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
4 Health hazards and the Works incidences, status, and trends of Yearly once Proponent, 10,000
spread of diseases diseases in the project area, Assess environmentalist, health
employees health safety and utilization office regulatory body
of safety devices
Total environmental monitoring cost 75,000
42
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
12.1 CONCLUSION
It is concluded that:
The total dour emission rate for the flour mill would not have a significant incremental or cumulative
dour impact at the Mechiso town Millennium kebele flour mill industry site and would equate to
<0.1% of the existing total dour emission rate for the project site facility (excluding emissions from
the surrounding residents).
Odor emissions from the flour mill would be likely to have a neutral hedonic tone, which is to say that
the odor would be regarded as being neither unpleasant nor pleasant.
All exhaust discharge points would be equipped with Buhler Air jet filters, which are capable of
achieving an in-stack particulate concentration of considerably less than 50 mg/m3.
Emissions of total suspended particulates would comply with the concentration prescribed by the
Protection of the Environment Operations (Clean Air) Regulation 2002.
The total particulate emission rate for the flour mill would not have a significant incremental or
cumulative impact at the project site and should be avoided emission rate.
The additional greenhouse gas emissions associated with the proposed flour mill at the established
Mechiso town Millennium kebele flour mill industry site would be no CO2 gas emissions.
The development and rigorous implementation of appropriate environmental management
measures throughout the construction period would minimize environmental impacts associated
with the construction process.
12.2 Recommendation
Here below few recommendations are forwarded:
To enhance the potential economic benefits and social acceptability of the project; it is very
important for the company management body and Proponents (a) to avoid or minimize any adverse
impacts of the project on human health and, (b) to reduce impacts on the environment,
It is recommended that the proposed mitigating measures are properly implemented on time.
To ensure proper implementation of mitigation measures, monitoring and auditing must be
conducted.
In addition, the company should create harmonious relationships with the local communities by
holding discussions with local people to develop strong ties with them.
All appropriate environmental management measures detailed in this report, together with any
other environmental management commitments detailed in the Environmental Assessment
document be developed in a Construction Environmental Management Plan (EMP) and implemented
throughout the construction phase
43
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
In collaboration with the local government and the affected community, the company should support
development efforts at the project site. This will strengthen trust between local people and the
company.
Therefore, major practical works are required to aware the local community develop their confidence in the
flour industry activities, and to conduct transparent mitigation measure application and the necessary steps
on what conditions the flour industry Waste Management Plan should consolidated by the consultant and
provide to the Regional and woreda EPA office for the acceptance and approval of to this envisaged flour
industry management plan. This will however be overcome through close follow-up and implementation of
the recommended Environmental Management and Monitoring Plans (EMPs).
44
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
14. REFERENCES
1 Birley (1991), Guidelines for forecasting the vector-borne disease implications of Water
2 Resources Development. PEEM Guidelines Series 2. Second edition PEEM Secretariat, WHO, Geneva.
WHO/CWS/ 91.3
3 EPA-ENVIRONMENTAL PROTECTION AUTHORIYTY – State of Environment Report for Ethiopia-Addis Ababa-
2003
4 Bureau of Africa; Office of Sustainable Development (June1996); Environmental Guidelines for Small-scale
Activities in Africa
5 THE FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA-October 31,2002-proclamation No 295: ``Environmental
Organs Establishment Proclamation``
6 FDRE-THE FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA-December 3, 2001-proclamation N o 299:
``Environmental Impacts Assessment Proclamation``
7 FDRE-THE FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA-December 3, 2001-proclamation N o 300:
``Environmental pollution control Proclamation`` Guidelines Washington D.C, fourth printing
8 IIRR (2002), Managing Dry land Resources-An Extension manual for Eastern and Southern
9 Africa. International Institute of Rural RE- construction, Nairobi,Kenya. Impact Assessment Service of EPA
(June 2003), Environmental and social Management plan (ESMP) for Agricultural Support project
10 The World Bank (2002), the Environment and the Millennium Development Goals.
11 The world Bank (May/1995) Environmental Assessment Sound Book; Volume II Sectorial FDRE August
24,1995-proclamation No9: ‘’Environmental protection Authority Establishment proclamation’’
45
ESIA Report: - Tsiyon Seyifu Flour-Mill Factory 20
46