PVSyst - Project Design-5
PVSyst - Project Design-5
Auxiliaries consumption
The auxiliaries consumption is the energy used for managing the system. This may be fans, air conditioning, electronic devices, lights, or any other energy consumption which has to be
deduced from the PV produced energy to be sold to the grid.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 146 of 174
NB: In some inverters, this internal consumption (internal fans) is included in the efficiency curve. In this case it should not be mentioned here, otherwise it would be accounted twice
during the simulation.
Unavailability loss
It is sometimes useful to foresee system failures or maintenance stops in the production expectations.
You can define a system unavailability as a fraction of time (or a number of days). For these failure hours, the system will be considered inactive (OFF) during the simulation.
You have the opportunity of defining specific periods of unavailability of the system. As this is usually unpredictable, it is also possible to ask PVsyst for creating these periods in a random
way (up to 5 periods of any duration along the year).
The effective energy loss is of course depending on the season, the day/night, or the weather during the unavailability periods. Therefore the energy loss evaluated by the simulation will
not correspond to the specified unavailability time.
Therefore the unavailability loss has only a statistical meaning.
NB: Due to its statistical nature, it is indeed not possible, in the present time, to specify an annual predefined value for this loss.
You can do that by manually adjusting the periods, by Try-and Error.
Simulation
When all necessary simulation parameters are defined and there are no error messages (LED's are all green or orange), the program will activate the buttons which allow to start the
simulation.
You can either use the quick simulation button directly, which will launch the simulation with the current settings, or alternatively, you can go to 'Advanced simulation' where you can
perform advanced configurations prior to simulation, or access the tools for multiple simulations.
The simulation process involves several dozens of variables, out of which a subset are stored in monthly or hourly values in the results file, and will be available for generating the
tables and graphs in the report and detailed results window.
After completion, the simulation allows for opening the "Results" dialog.
Simulation results for a particular "variant" are stored, with all involved parameters, in a file named as the project's file, with the extension .VCi (i = 0..9, A..Z).
Then the hourly simulation performs the following steps, for each hour:
Incident "effective" energy calculation
- Reading one hour data on the Meteo file (Horizontal global irradiance, temperature, eventually diffuse irradiance and wind velocity).
- If the diffuse irradiance is not available, it is computed with the Erbs (near to Liu-Jordan) correlation model,
=> defined variables at this stage: GlobHor, DiffHor, BeamHor, T Amb, WindVel.
- Performs the transposition (global, diffuse, albedo irradiances) in the collector plane, using either Hay or Perez model according to your user's preference.
This is done using solar angles at the middle of the time interval, taken from the meteo file (with possible time shift if defined in your meteo data).
=> defined variables at this stage: GlobInc, BeamInc, DiffInc, DiffSInc, AlbInc,
- If horizon is defined, applies the horizon correction on the beam component (ON/OFF),
- If near shadings defined, applies the shading factor on the beam component (from the Shading factor table, or recalculated) => evaluation of the "Linear" shading loss (loss due to
the irradiance deficit).
- Applies the IAM factor on the beam component.
- Applies the diffuse and albedo attenuation factors (previously computed) on Diffuse and Albedo parts.
- If soiling defined, applied the soiling factor to all components (global, diffuse, Albedo).
=> defined variables at this stage: GlobEff, BeamEff, DiffEff, Alb_Eff,
This leads to the so-called "Effective incident energy", i.e. the irradiance effectively reaching the PV cell surface after optical corrections.
Other secondary variables (essentially ratios of the above energy quantities) are available for displays:
=> Bm/Gl, Diff/Gl, DifS/Gl, Alb/Gl, Ftransp, FIAMBm, FIAMGl, FShdBm, FShdGl, FIAMShd.
Array MPP "virtual" energy EArrMPP and effectively used energy EArray
For each sub-array (i.e. each orientation independently), the simulation calculates:
- The array temperature TArray (energy balance between absorbed and heat loss energy),
It applies the one-diode model for the module, and evaluates:
- The MPP operating point of the array, calculated by the one-diode model if the system was running at STC efficiency (1000 W/m² and 25°C).
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 147 of 174
- The irradiance loss, i.e. the loss due to the low-light performances of the module.
- The temperature loss due to the cell's temperature TArray.
- The spectral loss if defined (amorphous modules or Sandia model).
- The electrical mismatch loss due to shadings
- The module quality loss.
- Eventually the LID loss if defined.
- The Mismatch loss.
- The Array wiring loss.
This results in the MPP virtually available energy EArrMPP.
This is not necessarily the true Array output energy:
- The operating point may be displaced by the rest of the system (inverter in overpower or other limit conditions, direct coupling on the battery, etc), resulting in a MPPLoss.
- The energy may be unuseable if the battery or water tank is full: this will lead to EUnused loss.
The energy really used by the system is called EArray.
For sub-array with mixed orientations, the whole meteo calculation is repeated for the second field orientation, output meteo variables are accumulated as averages between the two
orientations, weighted by the field area ratio.
Then both array characteristics are electrically combined (on a same inverter input), in order to search the real maximum power point. The loss with respect to a common orientation is
accounted as "MixLoss". It is usually negligible or very close to 0, as the mismatch when combining two different sub-arrays in voltage is very low.
System energy
The next simulation stages are system dependent :
- Grid connected system,
- Stand-alone system,
- Pumping system,
- DC-grid system.
NB. All energies are calculated here as average power during one hour. They are expressed in [kWh/h] or [MJ/h], that is in a power equivalent unit. Therefore with hourly steps Power and
Energy hold the same numerical values. Although most calculations are indeed related on power quantities, we will express them as energies for simplification.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 148 of 174
Advanced simulation
This dialog is used to make advanced configurations for the simulation execution. It also contains special tools that allow to perform multiple simulations in one go, namely the batch mode,
the optimization tool and the aging tool.
Simulation parameters
This group gives an overview of the main properties of the simulation configurations. The title of the variant can also be changed here.
Simulation dates
These two values specify the time range over which the simulation will be performed. The default values, that can be reset by clicking on the check-boxes, are the first and the last day in
the Meteo file. You can only choose start and end dates from within the range of dates in the meteo file.
Advanced tools
This group contains several buttons that give access to dialogs for advanced simulation configurations and execution of multiple simulations.
The simulation process involves several dozens of variables, which are not all stored in the simulation results within the variant file. Data of interest to the user should be defined before
the simulation, in order to be accumulated during the simulation process. PVsyst offers several ways for the output of detailed hourly or daily data as explained in the following.
Output File
The output file dialog provides a way of exporting hourly or daily data to another software (spreadsheet, e.g. Microsoft Excel). The user can choose the variables to be written in monthly,
daily or hourly values into this text file, which is then generated during the simulation process. The checkbox 'Enable output file' indicates whether the text file generation is active:
Special Graphs
The special graphs dialog allows to define graphs like histograms, scatter plots, ordered values, time evolution, etc, in hourly or daily values, and possibly with specific constraints. These
plots will be generated during the simulation process.
About ten specific and commonly used graphs are already defined by default, and will be created for every new simulation.
Comparisons
The comparison dialog is only used when a comparison with measured data is performed. It allows to define the data selections for the comparison plots.
Batch Simulation
for parametric analysis: allows to pre-define variations of some parameters on an EXCEL document, and perform series of simulations. Some main results (customized list of variables)
are gathered in this EXCEL document for immediate analysis (see Batch mode).
Optimization Tool
The optimization tool is used for performing parametric scans that allow to study the sensitivity of the simulation results on certain parameters like tilt, azimuth, pitch, etc.
Aging Tool
With the help of the aging tool, you can perform multi-year simulations that take into account the aging of the PV modules.
General
For this please use "Advanced simulation > Output file" in the main project's dialogue.
The variables desired in the Output file should be defined before the simulation. The file will be generated during the simulation process.
For activating the generation, you have to check the radio button "FileName", top left of the dialog. This will activate the generation during the next simulation, this option will be reset after.
Therefore you have to explicitly reopen this dialog and re-check this option if you want to create a new file for a new execution of the simulation.
Reading in EXCEL
This will create a CSV file ("Comma Separated Values"), misnamed as most of the times the separator is a semicolon.
Remember that this file is a CSV file, not an XLSX file. When opening it in EXCEL, you should choose this extension as filter.
Pay attention to the decimal character (dot or comma) in your EXCEL program (depending on Windows international settings). This should be specified here. If it is not correct, in EXCEL
all cells including this character will not be recognized as numbers, and will appear as Left-aligned. These values will not be included in the sums or other EXCEL calculations, leading to
erroneous sum values.
When reading it in EXCEL, it will sometimes appear as one only column. You have to use the EXCEL tool "Data > Convert" for transforming it into columns.
Procedure
The left side of the dialogue shows the file and format properties. The right side contains the variable selection.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 149 of 174
Load the file format and the variable selection from a template.
Save the file format and the variable selection as a template that can be reused in other variants or projects.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 150 of 174
- Ordered values are histograms in which each class accumulates all lower values, and therefore give the distribution of values lower than a given value. The necessary definitions
are the same as those for histograms.
- Please also give a name, which will be the plot title in outputs. You can use the button at the right to produce an automatic plot name.
Models
The user has the opportunity of saving the definition of each plot in a library, to reuse it in other projects.
Please note that the definitions of histograms will have to be updated according to the size of each system. However the histograms defined as default are automatically updated.
Detailed procedure
Just before the simulation, button "Batch simulations".
1 - Batch CSV files page:
- Input file: this indicates the CSV file to be defined for the parameters (fixed name, with BatchParams tag, always located in \UserBatch\ )
- Output file: this indicates the output CSV file ( (fixed name, with BatchResults tag).
- You may specify several locations. This can be used, for instance, to challenge several geographical options for your project. In this mode PVSyst first checks if the specified sites exist in
the database. If so, 2 possibilities :
- at least one meteo file (.MET) is available in the surroundings *. The nearest meteo file is then selected.
- no meteo file available in the defined area. PVSyst will generate a synthetically meteo file using the Meteonorm Dll.
- Choose if you want to start from VCi base files that differs from the current selection.
- Choose if you want to save the simulation version files (*.VCi).
- Consider the possibility to create hourly output files
(*) Default setting is 15km. This limit may be changed, see the Hidden parameter "project site - Meteo distance for auto synthetic proposal" - category Miscellaneaous : meteo,
simulation,...)
Plane orientation
- Modify tilt and azimuth for fixed tilt orientation (presently limited to a single orientation) plus shed characteristics (pitch, electrical effect) if unlimited sheds defined.
3D shadings parameters
- Sheds: define pitch, collector width,
- Tracking: pitch between trackers or rows, backtracking, stroke angles, etc
System parameters
- PV module type, number in series and number of strings, module quality loss.
- Inverter type, number of devices.
If you think other parameters are worthwhile to be varied in this tool, don't hesitate to ask us.
3. - Results variables specifications page
You can choose here any simulation variable, to be mentioned in the results of the CSV file as yearly results.
Optimization Tool
Overview
This tool helps to easily find the optimal values for some of the design parameters of a PV installation (especially shed-type installation for now).
It performs automatically a set of simulations, where one or more parameters are varied systematically according to a specified range.
The results of all simulations are stored, and can be viewed in a separate tab, which will plot several simulation variables as function of the varied parameters.
In contrast to the optimization tools of the 'Orientation' dialog, which perform approximations for their calculations, this tool will run a full simulation for each of the parameter settings,
allowing an even more precise result.
So far, the optimization tool is only available for projects that use 'shed' PV fields in the 3D scene.
The Optimization Tool dialog contains two tabs, one to create new parametric scans, the other one to view the scans that have already been performed.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 151 of 174
Enter a name for the scan that will be performed. This name will appear in the list of executed scans, once the scan is finished.
2. Select the Scan parameters
Use the combo-boxes on the left to select the parameters that should be used in the scan.
The available parameters depend on the type of project that is being used. The pitch parameter for example can be used only in projects where sheds are defined in the 3D near shadings.
The following parameters are available so far:
1. Tilt: This parameter is available for all projects with fixed tilt orientation or unlimited sheds.
2. Azimuth: This parameter is available for all projects with fixed tilt orientation or unlimited sheds.
3. Pitch: The pitch is the distance between two sheds (rows) of a PV installation. This parameter is available for projects where sheds are defined in the 3D near shading scene.
4. Ground Covering Ratio (GCR): In shed layouts, the GCR is defined as ratio of the width of the sheds and the pitch. This parameter is an alternative way to describe the Pitch.
For each parameter you have to define the start and end values (Min, Max) and the number of steps that should be performed. The sketches on the right side of the window visualize the
selected parameter ranges. The start and end values are drawn in gray, and the value used in the underlying variant is marked in blue.
3. Check Time Estimate
When all the scan parameters have been defined, check the estimated time display on the bottom, to get an idea of how long the scan will take. This estimate is based on the last
execution of the simulation. If the variant has not been simulated yet, the time estimate will not be available. Depending on the number of steps that were chosen for each parameter, the
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 152 of 174
scan time can become very long. In this case, consider reducing the number of steps for the parameters. To save time, you can go in several iterations, by performing first a coarse scan in
large steps, and then perform the subsequent scans in a more narrow range of the parameters with smaller steps.
4. Execute the Scan
When parameter ranges and numbers of steps have been defined, click on 'Run' to start the scan. On the right side of the parameter definitions a column with title 'Current' will appear,
displaying the parameter combination that is currently being simulated. A double progress bar will show how much of the overall scan and of the current scan step has already been
processed.
If during a scan, a combination of parameters is such, that a simulation is not possible (e.g. a pitch that is too short for a given tilt angle), this scan step will be skipped. In the results
viewer, this step will be omitted in the one-dimensional plots and be grayed-out in two-dimensional plots.
When the scan starts, the label on the 'Run' button will change to 'Abort'. When clicking on it, a confirmation dialog will pop up, and if confirmed, the scan will be aborted. Any results that
were calculated up to then, will be lost.
Once the scan is finished, the dialog will switch automatically to the 'View Existing Scan' tab and the results will be displayed.
The optimization viewer displays the results of the parametric scans performed with the 'Optimization tool'.
It helps in quickly identifying the optimal values of the parameters for a given simulation variable.
Scan Selection
The top left part in the tab gives an overview of the scans that have already been performed.
From the drop-down list on the left, a scan can be selected by its title. The parameter ranges that were used for the selected scan are displayed in five columns below the name.
The parametric scans are specific for each variant of the project, this is why the list will only display scans that have been performed for the current variant.
There is the possibility to remove the selected scan from the list by clicking on the 'Delete Scan' button. A message will pop up, asking to confirm the deletion of the scan.
The left part of the viewer allows to specify the parameters and plot options. The variable that is plotted can be chosen from a list on the top, next to the title of the plot. The plot itself is the
square area, containing axes, the curve or color map and a legend in case of a two-dimensional plot.
Result Variable
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 153 of 174
During the simulation, several variables are computed for the final and intermediate results. The following variables are stored in the optimization scans and can be selected from the
variable list:
GlobInc: Global incident irradiance, also known as Plane of Array (PoA) irradiance in kWh/m2
GlobEff: Global effective irradiance
EArray: Effective energy at the array output
E_Grid: Energy injected into the grid in kWh
By default the E_Grid is selected for display.
Plot Type
The results can be displayed either in a one- or a two-dimensional plot. The 1D-version is a curve of the result variable as function of one of the parameters. The 2D-version is only
available, if two or more parameters were scanned. It consists of a colored surface with one parameter on each axis and the variable value being color-coded. The color code ranges from
dark blue for small values to dark red for high values.
1-Dimensional Plot
2-Dimensional Plot
Axes
In this group the axes are associated to parameters that were varied in the scan. In a one-dimensional plot, only one parameter for the X-axis needs to be chosen, for two-dimensional
plots, parameters have to be associated to both, the X- and the Y-axis.
Non-displayed parameters
If more than one parameter was varied within a scan, it can happen, that one or more parameters are not associated to any of the axes. These are the 'non-displayed parameters'. In this
case, a field with a spin button and a slide bar will appear in this group for each non-displayed parameter. These controls allow to set a value for this parameters, and the plot will be
updated accordingly.
Additional options
The additional options control some details in the plot region.
Maximum: If this option is checked, the maximum value in the plot will be marked with a red dot, and its values of the parameters and variable will be displayed in a text box
Full Range Scale: If this option is checked, the range of the scale for the variable will be chosen so that it covers all values from the scan. Changing the non-displayed parameters will
have no effect on the displayed variable range. If on the other hand this option is unchecked, the range of the Y-axis for 1D plots and the range of the color code for 2D-plots will adapt to
best cover the values that are actually displayed. Changing the values of the non-displayed parameters will now change these ranges.
Ageing Tool
Overview
This tool describes the performance evolution of your PV system along the years, when taking the PV modules degradation and the increasing mismatch into account.
For the moment this tool is only available for Grid-connected systems.
This analysis may be performed:
- either from a single meteo data file (usually the meteo source of your project), which should ideally be an "average" or TMY year.
- or, if you avail of meteorological data for a series of years, it may be applied to each real meteo data file for the series years. This may be useful for analyzing the historical evolution
of an existing system, with the real data.
With a single meteo data file, simulating all the years is not necessary: you can simulate some years, and interpolate between these simulations. ,
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 154 of 174
Procedure
This tool is an addition to a "normal" simulation: it is only available when the simulation of your project has been successfully done.
Therefore if you change a parameter in your simulation, this tool will be erased, you will have to re-simulate it with the new parameters after performing the new simulation
When entering this tool, the blue panel (top right) will indicate what to do.
1. - You have to define the basic degradation parameters (module degradation rate, mismatch evolution). If you have already defined the degradation in the "detailed losses" of your
main simulation, this will take these parameters as initial values. But you can define any other ones for this tool.
2. - A tree view will show all the available meteo data files available in the vicinity of your project. There may be single generic files, or series of yearly meteo data. Note that only the
files containing a full year of data are available here.
3. - You should select the meteo or groups of yearly meteo that you want to simulate. It is possible to simulate up to 2 groups at a time.
4. - With single meteo files, you may specify the total number of years to be analyzed, as well as the time interval between the simulations really executed. The intermediate years will
be interpolated.
5. - It is possible to create specific variants, generate reports or generate the hourly output files (if available in the original simulation) for chosen simulations. For this simply click on
the corresponding cases in the table..
6. - When everything is ready, click on "Run simulation".
Results
After the simulation you directly obtain the results, as a table and 2 graphs.
You can choose the variable to be shown on the first graph The second graph will always show the evolution of the PR.
Besides the PR and its loss percentage evolution, you can get up to 3 chosen variables on the table.
All these results will be shown on the report (2 pages).
Export: The button "Copy the table" allows to paste the table directly in EXCEL.
NB: it is always possible to retrieve the input parameters by clicking the button "Show parameters".
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 155 of 174
Results
The simulation results are summarized in a printable "Report", which holds an exhaustive table of all parameters used during the simulation, as well as a short description of the main
results.
But many other results may be visualized and printed:
The simulation involves several dozens of variables, which are all stored in monthly values in the "Simulation variant" MyProject.VCi file.
These monthly results are available as:
- Pre-defined tables: several tables, grouped by parameter themes, are immediately available.
- Custom table: you can build your own monthly table by choosing eight among any of the calculated variables.
- Custom monthly graphs: you can choose up to 4 variables to be simultaneously displayed. Be sure to choose comparable variable types (energy, irradiation, etc) as the graph holds
only one common axis.
Moreover, hourly values are stored for some pre-chosen variables. These give rise to hourly and daily plots (even with simultaneous variables) with a comfortable navigation all over the
year. This constitutes a powerful tool for observing and understanding the instantaneous system behavior.
Special graphs may be defined before the simulation, in order to be accumulated "on-line" during the simulation process. About ten such "on-line" graphs of general use are present by
default with any new simulation.
They include a detailed energy loss diagram, Monthly or Daily normalized "yield" indicators index, performance ratio, input/output diagram, incident energy and array output distribution,
etc.
Economic evaluation
After the simulation you can perform a detailed economic evaluation of your project, taking the parameters (for example nb. of modules, inverters…) and results into account.
Printing
You can choose to print the following forms:
- General simulation parameters, which summaries all the parameters involved in a "variant",
- Detailed simulation parameters, such as Horizon (drawing+points table), Near shadings, detailed user's needs, etc,
- A pre-defined form with the main parameters and main results of this simulation,
- The detailed loss diagram,
- Any specific result graph or table displayed on the screen, along with the main parameters,
- The economic evaluation sheet.
In Report Preview dialog, you can compare reports of different projects and variants.
The Result dialog offers the possibility of recalling other "variants" of the project, in order to perform quick comparisons.
Loss diagram
The loss diagram provides a quick and insight look into the quality of a PV system design, by identifying the main sources of losses.
It is always present on the Simulation report, for the whole year. It is also available for each month, using the buttons "Detailed results > Predefined graphs" in the project's dialog. This
allows to evaluate the seasonal effect and impact of the different losses.
Please refer to Array losses, general considerations for a general explanation of the losses in PVsyst.
The array losses start from the rough evaluation of the nominal energy, using the global effective irradiance and the array MPP nominal efficiency at STC. Then it gives the detail of the
PV model behaviour according to the environmental variables.
In stand-alone systems, the diagram gives a detail of the battery use, that is which part of the energy effectively transits by the battery. Minimizing the battery use is of some importance for
the lifetime (number of charge/discharge cycles).
NB: Each loss is defined as percentage of the previous energy quantity. Therefore the percent values are of course not additive: when grouping the losses, the overall percentage is not
the sum of the detailed values!
NB: The accounting of the individual losses is far from being a trivial problem! The simulation process and some variable definitions had to be deeply reformulated for obtaining a coherent
figure.
And some contributions are impossible to evaluate rigorously. For example in stand-alone systems, the ohmic losses are evaluated using the usual relation Ploss=R * I². But in reality
the array resistance modifies the PV operating point and the whole circuit equilibrium, so that a more accurate calculation would probably be simulating the complete system with and
without this resistance, and evaluate the differences. But even with this method, some loss contributions will be transferred to other ones.
By the way, even if some individual losses are not quite well determined, the Energy values at each main step of the simulation are in principle correctly calculated.
You can refer to the following pages for a detailed description of the individual variables:
- Meteo, irradiation and PV array,
- Grid connected system,
- Stand-alone system,
- DC-grid system.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 156 of 174
Performance Ratio
See also the previous page Normalized Performance index.
The Performance Ratio is the ratio of the energy effectively produced (used), with respect to the energy which would be produced if the system was continuously working at its nominal
STC efficiency. The PR is defined in the norm IEC EN 61724.
In usual Grid-connected systems, the available energy is E_Grid. In stand-alone systems, it is the PV energy effectively delivered to the user, i.e. E_User - E_BackUp. In pumping
systems, this is E_PmpOp.
The energy potentially produced at STC conditions is indeed equal to GlobInc * PnomPV, where PnomPV is the STC installed power (manufacturer's nameplate value). This equivalence is
explained by the fact that at STC (1000 W/m², 25°C) each kWh/m² of incident irradiation will produce 1 kWh of electricity.
Therefore for a grid-connected system:
PR = E_Grid / (GlobInc * PnomPV)
Interpretation
The PR includes the optical losses (Shadings, IAM, soiling), the array losses (PV conversion, aging, module quality, mismatch, wiring, etc) and the system losses (inverter efficiency in
grid-connected, or storage/battery/unused losses in stand-alone, etc).
Unlike the "Specific energy production" indicator, expressed in [kWh/kWp/year], this indicator is not directly dependent on the meteo input or plane orientation. This allows the comparison
of the system quality between installations in different locations and orientations.
Namely, the PR is not dependent on the PV module efficiency. As an example an amorphous module and a crystalline high-efficiency module will lead to comparable PR. Only the low-
light performance and temperature dependency will induce differences.
A tracking system will have a similar PR than a fixed sheds arrangement. Even sometimes slightly lower because the array temperature (related to GlobInc) may be higher.
With equivalent yield performances, a tracking system with backtracking will have a significantly higher PR than a non-backtracking one, because the effective irradiance in the collector
plane is lower (due to the not optimal orientation). In a conventional tracking system the mutual shadings highly affect the PR.
In big systems (sheds or trackers), the far albedo is only "seen" by the first row, so that its effect is negligible (shading factor = (n-1)/n, where n = nb. of sheds). Therefore if you increase
the albedo in your project, the GlobInc value will increase, the albedo loss will increase for a same production, and the PR will decrease.
Self-consumption and storage
The PR is an indicator of the availability of solar energy for final uses. Therefore, when a part of the energy is used internally (E_Solar), this should obviously be included in the PR
evaluation. With systems including a storage, the storing losses (battery charge/discharge inefficiency, DC-AC and AC-DC conversion devices) should also be included in the PR.
Therefore in the above formula, the E_Grid should be replaced by E_Grid + E_Solar :
PR = (E_Grid + E_Solar) / (GlobInc * PnomPV)
Bifacial PR
If the above definition of the Performance Ratio calculation is applied to bifacial systems, then the bifacial contribution from the rear side of the PV modules will become a gain, which will
increase the PR. For systems with high tilt, like for example East-West facing vertical PV systems, this can easily lead to PR values larger than 100%. Conceptually this poses no problem,
as long as the bifacial contribution is just interpreted as a gain.
The revised IEC 61724 -1 standard (Ed.2 from 2021), introduces the concept of a bifacial Performance Ratio. The basic idea is that the additional irradiance contribution on the rear side of
the PV modules is added to the Global incident irradiance.
This is problematic if the PR value is used to compare different system designs, since the rear side irradiance depends on design choices like mounting height, row spacing and PV
module tilt and azimuth. Section 8.2.3.2 in the IEC standard specifies that the rear side irradiance contribution is to be measured on PV modules close to the center of the PV system, and
without exceptional sources of shadings, as to ensure "representative" conditions. This definition however leaves a wide margin of interpretation. Furthermore, the rear side irradiance
distribution is non-uniform by nature, and it is not possible to define a single representative measurement spot for all sun and weather conditions.
Another ambiguity of the IEC standard is in the use of the bifaciality factor as a multiplicative factor for the backside irradiance. Main paragraph §3.20 implies that the sum of front-side and
backside irradiances is to be considered, and this is the choice made in PVsyst (see formula below). However, notes 1 and 2 of §3.20 indicate that the bifaciality factor may be included in
the definition as a multiplicative factor for the backside irradiance. When measuring the total effective irradiance with a bifacial reference device such as a bifacial reference cell, this
second option may be the most natural one.
In PVsyst, in order to calculate the bifacial PR, the rear side irradiance is approximated as GlobBak + BackShd, where GlobBak is the effective irradiance on the rear side of the PV
modules, and BackShd are the losses induced by the 'Structure shading factor' in the bifacial model definitions.
The bifacial PR then becomes
PRbifi = PR / (1 + (GlobBak + BackShd)/(GlobInc))
Please note, that this concept of bifacial PR is by nature blind to changes in ground albedo, mounting height and to the effect that row spacing and PV module orientation have on the
bifacial contribution.
In the simulations of bifacial systems, the bifacial PR calculation will be displayed separately in the main results summary. By definition, it will be smaller than the standard PR value.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 157 of 174
Mathematically, if the TArrayAver is calculated with the same data, the yearly PR(corr) value should be equal to the yearly PR.
We have implemented this in the PVsyst version 6.74. However the result is not so convincing, because in most PV systems, other contributions are season-dependent.
With shed-systems, applying this PR correction seems to over-correct the PR seasonal behavior. This is due to the mutual shadings, which are more pronounced in winter.
This correction is almost unusable with tracking systems, as the seasonal variations due to tracking are largely dominating the temperature effect.
Therefore these results will be available on the report only when you ask it in the "Report Preferences", menu "Settings" in the Report editing window.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 158 of 174
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 159 of 174
Efficiencies
EffArrR Array Efficiency EArray / rough area
EffArrC Array Efficiency EArray / cells area (=0 when cells area not defined)
EffSyR System efficiency EOutInv / rough area
EffSyC System efficiency EOutInv / cells area.
EffInvB Inverter efficiency Threshold loss included
EffInvR Inverter efficiency When operating
Normalised performance index (cf IEC EN 61724, usually expressed and plotted as values per day)
Yr or Reference Incident Energy in collector plane = GlobInc [kWh/m²] (kWh irradiance)
Yr Normalized Reference nominal energy at STC = EArrRef / PNomArray [kWh/kWp] (kWh electrical)
Ya Normalized Array Production = EArray / PNomArray [kWh/kWp]
Yf Normalized System Production = EGrid or EAvail / PNomArray [kWh/kWp]
Lc Normalized Array Losses = Yr - Ya
Ls Normalized System Losses = Ya - Yf
PR Performance Ratio = Yf / Yr = E_Grid / (GlobInc * PNomArray)
NB: The Normalized Reference nominal energy at STC Yr [kWhel/kWp] is the electrical energy which would be produced by the Reference incident energy on the collector plane under
STC conditions (1 kWirrad/m2, 25°C). This explains that the values are identical.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 160 of 174
EArrMPP Array virtual energy at MPP (after wiring, module quality and mismatch losses),
Virtual calculation independent of the system running and voltage operation
EArUfix Array virtual energy at fixed voltage
Voltage as calculated by the balance loop (real battery voltage),
or Battery reference voltage when PV-array disconnected.
EUnused Unused energy (full battery) loss (EArUFix when Charging OFF)
MPPLoss Loss with respect to the MPP operation (when charging ON)
Earray Effective energy at the output of the array (when charging ON)
IArray Array Current (accumulated in Ah)
UArray Array Voltage (average when Charging ON)
ArrayON State / Duration of the PV production of the array
If converter present: converter losses
CL Oper Converter loss during operation (efficiency curve)
CL Pmin Converter Loss due to power threshold'
CL Pmax Converter Loss due to power overcharging
CL Vmin Converter Loss due to low voltage MPP window
CL Vmax Converter Loss due to upper voltage MPP window
CnvLoss Global converter losses
OutConv Energy at converter output
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 161 of 174
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 162 of 174
ELowLev Energy lost when Pump stopped due to low level aspiration (deep well, drawdown safety)
ETkFull Energy lost when Pump stopped due to tank is full
These two above losses are accounted only when the battery charging is OFF due to full battery.
EArray Effective energy at the output of the array (at operating voltage)
Accounted only when the charging condition is ON
IArray Corresponding charging current, instantaneous [A] or cumulated [Ah].
UArray Corresponding charging voltage, instantaneous or averaged [V].
SOC_Beg State of Charge, beginning of interval
SOC_End State of Charge, end of interval
UBatt Average battery voltage
IBatCh Battery charging current [A or Ah]
IBatDis Battery discharging current [A or Ah]
IBEffL Battery Charge/Discharge current efficiency loss
IBGass Gassing current (electrolyte dissociation when full)
IBSelf Battery self-discharge current
EBatCh Battery charging energy
EBatDis Battery discharging energy
ESOCBal Stored energy, Balance between SOCEnd and SOCBeg
EBatLss Battery Overall energy loss (EBatCh - EBatDis - ESOCBal)
EEffLss Battery efficiency loss (EBatLss - (IBGass+IBSelf) * UBatt
EPmpOp Pump operating energy
NB: The balances of the battery energies can never be rigorous due to the very complex behaviour of the battery. For example its effective capacity, which strongly varies with the
discharge current, the temperature, etc. If the current balances are well determined in the simulation process, the corresponding energies involve the operating voltage, which is
also model-dependent and varies with state of charge, charge and discharge currents, etc.
A lot of further (secondary) variables are available for results, which are not described here.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 163 of 174
Distributions - Histograms
Main definition
Many graphical results are presented as histograms (bar charts).
An histogram is a graph describing the distribution of a resulting accumulated variable (for example energy) as a function of a state variable (for example power).
The accumulated variable is stored in "bins" (also named bars or classes), according to some operating condition defined as the abscissa.
Cumulative distribution
In the cumulative distribution, each class contains the total energy of all running situations when the power was superior to the considered class power.
Therefore the first class contains the whole production of the year (here about 1.7 GWh).
We can observe that 0.92 GWh are produced when the system operates higher than 600 kW, i.e. 54% of the production.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 164 of 174
The annual production distribution as a function of the Power may be quite different according to the system kinds.
Installation at Marseille
Let's take as example a simple PV plant installed at Marseille (Europe, 43.5° latitude) with:
- Installed power PNomPV = 1.126 MWp
- Inverters PNom = 1 MWac
We can observe that the nominal PV power at STC (1.126 MWp) is never attained in any configuration.
This is partly due to the fact that the maximum irradiance on a tilted plane is of the order of 1000 W/m2 - rarely more. And the STC performance is specified for an array temperature
of 25°C, when the usual array temperature at full sun is of the order of 55-60°C. With a temperature coefficient of -0.34 %/°C, this represents a power loss of 10 to 12%.
But this is also due to the fact that the sun's rays are rarely or never perpendicular to the PV plane. In this respect, the best situation is the fixed planes (sheds) at 20° tilt. The domes
are never well oriented, so that the production is limited to around 850 kW. The trackers with horizontal axis are horizontal in the middle of the day, therefore not perpendicular to the
sun (except in subtropical regions); we see that the significant high power situations are slightly lower than for the sheds (limit at around 900 kW).
The global distribution is also rather different:
The sheds layout shows a global production rather proportional to the instantaneous power, up to about 800 kW. This is a consequence of the frequency distribution, rather constant
for this climate (see the previous page Histograms).
The domes production is enhanced at lower powers, as systems in both orientations are not working at the same time. The average operating power is lower, but better distributed in
the day 8morning and evening).
As expected, the trackers have a very high production distribution at higher powers.
Installation at Dakar
If we do the same exercise, with the same systems, at Dakar (Latitude = 14.8°, subtropical):
Economic evaluation
After simulation, an economic evaluation of the system may be performed on the basis of the defined parameters and the simulation results. The economic tool is accessible in the
"Project" dialog. It allows to define the initial installation costs and the yearly operating costs in order to calculate the cost of produced energy LCOE (Levelized Cost Of Energy). The tool
may estimate a long term profitability based on initial costs, yearly charges, financial parameters and tariffs. It provides detailed financial results such as ROI (Return On
Investment), payback period and NPV (Net Present Value).
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 165 of 174
Installation costs
This section determines direct and indirect installation costs of the system.
This includes component costs (modules, inverters, batteries, pumps, controllers, generator), expenses for studies and analysis, administrative fees (grid-connection cost, bank charges,
permitting, taxes), insurances, land costs, substitution credit and subsidies. The number and type of PV involved components (PV modules, inverters, batteries, etc.) are automatically
updated from the simulation parameters.
Depreciable asset :
Depreciation is an accounting method of allocating the cost of a tangible asset over its useful life and is used to account for declines in value. The yearly depreciation allowance is tax
deductible and decreases the taxable amount.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 166 of 174
When the depreciation allowance becomes lower than the straight-line depreciation allowance, the straight-line method is applied for last years of the project.
Add/delete/update costs
The predefined cost list is fully customizable to take into account any specific cost of your system which is not present in the predefined list. You can add, remove, reorder or rename costs.
You can also save defined cost list as template in order to reuse them in another project.
Select all
Selects all the investment costs to be deleted, edited or moved.
Unselect all
Unselects all the selected costs. This button is disabled if no cost is selected.
Move up
Moves up selected costs. The investment costs list displayed in the printed report uses this order. This button is disabled if no cost is selected.
Move down
Moves down selected costs. The investment costs list displayed in the printed report uses this order. This button is disabled if no cost is selected.
Update cost
Opens the installation cost edition dialog to update properties (name, section, type) of a selected cost. This button is disabled if no cost is selected or more than one cost
are selected.
New cost
Opens the installation cost edition dialog to add a custom cost if it is not existing in the predefined list.
Delete cost
Deletes selected installation costs from the list. This button is disabled if no cost is selected.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 167 of 174
Saves all defined installation costs in a template file in order to be reused later or in a different project.
Operating costs
This section defines the annual running expenditures of the system.
As for installation costs, operating costs are fully customizable to fit the specific needs of your system. The total sum of operating costs is called OPEX (for Operational Expenditure).
Select all
Selects all the operating costs to be deleted, edited or moved.
Unselect all
Unselects all the selected costs. This button is disabled if no cost is selected.
Move up
Moves up selected costs. The operating costs list displayed in the printed report uses this order. This button is disabled if no cost is selected.
Move down
Moves down selected costs. The operating costs list displayed in the printed report uses this order. This button is disabled if no cost is selected.
Update cost
Opens the operating cost edition dialog to update properties (name, section, type) of a selected cost. This button is disabled if no cost is selected or more than one cost
are selected.
New cost
Opens the operating cost edition dialog to add a custom cost if it is not existing in the predefined list.
Delete cost
Deletes selected operating costs from the list. This button is disabled if no cost is selected.
Financial summary
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 168 of 174
The Total yearly cost is the sum of running costs and loan annuities (defined in Financial Parameters). It is an annual average value on project duration including the inflation rate if
defined.
The LCOE (Levelized Energy Cost) is the price of the produced kWh. It takes into account the present value of future cashflows by applying a Discount Rate.
The formula used in Pvsyst for LCOE calculation is :
The Payback period is the duration required to recover the initial investment.
Financial parameters
Simulation period
Project start time and lifetime
Tax depreciation
This section contains the list of installation costs for which depreciation has been defined and the total redeemable value (total depreciable amount over the project lifetime).
See Investment and charges section for the procedure to set the depreciation for each asset.
Financing
This section defines the source of funds used to finance the investment. Pvsyst allows to define three source of investment : Own funds, Subsidies and Loans. The total sum of financing
funds must be equal to the total installation costs defined in Installation and operating costs dialog.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 169 of 174
Own funds : total amount used from the capital of the company or from external investors.
Subsidies : total amount granted by the state or a public body.
Loans : amount borrowed from a bank or any lending agency. Pvsyst allows to define up to three loans with different types.
- Redeemable with fixed annuity : the reimbursed annuity is the same every year during the loan duration. The cost of interests is declining over the repayment period.
Annuity = [borrowed amount x rate] / [1 - (1 + rate) - duration in years]
- Redeemable with fixed amortization : the reimbursed amortization part is the same every year during the loan duration. Annuities are higher at he beginning of the repayment period and
are falling over time
Annuity for year t = [borrowed amount / duration in years] x [1 + (duration in years - t) x rate]
- Interest-only bullet loan (also known as "in-fine" loan) : only interests are due during repayment period. Loan principal is reimbursed in full with a balloon payment at the end of loan
duration.
Annuity = borrowed amount x rate
Balloon payment at the end of loan = borrowed amount
Self-consumption economy
This concept is defined here with a consumption tariff when the owner is able to use the produced energy for himself (economy on the electricity bill), and another tariff for selling the
overproduction to the utility.
This calculation requires of course that the user's needs are specified, and computed during the simulation, and that these data are stored in hourly values.
These tariffs may also be modulated according to the day hour. The consumption tariff is likely to be increased during the next years; therefore an annual tariff evolution can be defined.
Financial results
This section summarize the profitability of the system. The most important results for makers are the net present value, the payback period and the return on investment ratio.
It also details annual balances between costs defined in Installation and operating costs section and revenues according to the pricing strategy defined in Tariffs section.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 170 of 174
Taxable income : annual amount on which the income tax rate is applied. There are many different and complex tax systems in the world. In most of them, interest part of the loan and
equipment depreciation are tax-deductible. Pvsyst tax calculation is based on this method.
Taxable income = Energy Sale Income - Running Costs - Loan Interests - Depreciation
After-tax profit : net income after charges and tax payment. This amount is the base for dividend calculation.
After-tax profit = Energy Sale Income - Running Costs - Loan annuity - (Taxable Income * Income Tax Rate)
Self-consumption saving : saving made on electricity bill by consuming produced energy. It represents the amount that would have been paid for buying the same energy from grid :
Self consumption saving for year t = Energy consumed from own production during year t x Consumption tariff
Payback period : duration in years required to recover the cost of the net investment defined in Installation and operating costs section. If the system is not profitable (more expenses than
income), the payback period is undefined.
The amount recovered each year is calculated by the formula :
Recovered amount for year t = Net balance of year t + Self-consumption saving for year t + Redemption part of the loan for year t.
Net balance of the year corresponds to the after-tax profit minus possible dividend payments.
Redemption part of the loan is the capital repayment of the borrowed amount (annuity excluding interest part).
Net present value (NPV) : the difference between the present value of cash inflows and the present value of cash outflows over a period of time
Internal Rate of Return (IRR) : value of the discount rate that makes the net present value (NPV) of all cash flows equal to zero
Return on investment (ROI) : ratio of net benefit against the initial investment which measures system profitability. A negative ROI indicates that the system is not profitable.
ROI ratio = Net benefit at the end of lifetime / Total investment
PVsyst calculations
Using the effective production given by the simulation, PVsyst shows the annual balance as well as the accumulated balance over the foreseen lifetime of the PV system, according to all
these strategies. It also shows details on an annual table.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 171 of 174
But be careful: these balances result in differences of large quantities, and little perturbations either on the real production or the effective costs may result in dramatic deviations of the
final profitability !
This is namely the case for the annual real irradiance variations, with respect to the meteo data used in the simulation. Failures of the system all over its lifetime may also significantly
affect the effective balance.
Procedure summary
For activating the P50 - P90 tool, please open the button "Energy Management", page "P50 - P90 estimation" in the grid's project dialog.
This should be done after a first simulation, since by default the P50 value corresponds to the simulation output.
First choose the "Kind of Data", which will impact how the P50 value is determined.
Then determine the shift, weather data annual variability, and other simulation uncertainties.
Finally, you may specify whether you want P90 or other values. The result will appear on the report if the parameters are correctly specified (no warning).
NB: This feature is not available for Stand-alone and Pumping systems, where it is more difficult to define.
Probability law
This approach supposes that over several years of operation, the distribution of the annual yields will follow a statistical law, which is assumed to be the Gaussian (or "normal") distribution.
P50/P90 represent different yield levels, for which the probability that the production of a particular year is over this value is 50%, resp. 90%.
The problem is now to establish the 2 parameters of this Gaussian distribution, i.e. the Mean value and the Standard deviation (named sigma or RMS).
The main contribution to those parameters will be the uncertainty and variability of the meteo data. But other uncertainties in the simulation process and parameters should be taken into
account.
Details
Variability determination
The annual variability (sigma value) will be dominated by the meteo year-to-year variability. This information is not commonly available.
- A report of Pierre Ineichen (2011) gives some evaluations for about 30 sites in the world. PVsyst proposes default values according to these data.
- The new version of Meteonorm 7.2, 7.3 and 8.0 provide this information for your site (see the "site definition" dialog, page "Monthly Meteo").
- Several meteo data providers can now deliver multi-year meteo data (sets of 15 to 25 years), that you can directly import in PVsyst (for example Solargis, 3-Tiers Vortex, Soda-
Helioclim, or other). If you avail of such meteo data for your site, you can calculate the RMS of the annual GlobInc distribution. You have a tool for doing this in PVsyst: please use
"Databases > Compare Meteo Data", and here choose the corresponding MET files for different years. You have an option "Histo and Probabilities" which shows the Gaussian
distribution, average and RMS.
Additional uncertainties in the simulation process could eventually be taken into account. These deviations should represent random variability of the uncertainty from year to year, not the
absolute uncertainty !
- PV modules model and parameters (the main uncertainty after Meteo)
- Inverter efficiency (negligible)
- Soiling and module quality loss (highly depending on the site conditions)
- Long term degradation This is not compatible with the P90 evaluation concept.
We don't know how to handle this in the present time.
- Custom other contributions
All these random contributions will add quadratically, giving a global standard deviation which may be applied for constructing the final Gaussian distribution function, and give estimation of
the P90 or any other Pxx indicator.
This is for very special uses: in usual situations, all these values may be let to null values.
NB: In the Gaussian distribution function, P90 represents a shift of -1.28 sigma, P95 => -1.64 sigmas, and P99 => -2.35 sigmas.
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 172 of 174
PVsyst shows a graphical representation of your choices, either as a Gaussian probability distribution for several years, or as the corresponding cumulative distribution (the integral of the
gaussian).
On this example, the simulation was performed using a specific year, which was supposed to be -3% below the yearly average. Therefore the P50 value is higher. A positive climate
evolution would have the same effect.
Playing with the uncertainty parameters is highly instructive about the representativity of the simulation result for the future years. It is interesting to observe that according to your
interpretation of the simulation result (i.e. E_Grid, fixed), the forecast productions distribution may move around your simulation result !
By the way the probability profiles for the determination of P90 are statistical estimations, which should be based on significant weather series (at least 15-20 years of meteo data).
But we don't avail of such generic data for monthly values, and this would be very dependent on the climate and the season.
If you want to do such evaluations, you should find monthly meteo data of 15 years or more for your site, and evaluate the probability distribution month-by-month.
Introduction
The Carbon Balance tool allows to estimate the saving in CO2 emissions expected for the PV installation. The basis of this calculation are so-called Life Cycle Emissions (LCE), which
represent the emissions of CO2 associated to a given component or energy amount. These values include the total life cycle of a component or energy amount, including production,
operation, maintenance, disposal, etc.
The reasoning behind the Carbon Balance Tool is, that the electricity produced by the PV installation will replace the same amount of electricity in the existing grid. If the carbon footprint of
the PV installation per kWh is smaller than the one for the grid electricity production, there will be a net saving of Carbon Dioxide emissions. Thus, the total carbon balance for a PV
installation is the difference between produced and saved CO2 Emissions, and it depends on four key factors:
E_Grid: The System Production, or energy yield, of the PV installation for one year as computed by the PVsyst simulation.
(Additionally, you can define an Annual Degradation, which is set to 1% by default, and which represents a yearly decrease of the energy yield due to aging of the PV
components).
System Lifetime: This is the lifetime of the PV installation given in years. It determines, together with E_Grid, the total amount of Energy that will be replaced by the PV installation.
Grid LCE: It is given in gCO2/kWh and represents the average amount of CO2 emissions per Energy unit for the Electricity produced by the Grid.
PV System LCE: It is given in tCO2 and represents the total amount of CO2 emissions caused by the construction and operation of the PV installation.
The difficulty of the calculation lies in finding appropriate values for the LCE of the different contributions. Often these figures are known with little precision. Furthermore they are very
specific to certain technologies or production methods. Last but not least, there can also exist controversy on how these numbers are or should be calculated, and different authors will
report different values.
The PVsyst tool will propose values for the Lifecycle Emissions related to the electricity that will be replaced by the PV installation (Grid LCE). These values are based on publicly available
data from several institutions (see below).
For the emissions associated to the construction of the PV installation (System LCE), no such values will be proposed for the time being. The PVsyst user will have to get those values
either directly from the manufacturers or suppliers of the different components, or to resort to dedicated databases like ECOINVENT, Carbon Trust, etc. As a first guideline a few example
values are For the future it is planned to include more LCE values directly into PVsyst, and which will also cover the System LCE.
As a general guideline we advise to crosscheck, if possible, the LCE values against up-do-date or more specific information from suppliers or manufacturers.
The Carbon Balance Tool is organized into three different tabs, which will be explained in the following sections. The 'Overview' Tab will always be visible, but the other two, 'Grid Energy
Mix' and 'Detailed System LCE', will only show up if the corresponding choice is selected in the 'Overview'.
Overview Tab
In this Tab you have the overview of the Carbon Balance calculation. The four values that can be modified by the user are the Grid LCE, the System Lifetime, the Annual Degradation and
the PV System LCE.
The System Production E_Grid is taken from the PVsyst simulation of the current Variant. The Carbon Balance values are the results from the calculation.
There are four values for the result:
The total saving of CO2 emissions in tons of CO2 over the expected lifetime of the PV installation.
The yearly saving of CO2 emissions in tCO2/year.
The savings of CO2 emissions per installed power, given in tCO2/kWp
The yearly savings of CO2 emissions per installed power, given in tCO2/kWp/year
The yearly values are averaged over the entire lifetime, taking into account the annual degradation.
For the Grid LCE there are three options to control the level of detail with which this value will be computed:
Manual: The value is supplied by the user and will be taken as it is for the calculation. A comment field will pop up, where the user can supply a text, specifying the source of the
value, and which will appear on the final report.
Country IEA:
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 173 of 174
A predefined value for the Grid LCE will be used. The selection allows to choose a value published by the International Energy Agency IEA. These values represent the
average CO2 emission in 2010 per kWh of electricity production for different countries or regions.
Energy Mix: This gives the most detailed control on how the Grid LCE will be determined. A separate Tab called 'Grid Energy Mix' will appear where a detailed computation can be
performed as explained below.
For the System LCE there are three options to control how this value will be determined:
Manual: The value is supplied by the user and will be used as it is for the calculation.
Default: An estimate will be computed for the System LCE. It is based on the 50th percentile LCE value for Photovoltaic electricity production published by the International Panel on
Climate Change (IPCC). This value amounts to 46gCO2/kWh and was extracted in a meta-study considering 26 publications. It represents a very coarse global average.
Detailed: With this option selected, the System LCE can be defined with some more level of detail. A new Tab called 'Detailed System LCE' will appear, where detailed information on the
system components can be entered. The full explanation on these values is given below.
If any of the 'Manual' options is selected, a comment field will appear, that allows to enter a text, describing the source of the value. This text will show up in the final report.
PV modules
This category is subdivided into the production of the modules themselves and the transportation to the site of the installation.
PV Modules
The PV module production is usually the most important contribution to the System LCE emissions. Values for LCE and grey energy vary in a large range. PVsyst provides default values
found in publications for mono-crystalline silicon. By default PVsyst will use the estimation via grey energy, and use as default conversion factor the Emissions associated to electricity
production for China, as given in the IEA list.
Transport 1 / 2
Transportation of the modules is divided into two separate contributions, to allow accounting for two different means of transportation. Usually these are ship cargo and land transportation.
The load of the transport is calculated from the total weight of the PV modules defined in the project. The distances have to be supplied by the user. The default values proposed for the
LCE values are 35 gCO2/t/km and 60 gCO2/t/km, which correspond to long distance ship cargo and large truck transportation respectively.
Additional
Maintenance
Maintenance can include regular inspections, repairs, cleaning of panels, cleaning of vegetation, etc. Since this is very specific for each project, PVsyst will not propose any default values.
It is left to the user to estimate a realistic value. In general this contribution is rather small and neglecting it will have little impact on the result.
Dismantling
This item should include everything that happens at the end of the PV installation lifetime, like dismantling, recycling, disposal, land restoration, etc. Since this is rather specific to each
project, the program does not propose any default values. It is left to the user to provide reasonable values here.
Other
This item can take any contribution that is not covered by the other groups and components. It is a single fixed value that is added to the total balance.
Data Sources
Detailed information on LCE values can be obtained from specialized providers, like for example ECOINVENT, Carbon Trust, International Energy Agency (IEA), Intergovernmental Panel
on Climate Change (IPCC), etc. The following table contains a few figures found in recent publications (be aware, that these are estimates based on conditions and assumptions that can
vary largely between countries, technologies and procedures):
Component LCE value Source
Single-Si module framed 213.9 kgCO2/m2 A. Karaiskakis et al, 28th PVSEC, 2013
1.53 kg CO2/Wp
Multi-Si module framed 173.0 kgCO2/m2 A. Karaiskakis et al, 28th PVSEC, 2013
1.32 kgCO2/Wp
Single-Si module laminate A. Karaiskakis et al, 28th PVSEC, 2013
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024
Project design Page 174 of 174
file:///C:/Users/jec/AppData/Local/Temp/~hhFDC7.htm 6/27/2024