Final Quiz 1143
Final Quiz 1143
All of the following items describe an aspect of life Life cycle cost only includes the project cost
cycle costing EXCEPT: from initiating through closing.
All the following are components of estimate cost
process EXCEPT: Cost of Quality.
All of the following statements are true regarding the
Plan Resource Management process except for which A RAM (or RACI chart) is an output of this
one? process that allows you to see all the people
Select one: assigned to an activity.
The activity list should include descriptions of activities. Ensure that the team members understand
This is required to: how the project work is to be done
The activity list should include descriptions of activities. Ensure that the team members understand
This is required to: how the project work is to be done.
The key benefit of this process is that it defines the
logical sequence of work to obtain the greatest
efficiency given all project constraints. Sequence Activities
The number of labor units required to complete a
schedule activity or work breakdown structure
component, often expressed in hours, days, or weeks
can be termed as efforts
The process of developing an approximation of the
cost of the monetary resources needed to complete
project activities is known as: estimate cost.
The process of establishing the policies, procedures,
and documentation for planning, developing,
managing, executing, and controlling the project
schedule. Plan Schedule Management
The process of identifying and documenting the
specific actions to be performed to produce the project
deliverables. Define Activities
The time or money set aside in schedule or cost base
line to cover the unknown unknowns can be referred
as which of the following Terminology? Management Reserve
The WBS, estimates for each work package, and
network diagram are completed. Which of the
following would be the NEXT thing for the project Create a preliminary schedule and get the
manager to do? team's approval
Time or Money allocated in the schedule or cost
baseline for known risks with active response
strategies can be referred as which of the following
terminology? Contingency Reserve
Total funding requirements and periodic funding
requirements (e.g., quarterly, annually) are derived
from the cost baseline
What does a staffing management plan describe? When and how resources will be added to
Select one: the project
What is the BEST report to use when reporting to
senior management?
Select one: Gantt chart
What is the right terminology for “In the critical path
method, the earliest possible point in time when the
uncompleted portions of a schedule activity can start
based on the schedule network? Early Start
Which of the following is not a characteristic of Rolling Plan must be prepared in complete detail at
Wave Planning the beginning of the project.
Which of the following is the most accurate method of
cost estimation? Bottom Up
Analogous estimating requires less
Which of the following statement is true: information and time than Parametric
Select one: estimating
Which of the following statements is not true about
Contingency Reserves: It is not a part of funding requirements
Which of the following terms best describes a provision
in the project budget to mitigate cost and / or schedule
risk? Reserve
indirect cost
Management Reserve
S curve
Sequence Activities
Contingency Reserve