Hcmhi Plumbing Work Schedule Nov 29 2022
Hcmhi Plumbing Work Schedule Nov 29 2022
NOVEMBER 30 2022
National Highway, Brgy. Bantug, Roxas, Isabela
GROUND FLOOR
SANITARY LINE
VENT SYSTEM
STORM DRAIGE LINE
DOWN SPOUT
AIR CON DRAIN
COLD WATERLIN
HOT WATER LINE
INSTALLATION OF PLUMBING FIXTURES
PRE TESTING
SECOND FLOOR
SANITARY LINE
VENT SYSTEM
DOWN SPOUT
AIR CON DRAIN
COLD WATERLIN
HOT WATER LINE
INSTALLATION OF PLUMBING FIXTURES
PRE TESTING
3RD FLOOR
SANITARY LINE
VENT SYSTEM
DOWN SPOUT
AIR CON DRAIN
COLD WATERLIN
HOT WATER LINE
INSTALLATION OF PLUMBING FIXTURES
PRE TESTING
4TH FLOOR
SANITARY LINE
VENT SYSTEM
DOWN SPOUT
AIR CON DRAIN
COLD WATERLIN
HOT WATER LINE
INSTALLATION OF PLUMBING FIXTURES
PRE TESTING
5TH FLOOR
SANITARY LINE
VENT SYSTEM
DOWN SPOUT
AIR CON DRAIN
COLD WATERLIN
HOT WATER LINE
INSTALLATION OF PLUMBING FIXTURES
PRE TESTING
MONTHLY PERCENTAGE ACCOMPLISHMENT ### 4.0% 7% 8% 8% 10% 12% 12% 10.0% 12% 6% 5%
ACCUMULATED PERCENTAGE ACCOMPLISHMENT ### 10.0% 17.0% 25% 33% 43% 55% 67% 77% 89% 95% 100%
MONTHLY ACCOMPLISHMENT ### 380,000.00 665,000.00 760,000.00 760,000.00 950,000.00 1,140,000.00 1,140,000.00 950,000.00 1,140,000.00 570,000.00 475,000.00
ACCUMULATED MONTHLY ACCOMPLISHMENT ### 950,000.00 1,615,000.00 2,375,000.00 3,135,000.00 4,085,000.00 5,225,000.00 6,365,000.00 7,315,000.00 8,455,000.00 9,025,000.00 9,500,000.00
MANPOWER LOADING ### 8 8 8 8 10 10 10 10 10 8 8
PREARED BY : NOTED BY : COMFORME BY :
PROJ - IN CHARGE OPERATION MANGER HEAD ENGINEERING AND PLANNING OWNERS REPRESENTATIVES:
MONTHLY PERCENTAGE ACCOMPLISHMENT ### 4.0% 7% 8% 8% 10% 12% 12% 10.0% 12% 6% 5%
ACCUMULATED PERCENTAGE ACCOMPLISHMENT ### 10.0% 17.0% 25% 33% 43% 55% 67% 77% 89% 95% 100%
MONTHLY ACCOMPLISHMENT ### 380,000.00 665,000.00 760,000.00 760,000.00 950,000.00 1,140,000.00 1,140,000.00 950,000.00 1,140,000.00 570,000.00 475,000.00
ACCUMULATED MONTHLY ACCOMPLISHMENT ### 950,000.00 1,615,000.00 2,375,000.00 3,135,000.00 4,085,000.00 5,225,000.00 6,365,000.00 7,315,000.00 8,455,000.00 9,025,000.00 9,500,000.00
MANPOWER LOADING ### 8 8 8 8 10 10 10 10 10 8 8
PREARED BY : NOTED BY : COMFORME BY :
PROJ - IN CHARGE OPERATION MANGER HEAD ENGINEERING AND PLANNING OWNERS REPRESENTATIVES:
MONTH OF DECEMBER
ACCUMULATED PERCENTAGE ACCOMPLISHMENT 67.0% ROUGH IN NING
ACCTUAL ACOMPLSHMENT
ADDITIONAL WORKS
AMT REMARKS
FOR FIRE PROTECTION
CHANGE ORDER 1 REVISED FIRE PROTECTION LAY OUT AT LOWER GROUND FLOOR ### 40% ON GOING
CHANGE ORDER 2 REVISED FIRE PROTECTION LAY OUT AT 5TH FLOOR ### 40% ON GOING
CHANGE ORDER 3 ADDITIONAL /REVISED FIRE PRO SYSTEM FOR PWD SERVICE STAIR ###
AT GROUND FLOOR TO 5TH FLOOR PROPOSAL FOR SUBMITION
###
FOR PLUMBING WORKS
CHANGE ORDER 2 ADDITIONAL GUTTER DRAIN FOR DOWN SPOUT ### 90% ON GOING
AT 5TH FLOOR
CHANGE ORDER 3 REVISED LAY OUT AND ADDITIONAL TOILETS AT ### 40% ON GOING
AT 5TH FLOOR
CHANGE ORDER 4 SUPPLY AND INSTALLATION OF OVER FLO DRAIN ### 90% ON GOING
CHANGE ORDER 5 REVISED LAY OUT FOR DOWN SPOUT AND STORM ### 90% ON GOING
DRAINAGE LINE PROPOSAL FOR SUBMITION
###
PREPARED BY