STP Manual
STP Manual
COLLECTION SUMP
COLLECTION SUMP
SUMP
TRANSFER PUMP (1W+1S)
COLLECTION SUMP
SUMP
AERATION TANK
SLUDGE DRYING
AIR BLOWER(1W+1S) SETTLING TANK
BED
GARDENING
OPERATING PROCEDURE OF STP PLANT
1) Check the inlet Electrical Power is on.
COLLECTION SUMP :
All the influents from the rest room are collected in the Collection
sump.
For Reusing the Sewage water for Gardening water we are installing
SEWAGE TREATMENT PLANT of Required Capacity
TRANSFER PUMP
AERATION TANK WITH FINE DIFFUSERS
TWIN LOBE AIR BLOWERS
SETTLING TANK
SLUDGE DRYING BED
SLUDGE RECYCLING PUMP
FILTER FEED TANK
FILTER FEED PUMP
DOSING PUMP AND DOSING TANK
PRESSURE SAND FILTER
ACTIVATED CARBON FILTER
ELECTRICAL PANEL
TRANSFER PUMP :
Transfer pump is used for transferring the sewage water from collection sump
into the Aeration tank. It can be operated by using the Electrical panel as
Working pump and Standby pump.
AERATION TANK WITH FINE DIFFUSERS :
The influent is pumped to the bio reactor tank at the properly Regulated
flow rate as required to maintain uniform distribution of organic load for the
Biological reduction through oxidization.
SETTLING TANK :
The overflow from the aeration tank enters into the Settling tank where
the bio-mass will be settled. The settled bio-sludge will be pumped into the
Aeration tank again for maintaining the MLSS.
ELECTRICAL PANEL :
Push Button Controls of All the Pumps and Motors are carried out by the
Electrical Panel. Control Panel also Consists of Air Blower Timer, Single Phase
Preventer and Emergency Stop Button.