Infra Project Techspec 12052018
Infra Project Techspec 12052018
TECHNICAL SPECIFICATION
PROJECT : CONSTRUCTION OF CONCRETE PERIMETER FENCE AND PARKING LOT
WITH GUARDHOUSE AND STORM DRAINAGE SYSTEM
SCOPE OF WORKS:
GENERAL CONDITIONS
All parts of the construction shall be finished with first class workmanship, to the fullest
talent and meaning of the plans and these Specifications, and to the entire satisfaction of the
Architect/ Engineer and the Owner.
The construction shall conform to all requirements of the National Building Code, as well
as the local rules and regulations of the municipality.
1. SITE PREPARATION/ EARTHWORKS
During the performance of the contract, the Contractor shall construct and
maintain a field office and facilities at the site of the work at which he or his
authorized agent shall be holding office and all times, while the work is in
progress. The location, dimensions and layout of such field office shall be
subject to approval, Construction shanties, sheds and temporary facilities
provided as requires for the Contractor’s convenience shall be maintain in
good condition and neat appearance including finishes as required.
1.1.5 Security
1.2 Earthworks
Excavations carried out below the depth indicated on the drawing without the
approval of the Project Manager shall be refilled to the proper grade with
thoroughly compacted suitable fill materials to the satisfaction of the Project
Manager except for footing excavation where concrete shall be replaced to the
bottom of the excavations; additional work of this nature shall be at the
Contractor’s expense. Where an existing structure lies adjacent to excavation
line, adequate shoring and bracing shall be provided to prevent damage to
persons and properties. Shoring, bracing and sheeting shall be removed in a
manner to prevent caving-in. The grading in the vicinity of excavated areas shall
be dome to prevent surface water from running into excavation and
embankments. Water pumped from excavations shall be diverted to suitable
disposal points. Trenches for pipelines shall be excavated along straight lines
and provided with minimum of 150-mm space between the outside of the pipe
and the side of the trench or bracing. Additional excavation shall be made for
each joint to allow for joining.
The entire area of the original ground under pavements and concrete slabs shall
be excavated to remove all objectionable matter, sod, muck, rubbish and other
unsuitable material to a minimum depth of 300 mm.
1.2.2. Filling and Backfilling
Fill and backfill materials shall consist of suitable materials from excavation or
from approved borrow areas, and shall be free from roots, wood scraps,
vegetations, and other extraneous materials and from large clods of earth or
stones greater than 100 mm. No fill material shall be placed until the surface to
be filled has been approved.
Before placing fill material, the surface upon which it will be placed shall
scarified to insure good bonding between the existing surface and the fill
material. Where embankment are to be constructed on sloping ground with
slopes steeper than 1 vertical to 4 horizontal, the new fill shall be cut into or
benched as the embankment is brought up in layers in such a manner that
the embankment material will bond with the existing surface.
All superficial obstructions shall be demolished and removed from the site to
disposal areas approved by the Consultant.
(a) Clearing
(b) Grubbing
Grubbing shall consist of the removal of tree stumps, brush and rubbish from the
work areas to be occupies by permanent structures, from other areas within the
indicated clearing limits as directed by the Consultant. Trees and shrubs to be
retained shall be protected properly form damage. Stumps shall be removed
entirely. Roots and matted roots shall be grubbed and cut to at least 450 mm
below the existing surface.
2. CONCRETE WORKS
The work includes construction of concrete structures complete in accordance with the
standard specifications and conformity with the lines, grades, thickness and typical cross-section
shown on the plan.
2.1.1 General
Concrete shall be composed of Portland cement; fine and coarse aggregates,
water and admixture as specified all thoroughly mixed and brought to proper
consistency, uniformity and temperature for final placement.
2.1.2 Cement
Concrete shall be Portland cement of a brand approved by the Project Manager
and conforming to ASTM Specification C150, Type I of Type II.
2.1.3 Water
Water shall be clean and free from injurious amounts of oils, acids, alkalics,
salts, organic materials, or other substances that may be deleterious to concrete or
steel.
2.1.4 Admixtures
Admixtures shall be subject to prior approval by the Project Manager. The
admixtures shall be capable of maintaining essentially the same composition and
performance throughout the work.
2.1.5 Fine Aggregates
Fine aggregates shall consist of natural sand, manufactured sand, or a
combination thereof. If the fine aggregate shall be a combination of separately
processed sizes, or if batching shall result in a combination of natural and manufactured
sand, the different components shall be batched separately. Fine aggregates shall
consist of hard, tough, durable, uncoated particles. The specified percentages of fines in
the sand may be obtained either by the processing of natural sand or by the production
of suitably graded manufactured sand. The shape of particles shall be generally rounded
or cubical and reasonably free from flat or elongated pieces. The use of beach sand shall
be prohibited. The fine aggregate shall conform to the following specific requirements:
In addition to the grading limits shown above, the fine aggregates, as delivered to the
mixer, shall have a fineness modulus not less than 2.3 more than 3.0 and during normal
operations, the grading of the fine aggregate shall be controlled so that the fineness
modulus of at least nine (9) out of ten (10) test samples of fine aggregate as delivered to
the mixer shall not vary by more than 0.20 from the average fineness modulus can be
determined by dividing 100 the sum of the cumulative percentages retained on U.S.
Standard Sieves Nos. 4, 8, 16, 50 and 100.
The grading of the aggregate within the separated size groups as delivered to the mixer
shall be as follows:
Sieve Sizes Percent by Weight Passing Individual 1-1/2
50 2” 100
25 1” 100 20-55
19 ¾” 90-100 0-15
Use 19-mm (3/4”) coarse aggregate for slab on grade, columns, beams,
suspended slabs and tie beams.
2.1.8 Forms
Concrete form shall be wood, plywood, steel or other suitable materials. Form
surfaces requiring standard or special finish shall be plywood or a non-absorptive
hand pressed fiberboard or other suitable materials. Plywood shall not be less
than 12 mm thick and shall be free from irregularities, dents and sags. Forms
shall be coated with non-staining form coating compound such as form oil of the
approved make.
Sampling and testing of concrete shall be done by and at the expense of the
Contractor. Throughout the period that the concrete is being poured into cylinder
shall be taken from fresh concrete from the forms.
The rests shall be made for each 10 cu. m. of concrete or fraction thereof for
each portion of structure as may required by the Project Manager as follows:
1. Compression Tests:
At least two (2) sets of samples consisting of three (3) concrete cylinder
specimens per set shall be made. Fresh concrete shall be placed inside
standard 150 x 300 mm cylindrical mould in three (3) separate equal layers
and rodded separately with 25 strokes with a 16 mm diameter. Surface shall
be leveled with trowel and samples are to be labeled to identify the class,
strength of concrete, date taken and part of structure samples are taken. The
samples shall be cured in accordance with ASTM C31.
One set of cylinders shall be tested at the age of seven (7) days, and one
set at the age of twenty-eight (28) days, in accordance with ASTM C39.
Additional cylinder samples may be molded in reserve for further tests, if the
results of the twenty-eight (28)-day-test do not meet the requirements.
2. Additional Tests
If, in the opinion of the Project Manager, based on the cylinder reports,
concrete with strengths below specification requirements has been placed,
the Project Manager, at the expense of the Contractor shall make additional
tests. Additional tests may be compression test on cored cylinder, ASRM
C42, and/or load tests as outlined in ACT 318 Sec. 202.
2. Ready-Mixed Concrete
The rate of delivery of the mixed concrete shall be such that the interval
between placing of successive batches shall not exceed thirty (30) minutes.
The elapsed time between the introduction of mixing water to the cement
and aggregate, and completion of discharge shall not exceed one (1) hour,
or not more than 1 ½ hours if retarder is used. It should be kept constantly
agitated during the transit period. Delivery tickets shall contain data on the
weight of sand, gravel and amount of cement and water added. The
Contractor shall keep legible copies available for examination of the Project
Manager.
Concrete shall be handled from the mixer to the place of final deposits as
rapidly as practicable by methods, which shall prevent segregation or loss of the
ingredients. It shall be deposited in the forms in approximately layers and as
nearly as practicable in its final position to avoid re-handling.
1. General
The surface of the concrete shall be kept continuously wet water for a period of
seven (7) days, by spraying or covering with burlap or other approved material
thoroughly saturated with water and keeping the covering wet by spraying or
intermittent hosing. Water for curing shall be generally lean and free from any
element, which might cause objectionable staining or discoloration of the
concrete.
3. MASONRY WORKS
The work includes furnishing and placing of concrete masonry units in conformity
with the lines, grades and cross-sections shown on the drawings and in accordance with
the specifications.
3.2.1 Workmanship
Masonry walls shall be placed level and plumb all around. One section of
the walls shall not be placed in advance of the others, unless specifically
approved. Unfinished work shall be stepped back for joining with the new work;
tooting shall not be permitted. Heights of masonry work shall be checked with an
instrument at sills and heads of openings, to maintain the level of the walls. Door
and window frames, louvered openings, anchors, pipes and conduits shall be
installed carefully and neatly as the masonry work progresses. Spaces around
door frames shall be filled solidly with mortar. Drilling, cutting, fitting and patching
to accommodate the work of others, shall be performed by skilled workers. Bolts,
anchors, inserts, plugs, ties and miscellaneous metal work specified elsewhere
shall be placed in position as the work progress. Chases of approved dimensions
for pipes and other purposes shall be provided, where indicated or necessary.
Top of exposed walls and partitions, not being worked on, shall be covered with a
waterproof membrane, well secured in place. Wall and partitions shall be
structurally bonded or anchored to each and to concrete wall beams, and
columns.
Fine mortar grout shall be mixed in the volumetric proportion of one part
Portland cement. ¼ part hydrated lime and 3 parts sand. Coarse grout shall be
mixed in proportion of one part Portland cement, ¼ hydrated lime, 3 parts sand
and 3 parts pea gravel passing a 3/8-inch sieve.
3.2.4 Use of Fine and Coarse Grout
The first course of concrete masonry unit shall be laid in full bed of mortar, for the
full width of the unit; the succeeding courses shall be laid with broken joints.
Concrete masonry units with the cells verticals shall have bed-joints formed by
applying the mortar to the entire top of the surface of the inner and outer face
shall, and the head joints formed by applying mortar of a width of about 25 mm to
the ends of the adjoining units lay previously. The mortar for joints shall be
smooth, not furrowed, and shall be of such thickness that it will be forced out of
joints as the units are being placed in position. Where anchors, bolts, ties and
reinforcing bars occur within the cell of the units, such cells shall be solidly filled
with mortar or grout as the work progress.
3.2.7 Reinforcement
Unless otherwise shown on the drawings, the size and spacing of bars shall be
as follows:
For Vertical Bars:
(24”) on centers
for 150 mm
4. REINFORCEMENT
Steel reinforcement shall be provided together with all the necessary wire tie
chairs, spacers, support and other necessary devices.
Reinforcing steel shall be accurately cut and bent in accordance with the
approval detailed reinforcement drawings. Reinforcing steel shall not be straightened or
re-bend in a manner that will injure the material. Bars with kink or with bends not
shown on the approved detailed reinforcing drawings or with cracks or splits of the
bends shall not be used. All the bars shall be bent cold. If Contractor elects to have
reinforcing steel cut and bent off the site, he shall provide, maintain and operate a small
cutting and bending shop on the site and maintain and representative stock of steel.
This provision is to take care of minor revisions and additions in an expeditious manner.
The Project Manager may require the contractor to prepare and submit bar cutting
schedule prior to fabrication of reinforcing steel bars.
Forms shall be used whenever necessary to confine the concrete and shape it to
the required lines and dimensions, or to protect the concrete from contamination. Forms
shall have sufficient strength to withstand the pressure resulting from placement and
vibration of the concrete, and shall be maintained rigidly in correct position. Forms shall
be sufficiently tight to prevent loss of mortar from the concrete. Forms for exposed
surface shall be lines with form grade plywood. Bolts and roods used for interval ties
shall be so arranged that when the forms are removed, they shall not be less than two
(2) centimeters from the formed surface.
Removal of forms or shoring is subject to approval by the engineer, and under no
circumstances shall bottom form and shoring be removed until after the members have acquired
sufficient strength to support their weight and the load thereon. Forms shall remain in place for a
minimum time as follows:
Reshore immediately after stripping beams and girders that support subsequent
formwork.
Before placing concrete, the contact surface if the forms shall be cleaned of
incrustations of mortar, grout or other foreign material. Forms shall be coated
with standard form oil that can effectively prevent sticking and will not stain
the concrete surfaces.
The work includes the furnishing, fabrication, erection or installation of structural steel
roof framing in accordance with this specification and as shown in the drawings.
It shall conform to specification STM A370, with a minimum yield point of 33, 000
psi, unless otherwise shown in the drawings. Heavy hexagonal structural bolts, heavy
hexagonal nuts and hardened washers, shall be quenched and tarpapered medium-
carbon steel bolts, nuts and washers complying with ASTM A325.
6.1.5 Electrodes
6.1.6 Galvanizing
Fabricated materials delivered to job site shall be stored in clean and protected dry
areas in manufacturer’s protective package. Structural steel materials to be stored shall
be placed on skids above the ground. It shall be kept clean and properly drained. Skids
placed near enough together to prevent injury from deflection shall support long
members, such as purlins and chords. The Contractor shall check the quantity and
quality f materials turned over to him against the delivery list and repot promptly in
writing my shortage or damage discovered.
6.2.1 General
Fabrication and erection of structural steel shall be in accordance with AISC specification
for the design. Fabrication and erection of structural steel for buildings, except as
specified herein. The Contractor shall submit to the Project Manager for approval shop
drawings showing the proposed method of fabrication and installation of all metal work.
No work shall be started until the shop drawings have been approved. And all work shall
conform to the approved shop drawings.
The work shall be well formed at the shape and size shown and assembles as detailed.
Structural members shall be fabricated and assemblers in the shop to the greatest
extent as possible. Shearing and punching shall be produced in clean, true lines and
surfaces with burrs removed. Nuts shall be drawn up tight. Joints, which ate to be
exposed to the weather, shall be waster lights. Hole shall be cut, drilled or punched at
right angles to the surface of the metal and shall not burning enlarge made ort. Holes in
base or bearing plates shall be drilled.
1) Welding
Structural steel shall be welded in accordance with the standard code of Are and Gas
Welding in Building Construction of the American Welding Society. Qualified welders
shall perform all welding work only.
2) Shop Painting
Unless otherwise specified of indicated in the drawings, all structural steel work (except
galvanized surfaced and surfaces that will be painted with epoxy) shall be given a shop
coat of red lead or zinc chromate primer.
6.2.3 Erection
The steel structure shall be erected true to line and grades. Bracing’s and supports shall
be introduces whenever necessary to take care of all the loads to which the structure
may be subjected. Such bracings shall be left in place as ling as may be required for
safety. As erection progress, the work shall be securely bolted to take are of all the dead
loads, wind and erection stresses. No reaming of undersize bolt holes shall be
permitted, and erection bolts shall not be used for lining up members.
(5) Setting Up
Steel shall be erected plumb, level and properly guyed. In setting or erecting structural
steel, the individual piece shall be considered plumb or level where the error does not
exceed 1 to 500.
(6) Inspection
The Contractor shall give the Project Manager at least fifteen (15) day notice prior to the
start of work at the mill shop, so that the required inspection may be made. The term
“mill” means any rolling mill, shop or foundry where material for the work is to be
manufactured or fabricated. No materials shall be rolled or fabricated until the said
inspection has been provided.
The Contractor shall furnish the Project Manager with copies of the certificate mill
reports of the structural steel structure preferably before but not later than the delivery
of steel structure to the job site.
The Contractor shall furnish all facilities for inspection and the Project Manager shall be
given free access to the mill or shop and premises at all times. The Contractor shall
furnish without charge all labor; machinery, materials and tools necessary to prepare
test specimens.
Inspection at the mill or shop is intended as a means of facilitating work and avoiding
errors. It is expressly understood that it will not relieve the Contractor form any
responsibility for imperfect materials or workmanship and the necessity for replacing
the same. The acceptance of any materials or furnished member at the mill or shop by
the Project Manager shall be preclude their subsequent rejections if found defective
before final acceptance of the work. Inspection of welding works will be in accordance
with the provision of Section 5 of the “Standard Code for Arc and Gas Welding in
Building Construction” of the American Welding Society.
The work includes installation of pre-painted Rib-type Long Span roofing and Roof
Insulation with complete with hardware and accessories.
7.1 GENERAL
The work includes furnishing all materials and requirements performing all operations to
provide a long span corrugated twin ribbed roofing and miscellaneous roofing work as required
to provide an acceptable installation. Surfaces to which metal formed roofing sheets are to be
applied shall be thoroughly cleaned and prepared, free from any defects that may affect the
application. Metal formed roofing shall be locked and lapped and installed as applicable. Details
shall be in accordance with manufacturer’s recommended installation practice.
7.2 MATERIALS
All Roofing Sheets (.5mm thk), Gutters, Ridge and Valley Roll, and Flashing must be Pre-
Painted and should be #24 of thickness. Roofing insulation must be at least 100mm thick.
7.3 INSTALLATION
Lay and install the first sheet with turned down edge towards the outside of the area to
be covered. Overlap the next sheets to the previous sheet in such a manner that the exposed
edge I turned down and the covered edge is turned up. Side up fasteners should be done by
rivets and washers spaced from 300mm to 450mm on centers.
Ridge strips for ridge rolls and ridge flashings are attached to the roofing sheets by means
of rivets. Other flashings are to be fabricated from plain sheets of the same materials as the
roofing in accordance with the details and/or site requirements. These are also attached to
roofing sheets by means of rivet.
Metal formed roofing sheets surfaces requiring protection from stains, discoloration,
surface abrasion and other construction abuses shall be suitably protected in accordance with
the manufacturer’s recommendations.
Upon completion, the Contractor shall clean the metal formed roofing sheets surfaces and
drain line of burrs, leaves, stones and other foreign matter that may impair the flow of water.
Surface shall be kept clean by periodic inspection.
8. CARPENTRY WORKS
This section includes all rough and finish carpentry and joinery works, as shown
in the drawings and in accordance with this specification.
Fasteners shall be of the type and size best suited for the purpose as
shown in the drawing. Fasteners shall be zinc coated regular commercial size as
indicated and shall conform to ASTM specification A307.
8.2.1 Workmanship
Lumber for framing and other carpentry or metal framing shall be fitted
closely, set accurately to the required lines and levels, and shall be secured in a
place in a rigid and substantial manner. Spiking, nailing and bolting shall be done
in an approved manner. Spikes, nails and bolts shall be of the proper size, and
care shall be taken so as not to split the members. All frames coming in contact
with concrete or masonry shall be anchored by means of nails metal screws with
tox spaced sufficiently apart all around the contact surfaces. Bolt holes shall be
drilled accurately and shall have a diameter of 3 mm more than the bolt size. All
exposed wood surfaces shall be smoothly dressed and if so required, shall be
well sand papered to an even smooth surface ready for finishing.
Framing and other rough carpentry shall be fitted closely and set accurately to
the required line and levels and shall be secured in place in a rigid and
substantial manner. Framing members shall not be spliced between bearing
points and shall be provided as necessary for the proper completion of the work.
Nailing shall be done in an approved manner, so as not to split the framing
members.
8.2.4 Protection of Work
The Contractor shall protect all finished woodwork and millwork from injury after it
has been set in place until completion and final acceptance.
8.2.5 Hardware
This section calls for the furnishing, fabrication and installation of doors and
windows in accordance with the plans and specifications.
9.1 General
Doors schedule, color and design shall be in accordance with the plans.
Door panels shall have 44-mm thickness, unless otherwise specified or shown on
plans, except for counter doors, which shall be 31 mm thick.
Except as otherwise specified, flush door shall be done in accordance with the
detail as shown on the plans. The plywood edge protection shall be around and
into the outside frame of the door in order to prevent “peeling off” of the plywood
veneers at the edges.
PVC doors for interior shall be of best quality. PVC doors shall be 44
mm. thick. and shall also be provided with bottom louvered portions as indicated
in the plans.
Tubular framed Steel Door with 1.5mm G.I. Sheet body. With complete
lock system.
This type of jalousie window shall be capable of locking the unit in any position and
cannot be opened outside. Louver with glass slat clips and tilt gar casing shall be
extruded aluminum sections, true to details with clear, straight, sharply defined profiles
and green from defects impairing its strength or durability. Aluminum extruded section
and strips shall be Type AA conforming to ASTM B 235-50T.
10. TILEWORKS
Tiles shall be standard grade and 6 mm thick. Color and pattern shall be as
specified in the drawing or as approved by the Project Manager.
For all other floor finishes not indicated below, refer to schedule or call-
out specifications of finishes indicated in the plan.
Scratch Coat: 1 part Portland cement to 5 parts damp sand to 1/5 part
hydrated lime.
11.1 Materials
11.2 Electrodes
11.3 Galvanizing
This item shall consist of furnishing all materials, tools, equipment and
fixtures required as shown on the Plans for the satisfactory performance for the
entire plumbing system including installation in accordance with the latest edition
of the National Plumbing Code, and this Specification.
12.1.1 For cold water lines, Pn 10 Fusion Weld Polyprophylene Pipes. Provide
coal tar with burlap for embedded pipe.
12.1.2 UPVC Pipe series 1000 conforming to ASTM D-2729 for all downspouts and
sewer, waste & vent lines.
12.1.3 Water Closets shall be Tank Type Push Button Flush, Free Standing
Combination round front bottom outlet siphon vortex or wash-down bowl
with jet round front with close coupled tank with cover with complete
fittings and mounting accessories.
12.1.4 Toilet lavatories be wall hung lavatory with rear overflow and cast-in
soap dishes pocket hanger and integral China Brackets complete with
twin faucets, supply pipes, P-trap and mounting
12.1.5 Pipes, plumbing fixtures, water lines, clean out and vents shall be
supplied and installed in accordance with the approved workmanship.
Inlet and outlet pipes shall conform to the latest edition of the National
Plumbing Code.
B. Valves for water supply shall be bronze body with threaded ends ratted
21.0 kgf/cm. square. All valves are gate valves unless otherwise specified.
Gate valves shall have solid wedge body and discs conforming to
specification requirements defined in ASTM B-62. Globe valves shall have
plug type discs with ferrule-threaded ends and bronze body.
Pipes and fittings for sanitary and potable water lines as approved
alternative shall be Galvanized Iron Pipes and Fittings Schedule 40 and
Unplasticized Polyvinyl Chloride Pipes and Fittings (UPVC). Pipes and fittings
shall be made of virgin materials conforming to specification requirements
defined in ASTM D-2241 and PNS 65: 1986. Fittings shall be molded type
and designed for solvent cement joint connection for water lines and rubber
O-ring seal joint for sanitary lines.
12.2.1b Vent pipes in roof spaces shall be run as closest possible to under
side of roof with horizontal piping pitched down to stacks without
forming traps. Vertical vent pipes connected into one main vent riser
above the highest vented fixtures.
12.2.1c Where an end circuit vent pipe from any fixtures is connected to a
vent line serving other fixtures, the connection shall be at least 1.20 m
above the floor on which the fixtures are located.
12.2.1d Horizontal waste line receiving the discharge from two or more
fixtures shall be provided with end vents separate venting of fixtures is
noted on the plans.
12.2.1e All changes in pipe size on soil and waste lines shall be made with
reducing fittings or recessed reducers. All changes indirection shall be
made appropriate use of 45 degrees, wyes, half wyes, quarter bends
or elbows may be used in waste lines where the change in direction of
flow is the horizontal to the vertical and on the discharge from waste
closets. Where it becomes necessary to use short radius fittings in
other location the approval of the Project Manager shall be obtained
prior to installation of the same.
12.2.1d Vent pipe shall be provided with Vent Cap (Studor) and flashed and
made watertight at the roof with ferrule lead. Flashing shall be turned
down into pipes.
12.2.2 Water Pipes, Fittings and Connections
All water piping inside the building and underground, 100-mm in diameter
and smaller shall be schedule 40, series 1000 PVC pipes fittings.
12.2.2a The water piping shall be extended to all fixtures, outlets and
equipment from the gate valves installed in the branch neat the rise.
12.2.2b The cold water system shall be installed with a fall towards a main
shut off valve band drain. Ends of pipes and outlet shall be capped
or plugged and left ready for future connections.
12.2.2e. All piping above the ground shall be run parallel with the lines of the
building unless otherwise indicated on the plans.
12.2.2f All service pipes, valves and fittings shall be kept at sufficient
distance from other work to permit finished covering on the different
services.
All pipes shall be reamed before threading. All screw joints shall be
made with graphite and oil or with an approved granite compound
applied to make threads only. Threads shall be cut not more than
three threads on the pipe shall remain exposed.
12.2.3a All fixtures and equipment shall be supported and fastened in a safe
and satisfactory workmanship as practiced.
12.2.3c Insert shall be securely anchored and properly flushed into the
walls. Inserts shall be concealed and rigid.
12.2.3d Bolts and nuts shall be horizontal and exposed. It shall be provided
with washers and chromium plate finish.
12.2.4a Plates to cover exposed pipes passing through floor finished walls
or ceiling shall be fitted with chromium plated cast brass plates or
chromium plated cast iron steel on ferrous pipes.
12.2.4b Plates shall be large enough to cover and close the hole around the
area where pipes pass. It shall be properly installed to insure
permanence.
12.2.4c. Roof areas penetrated by vent pipes shall be rendered watertight by
lead sheet flashing and condor flashing. It shall extend at least 150
mm above the pipe and 300 mm along the roof.
a. Shower head and fittings shall be movable, cone type with escutcheon
arm complete with stainless steel; shower valve and control lever. All
exposed surface to be chromium finish.
b. Grab bars shall be made of tubular stainless steel pipe provided with
safety grip and mounting flange for disabled people.
c. Floor drains shall be made of steel beehive type, measuring 10cm x 10
cm and provided with detachable stainless strainer, expanded metal lath
type.
d. Toilet paper holder and soap holder shall be vitreous china or approved
equal wall mounted. Color shall reconcile with the adjacent fixture and
facing tiles.
e. Faucets shall be made of stainless steel for interior use.
f. Hose bibs shall be made of bronze cast finish.
12.3.1 The entire drainage and venting system shall have all necessary openings,
which can be plugged to permit the entire system to be filled with water to the
level of the highest water or a full 30 minutes during which time there shall be
no drop greater than 102 mm.
12.3.2 Where only a portion of the system is to be tested, the test shall be
conducted in the same manner as described for the entire system except that
a vertical stack 3.00 m highest horizontal line to be tested may be installed
and filled with water to maintain sufficient pressure or water pump may be
used to supply required pressure.
12.3.3. If and when the Project Manager decides that an additional test is needed,
such as an air to smoke test on the drainage system, the Contractor shall
perform such test without any designated representative.
12.4.1. Upon completion of the roughing-in and before connecting fixtures the entire
cold water piping system shall be tested at a hydrostatic pressure 1 ½ times
the expected working pressure in the system during operation and remained
tight and leak-proofed.
12.4.2. Where piping system is to be concealed the piping system and in the
presence of the Engineer of his duly designated representative.
12.5 Defective Work
12.5.1. All defective materials replaced and tested will be repeated until satisfactory
performance is attained.
12.5.2. Any material replaced for the satisfactory performance of the system made
shall be at the expense of the Contractor.
12.6 Disinfection
12.6.1. The entire water distribution system shall be thoroughly flushed and treated
with chlorine before it is operated for public use.
12.6.3. Valves for the water distribution system shall be opened and closed several
times during the 16 hours chlorinating treatment is done.
1) To secure and pay for the electrical permits, certificates, and other related
permits. (if applicable)
2) To secure and pay for the service charges and other fees required by the local
electric utility company for the energization of the proposed transformer bank. (if
applicable)
3) To secure and pay for the insurance required for the project. (if applicable)
4) Roughing-in and wiring for lighting and power system.
5) Supply, installation, testing, and commissioning of distribution transformer and
construction of elevated transformer pad. (if applicable)
6) Supply, installation, testing and commissioning, of generator sets and grounding
system. (if applicable)
7) Supply and install/cause to install primary metering. (if applicable)
8) Supply and install/cause to install metal post with LED parking lights.
9) Supply and install/cause to install perimeter lights.
10) Supply, installation, and testing of automatic transfer switches, manual transfer
switches, panel boards, and disconnect switches. .(If applicable)
11) Supply and installation of underground feeder system included in the plan to
powerhouse.(If applicable)
12) Supply and installation of boxes, pull boxes, auxilliary gutters, wire gutters, bus
bar gutters, circuit breaker gutters and the like.
13) Supply and installation of lighting fixtures, switches,and power outlets.
14) Supply and installation of hangers and supports of conduits for power, feeder and
sub-feeder system and auxiliary system.
15) Painting of electrical works covering conduits, boxes, hangers, gutters, and the
like.
16) Testing for electrical system:
Insulation resistance test
Operational test
Polarity check
All materials and equipment to be used in the electrical installations and construction
shall be in accordance with the provisions of the latest edition of the Philippine Electrical
Code and the pertinent ordinances of the municipality wherein the project is located.
All work shall comply with the rules and regulations of the local power utility company in
so far as they are concerned in providing the respective permanent services to the
building.
The electrical plans and these specifications are meant to be complementary to each
other, and what is called for in one shall be as binding as if called for by both.
Any permanent conflict between the electrical plans and these specification and any
unclear points of controversial matter in either shall be referred to the owner’s assigned
representative for final decision.
Upon final completion of the work herein described, the electrical contractor shall furnish
the Owner two (2) copies of the “As-built” plans for future reference and maintenance
purposes.
The electrical plans indicate the general layout of the complete electrical system,
arrangement of feeders, circuit outlets, switches, controls, panel boards, service
equipment and other work. Field verification of the scale dimensions on the plane must
be made, since actual locations, distances and levels will be governed by actual field
conditions.
The Electrical Contractor shall check architectural, structural and plumbing plans if
necessary to resolve such conflicts. The Electrical Contractor shall notify the architect
and secure approval and agreement on necessary adjustments before installation is
started.
13.4 PERMITS AND INSPECTION
The Electrical Contractor shall obtain all necessary permits and certificates of electrical
inspection from the proper government authorities concerned, required both for the
performance of the work involved and the operation of the system upon completion of
the work.
The Electrical Contractor shall pay all the fees necessary to secure the above-mentioned
permits and certificates.
The Electrical Contractor shall at his own expense, reproduce the electrical plans to the
necessary scale and size, complete them with all the necessary information and
requirements as maybe required by the government authorities concerned with the
approval of plans.
The Electrical Contractor shall coordinate with the local power company regarding the
power facilities and secure approval of the power requirements.
All materials to be used shall be brand new, with trade name, unused, and shall in every
case be the best where such standards have been established for the particular type of
materials used.
Only skilled workmen using proper tools and equipment shall be employed during the
entire course of the installation work. All workmanship shall be of the best quality and all
works shall be done in accordance with the best engineering practice of the trade
involved.
Lighting and Power Branch Circuit – uPVC pipes concealed in ceilings and double walls
and/or embedded in concrete walls/slabs. All uPVC pipes ran underground outside of
buildings shall be buried not less than 40mm below nat. grd. line and enclosed in
concrete envelope. All concrete envelopes passing under roadways or areas accessible
to vehicles shall be steel reinforced up to 1.0m from the edge of the roadway.
Low Voltage Service Entrance and All Feeders – rigid steel conduit, exposed/concealed
in ceiling/double walls, embedded in concrete walls/slabs or ran underground encased in
concrete.
All Other Auxiliary Layout – uPVC pipes concealed in ceilings/double walls and/or
embedded in concrete walls/slabs.
Use flexible metal pipe for connection between junction boxes inside ceiling and lightings
and other fixtures using approved fittings.
All boxes for lighting outlets, convenience outlets, tumbler switches and other devices
shall be galvanized pre-painted and approved products of reputable manufacturers. Cut
ends of conduits shall be reamed and cleaned to remove burr and sharp edges. Threads
cut on conduits shall be the same thread dimensions as factory cut conduit threads.
Conduits joints shall be made straight and true. Elbows and offsets and changes in
direction and runs shall be uniform. Bends shall be made without kinking or destroying
the cross-sectional contours of the conduits. Conduit terminals shall be provided at outlet
boxes and cabinets with locknuts and bushing. Conduits shall be continuous from outlet
and from outlet to pull boxes and cabinets in the manner that the conduit system shall be
electrically continuous.
Where conduit runs are exposed, they shall be supported at an interval of not more than
0.75 m maximum with proper clamps and bolts or expansion shields or other means of
support.
All splices, taps, junction in wires larger than 8.0 sq.mm. shall be done with solderless
connectors of suitable sizes and properly insulated with rubber tapes and protected by
friction tapes, so that the insulation strength shall at least be equal to the insulation of
the conductors they join.
Unless otherwise specified, the type of wires to be used shall either be THW or
THHN.Smallest size of wire to be used for lighting and power unless otherwise indicated
shall be 3.5 sq.mm.
13.7 FEEDERS
Feeders shall be laid out in accordance with the riser diagram shown in the electrical
plans.
Unless otherwise specified type THW or THHN wires shall be used for feeder lines. The
wires and conduits sizes shown in the electrical plans shall be the minimum sizes to be
used.
All wall switches shall be flush type and mounted 1.40 meters above finish floor line
unless otherwise specified.
Convenience outlets shall be grounding type, wall flushed, mounted 0.30 meter above
finished floor line or finished counters unless otherwise specified in the plan. Ground
fault circuit interrupter protected convenience outlets shall be used in bathrooms,
lavatories, sinks, laundry areas and the like.
The cabinets for the above shall be of standard sizes and shall be gauge #16. Circuit
breakers shall be 250 Volts, AC, rated 75C, interrupting ratings specified in the plan shall
be followed at all times.
Install all lighting fixtures and lamps as specified and as shown on plans, Fluorescent
lamps shall either be 48 inches/40 watts or 24 inches/20 watts, standard cool white or
daylight with the minimum light output of 3,000 lumens. Use high power factor ballast.
Submit one sample of each type of fixtures to the Architect for approval prior to
manufacturing and installation.
The Electrical Contractor shall supply and install distribution transformers, pole line
hardware for the receiving pole and pole at midspan, transformer pads and grounding
system as indicated/specified in the plan. He shall also supply service metering
instruments and accessories, and at his expense, shall submit these to the local electric
utility company for connection.
Materials for the works mentioned above shall be from manufacturers
accredited/acknowledged by the local electric utility company.
Sample panels of selected colors, as least (1) meter square in area shall be
prepared for approval by the Project Manager prior to the application.
14.2 Workmanship
Skilled workers shall do all work in a workmanlike manner. Paints shall be evenly
applied and free from sags, runs, crawls and other defects. All coats shall be of
proper consistency and well brushed out or rolled on so as to show a minimum
brush or rolled marks. Brushes or rollers shall be clean and in good condition.
All coats shall be thoroughly dry before the succeeding coat is applied. Allow at
least twenty-four (24) hours or more between applications of coat. For exterior
painting during rainy season, allow one (1) week drying time before the
succeeding coat is applied.
Painting coats as specified are intended to cover surfaces perfectly, its surfaces
are not fully covered, further coats shall be applied to attain the desired evenness
of the paint application. All finishes shall be uniform as to sheen, color and
texture. Paint may be applied by spray method, except when, in the opinion of
the spraying in any particular application would produce unsatisfactory results.
The Contractor shall provide all drop cloths and other covering requisite to the
protection of the floors and other work.
Each surface shall be inspected carefully before applying any finish; and if
surface is not in proper condition, they shall be notified to that effect in writing,
otherwise the Contractor shall be held responsible for any defects in the finishes
arising there from. Should a coat of paint be applied to a certain area and defects
shall be knocked out and re-plastered by the Contractor and repainted to the
satisfaction of the Project Manager.
(b) Finishing:
For exterior and interior concrete surfaces and all other surface with cement
plaster finish, use flat latex paint with the specified brand approved by the Project
Manager.
First Coat- Apply flat concrete paint thinned with ½ liter water per 4 liters of paint;
tint with latex tinting color to closely match color of topcoat or use premixed paint.
Dry for 3 to 6 hours.
Intermediate Coat- Repair all minor surface imperfection with paint putty made by
mixing paint with patching compound powder. Let it dry for 24 hours, and then
smoothen the surface with sand paper, before applying the intermediate coat.
Final Coat- Apply semi-gloss or gloss paint tinted with latex tinting color to the
shade specified.
Ducco or semi-ducco finish shall be applied using the appropriate paint sprayer
by a well experienced painter.
(b) Finishing
For all wood work, use gloss latex house paint with the specified brand approved
by the Project Manager.
First Coat- Apply paint thinned with ½ liter water per 4 liters of paint.
Second Coat- Apply latex thinned with latex tinning colors to the shade specified
for 4 to 6 hours.
15. SIGNAGES AND MARKINGS
The contractor shall provide all necessary signages and markings before and
during construction.
All warning signs must be placed in areas where there are dangers in
construction activity
Sinages and markings must be visible and readable and can easily be seen by
people.
The contractor upon receipt of the notice to proceed shall immediately mobilize
and transport his plant, equipment, materials and employees to the site and demobilize
or remove the same at the completion of project.
Prepared By: