BN - HSE - PD - 13 Procedure For Controlling and Maintaining Plant & Equipment
BN - HSE - PD - 13 Procedure For Controlling and Maintaining Plant & Equipment
Revision History
1. Purpose………………………………………………………………………………………………………………….2
2. Scope……………………………………………………………………………………………………………………………………….2
3. Roles and Responsibilities……………………………………………………………………………………………………… 2
4. References……………………………………………………………………………………………………………………………….4
5. Definitions and Abbreviations………………………………………………………………………………………………4
6. Procedure……………………………………………………………………………………………………………………………….4
7. Appendix………………………………………………………………………………………………………………………………..22
1
BN_ HSE_PD_13 REV 00
1. Purpose
The purpose of this procedure is to describe the management of the Plant and
Equipment Department covering the purchase, servicing, maintenance, hire and
disposal of plant and equipment.
2. Scope
4. References
QCS 2014
5. Definitions and Abbreviations
6. Procedure
The Project Engineer shall establish maintenance and servicing schedules for plant
and equipment. Where appropriate, the schedules shall take account of the
manufacture’s recommendations.
The working hours or distance travelled of the plant equipment shall be record.
Defects identified during routine servicing shall be reported to the project Engineer
who shall decide the action to be taken. The plant or equipment shall not be used
until defects that compromise safe operation, health of the operator or pollute the
environment have been repaired.
Servicing of plant and equipment shall normally take place in a dedicated workshop.
The workshop shall meet all the health, safety and environment standards.
When servicing is not possible in the workshop, the Project Engineer shall ensure
proper arrangements have been made to service the plant or equipment on site and
ensure that the generated waste i.e. used oil filters, hydraulic fluid, spare parts) are
disposed in a proper manner.
Operators of plant and equipment have the duty to report defects, fluid leaks and
visible exhaust emissions. Upon receipt such report, the Workshop Engineer shall
ensure that the effective remedial action is promptly taken.
7. Appendix
Forms
Daily Equipment checklist Doc No: BN_HSE_FRM 026
Equipment and Maintenance record.