B. Interim Payment
Item Date Before VAT 15% VAT Total Amount
1 (A) Work Executed to Date 418,946.61
2 (B) Supplementary Agreement Executed
3 (C) Material on Site
4 (A+B+C) 418,946.61
5 DEDUCTION
6 1. Previous Payment -
7 2. Retention 5% 20,947.33
8 3. Rebate 2%
9 4. Penality
10 5.Advance Repayment 10%
11 for main Contract
12 6. Advance payment 10%
14 Suplmentary (A+B)
15
16
Total Aamount (B) - - -
Total Aamount (A+B) - - -
VAT PAYMENT
- VAT on Amount of Work Executed 62,841.99
VAT on Previous Payments -
This Payment Retention 15% VAT
Total VAT Payment
Net VAT Payment on this Certificate 62,841.99
We Certify that contractor is now entitled to the sum of Birr 460,841.27 ( Four Hundred sixty Thousand eight Hundred fourty one & 27/100)
______________________ _____________________
PROJECT:-4B+G+13 METROPOLITAN TOWER APARTMENT Page 01 of 01
B. Super Structure
II.Ceiling Work
1.Edge Rooms Gypsum Celing H=45cm Ceiling
Type-1
Dining Room A=77.19 (Auto cad) 1 77.19 77.19 m2
Room B/N Axis 12-16 & J-H A=44.34 (Autocad) 1 44.34 44.34 m2
For Aluminum Ceiling b/n axis H-G &4-10 1 28.86 0.45 12.99 m2
For Aluminum Ceiling b/n axis H-G &11-16 1 28.86 0.45 12.99 m2
For Aluminum Ceiling b/n axis G-E &3-5 1 13.26 0.45 5.97 m2
For Aluminum Ceiling b/n axis G-E &17-15 1 13.26 0.45 5.97 m2
For Aluminum Ceiling b/n axis F-E &10-11 1 15.66 0.45 7.05 m2
For Aluminum Ceiling b/n axis E-D &3-10 1 25.26 0.45 11.37 m2
For Aluminum Ceiling b/n axis E-D &11-17 1 25.26 0.45 11.37 m2
At the Back
Axis 2-4 1 7.40 0.45 3.33 m2