MJB Bridge Estimate - Part-1
MJB Bridge Estimate - Part-1
4 x 40.00
Ranavav-Bhanvad-Khambhaliya_DPR_Estimate
Sor Clause
Sl. No. Item Unit Qty. Rate Total Cost
No.
Taking, exploratory boring 100mm dia at the
location of piers and abutments or for high
12.32 embankments in approaches in all types of strata as
per IRC-78-1983 and section 2400 of specifications.
1
a) Upto 1.0 m below bed level Meter 2.000 2722.000 5444.000
b) Beyond 1.0 m depth upto 5.0 m Meter 8.000 2847.000 22776.000
c) Beyond 5.0 m depth Meter 30.000 2970.000 89100.000
Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
12.1 construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom as
per relevant clauses of section 300 & 2100 in
5
12.1 I (i) Ordinary soil (Depth upto 3 m ) Cum 5112.746 189.150 967075.839
12.1 I (ii) Ordinary soil (Depth 3 m to 6 m) Cum 4995.788 243.750 1217723.423
Ranavav-Bhanvad-Khambhaliya_DPR_Estimate
Sor Clause
Sl.10
No. Item Unit Qty. Rate Total Cost
No.
Pedestal M40
13.5(I) RCC M-40 UPTO 5 MTR. Cum 0.000 5046.000 0.000
RCC M-40 5 TO 10 MTR. Cum 40.960 5156.000 211189.760
FE 500
Feedback Infra Private Limited
Ranavav-Bhanvad-Khambhaliya_DPR_Estimate
Sor Clause
Sl. No. Item Unit Qty. Rate Total Cost
No.
Reinforced Cement Concrete Crash Barrier
Providing of an Reinforced cement concrete crash barrier
at the edges of the road, approaches to bridge structures
and medians, constructed with M-40 grade concrete with
HYSD reinforcement conforming to IRC:21 and dowel bars
25 mm dia, 450 mm long at expansion joints filled with pre-
moulded asphalt filler board, keyed to the structure on
15 which it is built and installed as per design given in the Cum 640.000 3691.000 2362240.000
enclosure to MoRT&H circular No. RW/NH - 33022/1/94-
DO III dated 24 June 1994 as per dimensions in the
approved drawing and at locations directed by the Engineer,
all as specified.
M 40 grade concrete
Bearings
Supplying, fitting and fixing in position true to line and level
elastomeric bearing conforming to IRC: 83 (Part-II) section
13.13 IX and clause 2005 of MoRTH specifications complete Cubic Cm 921600.000 1.230 1133568.000
including all accessories as per drawing and Technical
Specifications.
Expansion joint
18
Feedback Infra Private Limited
Ranavav-Bhanvad-Khambhaliya_DPR_Estimate
Sor Clause
Sl. No. Item Unit Qty. Rate Total Cost
No.
Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint catering
to maximum horizontal movement upto 70 mm, complete
18 as per approved drawings and standard specifications to be
14.21 installed by the manufacturer/supplier or their authorised Meter 160.000 1716.000 274560.000
representative ensuring compliance to the manufacturer's
instructions for installation.
Filter media
Providing and laying suitable designed Filter material
16.5 underneath pitching in slopes complete as per drawing and Cum 55.155 869.000 47929.539
Technical specification
24
Feedback Infra Private Limited
Ranavav-Bhanvad-Khambhaliya_DPR_Estimate
Sor Clause
Sl. No. Item Unit Qty. Rate Total Cost
No.
Providing and laying of Filter media with granular
materials/stone crushed aggregates satisfying the
24 requirements laid down in clause 2504.2.2 of MoRTH
specifications to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the
16.5 Cum 159.790 750.000 119842.484
wall and provided behind entire surface after abutment,
return wall and wing wall to the full height compacted to a
firm condition complete as per drawing and technical
specification.
TOTAL 465143757.628
H
Un
Ranavav-Bhanvad-Khambhaliya_DPR_Estimate
DETAILS OF QUANTITY CALCULATION - Major Bridge
Major Bridge Reconstruction
Chainage - 34+300 Span- 4X40
Sr. No. Item Name Unit Nos Length Width Height/ Depth Area Factor Qty To. Qty.
1 Taking, exploratory boring
Un
Ranavav-Bhanvad-Khambhaliya_DPR_Estimate
DETAILS OF QUANTITY CALCULATION - Major Bridge
Major Bridge Reconstruction
Chainage - 34+300 Span- 4X40
Sr. No. Item Name Unit Nos Length Width Height/ Depth Area Factor Qty To. Qty.
For Abt Upper Rectangular Portion Cum 2 1.60 16.00 1.50 76.8
TOTAL 1118.4
6 RCC M-35 for Foundation
Pier Foundation Lower Rectangular Portion Cum 3 7.50 12.00 0.65 175.5
Pier Foundation Upper Rectangular Portion Cum 3 1.50 12.00 0.65 35.1
Pier Foundation Triangular Portion Cum 6 3.00 12.00 0.65 0.50 70.2
For Retaining Wall Lower Rect Portion Cum 2 19.37 8.40 0.80 260.3
Retaining Wall Upper Rect Portion Cum 2 19.37 1.20 0.90 41.8
Retaining Wall Toe Portion Cum 2 19.37 3.60 0.90 0.50 62.7
Retaining Wall Heel Portion Cum 2 19.37 3.60 0.90 0.50 62.7
TOTAL 1416.8
7 PCC M 20 Toe wall
Toe wall Rectangular Portion Cum 1 24.98 1.20 0.60 18.0
Toe wall Upper Rect Portion Cum 1 24.98 0.30 1.45 10.9
Toe wall Triangular Portion Cum 1 24.98 0.30 1.45 0.50 5.4
Total 68.6
8 RCC M-35 for Sub-Structure up to 5 mtr.
Abt Stem Cum 2 1.00 16.00 5.00 160.0
Abut. Cap Cum 2 1.00 16.00 0.00 0.0
Overhang Cap Rect. Portion Cum 2 0.32 16.00 0.00 0.0
Wall type Abt Dirt wall Cum 2 0.30 16.00 0.00 0.0
For Retaining Wall Cum 2 19.37 0.75 5.00 145.2
Pier stem rectangle Cum 3 1.00 9.00 5.00 135.0
Pier stem semi circuler Cum 3 0.79 5.00 11.8
Pier Cap Lower Rect Portion Cum 3 2.00 9.70 0.00 0.0
Pier Cap Triangular Portion Cum 6 2.00 1.65 0.00 0.50 0.0
Pier Cap Upper Rect Portion Cum 3 2.00 13.00 0.00 0.0
Bracket Rect portion Cum 2 0.30 16.00 0.00 0.0
Bracket Triangular portion Cum 2 0.30 16.00 0.00 0.50 0.0
Return Wall Cum 4 0.60 4.80 5.00 57.6
Total 1019.3
9 RCC M-35 for Sub-Structure 5 to 10 mtr.
For Retaining Wall Cum 2 19.37 0.75 5.00 145.2
Total 959.0
10 RCC M-40 for Sub-Structure
Pedestal Cum 64 0.80 0.80 0.50 20.5
Total (up to 5 mtr.) 0.0
10 RCC/PSC Girder Upto 5 mtr.
H
Un
Ranavav-Bhanvad-Khambhaliya_DPR_Estimate
DETAILS OF QUANTITY CALCULATION - Major Bridge
Major Bridge Reconstruction
Chainage - 34+300 Span- 4X40
Sr. No. Item Name Unit Nos Length Width Height/ Depth Area Factor Qty To. Qty.
M-45 for Psc Longitudnel Girder Cum 32 - - - 1401.1
M-45 for Psc Cross Girder Cum - - - - 140.1
Total 0.0
Deck Slab Cum 4 40 16 0.22 0.0
Camber of Deck Slab Cum 8 40 8 0.10 0.0
11 PCC M-15 for Approach slab
Approach slab Cum 2 3.50 16.00 0.15 16.8
Total 33.6
12 RCC M-30 for Approach slab
Approach slab Cum 2 3.50 16.00 0.30 33.6
Total 67.2
13 Reinforcement (HYSD Bars)
Foundation
For abutment 110.00 1118.40 123.0
For Pier 110.00 280.80 30.9
For retaining wall 110.00 427.61 47.0
Total Mt 110.00 2535 - - 278.9 557.7
Sub structure
For abutment 110.00 368 40.4
For Pier 110.00 447 49.2
For retaining wall 110.00 375 41.3
For Return Wall 110.00 142 15.6
Total Mt 110.00 2622 - - 288.4 576.8
For Psc Girder150 kg / cum conc. Mt 150.00 3082 - - 462.4 924.7
Total 2435.1
15 Crash Barrier
Crash barrier RCC Rm 2 160.00 - - 320.0
Total 640.0
16 RCC Railing
Railing RCC 2 167.00 - - 334.0
Total 668.0
17 Elastomeric Bearing
Elastomeric Bearing Cu cm 64 30.000 40.000 6.000 460800.0
Total 921600.0
17 Strip seal Expansion joint
Strip seal Expansion joint Rm 5 - 16.00 - 80.0
Total 160.0
18 Concrete Wearing coat M 30