Box Jacking Explanation: Rohini College of Engineering & Technology
Box Jacking Explanation: Rohini College of Engineering & Technology
Box Jacking
Procedure
jacking slab
The box is then jacked carefully through the ground
Excavation and jacking take place in small increments of advance.
Measure are taken to ensure stability of the tunnel face and to
prevent the ground from being dragged forward by the advancing
box
When the box has reached its final position the shield and jacking
equipment are removed.
•First the box section is designed and cast at the site or can be
transported to the site according to the requirement.
•The foundation boxes are jacked into the ground designed to carry the
dead and the live loads.
•Then the high capacity jacks are placed at the back and it pushes the
box into the ground.
•A purpose designed tunneling shield is provided in the front end.
Throustboring method
ARCHED JACKING
FREEZING OF GROUN
•So when this brine solution is circulated through these pipes it freezes
the ground and the ground behaves like an ice block.
•The spacing of the freezing pipes will vary according to the type of
soil, its permeability and other factors.
•Generally it is kept at a spacing of 1.2 m
PROBLEMS IN FREEZING
ADVANTAGES
DISADVANTAGES
PIPE JACKING
•The thrust pit and the reception pit are excavated at the required
places.
•Then the thrust wall is set up in the thrust pit according to the
requirement.
•In case of mechanized excavations, a very large pit is required.
ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
THRUST SETUP
ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
ADVANTAGES
DISADVANTAGES
•Very costly method.
•Skilled personnel is required.
ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
Then the soil cement is poured into the groove wall, after which the steel
material is built as the core material
Tunnel boring machine (TBM) as mole recent developments in the tunnel driving
technique. The function of TBM is to loosen the earth or break the rock
continuously in the entire section of the tunnel, in to cuttings and convey to the
rear of the machine, where it can be loaded into muck cars or dumpers or on to
conveyor belts for the transportation to the ultimate disposal site.
These machines perform the boring operation through rotation of the front head
against the rock face. The mole has circular cutter head in the front provided with
fixed cutters of desired shape. The cutter head while rotating is pressed against
the rock to cut or pulverize it. The cuttings while failing down is collected in the
buckets provided around the cutter head periphery. These buckets discharge the
muck into a hopper to feed it into the belt conveyor leading to the rear of the
machine. This conveyor then discharges the muck either into the mine car or to
another belt conveyor leading to the portal of the tunnel. The muck of cuttings
can also be disposed off by using the slurry pipelines after mixing the fine muck
into water to form slurry.
For driving through full- face on full-face TRMs number of cutter heads is
mounted on a drum. The drum when rotates in one direction, the individually
driven cutter heads having projected Tungsten carbide tipped tools can be rotated
in another direction and the drum advances into the tunnel face, by providing a
thrust with the help of hydraulic systems. The tips of the tools when worn out can
be easily replaced. The tips are kept cooled by spraying a mixture of water and
compressed air into the cutting area. This also suppress the dust formed during
cutting.
There is very less danger of fall outs in machine bored tunnels, since
adjacent or surrounding rocks are undistributed as no blasting is done.
Mucking is also safe and convenient, since muck is conveyed from the face
to the rear of the machine and is loaded automatically by means to the rear of the
machine and is loaded automatically by means of belt conveyors.
Higher speed of excavation.
Drill jumbo
Drill jumbos used in tunnels are also known as tunnel jumbos. A drill
jumbo is a portable carriage having one more carriage having one or
more working platforms equipped with columns, bars or booms to
support and guide the drills, enabling the drills to perform drilling
operation at any desired pattern. These platforms have arrangement for
the supporting the compressed air pipes, water pipes. The booms are
operated by hydraulic fluid or air and support the drifters, and are
equipped with control enabling the operator to spot a drill in any
desired position conforming to the drilling pattern. The platforms are
constructed as per the size of tunnel and can be raised or lowered so as
to allow mockers or hauling equipment to pass under the jumbo several
drill can be operated from each platform for speedy excavation
The jumbos either on rails on pneumatic tyres depending upon the type
of work. The jumbo can be equipped with electricity feeding cables,
pneumatic concrete placers etc. Mobile jumbos of modern design with
four wheels drive and centrally articulated steering speeds production
and reduce tunneling costs
Drilling
For driving a tunnel number of holes are drilled as per drilling pattern in size
and depth as decided depending upon the size of the tunnel and its formation
Drifters are generally used for drilling in the tunnels where in water is used to
remove the cuttings from the holes instead of compressed air to reduced the
amount of dust in the air. Holes are drilled slightly deeper than the advance per
round to taken care of loss in depth during blasting. Depth advanced due to
drilling and blasting operation is called as one round. Types of well point
systems
a) Line system
b) Ring system
piles
Use of H-piles
H-Piles are used in construction of bridges where they can be driven through
existing construction in small spaces they are used useful for driving close to
existing structures since they cause little displacement of soil. It can be
withstand large lateral forces. They require less space for shipping and storing
than wood, pipe or precast concrete
They not require special slings or special care in handling.
DEEP EXCAVATIONS
Problems normally developed during deep excavations
To prevent the collapsing of sides of the trenches
To prevent water oozing or coming out from the sides and bottom
of the trenches
CE3013 ADVANCED CONSTRUCTION TECHNIQUES
ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
Line system
Ring system
3.4 CAISSON
Caisson has come to mean a box like structure, round or rectangular, which
is suck from the surface of either land or water to some desired depth. Caissons are
of three types:
Box caisson
A box caisson is open at top and closed at the bottom and is made of timber,
reinforced concrete or steel. This caisson is built on land, then launched and
floated to pier site where is suck in position. Such a type of caisson is used where
bearing stratum is available at shallow depth, and where loads are not very heavy.
Open caisson
A small cofferdam that is set in place, pumped dry, and filled with concrete to
form a foundation (as for a pier)
Pneumatic caisson
A caisson in which air pressure is used to keep out the water a pneumatic
caisson is a watertight box or cylinder-like structure that is closed at the top and
open at the bottom, resting on the bed of the water body. They are used for
underwater construction of foundations for bridge piers, abutments in rivers, and
foundations for large multi-story buildings. They are designed to keep water out
of the construction zone and act as a seal that keeps the inside of the caisson dry
for workers to carry out work safely.
The inside of the caisson is kept dry by using compressed air to force water
out of the structure. This process creates an airtight working chamber where
construction activities, such as excavations, can be carried out safely. Pneumatic
caissons are ideal for challenging situations where it is not possible to carry out
wet ground excavations in the open. However, this method is complex, time-
consuming, and relatively expensive when compared to other types of caissons.
SHEET PILES
Sheet piles are thin piles, made of plates of concrete, timber or steel, driven
into the ground for either separating members or for stopping seepage of water.
They are not meant for carrying any vertical load. They are driven into ground
with help of suitable pile driving equipment, and their height is increased while
driving, by means of addition of successive installments of sheets.
1. To enclose a site or part thereof to prevent the escape of loose subsoil, such as
sand, and to safeguard against settlement.
2. To retain the sides of the trenches and general excavation.
4. To protect the foundations from scouring actions of nearby river, stream etc.
3.5 COFFERDAM
Types of cofferdam
2. Braced cofferdam
5. Cellular cofferdam
This method is most commonly used where area is large enough for
allowing excavation to be cut back to stable slopes and where there are no
Pumping is simple and less expansive, but has serious limitations. When fine
sand or cohesion less soil lie below the water, this type of pumping removes
the fine material from the surrounding soil and results in settlement of adjacent
structures. To product it sumps lined with gravel filter are sometimes used.
stages.
The filter wells or well points are usually 1m long and 60 to 75mm
diameter gauge screen surrounding a central riser pipe. The capacity of a single
we;; point with 50mm raiser is about 10 lit/min. Spacing between two well
points depends on the permeability of the soil and on the time available to
effect the drawdown. In fine coarse sand or sandy gravels a spacing of 0.75 to
1m is required, while in silty sands of low permeability a 1.5m spacing is
sufficient .In permeable course gravels spacing should be as low as only
0.3m.A normal set of well point system comprises 50 to 60 points to a single
150 or 200mm pump with a separate 100mm jetting pump.
Pumping from wells, for draw-down depth of than the meters can be
under taken by surface pumps with their suction pipes installed in bored wells.
When dewatering is required to be undertaken from a considerable depth, electrify
driven submersible pumps are installed in deep bore holes with rising main to the
surface. Since heavy boring equipment is used, installation of wells can be done in
all ground conditions including boulders and rocks. Due to higher costs of
installation, this method is adopted where construction period is long and other
methods of dewatering are not possible. Installation of bore well consists of
sinking of a casting having a dia of about 20-30 cm larger than the inner well
casting. The dia of inner well casting depends on the size of submersible pump.
This inner well casing is inserted after complete sinking of borehole screen over
the length where dewatering of the soil is required and it terminates in a 3-5 m
length of unperformed pipe to act as a sump to collect any fine material which
may be drawn through the filter mesh. Screen having slots are preferable to holes,
since there is less risk of blockage from round stones.
A high pressure systems supplies oil for the main jacking cylinders and till
intermediate jacking stations
A low pressure system supplies oil, via hydraulic lines, for the boring head and
conveyor. An auxiliary power pack may be easily installed to double the low
pressure hydraulic flow. This may be necessary for larger and more powerful
boring heads
Thrust yoke
The yoke is the frame that the main cylinders push against to advance
the boring head and pipe. The ring provides a 360 degree surface against the
pipe to minimize point pressure and reduce the chance of breakage.
Skid base
The skid base is the foundation of the pump unit and yoke. It also acts as
a guide for launching the boring head and pipe into the ground.
Power packs
Power packs with high and low pressure systems typically are matched with
the multiple cylinder system.
When tunneling, a lower pressure power pack may be selected to supply oil for
the tunnel boring machine (TBM)
Power required depend on the size and features of the boring head
A mobile electric power pack may be positioned in the boring head/ TBM
CE3013 ADVANCED CONSTRUCTION TECHNIQUES
ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
1. Stay bracing
2. Box sheeting
3. Vertical sheeting
4. Runners
5. Sheet piling
2. Box sheeting
3. Vertical sheeting
4. Runners
Carried out in extremely loose and soft ground which requires immediate
support as the excavation progresses
The runners which are long thick wooden sheets or planks are used in this
arrangement
CE3013 ADVANCED CONSTRUCTION TECHNIQUES
ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
5. Sheet piling
provided when large area is to be excavated for a depth greater than 10m
Used when the soil is soft or loose
Provided when the width of the trench is large
It is also provided when the subsoil water is present
Most of the major earth dams constructed before 1925 were provided with
central concrete core walls or concrete slabs on the upstream face
Concrete slab
When single reinforced slab is adopted, some leakage will occur due to the
hairline cracks so drains should be provided.
Steel plates
Asphaltic concrete
When the membrane is on the upstream side optimum stability condition are
produced ,so the volume of embankment can be reduced
Since the upstream slab is exposed ,damage can be inspected and repaired
easily
The upstream membrane can be built after the embankment is completed
CE3013 ADVANCED CONSTRUCTION TECHNIQUES
ROHINI COLLEGE OF ENGINEERING & TECHNOLOGY
Foundation grouting can be carried out while the dam is being built
The membrane can serve a secondary function as wave protection
The area of the membrane is smaller than that of an upstream facing, so less
material is required
The surrounding embankment protects the internal membrane
The core can be made almost watertight even if cracking develops, by placing
thin layer of clay upstream
A vertical extension of the core membrane below the base of the dam can be
used through soil deposits in the foundation
The length of the grout curtain in is shorter.
cofferdams are constructed around the site of the . Well and is lands are made.
The sizes of the island should be such to allow free working space necessary to
3. Sinking operations
A well is ready to be set in after having cast the curb and having
built first short stage of masonry over it. The well is suck by excavating
material from inside under the curb. In the initial stage of sinking, the well is
unsuitable and progress can be very rapid with only little material being
excavated out. Great care should therefore be exercised during this stage, to
see the well sinks to true position. To sink the well straight it should never be
allowed to go out of plumb.
Excavation and scooping out of the soil inside the well can be
done by sending down workers inside the well till such a stage that the depth
of water inside becomes about 1m.As the well sinks deeper, the skin friction
on the sides progressively increases. To overcome the increased skin friction
and the loss in weight of the well due to buoyancy, additional loading known
as Kent edge is applied on the well.
Pumping out the water from inside the well is effective in sinking
1. The outer surface of the well curb and staining’s should be as regular and
smooth as possible.
2. The radius of the curb should be kept 2 to 4 cm larger than outside of well
staining
3. The cutting edge of the curb should be of uniform thickness and sharpness
since the sharper edge has a greater tendency of sinking than a blunt edge.
4. As soon as tilt exceeds 1 in 200, the sinking should be supervised with
special care and rectifying measures should be immediately taken.
5. Completion of well
When the well bottom has reached the desired strata, further
sinking of the well stopped .A concrete seal is provided at the bottom. The
bottom plug is made bowl shaped so as to have inverted arch action. As
generally under watering concerting as to done, no reinforcement can be
provided. Under watering concreting is done the help of tremie. However,
if it is possible to dewater the well successfully, the concrete can be placed
dry also.
well is capped at its top, with help of reinforced concrete slab. If however sand
has been filled inside, top plug of lean concrete is interposed between the wall
cap and sand filling.
COFFERDAM
Types of cofferdam
2. Braced cofferdam
5. Cellular cofferdam
In most cases, however anchorages may be embedded below ground level, with backstays
connecting them to adjacent towers, or they may constitute the end abutments of the end spans.
In addition to stability sliding, the anchorage structure must also be checked for stability
This method is most commonly used where area is large enough for allowing excavation
to be cut back to stable slopes and where there are no important structures close to the excavation
to effect their stability by settlement resulting from erosion due to water flowing towards the
This method costs comparatively low for installation and maintenance.In this method
one or more sumps are made below the general level of the excavation.In order to keep the
excavator area clear of standing water, a small grip or ditch is cut around the bottom of the
For grater depths of excavation the pump is used or submersible deepwell pump
suspended by chains and progressively lowered down.Pumps suitable for operating from open
sumps are:
Pumping is simple and less expansive, but has serious limitations. When fine sand or cohesion
less soil lie below the water, this type of pumping removes the fine material from the
surrounding soil and results in settlement of adjacent structures. To product it sumps lined with
This system comprises the installation of a number of filter wells generally 1m long,
around the excavation. These filter wells are conducted by vertical riser pipes to a large dia
header main at ground level which is under vacuum from a pumping unit. The water flows to the
filter well by gravity and then drawn by the vacuum upto the header main and discharged
through the pump. This system has the advantage that the water is filleted as it removed from the
ground and carries almost no soil with it once steady discharge conditions are attained. This
system has the limitation of limited suction lift. Therefore for deeper excavations the well points
The filter wells or well points are usually 1m long and 60 to 75mm diameter gauge screen
surrounding a central riser pipe. The capacity of a single we;; point with 50mm raiser is about 10
lit/min. Spacing between two well points depends on the permeability of the soil and on the time
available to effect the drawdown. In fine coarse sand or sandy gravels a spacing of 0.75 to 1m is
required, while in silty sands of low permeability a 1.5m spacing is sufficient .In permeable
course gravels spacing should be as low as only 0.3m.A normal set of wellpoint system
comprises 50 to 60 points to a single 150 or 200mm pump with a separate 100mm jetting pump.
Pumping from wells, for draw-down depth of than the meters can be under taken by
surface pumps with their suction pipes installed in bored wells. When dewatering is required to
be undertaken from a considerable depth,electrity driven submersible pumps are installed in deep
bore holes with rising main to the surface. Since heavy boring equipment is used, installation of
wells can be done in all ground conditions including boulders and rocks. Due to higher costs of
installation, this method is adopted where construction period is long and other methods of
dewatering are not possible.Installation of bore well consists of sinking of a casting having a dia
of about 20-30 cm larger than the inner well casting. The dia of inner well casting depends on the
size of submersible pump. This inner well casing is inserted after complete sinking of borehole
screen over the length where dewatering of the soil is required and it terminates in a 3-5 m length
of unperforted pipe to act as a sump to collect any fine material which may be drawn through the
filter mesh. Screen having slots are preferable to holes, since there is less risk of blockage from
round stones.
Pipe jacking is specialist tunneling method for installing underground pipelines by assembling
the pipes at the foot of an access shaft and pushing them through the ground with the minimum
of surface disruption Component parts of jacking systems The pump unit has two distinct
hydraulic systems A high pressure systems supplies oil for the main jacking cylinders and till
intermediate jacking stations A low pressure system supplies oil, via hydraulic lines, for the
boring head and conveyor. An auxiliary power pack may be easily installed to double the low
pressure hydraulic flow. This may be necessary for larger and more powerful boring heads
Thrust yoke The yoke is the frame that the main cylinders push against to advance the boring
head and pipe. The ring provides a 360 degree surface against the pipe to minimize point
pressure and reduce the chance of breakage. Skid base The skid base is the foundation of the
pump unit and yoke. It also acts as a guide for launching the boring head and pipe into the
ground. Power packs Power packs with high and low pressure systems typically are matched
with the multiple cylinder system. When tunneling, a lower pressure power pack may be
selected to supply oil for the tunnel boring machine (TBM) Power required depend on the size
and features of the boring head A mobile electric power pack may be positioned in the boring
head/ TBM Intermediate jacking stations Installing intermediate jacking stations is a simple