Project Audit
Project Audit
Master Plan:
The Master Plan of the project is generally prepared by Design
Team or external Contractor and approved by BoD. The baseline
schedule (i.e. project plan) using Primavera P6 software which
shows the critical path of the project is included as part of the
Master Plan.
Project Budgeting:
Based on the information gathered from the Project Charter and
discussions with the Finance Team, total budget is approved for
the project by BoD. The budget is detailed to include all the
material, manpower, equipment, etc.
Project Contracting:
A project contractor is hired for the execution of the project. A
competitive bidding process is followed.
Communication Plan:
Communication plan details the processes and procedures for
Communication management. This includes Communication
Approach and Process, Communications Philosophy,
Communications Analysis, Communication Procedures, Roles
and Responsibilities of the Project Team and responsibility
matrix.
Contract Compliance:
All the below at the minimum or as part of the contract should
be obtained and reviewed:
1. Performance Security insurance
2. Advance Payment bond insurance
3. Contractor's Equipment insurance
4.Third party Liability insurance
5. Workmen's compensation insurance
6. Employer's liability insurance
7. Motor vehicle insurance
8. Professional indemnity insurance
Project Schedule:
Based on the project requirements contractor prepares, PMC
reviews and Business Unit approves the baseline cost loaded
project schedules to forecast the key milestones of the project
and expected completion date. Schedule reviews were
performed by the PMC and sends to the contractor for schedule
update.
Risk Management:
1. Stages for effective risk management are as follows:
• Risk Identification Procedure
• Risk Assessment Procedure
• Risk Analysis Procedure
• Risk Response Planning Procedure
• Risk Monitoring and Control Procedure
• Risk Close-Out Procedure
2. PMC prepares a monthly risk register as a record of the
management of risk, once a baseline risk register has been
prepared.
3. Monthly Risk Profile Report based on the analysis of the
revised/ updated risk register is prepared in pre-defined
template.
Change Management Process:
1. Variations and Adjustments in Contract details procedures for
Variation Management and includes Process for:
- initiation
- review of variations
- approval / rejection of variations.
Variations due to Client Request:
1. The client requests the Contractor through PMC to execute
additional works as part of the scope for the project.
2. The contractor reviews the additional scope items and
identifies time and cost impact and submits to the PMC (ROM).
3. The Cost consultant prepares an estimate and compares the
same with the contractor's estimate and informs the Client of
the Price range.
4. Go ahead from client is received on all items.
5. PMC and the Cost Consultant reviews the contractor
estimates and conduct negotiations.
6. The final agreed price and time impact (if any) between the
Contractor, PMC and Cost Consultant are submitted to the
Client for review and approval.
7. Approval is received from the client and is shared with the
Contractor to start the work.
Variations raised by Contractor:
1. The Contractor raises a request for Variation and submits the
list of items.
2. The PMC reviews the same and conducts meeting to clarify
such items.
3. On the agreed items the PMC requests the Contractor and
Cost Consultant separately to provide estimated cost and time
impact.
4. The contractor and cost consultant submits their estimates
(time and cost)
5. The Cost consultant & PMC compares the same with the
contractor's estimate and informs the Client of the Price range.
6. PMC and the Cost Consultant reviews the contractor
estimates and conduct negotiations.
7. The final agreed price and time impact (if any) between the
Invoicing:
1. All Consultants and Contractor raise invoice as per the
process defined in the Contract
2. The invoicing of all consultants and contractor should be as
follows:
- For Contractor Invoicing: PMC, Technical Advisor and Cost
Consultant review the Payment Requests from the Contractor
against the actual progress.
- For PMC Invoicing: Cost consultant review the Payment
Requests from the PMC against the contractual deliverables /
KPIs.
- For TA Invoicing: Cost Consultant reviews the Payment
Requests from TA against the contractual deliverables / KPIs and
sends to PMC for review and endorsement.
- For Cost Consultant Invoicing: PMC reviews the Payment
Requests from the cost consultant against the contractual
deliverables / KPIs.
4. A payment log is maintained to track the actual payments
made against invoices.
3 Project Closing Lessons Learnt Process:
1. Lessons learned for each contract and the Project as a whole
is to be identified and documented throughout the Project life
cycle and compiled as a comprehensive list prior to contract
close-out.
2. Lessons learnt document to be prepared with support from
all the stakeholders for good and bad instances of each contract
and for entire project.
Project Closing:
1. All the deliverables are received before the contract closure.
2. Snag list is prepared to identify any corrective actions to be
taken by the contractor before the Project Completion
Certificate
Key Data Points Document
Alignment of Project Charter with approved scope 1. Project Scope of work
of Works. 2. Project Charter
Alignment of master plan with the Business Strategy 1. Project master Plan
2. Business Strategy
3. Project Charter
1. Alignment of Planned Vs. Actual Progress 1. Project S-Curves (Physical and Financial
Progress)
1. Review the progress report to identify any delays 1. Daily, weekly and monthly progress
and the justifications for the delays. reports
1. Check the detailed progress reports to identify 1. Daily, weekly and monthly progress
any HSC related incidents / events. reports
2. Check the HSE audit plan for compliance and 2. HSE Audit Reports
review the reports for observations
1. Check approved quality plan for complaince and 1. Approved Quality Plan
approvals
1 Strategy Infrastructure- Absence of or inadequate policies and procedures leading to Infrastructure department follows the workflow process defined for 1. Policies and Procedures for - Obtain and review workflow process for project
Estimation & ineffective implementation of Procurement processes. project development team. Infrastructure department development team to ensure all operational aspect of
Planning 3-Moderate 3-Possible 6 2. Delegation of Authority infrastructure department are covered adequately.
2 Operational Infrastructure- Absence of detailed Project Charter (including project need, A high level presentation is made to the Tender & Project Committee (T 3. Approved project Charter for the Obtain approved project charter for sample projects to
Estimation & scope, objectives, key stake holders, high level budget, key &PC) for approval; referred to the Board when deemed necessary by T selected project(s) validate following:
Planning risks and ROI etc.) to formally authorize the project. &PC. - Project charter approved by the Tender & Project
Committee/ Board.
2-Minor 2-Unlikely 4 - Validate if project objective, high level scope of work, key
risks, stakeholder roles and responsibility etc. included in the
project charter.
3 Operational Infrastructure- Absence/ Delay in defining technical and commercial - Tamouh involves Consultant for tendering and bidding process to 4. Technical and commercial - Obtain the Evaluation Criteria and scoring guidelines and
Estimation & evaluation parameters may result in favoring of one of the finalize the contractor. As per the scope, PMCs are responsible for Evaluation Criteria verify if the scores against each criteria were given as per the
Planning bidders and selection of incompetent vendor. bidder's technical and commercial evaluation and award 5. Technical and commercial guidelines.
recommendation. evaluation report including - Obtain and review consultant's evaluation report to ensure
3-Moderate 3-Possible 6 - Based on the Consultant's award recommendation, T&PC finalize the contractor's scores against the technical and commercial evaluation are carried out
contractor and issue LOA. evaluation criteria for the selected adequately and recommendation is made to T&CP
project(s) accordingly.
4 Operational Infrastructure- Inadequate review of estimates prepared by in-house - In case consultant involves in estimation, consultant prepares the 6. Final Estimate and budget for - Obtain and review the estimate and budget prepared for
Estimation & estimation team / third party QS firm to ensure BOQ is in line estimate and budget. master plan (detailed estimation master plan.
Planning with design specification and client BOQ. - In case in-house team involves in estimation, CM/ QS/ Contract sheet) - Review the benchmark considered for initial estimate and
department prepares the estimate and budget. 7. Benchmark considered for initial correlation with current market price.
- CD, CDO and ExCom review and approve the estimate and budget for estimate and correlation with current - Review the calculation and interlinking with different tabs
3-Moderate 3-Possible 6 master plan. market price, if any of estimation sheet.
- On yearly basis, Infrastructure Director reviews the estimation sheet
and update the budget based on actual site condition and existing
contract for similar service.
5 Operational Infrastructure- Inadequate or absence of documentation to capture key - Assumption and justification are captured in the estimation sheet for 8. Assumptions and justifications - Obtain and review master plan estimation sheet and validate
Estimation & assumptions made during project estimates to help project future reference. considered for master plan estimation the justification and assumption highlighted against the
Planning team during execution phase. 3-Moderate 2-Unlikely 5 - In case of any update in the unit price, explanation are captured for change.
future estimate/budget update.
Operational Infrastructure- Inaccurate cost to complete report / analysis by Project team/ - Tamouh receives comprehensive monthly reports from PMC. 9. Last 6 weekly and monthly - Obtain and review periodic cost report, monthly and weekly
Estimation & cost consultant on account of incomplete cost components, - In-house team also updates the expense record and contract summary progress and cost reports for the progress reports generated by project team to ensure effective
6 Planning inaccurate basis for estimation. 2-Minor 2-Unlikely 4 report to monitor the cost performance. selected project(s) including Cost to cost monitoring.
complete estimates
Operational Infrastructure- Absence of consistent and comprehensive procedure for Contractor invoices are reviewed and verified by PMC and Tamouh 10. Contract agreement for selected - Obtain contract agreement for sample projects.
Estimation & verification and approval of invoices from consultants and before payment. Payment to contractor is done as per agreed terms project(s) - Review the payment certification and invoicing procedure
Planning contractors. mentioned in contract. In case of consultant payment, Tamouh reviews 11. Last 6 approved invoices along stipulated in the contract agreement.
and verifies the invoice before releasing the payment. with progress certificate and other - Obtain sample invoices along with progress certificate and
supporting documents for the selected other supporting documents.
project(s) - Verify whether progress certificate is endorsed and
7 2-Minor 2-Unlikely 4 12. Updated invoice tracker for the approved by project team.
selected project(s) - Verify whether invoice figures are matching with progress
certificate and necessary adjustment and deductions i.e.
retention money, advance payment deduction etc. has been
done.
Operational Infrastructure- Absence of a formal process to document/ capture lessons - Contractor prepares the close out report which captures financial 13. Lessons learnt register for the - Verify if lessons learnt document has been prepared by
Estimation & learnt from previous / current projects experience. summary, status, s-curve & histogram, lesson learned and list of selected project(s) contractor / consultant.
8 Planning 3-Moderate 2-Unlikely 5 documents for dossier. - Verify if all learning experience has been captured
adequately in the lesson learnt register.
Operational Infrastructure- Absence of comprehensive and documented risk management Tamouh relies on PMC / Contractor to provide risk registers relevant to 14. Risk management procedure, if - Obtain risk management procedure.
Estimation & process / risk register in project execution phase. the specific project. any - Obtain last 6 month's updated risk register to validate if risk
Planning 15. Updated risk registers for the past register has been updated on time.
6 months for the selected project(s) - Validate if all project related risk has been captured in the
register.
- Validate if captured risk has been evaluated as per the
approved procedure.
9 3-Moderate 2-Unlikely 5 - Validate if a mitigation plan is in place along with assigned
responsibility and timeline for each risk.
- Validate if risk has been discussed and adequate action has
been taken to mitigate the risk by project team.
Compliance Infrastructure- Risk of non compliance with statutory requirements (e.g. All compliance requirements are managed by the PMC. 16. Updated regulatory authority
Estimation & licenses/ permits/ regulations from statutory bodies and approval tracking sheet
10 Planning government, e.g. RERA, BIM, Civil Defense, Dubai/ Abu 3-Moderate 2-Unlikely 5
Dhabi Municipality etc.).
Compliance Infrastructure- Delays in obtaining necessary authority approvals (e.g. All documents are submitted to regulatory authorities in a timely
Estimation & licenses/ permits/ regulations from statutory bodies and manner. - Obtain authority approval tracking sheet to ensure
11 Planning government - RERA, BIM, Civil Defense, Dewa, Dubai/ Abu 3-Moderate 2-Unlikely 5 adherence with the timeline and requirement.
Dhabi Municipality etc.).
Compliance Infrastructure- Lack of awareness and knowledge of local regulations Tamouh has no regulatory tracking mechanism, this risk is covered by
12 Estimation & amongst stakeholders new to UAE. 3-Moderate 2-Unlikely 5 the PMC.
Planning
Operational Infrastructure- Absence of clearly defined roles and responsibilities may lead Tamouh has approved organization structure with defined roles. 17. Approved organization structure - Obtain and review approved roles and responsibilities
Estimation & to ambiguity in decision making at different stages of project. Workflow process also defines the roles of each department involved including roles and responsibilities document to ensure roles are clearly defined and aligned with
13 Planning 3-Moderate 2-Unlikely 5 during project lifecycle. for the selected project(s) the project requirements.
Operational Infrastructure- Absence of review of project progress on a continuous basis PMC is responsible for timely reporting and arranging of review 18. Past 6 monthly / weekly progress Obtain and review sample periodic reports to ensure the
Estimation & leading to inadequate monitoring and absence of timely meetings. reports for the selected project(s) following:
14 Planning corrective actions to avoid delay in completion of project. 3-Moderate 3-Possible 6 along with distribution email - Reporting frequencies;
- Reporting structure and content.
Operational Infrastructure- Absence of approved site HSE plan and HSE monitoring PMCs are responsible for compliance with QHSE requirements. 19. Approved HSE plan for the Obtain and review approved site HSE Plan, periodic HSE
Estimation & mechanism may lead to reputational loss due to accidents and selected project(s) reports to ensure adequate monitoring of HSE related issues.
15 Planning injury. 3-Moderate 3-Possible 6 20. Past 6 monthly / weekly HSE
reports for the selected project(s)
Operational Infrastructure- Failure to deliver project on time and as per contract terms Infrastructure Director and PMC monitors contractor performance 21. Approved baseline and updated - Obtain baseline and updated project schedule along with
Estimation & may lead to financial loss and reputational damage to the against the program, deliverables, and milestones in line with progress project schedule for the selected progress report to verify whether ETC has been reviewed and
Planning company. measurement and reporting system set out in the contract. project(s) (Primavera / MSP, PDF reported.
and Excel file) - Validate if contractor has submitted catch up plans to
16 3-Moderate 3-Possible 6 22. Crashing Plan / Catch up Plan mitigate the delays.
prepared for the selected project(s)
Operational Infrastructure- Inadequate evaluation of consultant / contractor's performance Tamouh has no defined procedure for consultant / contractor's 23. Contractor's and Consultant's Obtain and review post contract consultant / contractor's
Estimation & post contract closure may lead to selection of non-performing performance evaluation post contract closure. performance evaluation for the performance evaluation guidelines
17 Planning consultant / contractor being selected for future projects which 3-Moderate 3-Possible 6 selected project(s)
may further affect the quality project.
Operational Infrastructure- Inadequate monitoring of the budget may lead to project cost - Tamouh receives comprehensive monthly reports from PMC. 24. Approved budget amendments, if - Check the approved budget for any amendments.
Estimation & overruns - In-house team also updates the expense record and contract summary any for the selected project(s) - Check if approvals were taken before the amendments were
18 Planning 3-Moderate 2-Unlikely 5 report to monitor the cost performance. made.
Department / Function: Projects
24
25
26
27
Tendering & Procurement
28
29
30
31
32
33
34 Contract Management
35
36
37
38
39 Inventory & Material Management
40
41
42
43
Risk Management
44
45
46
47
Project Governance
48
49 Project Governance
50
51
52
53
54 QHSE
55
56
57
58 Sustainability
59
60
Project KPI Assessment
KPI
Project Internal Rate of Return (IRR)
Adherence to Feasibility Budget (Design to Cost Target)
Adherence to Feasibility Timeline
Timeliness for Release of Monthly Executive Dashboard Reporting
Type of Reporting used in organization
Timeliness of Decisions from Executive Management
Schedule Performance Index by Phase and Project
Schedule Completion Risk Probability Trending
Aging of Problems Reported - Schedule & Progress Related
Average response time for design team for site-related design issues
Average timelines for addressing Request for Information
Average timelines for addressing change requests in Design
Number of Non-Compliances / Delay in Design MIS Submission
Manpower deviations from the Planned histogram
Use of Leading Project Management Tools
Use of Leading Document Management Tools
Cost Performance Index by Phase and Project
Cost Completion Risk Probability Trending
Aging of Problems Reported - Cost Related
Turnaround time for invoicing and payment receipts
Demonstrated Time savings by Project Parties
Demonstrated Cost savings by Project Parties
Number of Value Engineering & Value Management Workshops conducted across each Project Phases