Chapter 1 Part 2 Earthworks
Chapter 1 Part 2 Earthworks
1.1 Earthwork
INTRODUCTION
• Earthwork: the processes whereby the surface of the
earth is excavated and transported to and compacted
at another location.
o the choice and efficient use of the correct types and size
of plant to meet the particular requirements of the site.
o Weather condition
SCOPE OF EARTHWORKS
Site clearing
Parameters to be checked on before commencing the clearing works;
marking of the respective area to be cleared and grubbed
checked the cut-off elevations
checked depth and size of trees to be removed
identified clearly and verified the existing utilities and services
lines
ensure that monuments, markers and special trees are
properly marked for protection.
marks all trees and vegetations that are to be undisturbed
potential hazard such as flammable area, slipping area, etc.
terrain, soil condition and foliage
ensure that sub contractor has proper controls of erosion and
drainage
environment protection plan has been approved and the
contractor is familiar with the requirements
Site clearing
• Site Clearing Involves;
demolition of existing buildings,
the grubbing out bushes and trees,
disposal works and
the removal of top soil to reduce level.
To be continue…..
Links to learning
materials
Site clearing:
https://www.youtube.com/watch?v=f3XKGOaqYUU
Earthwork Cuts & Fills
https://www.youtube.com/watch?v=dZKzPIvR5Wc
Soil transportation
https://www.youtube.com/watch?v=PY5z08F1_kk
Compaction
https://www.youtube.com/watch?v=MgvUDs5tcu0
Sloping
https://www.youtube.com/watch?v=BBRI9QvWa4k
https://www.youtube.com/watch?v=y8X2q5DWLH4
CUTTING AND EXCAVATION
Cutting and excavation
• Most construction projects require the movement of earthwork on site. This will
result in altering the existing elevation to a different or finish elevation.
• To determine the amount of soil to be moved, the estimator needs to have a plot
plan or topographic survey.
Purposes
Topsoil excavation
Earth excavation
Rock excavation
m/f
m/f
Cell
The Grid Method…cont.
vertical axis
2. On a piece of graph paper, plot out the
existing elevations from the beginning to
the end of each cross-section line.
Proposed
elevations
Horizontal
Axis
Cut and Fill Calculation
3. The vertical axis is for elevations and the
horizontal axis is for the distance along the cross-
section.
Construction Site
The Cross-section Method...Cont.
https://www.youtube.com/watch?v=TfqNK4v73nk
QUIZ