ACCROPODE™ II - Basic Specifications - Version D
ACCROPODE™ II - Basic Specifications - Version D
ABSTRACT OF
TM
ACCROPODE II
Technical Specifications
Warning: Limited validity
ABSTRACT OF
TM
ACCROPODE II
Technical Specifications
--
Presentation Note
The ACCROPODE™ II and ECOPODE™ blocks being similar (except the skin aspect and formworks),
information contained in this document is valid for both armour types.
Contents
INTRODUCTION .............................................................................................. 1
LEGAL PROVISIONS ...................................................................................... 1
CLI COORDINATES ........................................................................................ 2
PRESENTATION OF THE TID AND AIM ........................................................ 2
PRESENTATION .............................................................................................................. 2
AIM ................................................................................................................................. 3
PROVISIONS CONCERNING SAFETY .......................................................... 3
TECHNICAL ASSISTANCE FROM CLI .......................................................... 3
STANDARDS ................................................................................................... 4
INTRODUCTION
In relation to its specialised activity in coastal The CONTRACTOR shall comply with all
engineering, ARTELIA Eau et Environment, Sub-Licence requirements associated with
Licensor of the ACCROPODE™ II Technique the use of these concrete armour blocks and
has designed and developed a special obtain the conditions for their use from CLI
system of artificial armour blocks for whose coordinates are given below.
defences protecting maritime and river
structures against waves and currents, Generally, it has always been CLI’s policy to
together with a specific unit fabrication continuously improve its products. CLI
process using moulds. therefore reserves the right to make changes
in guidelines and specifications and to make
The artificial units referred to hereinabove additions or improvements to its products
are known under the trade name without incurring any obligation to
"ACCROPODE™" II which is a distinctive incorporate the new changes on previous
TRADEMARK registered internationally. applications.
LEGAL PROVISIONS
This document is an abstract from the This document is provided to
TECHNICAL INFORMATION DOCUMENT DESIGNERS and CONTRATORS before
(TID) referred to in the contract granting the the construction stage to allow them to
right to use the ACCROPODE™ II technique carry out their preliminary tasks. The full
for a designated project. TID shall be supplied to the
CONTRACTOR before the start of the
The CONTRACTOR is required to comply with construction works once the sub-license
the legal provisions in force. contract is effective.
CLI COORDINATES
6, rue de Lorraine
38 130 ECHIROLLES – France
Presentation
1) Specifications The SPECIFICATIONS section of the TID document
corresponds to the bases of the ACCROPODE™ II
technique. The specifications are the compulsory
requirements that must be followed to achieve the quality
standards of the ACCROPODE™ II trademark and meet the
characteristics defined by the international patent registered
in the name of ARTELIA. The “project specifications” can be
used if the variations from the CLI’s specifications are
compatible with the ACCROPODE™ II technique and
approved by the Designer of the structure.
3) Data sheets The data sheets are documents to help provide the
CONTRACTOR with additional information on particular
points of the structure or on working methods.
They may be obtained on request by the CONTRACTOR.
STANDARDS
The standards used for implementing the ACCROPODE™ II technique are European
standards. However, the CONTRACTOR may choose to use other equivalent standards in
accordance with the Works Contract.
For reference purposes, the following is a list of the original standards used. The Contractor is
responsible for ensuring that the most recent versions of these standards are used.
NF EN 196-1 Methods of testing cement - Part 1: Determination of strength
NF EN 196-2 Methods of testing cement - Part 2 : chemical analysis of cement
NF EN 196-3 Methods of testing cement - Part 3 : determination of setting times and
soundness
NF EN 196-7 Methods of testing cement - Part 7 : methods of taking and preparing
samples of cement
Methods of testing cement. Determination of the chloride, carbon dioxide
NF EN 196-21
and alkali content of cement
Cement - Part 1 : composition, specifications and conformity criteria for
NF EN 197-1
common cements
NF EN 197-2 Cement - Part 2 : conformity evaluation
NF EN 206-1 Concrete - Part 1 : specification, performance, production and conformity
Fly ash for concrete - Part 1 : definition, specifications and conformity
NF EN 450 criteria
NF EN 932-1 Tests for general properties of aggregates. Part 1 : methods for sampling
Tests for geometrical properties of aggregates. Part 1 : determination of
NF EN 933-1
particle size distribution. Sieving method
Tests for geometrical properties of aggregates. Part 2 : determination of
NF EN 933-2
particle size distribution. Test sieves, nominal size of apertures
Tests for geometrical properties of aggregates. Part 3 : determination of
NF EN 933-3 particle shape. Flakiness index
Tests for geometrical properties of aggregates. Part 8 : assessment of
NF EN 933-8 fines. Sand equivalent test
NF EN 933-9 Tests for geometrical properties of aggregates - Part 9 : assessment of
fines - Methylene blue test
NF EN 934-2 Admixtures for concrete, mortar and grout - Part 2 : concrete admixtures -
Definitions, requirements, conformity, marking and labelling
Mixing water for concrete - Specification for sampling, testing and
NF EN 1008 assessing the suitability of water, including water recovered from
processes in the concrete industry, as mixing water for concrete
NF EN 1097-3 Tests for mechanical and physical properties of aggregates - Part 3 :
determination of loose bulk density and voids
Tests for mechanical and physical properties of aggregates - Part 6 :
NF EN 1097-6
determination of particle density and water absorption
Determination of compressive strength of lightweight aggregate concrete
NF EN 1354
with open structure
Tests for thermal and weathering properties of aggregates - Part 1 :
NF EN 1367-1 determination of resistance to freezing and thawing
NF EN 1744-1 Tests for chemical properties of aggregates. Part 1 : chemical analysis
NF EN 12350-1 Testing fresh concrete - Part 1 : sampling
Testing hardened concrete - Part 1 : shape, dimensions and other
NF EN 12390-1 requirements for test specimens and moulds
NF EN 12390-2 Testing hardened concrete - Part 2 : making and curing specimens for
strength tests
NF EN 12390-5 Testing hardened concrete - Part 5 : flexural strength of test specimens
Testing hardened concrete - Part 6 : tensile splitting strength of test
NF EN 12390-6 specimens
NF EN 12620 Aggregates for concrete
Pigments for the colouring of building materials based on cement and/or
NF EN 12878
lime - Specifications and methods of test
Curing compounds - test methods - part 1: determination of water
PR NF EN 14754-1 retention efficiency of common curing compounds
NF P 15-317 Hydraulic binders - Sea-water resisting cements
Rock Manual Manual for the use of rock in hydraulic engineering
ABSTRACT OF
TM
ACCROPODE II
Technical Specifications
Warning: This document has been updated at the date of issuance by
CLI. The updates include important improvements for a proper
implementation of the works. It is recommended to obtain the last
update by contacting CLI.
Contents
1.CHARACTERISTICS OF THE ACCROPODE™ II BLOCK ......................... 1
1.1 - GEOMETRIC CHARACTERISTICS ......................................................................... 1
1.2 - ACCROPODE™ II BLOCK DRAWINGS ................................................................. 1
2.ACCROPODE™ II BLOCK FORMWORK.................................................... 2
2.1 - FORMWORK PRINCIPLE ........................................................................................ 2
2.2 - DESIGN .................................................................................................................... 2
2.3 - FORMWORK FABRICATION TOLERANCE ........................................................... 2
3.FABRICATION OF ACCROPODE™ II BLOCKS ........................................ 3
3.1 - CONCRETE.............................................................................................................. 3
3.1.1 - Main characteristics of concrete ................................................................................. 3
3.1.2 - Other characteristics ................................................................................................... 3
3.1.3 - Durability of concrete .................................................................................................. 4
3.1.4 - Production monitoring ................................................................................................. 4
3.2 - GENERAL SIMPLIFIED FABRICATION PROCEDURE.......................................... 4
3.2.1 - Installing the formwork ................................................................................................ 4
3.2.2 - Pouring........................................................................................................................ 4
3.2.3 - Vibration ...................................................................................................................... 5
3.2.4 - Setting and hardening ................................................................................................. 5
3.2.5 - Form striking ............................................................................................................... 5
3.2.6 - Curing ......................................................................................................................... 5
3.2.7 - Transporting blocks..................................................................................................... 5
3.2.8 - Storage ....................................................................................................................... 5
4.ACCROPODE™ II UNITS ACCEPTANCE CRITERIA................................. 6
4.1 - BLOCK CLASSIFICATION ...................................................................................... 6
4.2 - BLOCK WEIGHT ...................................................................................................... 6
5.ARMOUR UNDERLAYER AND TOE ........................................................... 7
5.1 - PRESENTATION ...................................................................................................... 7
5.2 - GEOMETRIC CHARACTERISTICS OF THE UNDERLAYER ................................. 7
5.3 - CHECKING THE UNDERLAYER............................................................................. 8
5.3.1 - Purpose....................................................................................................................... 8
5.3.2 - Equipment ................................................................................................................... 8
5.3.3 - Minimum method ........................................................................................................ 8
5.3.4 - Additional inspection ................................................................................................... 8
6.PLACING ACCROPODE™ II BLOCKS ....................................................... 9
6.1 - AIM ........................................................................................................................... 9
6.2 - PLACING DRAWINGS ............................................................................................. 9
6.2.1 - General principles for placing drawings ...................................................................... 9
6.3 - PARTICULAR MINIMUM CONDITIONS FOR PLACING ARMOUR BLOCKS ....... 9
6.3.1 - Positioning system ...................................................................................................... 9
6.3.2 - Placing under water .................................................................................................. 10
6.4 - PLACING DENSITY ............................................................................................... 10
6.4.1 - Calculation of placing density ................................................................................... 10
6.4.2 - Placing density tolerances ........................................................................................ 10
6.5 - CALCULATION OF THEORETICAL NUMBER OF BLOCKS TO PLACE............ 10
6.6 - VALIDATION OF THE ARTIFICIAL BLOCK ARMOUR ........................................ 10
7.DOCUMENTS TO BE PRODUCED FOR THE STRUCTURE ................... 11
The block shape must be scrupulously reproduced in order to guarantee the structural capability and
stability of the ACCROPODE™ II block.
Content of drawings
001 Shape definition drawing
002 Drawings of individual plates
003 Simplified formwork drawing (this is not a working drawing)
The ACCROPODE™ II formwork consists of two symmetrical, bottomless half-shells that can be
separated. They are assembled to create a mould into which the concrete is poured.
The two half-shells are struck using a jack that presses on the end of the noses, thus detaching the
form from the ACCROPODE™ II block.
2.2 - DESIGN
The CONTRACTOR is responsible for designing the formwork and all ancillary parts. The design must
comply with all standards in force. Safety devices such as access gangways must be sized in
accordance with local legislation.
1. Jig: ±1mm
4. The volume of the block produced with the form must be at least equal to the theoretical
volume
3.1 - CONCRETE
3.1.1 - Main characteristics of concrete
The present specifications are given in relation to standard EN NF 206-1
Criteria Specifications
3
Minimum 28-day strength for blocks ≤ 4m C25/30 (25 MPa on cylinder and 30 MPa on cube)
3
Minimum 28-day strength for blocks > 4m C30/37 (30 MPa on cylinder and 37 MPa on cube)
Exposure class (unless specified otherwise by the XS3: Parts of marine structures, tidal range area subject to splashing
CLIENT)
3
Minimum 28-day tensile strength – Blocks ≤ 4m 2.5 Mpa
Brazilian test / Fct,sp
3
Minimum 28-day tensile strength – Blocks > 4m
Brazilian test / Fct,sp 3.0 MPa
Workability: consistency S2 to S4
These values are given for general situations, and are to be used in all cases that do not call for any
particular precautions. However, the CONTRACTOR may propose lower values if he can provide
proof that they do not affect the structural integrity of the block.
Furthermore, the CONTRACTOR must take special care in choosing the cement to be used and the
quality of the aggregates. They must be compatible with the durability required by the structure's
designer.
The recommended tests and sampling procedures are those given in standard EN NF 206.1
The formwork must be positioned so that it is stable throughout the operations and perfectly
watertight.
3.2.2 - Pouring
Concrete must be poured in layers of suitable thickness to ensure adequate compaction.
3.2.3 - Vibration
Each layer of concrete must be vibrated to remove air bubbles and ensure adequate compaction. The
degree and duration of vibration must be adapted to ensure that it fulfils its role, but special care must
be taken to avoid any segregation of the concrete constituents.
3.2.6 - Curing
Blocks must be cured after being removed from the forms, either with a chemical or with water
(14 days in the case of water), to prevent the water from evaporating quickly.
Blocks are to be transported in such a way that they do not suffer any impact liable to affect their
integrity.
3.2.8 - Storage
Blocks are to be stored resting on three points or vertically if their stability is properly ensured. Blocks
less than 6 m³ may be stored in two layers. The ground must be able to support the weight without any
differential settlement or scouring that could destabilise the blocks.
Category C The blocks have major defects These blocks are rejected and must not be used on
the structure
5.1 - PRESENTATION
The underlayer of the concrete armour consists of natural rockfill but other materials such as shattered
concrete may be included when the structure's designer has clearly specified this.
The size and characteristics of the underlayer rockfill are defined by structure's designer. However the
following principles are recalled to ensure that the underlayer is suited to the armour:
Rocks must be sufficiently large to prevent them from escaping through the armour. If they should
have large flat surfaces they must not create any slip plane. Underlayer placing tolerances must be
observed regardless of the size of the rocks used.
Underlayer rockfill
Category Item Values Note
N.U.L. Refer to the design tables available on the CLI
Unit weight of rockfill
N.L.L. website www.concretelayer.com
Grading L: largest dimension
L+G/2E ≤ 3 and G: largest measurable dimension perpendicular
Dimensions L/E<3 to direction L
E largest dimension perpendicular to plane LG
Measured vertically. H is the height of an
Local defects in underlayer +/- H/6 armour block valid at all points of the
Underlayer underlayer, or else on berms.
tolerance
Generalised deviation of the Mean value calculated from measurements on 3
underlayer +/- H/10 profiles spaced no more than 10 m apart
The ease with which the blocks can be placed and the resulting quality of the armour facing depend to
a large extent on the quality of the underlayer rockfill and in particular the geometric tolerances of the
last two lines in the above table. If these criteria are not met, this could have detrimental
consequences on block placing time and on the stability of the entire armour facing.
The rockfill quality shall comply with the specifications of the designer of the structure. If the designer
of the structure does not define any specific requirements, then it is suggested that the
CONTRACTOR will refer to applicable standards such as the Rockfill Manual "The use of rock in
hydraulic engineering", 2009. Approval will have to be obtained from the ENGINEER prior to
commence the works.
5.3.2 - Equipment
The CONTRACTOR is free to choose the type of equipment to be used for measuring the underlayer.
It may be mechanical (soundings along the underlayer) or electronic (single- or multi-beam sonars).
1 profile every 10m along the breakwater. This minimum may be lowered to 5 m in complex areas.
Each profile will involve at least one sounding every H m (H = block height) along the slope, taking care
to investigate precisely the foot of the underlayer, the horizontal berm and the crest of the
underlayer, The berm at the foot of the structure is measured over a minimum distance of 2H from
the angle formed by the slope and flat part of the structure.
The fact that the profile surveys can be spaced up to 10 m apart does not alter the requirement that
the tolerance must be observed at all points of the underlayer.
The CONTRACTOR must take all necessary measures to ensure that this tolerance is observed
between profiles. If necessary the profiles can be surveyed much closer together.
Armour block placing must not begin under any circumstances until the underlayer has been validated
by the ENGINEER.
6.1 - AIM
The aim of placing work is to obtain a stable armouring that complies with the fundamental principles
of the ACCROPODE™ II technique:
Placing density within the limits set out in section 6.4.
Blocks are in a single layer and no block must be out of profile (less than 1/3 of the block outside
the armour). Each block is in contact with the underlayer.
Blocks are interlocked with one another and not free to move.
The lozenge-shaped grid is used everywhere. Local exceptions are tolerated.
The underlayer rockfill cannot escape if there are any gaps between blocks.
Blocks are placed in mostly varied attitudes.
At the beginning of work on site, the CONTRACTOR must make a precise estimation of the number of
blocks needed for the structure. This estimation involves a theoretical calculation based on the
number of blocks per 100 m² indicated by CLI (refer to CLI web site with the “design tables” ) and the
area to be covered.
For the inspection to go smoothly, the CONTRACTOR shall forward the Technical Specifications to
the CLIENT and ENGINEER. The CLIENT and / or the ENGINEER may instruct the CONTRACTOR
to organise a training session by a CLI specialist for the ACCROPODE™ II armour layer works
approval. CLI is not in charge of approving the works.
Inspections should be performed as work progresses.
Documents handed to CLI are for information purposes only and CLI may express its technical opinion
on them. The documents to be handed over to the ENGINEER or CLIENT are those for monitoring
works implementation.
The CONTRACTOR is left to choose the monitoring system, but the following documents at least must
be produced:
ENGINEER/CLIENT CLI
DOCUMENTS TO PRODUCE For approval For information
Theoretical drawings of the structure (plan view/typical At least 3 weeks before starting
sections) works
Detailed block fabrication procedure Before starting fabrication Before starting fabrication
Inspection of form dimensions Before starting fabrication Production of forms
Concrete design mix documents Before producing blocks Before producing blocks
Concrete trial mix documents Before industrial block Before industrial block
production production
Traceability sheet for each block During block production First month of fabrication
Block weights During block production First month of fabrication
Concrete inspection/traceability records During block production First month of fabrication
Detailed procedure for placing the underlayer and armour
Before start of block placing Before start of block placing
blocks
Profiles of the underlayer every 5m or 10 m Throughout works First month of placing
Underlayer inspection report
Photographs of the underlayer Throughout works First 100 metres
Block placing monitoring sheet Throughout works First 50 blocks
As-built drawings of block placing (AutoCAD format) Throughout works End of works
Density calculations area by area over the entire structure As placing progresses First month of placing
End of works unless anomaly
Periodic survey of settlement reference points observed If anomaly observed