BM PACKAGING (PTY) LTD v. PPC BOTSWANA (PTY) LTD 1998 BLR 309 (HC)
BM PACKAGING (PTY) LTD v. PPC BOTSWANA (PTY) LTD 1998 BLR 309 (HC)
Case No:
Judge: Mosojane J
Counsel:
Considered Ropace Botswana (Pty) Ltd v. Dawson and Fraser (Pty) Ltd [2001] 1 B.L.R. 479 (HC)
Referred to Fencing Centre (Pty) Ltd v. Murray & Roberts Construction and Others [2002] 2 B.L.R.
269 (HC) Distinguished Botswana Ash (Pty) Ltd v. Zuzumbe
Flynote
Headnote
Held:
(1) on the interpretation of clause 15 of the agreement, if either party required that a dispute should
be referred to an arbitration, the other party must accede to it, in that the parties had agreed to do
so in advance in terms of the contract. A party to the agreement could not unilaterally elect to
proceed to court for the purpose of resolving any dispute and thus deprive the other party of its
contractual right to arbitration.
(2) It is well established that a dispute must exist before any question of arbitration can arise. On
the evidence, a G dispute did exist between the parties at the time of issue of summons and prior
thereto.
(3) The defendant did state in its special plea that it was willing and able to submit to an arbitration
in terms of the provisions of clause 15 of the agreement. Such a plea is the equivalent of the
exceptio litis pendentis in the case of a pending suit. Thus filing of the special plea by the defendant
unequivocally constituted the expression of H willingness and ability on the part of the defendant to
arbitrate the dispute. Stanhope v. Combined Holdings and Industries Ltd. 1950 (3) S.A. 52 at p. 57D
applied.
(4) The defendant was not precluded from applying for a stay of the proceedings by virtue of the
provisions of section 6 of the Arbitration Act. The defendant was entitled to raise in a special plea an
arbitration clause as the procedure provided in the Arbitration A Act was not obligatory but
permissive and did not derogate from the practice of pleading the submission clause either by way of
a preliminary plea or by way of defence. Rhodesian Railways Ltd. v. Mackintosh 1932 A.D. 359 at p.
371 and Street v. Dublin 1961 (2) S.A. 4 applied.
(5) A court has a discretion whether or not to stay proceedings, but it would generally do so once it
was satisfied that a dispute fell within an ambit of an arbitration, and a very strong case would have
to be made before a court B would exercise its discretion so as to preclude the operation of an
arbitration agreement. In the instant case, the action would be stayed pending resolution of the
matter by arbitration.
Case Information
Judgment
Mosojane J.:
It is common cause between the parties in this matter that on or about 21 December 1994 in
Gaborone the parties concluded a written agreement styled a "Supply Agreement". The agreement
contains various dispute resolution provisions the most material of which, in so far as these
proceedings are concerned, is clause 15.1 which provides in part: G
"Subject to any clause providing for an alternative procedure, should any disputes or differences
whatsoever arise at any time between the parties concerning this agreement or its construction or
effect or as to the rights, duties and/or liabilities of the parties or either of them under or by virtue
of this agreement or otherwise or as to any other matter in any way H arising out of the subject
matter of this agreement then either party (The emphasis is mine.):
15.1.1 may declare a dispute by delivering the details of the dispute to the other party, and
1998 BLR p312
MOSOJANE J
15.1.2 request that the dispute be referred to by the parties . . . to mediation by a single
mediator at a place and time to be A determined by him;
15.1.3 if, within 30 days of the delivery of the declaration of a dispute, the parties have not
agreed to accept mediation then the dispute shall be determined by arbitration as prescribed
below." B
Then follows the provisions relating, inter alia, to agreement for appointment or selection of a
mediator and/or arbitrator).
On 25 September 1996 the plaintiff caused a writ of summons to be issued out of this court claiming
against the defendant an amount of Pl,292,798.00 as penalty or compensation for the loss of
revenue suffered by the plaintiff C from the failure by the defendant to order and take delivery of
the target number of bags of cement in terms of the said supply agreement, it being also alleged
that the defendant failed and/or refused to make payment notwithstanding demand. The defendant
duly registered an appearance to defend and subsequently filed its plea denying the claim and at the
same time counterclaimed against the plaintiff. It also filed a special plea pleading D that the
plaintiff was obliged to have recourse to the provisions of clause 15 of the agreement before
attempting to enforce its claim by way of litigation in a court of law and further that the plaintiff's
action, was in the premises, inapposite and ought to be stayed pending arbitration.
It is not necessary to set out in any detail the claims of each party except those claims which fall to
be determined under the arbitration provisions of the agreement aforesaid. In its special plea the
defendant pleads: E
(1) that the cause of action pleaded by the plaintiff arises in consequence of a dispute between
the parties as contemplated in clause 15 of the agreement;
(2) that, in the premises, the plaintiff was obliged to have recourse to the provisions of clause
15 of the agreement; F
(3) that the defendant, at all material times was willing and able to submit itself to the
provisions of clause 15 of the agreement;
(4) that, notwithstanding this, the plaintiff has sought resolution of its disputes in a court of
law;
(5) that in the circumstances the plaintiff's action against the defendant is out of order and
ought to be stayed. G
In response the plaintiff contends:
(1) that the provisions of clause 15 of the agreement relating to mediation and arbitration are
permissive and not peremptory; H
(2) that as at the date of issue of the summons, no dispute existed between the parties as to
the plaintiff's entitlement to the amount claimed or the defendant's liability to pay such amount;
(3) that the defendant was, at all material times, not willing and able to submit itself to the
provisions of clause 15 of the agreement;