Chapter 3 FD
Chapter 3 FD
METHODOLOGY
3.1 Introduction
that the objectives of the study are accomplished as it depicts the process on what actions
the researchers can take to complete the study. Figure 3.1 shows the specific actions to
reach
In order to obtain information, the researchers need to gather data such as the
energy consumption of each building on the campus and rank them from highest to
lowest then choose five that consume energy the most and the researchers will also need
the vicinity map of the campus. The researchers will also acquire data of the chosen
building such as the position and distance from the base station, location and ampere
rating of the main panel board, the riser or single line diagram.
3.2 System Design Consideration
of the Energy Monitoring System. The researcher will then acquire the location and
positioning of the selected building from the base station. The selected buildings have
different distances and positioning in the campus. The researchers must consider the
obstacles of data transmission because this can affect the overall performance of the
system. These includes trees, windows, and walls. Hence, the researchers must create a
configuration of data transmission and provide a data transmission path for stable data
acquisition.
Is Data Transmission
Successful? No
Yes
End
The researchers will inquire data needed for the study from the Electrical
Engineering Department of the campus such as the monthly energy consumption from
past years of each building and rank them from highest to lowest and select five buildings
Digital Arts (UDA) and ask for the updated vicinity map of the campus in order to
determine the location and positioning of each selected building from the base station.
The researchers will seek for assistance and approval letter from the department
heads of MEWS of the university authorized electrical personnel of the building to assess
and visually check the location of the Main Panel Board of the building.
The researchers will visually inspect the design and positioning of the building
from the base station. The researchers will check if there is available route for wired data
transmission from main panel board to the building’s rooftop. The researchers will
employ wireless data transmission from main panel board up to building’s rooftop.
3.2.1.5 Creation of Transmission Data Path
The researchers will create a data transmission path in order to avoid unstable data
acquisition and successful data transmission rate. The researchers will use the vicinity
map of the campus and pin locations for possible adding of nodes for point-to-point
transmission.
The rating of the current transformer sensor is essential for designing of the
system. The selection requires calculation for accuracy of the data to be collected.
Buildings have different main panel board ratings so the diameter of the wires are not the
same and the current transformer sensor must have a rating compatible to the size of the
wire. The current transformer sensor must have a turns ratio that will be compatible with
the smart meter and the main panel board. Figure below presents the steps on choosing
End
The researchers will seek for assistance from electrical staff in charge of the
building and visually inspect the location of the line source of the building. This is
important part for the mounting and installation of the current transformer sensor and the
The researchers will seek for assistance and coordinate with the department heads
of MEWS of the university or authorized electrical personnel of the building to ask and
acquire the ampere rating of main panel board of each building and ask the size of the
wires used.
Current transformer sensors come in various types. The researchers must consider
the size of the wire and the effort of installing the sensor. The researchers must avoid less
hassle installation of the sensor and the most suitable one is the split core or the clamp
The researcher will choose the measuring range of the current transformer that is
compatible with the main panel board rating and the smart meter. It must have a turns
ratio or input and output values close to the ratings of the main panel board and smart
Building
1000/5 A
1200/5 A
1500/5 A
Table 3.2.2.4
The table 3.2.2.4 above presents on how to select measuring range of the current
transformer. For better accuracy, option 1200/5 A is the best option. The 1250 A rating
is the max or the full operating current and when on steady operating condition, this
range is -80% of its full operating current so 1200/5 A can be utilized. 1500/5 A can also
The researchers must acquire the phase source measurement of each building. The
researchers must know if the building uses three-phase or single-phase source. The
researcher must also choose a smart meter with a communication protocol. Then, the
researcher must also choose a smart meter that has a current capacity rating that is
designed to use a current transformer sensor. The researcher must also consider the
accuracy of the smart meter. Cost must also me considered of the smart meter, including
factors such as
maintenance, upgrades, and the potential for future scalability. Figure 3.2.3 presents the
Start
End
The researchers will seek for assistance and coordinate with the department heads
of MEWS of the university or authorized electrical personnel of the building to ask the
phase source measurement of the building or to visually inspect and count how many
wires are connected to the service entrance of the building to determine what type of
meter to be used.
In order for the electrical parameters to be transmitted from the building to the
base station, the smart meter must have a communication protocol. The researchers will
visually check the smart meter by scanning through the specifications if it features
communication protocol or by checking the available ports of the smart meter for
communication purposes.
The researcher must visually check the specification of the smart meter and must
consider the operating current. The operating current must be in range of the output of the
current transformer sensor for compatibility. By Scanning through the specifications, the
With all the gathered data, the researchers can now proceed in creating a system
design. This comprises selecting the appropriate sensor together with their corresponding
only had the monitoring system as a component. The figure shown below is the general
system design.
Figure 3.3 depicts the general process of the suggested Energy Monitoring model
through a block diagram. This could aid in putting the idea of conveying the raw data
from arbitrary structures (node stations) to the base station or central node.
The researchers will physically install the hardware and software components of the
system, such as the sensors, microcontrollers, and LoRa transceivers. Installing the
transceiver in the proper location to gather data on energy consumption, coupling the
sensors with the microcontroller, and setting up the microcontroller to process, send and
this would help the researchers as a prelude to designing the energy monitoring system
for USTP-CDO Campus. This is the essential and crucial stage of designing of the system
for compatibility. The figure 3.4.1 provides a general overview on the actual selection
process which considers functionality and cost-effectiveness in such a way that the main
objective will be achieved without compromising the quality of the entire system.
Start
Selection of Microcontroller
Selection of Enclosure
End
Selecting the right microcontroller can be a daunting task. Not only are there a
temptation to jump in and start selecting a microcontroller before the details of the system
has been hashed out. This is of course a bad idea. Before any thought is given to the
Cost
Availability
Selecting an energy meter that is appropriate for your system’s size and energy
requirements can help the researcher identify areas where you can prove energy
efficiency. Selecting a compliant energy meter can help you avoid penalties and
ensurethat your system is safe and efficient. In selecting energy meter, the researcher will
Accuracy
Communication
Cost
Availability
Table 3.4.2.1 Selection of Energy Meter
Communication
Cost
Availability
Table 3.4.3.1 Selection of Current Transformer
In the selection process, the researcher will consider various current transformer
range, data rate, power consumption, security, and regulatory compliance in wireless
software that can be used in Energy Monitoring System. Selecting the right web serveris
The researcher will select the right enclosure to ensure protection, size, material,
customization and aesthetics of the electrical and electronic components. The researchers
The researchers will calibrate the components used in the system such as the
smart meter, LoRa and the microcontroller to obtain accurate data and avoid
discrepancies.
manufacturer in order to configure the baud rate, address and current ratio of the current
transformer. The smart meter must have the same baud rate and address programmed on
the ESP32. Furthermore, the researchers must know the ratio of the current transformer
The researchers will set a program configuration on each lora module. The
configuration of each lora module is different. The base and the nodes must not have the
same AddL values but they must have the same AddH values. This process is crucial in
order for the LoRa modules to send and receive data to specific nodes.
The researchers will configure the program on each ESP32 microcontroller. The
researcher will modify the txaddress of each microcontroller on the eMon_structs file.
The researchers will then modify the name of each assigned building. The base and nodes
In this section, the researchers must determine the requirements needed in testing
and evaluating the effectiveness of the components in operation of the energy monitoring
system specifically the accurate transmission of data gathered from the sensors through
the modules.
Start
Communication Testing
Transmission Testing
Range Testing
Accuracy Testing
Interference Testing
End
The researchers will test the selected compatible current transformer sensor and
connect it to the smart meter. Then tap the current transformer sensor to the main panel
board of the building. The researchers will then observe the performance of the
components and acquire the measured electrical parameters on the smart meter.
The researchers must select a smart meter with communication protocol. The
researchers must determine the type of communication protocol of the smart meter in
order to select a component for conversion. The researchers will connect the smart meter
to the ESP32 using a RS485 to TTL converter in order for the smart meter and
microcontroller to communicate with each other. In order for the electrical parameters or
holding registers to be called and determined, a list of holding registers is provided and
End
The researchers will visually check the smart meter by scanning through the
The researchers will visually check the type of communication protocol available
of the selected smart meter by looking at the port and identify what type of
The researchers will select the communication protocol component based on the
specification or construction of the port of the smart meter. The researchers will also
determine the type of conversion of the communication protocol by checking the required
The researchers will check and scan the user’s manual guide of the smart meter in
order to determine the values or holding registers of the smart meter and in order for the
The locale of the study is a university and the path of data transmission is blocked
by obstacles such as a high-rise buildings and trees. The data transmission rate is not
stable and the researchers must design a system that can transmit data successfully
The researchers will utilize the length of the ethernet cable. A wired
configuration from the main panel board up to the building’s rooftop is possible for
stable data
transmission from the building to the base station. This can be done by using two wires of
the ethernet cable as A and B for it to transmit signal. This configuration also lessens the
overall cost of the system. But, the routing of the wire must also be considered.
The researchers will have a site visit of the building and estimate the height and
distance of the rooftop from the main panel board. The researchers can also coordinate to
the departments of the campus that knows the height and dimensions of the buildings.
The researchers will have a site visit of the building and assess the possible
routing of the Ethernet cable from the main panel board to the building’s rooftop. The
researchers must select a route that will not be exposed for security of the wiring.
The researchers will choose a placement for the node on the rooftop and ensure
that the node is having a line of sight to the base station in order to achieve data
transmission and have a stable connection. Then the researchers must also consider the
safety of the node in order to be immune and resistant from environmental factors.
The researchers will test the LoRa’s transmitting and receiving capabilities from
the main panel board of each building to the base station. This involves testing the range
of the system by placing sensors at different distances from the gateway and measuring
the success rate of data transmission. This test can be done in an open field or a
controlled environment with obstacles such as walls and trees. The researchers will
employ wireless and wired configuration of data transmission. The researchers will
on the base station to test the transmission and observe the communication of the nodes.
The researcher will measure the packet loss rate and the success rate of data
transmission under different operating conditions. This measures the reliability of the data
transmission from the sensors to the gateway. The researchers will also ensure the safety
of the node by placing it in a plastic or weather proof junction box where the electronic
components are integrated. The researchers will also use a Stepdown AC-DC 24-5V
The researcher will compare the data visualized on the platform from the actual
reading on the sensors on the main panel boards. This involves measuring the accuracy of
the energy measurements provided by the sensors. This can be done by comparing the
sensor readings from the measuring instruments and data visualized on the base station.
The researchers will test the susceptibility of the system to interference from other
introducing known sources of interference and observing the performance of the overall
system.
3.5.8 Security and Privacy testing
The researchers will enclose the smart meter and place it on a room where
authorized electrical personnel are allowed to enter for security purposes since the data is
confidential. The researchers will implement encryption and other security measures as
well as testing for vulnerabilities of the system. This involves testing the security of the
system to prevent unauthorized access to energy data. Figure 3.5.5 shows the flow chart
of the testing.
Accuracy Testing
Scalability Testing
Security Testing
In this section, the researchers will identify how to develop a plan expansion and
additional building for an energy monitoring system. The researcher must gather data
such
as determining the location site of the building, location of the main display panel of the
The researcher will then identify the materials specification after the gathering of
data to use in selecting suitable measuring parameters, sensors, and modules that are
needed in implementation for system compatibility. After selecting the materials, the
After all the updated configurations of the energy monitoring system, the
researcher then conducts a Test and Evaluation of the system has some analysis of results
as an end.
Start
Software Modification
End
The researchers will instruct the future researchers what data are needed to be
gathered and things to consider for the designing of the system. The researchers will also
results are obtained of the system in order to further improve the overall performance of
the system.
The researchers will provide a software modification for the future researchers to
lessen the duration of implementation of the system. The researchers will give
instructions or steps to modify the software of the system such as the storing and
The researchers will develop or create a data path after range and transmission
testing. Then the researchers will utilize the vicinity map of the campus and pin location