Unit 6 Project Scheduling and Markov Process Dated 9th June 23 - SOL - DU - MBAFT - 6202
Unit 6 Project Scheduling and Markov Process Dated 9th June 23 - SOL - DU - MBAFT - 6202
TRADE-COST TRADE-OFFS
The initial creators of CPM gave the project manager
the choice to allocate resources to tasks in order to
speed up project completion. The option to shorten
activity times must consider the increased expenses
involved, as more resources (such as additional
c) The critical path is shown by thick line in Fig. where employees, overtime, etc.) typically raise project
E-values and L-values are the same. The critical path is: costs. In essence, the decision that the project
1 – 4 – 7 and the expected completion time for the manager must make entails exchanging decreased
project is 42.8 weeks activity time for increased project cost
Project Crashing –Time Cost Trade-off
Project Crashing: It is usual for a project manager to tasks have crashed. The process of determining time-
encounter one or both of the following circumstances cost trade-offs for project completion can be
while overseeing a project: Both the projected project summed up as
completion date and the project's timeline are behind Step 1: Determine the normal project completion time
schedule. In either case, some or all of the ongoing and associated critical path.
tasks must be expedited in order to complete the Step 2: Identify critical activities and compute the
project by the target deadline. Crashing is the process cost slope for each of these by using the relationship
of reducing the length of a project in the most
affordable way possible. Additionally, extending an
activity's duration past its usual point (cost-efficient)
may raise the expense of carrying out that action. For The values of cost slope for critical activities indicate
the sake of simplicity, it is assumed that the the direct extra cost required to execute an activity
relationship between an activity's normal time and per unit of time.
cost as well as crash time and cost is linear. Step 3: For reducing the total project completion
Therefore, by calculating the relative change in the time, identify and crash an activity time on the
cost per unit change in time, the crash cost per unit of critical path with lowest cost slope value to the point
time may be determined where another path in the network becomes critical,
Time-Cost Trade-Off Procedure: When all essential or the activity has been crashed to its lowest
tasks are accomplished in accordance with schedule, possible time.
crashing begins, and it ends when all essential
Project Crashing –Time Cost Trade-off
Step 4: If the critical path under crashing is still (a) Draw the network diagram for the project and
critical, return to step 3. However, if due to crashing of identify the critical path.
an activity time in step 3, other path(s) in the network (b) What are the normal project duration and
also become critical, then identify and crash the associated cost?
activity(s) on the critical path(s) with the minimum joint (c) Find out the total float associated with non-
cost slope. critical activities.
• Step 5: Terminate the procedure when each critical (d) Crash the relevant activities and determine the
activity has been crashed to its lowest possible optimal project completion time and cost.
time. Determine total project cost corresponding Sol;-a)Network for normal activity times is:-
to different project durations.
Example : The data on normal time, cost and
crash time and cost associated with a project are
The Indirect
cost is Rs 50
per week
( 6,7)
Properties of TPM:-pij∈S ≥ 0
– If each row sum is 1, then the
matrix is known as stochastic
matrix. Therefore, P(X3 = 0 | X1 = 0) = 5/12
– If each column sum is 1, then the Second method using transition graph: Let the
matrix is known as doubly transition matrix is
stochastic matrix.
Example: Suppose that the probability of a dry day
(state 0) followinga rainy day is 1/3 and probability of
a rainy day (state 1) following a dry day is 1/2. If there
is a two-state Marcov chain such that p10 = 1/3 and Hence -
p01 = 1/2 and the transition probability matrix (TPM),
MARKOV PROCESS
Example: Consider a markov chain {Xn | ≥ 0} with Then, find P(X3 = 1 | X0 = 1) and calculate the joint
state space {1, 2, 3} and transition matrix, probability, P(X3 = 1, X1 = 1, X0 = 2)
Then, find P(X3 = 1 | X0 = 0) Sol: S = {0, 1, 2}
Sol: The transition graph Find P(X3 = 1 | X0 = 1)
corresponding to the given = 3/16
TPM is
INITIAL DISTRIBUTION
Let the state space is {0, 1, 2,…},
initial state = 0, then P(X0 = i) is called initial
distribution and
Example: Let {Xn, n ≥ 0} be a markov chain with 3
sattes 0, 1, 2 and with transition matrix is :-
& initial distribution,
Pr(X0 = i) = 1/3,
i = 0, 1, 2
CLASSIFICATION OF STATES
Accessibility otherwise the markov chain is called reducible
If pij(n) > 0, where n ≥ 1, then state j is accessible from markov chain.
state i.Let if p01 = 1/2 > 0, which means that state 1 is Example: Check whether the given transition matrix is
accessible from state 0 And if p10 = 0, which means irreducible or reducible for the state space {0, 1, 2}
that state 0 is not accessible from state 1. Sol: The transition diagram
Communicating state for the given TPM is,