Budget Escalation Detail - Part 2 Back Side Shed 1, V Line, Sikandrabad
Budget Escalation Detail - Part 2 Back Side Shed 1, V Line, Sikandrabad
Account Reconcilition
Particulars New Office (WO/2324/002) FG Warehouse (WO/2324/005)
Supply of Matesrial Civil Work Total Supply of Matesrial Civil Work Total
PO Value 5,975,000 5,789,980 3,100,223 8,890,203
Additional PO Value - - 611,006 611,006
Total PO Value Excluding GST - - 5,975,000 5,789,980 3,711,229 9,501,209
Payment done till date 5,000,000 4,750,000 1,500,000 6,250,000
Retention for Fire NOC (Incl. GST) 944,000
Retention @ 5% 298,750 289,499 185,561 475,060
Balance Payment - - -267,750 750,481 2,025,668 2,776,149
82% 48% 70%
Progress update
Precentage of
Particulars PO Value Payable Paid Payable
work
Civil work 1,367,006 100% 1,367,006 1,500,000 1,507,962
Structure 2,344,224 70% 1,640,956
Material 3,939,170 100% 3,939,170 4,750,000 222,048
Fabrication 1,475,540 70% 1,032,878
9,125,939 7,980,010 6,250,000 1,730,010
RCC - M25
Providing and laying of RMC/cast-in-situ weigh
batched cement concrete of M25 grade i/c placing
cover blocks, spreading slurry, placing in position,
compaction with needle/surface vibrators, ramming,
7 levelling, providing shuttering of construction joints, Cum 124.20 6,750.00 838,350 145.73 983,705
finishing and curing i/c covering with hessian cloth,
ponding for the specified days all complete as per
specifications and instructions of the owner's
representative for Substructure/Superstructure in all
shapes, sizes & forms and at all story, heights,
depths and levels.
Shuttering work
Providing and laying cantering and shuttering
including strutting, propping etc. for all heights and
levels including removal of form work for
8 foundations, footings, bases for columns, retaining Sqm 420.00 475.00 199,500 478.541 227,307
walls, walls (any thickness) including attached Quantity executed in Dock &
pilasters, buttresses, plinth and string courses fillets, Ramp Area Works while Budget
kerbs and steps etc., suspended floors, roofs, was prepared without Dock &
landings, balconies and access platform. Ramp Work
Reinforcement
Providing, laying, fabrication and fixing in position
Steel reinforcement - FE 500 in all reinforced
concrete work including straightening, cutting,
removal of rust by wire brush & coating with
9 cement slurry, bending, hoisting, laying in position MT 12.35 80,000.00 988,000 17.088 1,367,006
to shape & profile required at all levels & heights as
per drawing & designs including providing and
fixing binding wire with 16 gauge MS annealed wire
complete. (Quoted rate to include providing &
fixing the binding wire and cement spacer blocks)
Plaster With Neat Finish
Amount of
S. Completio
Description Unit Qty Rate Amount Actual qty completed n% Remarks
No. work
Providing and applying Wall Plaster With Neat
10 Finish as detailed in specifications and drawings. Sft 2,166.92 60.00 130,015 2,411.410 144,685
(Quoted rates are inclusive of all materials, labour,
machineries and for all heights, all depths, all levels
& all leads and lifts).
20 Gauge Plain Black Sheet Rolling Shu
Providing and Fixing 20 Gauge Plain Black Sheet
11 Rolling Shutter as detailed in specifications and Sft 520.52 240.00 124,924
drawings. (Quoted rates are inclusive of all
materials, labour, machineries and for all heights, all Earlier Shutter of grinding
depths, all levels & all leads and lifts). machine area to be removed but
Mechanical Operation Handle Machine now not required
Providing and Fixing Mechanical Operation Handle
11A Machine as detailed in specifications and drawings. Nos 2.00 8,500.00 17,000
(Quoted rates are inclusive of all materials, labour,
machineries and for all heights, all depths, all levels
& all leads and lifts).
12 Column Pedestals Grouting with GP 2
Column Pedestals Size - 0.4X0.73X0.05 mtr.
A (Consumption per Pedestal - Approx. 5 Bag of 25 Nos 10.00 2,000.00 20,000
kg)
Column Pedestals Size - 0.63X0.73X0.05 mtr. Earlier depth of pedestals was
B (Consumption per Pedestal - Approx. 8 Bag of 25 Nos 4.00 3,200.00 12,800 500MM but after decided depth
kg) 1500MM therefore anchoring
Column Pedestals Size - 0.4X0.68X0.05 mtr. bolt fixed in RCC it self so no
C (Consumption per Pedestal - Approx. 5 Bag of 25 Nos 10.00 2,000.00 20,000 need these material
kg)
Column Pedestals Size - 0.4X0.5X0.05 mtr.
D (Consumption per Pedestal - Approx. 3.5 Bag of 25 Nos 5.00 1,400.00 7,000
kg)
17 Rewiring work 16 dia Nos - 380.00 292.000 110,960 Quantity executed in Dock &
Ramp Area Works while Budget
was prepared without Dock &
18 Rewiring work 12 dia Nos - 220.00 256.000 56,320 Ramp Work
1 Cement Sheet Roofing Dismantling Sft 3,780.750 6.00 22,685 3,780.750 22,685
Cement Sheet Roofing MS Structure Kg
2 3,567.166 6.00 21,403 3,567.166 21,403
Dismantling
Platform Dismantling & Ramp Making - Door
C -
Along Block C
1 Platform Dismantling -
A CC Floor Dismantling Cft 45.443 60.00 2,727 95.930 5,756 Quantity is including Head D
C Excavation i/c Soil Shifting Cft 206.492 6.00 1,239 206.492 1,239
D Rolling Shutter Removing & Refixing at Other Lo Job 1.000 4,000.00 4,000 -
3 Platform Shifting -
Payable Paid
Material 1,367,006 100% 1,367,006 1,500,000
Civil work 2,344,224 70% 1,640,956 -
3,711,229 3,007,962 1,500,000
1,507,962
REVISED ( 47x45=2,115 SMTR=
PROPOSAL OF STRUCTURE STEEL OF SHED OF SIZE 47x45 Mtr 22,757 SQFT( 1 Bal work to be completed
WITH A HEIGHT OF 4 Mtr sqmtr=10.76smft) Actual work completed
Amount of
Amount of Completi completed
S.No Particulars Unit Qty Rate Amount Actual qty completed work on % Actual qty work
Designing, & Drawings in details for all steel
structure, foundation, GA, Foundation Bolt,
1 foundation details, erection, sheeting for entire
building, including guidance for fixing of
foundation bolts.
Job 1 70000 70,000 1.000 70,000 100% - -
Civil 12 30.5
Fabrication 80 75
Dismantling job 3 3
Total 95 108.5
Roof Insul. - -
Grand Total