Expense Report
STATEMENT
PURPOSE: Roof BoQ NUMBER: #2 PERIOD: From
To
EMPLOYEE INFORMATION:
Name Ryan Cooper Position Civil Engineering Technician Scope of Work Refurbishment Of PumpHouse Roof
Department Engineering
RATE AMOUNT
ITEM BRIEF DESCRIPTION UNIT QTY
(US$) (US$)
Page 1 of 3
3.04 Fascia Boards (228x38mm)6m Unit 4.0 31.60 126.40
3.05 Wiire Nails 4inch Unit 4.0 2.75 11.00
3.06 Wiire Nails 3inch Unit 4.0 2.75 11.00
3.07 Branders (50x50mm)6m Unit 12.0 7.00 84.00
3.08 Techiad PVA Interior/exterior 5litres Unit 2.0 8.00 16.00
3.09 Thinners 750ml Unit 2.0 2.00 4.00
3.1 Paint Brushes 75mm Unit 3.0 3.00 9.00
4 3.11 Ladder 2-6.8m Unit 1.0 177.00 177.00
3.12 Scaffolding 3m Tower (for two weeks) Unit 2.0 60.00 120.00
3.13 Roof Sealer 1litre Unit 2.0 8.00 16.00
3.14 claw hammer Unit 2.0 12.38 24.76
3.15 Plastic cover 50m Unit 1.0 110.00 110.00
4
Materials For Gutters
Page 2 of 3
Notes: Items in red are the costs of IBR roofing sheets in the event COB requests for the roof to have new sheets.
At the time of request for new sheets, the size 0.4/0.5mm will be decided upon