Ch.1 Projects in Comtemporary Organizations
Ch.1 Projects in Comtemporary Organizations
All these factors combine to make the projects large, complex and multidisciplinary endeavors.
Project Management is the application of knowledge, skills, tools and techniques to project activities
to meet project requirements. Routine production and project in terms of time, cost and performance.
Project Manager :
PM is the person who manages the project and applies the principles of Project management.
Project Manager’s responsibility is to integrate all aspects of a project, ensure that proper knowledge
and resources are available when and where needed and ensure that expected results are produced in
a timely, cost effective manner.
Problems faced by PM
1. Frustration of being responsible for outcomes while lacking full authority to command the
requisite resources or personnel.
2. Dealing with parties involved in any project – senior management, client, project team and
public, each with different smaller objectives.
3. Project already is more work than routine organization.
4. Technical Problems.
5. Organizational problems
6. Vendors who are not punctual in delivering of raw material.
Distinction between Program, Project, Task, Work Package and Work Unit
Exceptionally large, long range objective that is broken down into asset of projects.
Tasks :- The projects are divided further into tasks.
Work Package :- Tasks are divided into Work Packages.
Work Units :- Work Packages are divided into Work Units.
Purpose of a Project :- A project is usually a one-time activity with a well-defined set of desired
end results. It can be divided into subtasks that must be accomplished in order to achieve the project
goals. The project is complex enough that the subtasks require careful coordination and control in
terms of timing, precedence, cost and performance. Often the project itself must be coordinated with
other projects being carried out by the same parent organization.
Life Cycle :- Projects have life cycles. From a slow beginning they progress to a buildup of size,
then peak, begin to decline, and finally must be terminated.
Interdependencies :- Different projects pursued by the same organization sometimes interact with
one another for resources, technical know-how etc. Also projects interact with the various functional
departments of the parent organization e.g marketing may be interacting with the project in the
beginning. Manufacturing may be involved throughout the project life time. Finance in the
beginning and accounting at the end. PM must keep all these interactions clear and maintain the
appropriate relationships with all external groups.
Uniqueness :- Every project has some elements that are unique. No two construction or R& D
projects are precisely alike. Projects by their nature, cannot be completely reduced to routine.
The projects are created to focus the responsibility and authority for the attainment of goals to an
individual or a small group.
The project manager is expected to coordinate and integrate all activities to reach the project
goals.
Discourage Suboptimization
Disadvantages
1. The creation of the project itself indicates that there was a limitation of routine output.
2. Conflict
3. PM’s responsibilities and his lack of authority.
Graph on page 13
Graph on page 14
How PM can save project costs if closely follows project life cycle.
Trade off’s between cost, time and performance at different stages of the life cycle of the
project.