00 Introduction and Overview
00 Introduction and Overview
Risk Management in
Construction
Course Objectives
management in construction.
Assignments 20 %
Midterm Exam 20 %
Final Exam 40 %
Opportunities or Threats
This definition includes two key dimensions of risk: uncertainty and effect
on a project’s objectives.
▪ When assessing the importance of a project risk, these two dimensions
must both be considered. The uncertainty dimension may be described
using the term “probability” and the effect may be called “impact”
(though other descriptors are possible, such as “likelihood” and
“consequence”).
▪ It is important to address both threats and opportunities within a unified
Project Risk Management process.
Dr. Ahmed Eldeep, Ph.D., PMP ®, PMI-RMP® Introduction and Overview 8
• Risks are uncertain future events or conditions which may or may
What is Risk?
not occur, but which would matter if they did occur.
• Threats which occur may be called issues or problems; opportunities
which occur may be called benefits. Both issues/problems and benefits
entail project management actions that are outside the scope of the
Project Risk Management process.
Opportunities.
• Risk threshold: The limits of the Risk approval by organization. Or The level of risk exposure above which
Risk Threshold
▪ Looks at Risk as a
▪ Uncomfortable with risk ▪ Embraces Risk for ▪ Don’t worry too much
challenge.
▪ Avoids Risks Future Payoff in a about the risk unless
▪ Sometimes this
▪ Not creative and supportive calculated way. it becomes an Issue.
excessive optimism
for new ideas
cause them losses
❑ Risk Attitude is inbuilt in human nature, some people are scared of it and some others
enjoy. It truly depends on person to person that how he look into the risk.
Risk Parameters
Frequency
When evaluating risk the following should
determined;
Decrease
Greater probability
Control of of negative
project events
Increase
Proactive probability
approach of Positive
Risk events
Management
✓ Car accident;
R2 T Car accident
R3 T Get lost
Total 620
Risk Response
Risk ID T/O Risk Description Response
Owner
• The risk attitudes of the project stakeholders determine the extent to which an individual risk or overall
project risk matters.
• A wide range of factors influence risk attitude; These include the scale of the project within the
range of stakeholders’ overall activities, the strength of public commitments made about the
performance of the project, and the stakeholders’ sensitivity to issues such as environmental
impacts, industrial relations, and other factors.
• How risk is regarded is usually also strongly influenced by an organization’s culture. Different
organizations are more or less open, and this often impacts the way risk management can be applied.
• These attitudes should be identified and managed proactively. They may differ from one project to
another.
• In fact a single stakeholder may adopt different risk attitudes at various stages in the same
project.
choose.
• Not all risks are bad, but almost all are seen as threat.
Dr. Ahmed Eldeep, Ph.D., PMP ®, PMI-RMP® Introduction and Overview 30
Project Risk Management
▪ Project Risk Management aims to identify and prioritize risks in advance of their occurrence, and
provide action-oriented information to project managers. This orientation requires consideration of
events that may or may not occur and are therefore described in terms of likelihood or probability of
management.
▪ Project Risk Management should be applied to all projects and hence be included in project
plans and operational documents. In this way, it becomes an integral part of every aspect of managing
▪ Project Risk Management addresses the uncertainty in project estimates and assumptions.
Therefore, it builds upon and extends other project management processes. For instance, project
scheduling provides dates and critical paths based on activity durations and resource availability
assumed to be known with certainty. Quantitative risk analysis explores the uncertainty in the
estimated durations and may provide alternative dates and critical paths that are more realistic
given the risks to the project.
Iterative Process
• It is the nature of projects that circumstances change as they are being planned and executed. The
amount of information available about risks will usually increase as time goes on.
• Some risks will occur while others will not, new risks will arise or be discovered, and the
characteristics of those already identified may change.
• As a result, the Project Risk Management processes should be repeated and the corresponding
plans progressively elaborated throughout the lifetime of the project.
• To ensure that Project Risk Management remains effective, the identification and analysis of risks
should be revisited periodically, the progress on risk response actions should be monitored, and the
action plans adjusted accordingly
• The development of an initial risk management plan and risk assessment is the start of the
process, not the end.
to Project Risk Management should be in proportion to the characteristics of the project under
management and the value that they can add to the outcome.
• Thus, a large project that provides value to an important customer would theoretically require
more resources, time, and attention to Project Risk Management than would a smaller, short-
term, internal project that can be conducted in the background with a flexible deadline.
Objectives
1) Plan Risk management;
2) Identify Risks;
7) Monitor Risks.
Monitor and Control
A project team can Skip Qualitative Risk Analysis when they have
responses.
002-01063813636 @ah7madmo