Schedule of Approach and Methodology
Schedule of Approach and Methodology
Our understanding of the project is that you must work according to the given scope of works.
Make sure that our work done is of high quality.
Work to be done according to the proposed schedule of time.
3. Considering1 and 2 above, please provide a summary of your proposed approach, work plan and quality plan
(including legal compliance where applicable) for the completion of the project
There is no innovation design at this moment that we are planning but when we are on the site we will come with the proposals
of alternative and cost effective methods of strensactions the pavement layers and maximizes on labour participation
5. Indicate how your company will communicate with the municipality from order date to delivery
Communication changes will be established between the municipality and Gadalani to ensure and promote clear and effective
communication channels. Liaison will be with our director Mr J. Gadalane
6. Site Establishment
Our plant machinery will be on site within 14 working days of after we've been handed over to the community.
The site camp together with the site office will be identified before the commencement of any work with the help of PSC
members.
Our establishment includes the hiring of the Project C.L.O
Construction name board will be installed during the process of establishment.
Gadalani Trading JV Morrie Gee will give some of its work to the local SMME for the purpose of growing them up and increases
their company grades.
ACTIVITIES DURATION
1. Signing of contract 1 day
2. Site establishment 2 Weeks
3. Earthworks 3 Weeks
4. Pit Excavations 4 Weeks
5. Structures Installation 3 Weeks
6. Concrete works 3 Weeks
7. Back filling 3 Weeks
8. Compaction 4 Weeks
14. Cleaning 3 Weeks
15. Site handover 1 day