Risk Assessment of Electrical Installation Risk Assessment
Risk Assessment of Electrical Installation Risk Assessment
CORPORATION
SHE MANAGEMENT SYSTEM LIMITED – CC-04
HAZARD IDENTIFICATION, RISK ASSESSMENT
& CONTROL MEASURES OF
CEC-CICI JV Electrical Installation/ Operations
ELECTRICAL INSTALLATION/OPERATIONS
Sl no Activity Hazard/Im Associated Risk rating Risk Risk Risk/Impact Control measures Final Risk Residu Risk
pact Risk/Imapct(po Level Required Rating al Accept
(source or ssible Probabilit Severity Probabili Severity Factor able
y ty
situation consequences of
with a exposure to
potential hazard)
for harm)
Electrical a) Short a) Can cause 3 3 H 9 1) Depute only licensed 2 3 6 LOW
Installati circuiting electrocutio electrician to perform on
on/Oper n or fire electrical
ations facilities/Operations.
2) Use one socket for one
Operation.
3) Ensure usage of only fully
insulated wires or cables.
4) Do not place bare wire ends
in a socket.
5) Do not use damaged cords
and avoid temporary
connections.
6) Ensure proper earthing of
all machines/equipments.
7) Provide all connections
through ELCB.
DELHI METRO RAIL
CORPORATION
SHE MANAGEMENT SYSTEM LIMITED – CC-04
HAZARD IDENTIFICATION, RISK ASSESSMENT
& CONTROL MEASURES OF
CEC-CICI JV Electrical Installation/ Operations
ELECTRICAL INSTALLATION/OPERATIONS
Sl Activit Hazard/Impact Associated Risk rating Risk Risk Risk/Impact Control Final Risk Rating Residual Risk
n y (source or Risk/Imapct(possibl Level measures Required Factor Acceptab
e consequences of Probabi Severity Probability Severity
o situation with a lity
le
potential for exposure to hazard)
harm)
3) Switch off the
electrical utilities when
not in use.
4) Do not allow un
authorized connections.
5) Ensure grid wise
distribution of power.
6) Ensure proper
permissions from
competent authorities
for electrical
installations.
DELHI METRO RAIL
CORPORATION
SHE MANAGEMENT SYSTEM LIMITED – CC-04
HAZARD IDENTIFICATION, RISK ASSESSMENT
& CONTROL MEASURES OF
CEC-CICI JV Electrical Installation/ Operations
5) Wherever possible,
provide temporary
fencing all-around the
transformer &
switchgear areas.
6) Mark the path of
U/G electrical cables
to avoid damage
during excavation
operation.
7) Do not allow
excavation activity
without intimation to
electrical authorities.
8) Use PPE while
handling with
electrical installations.
DELHI METRO RAIL
CORPORATION
SHE MANAGEMENT SYSTEM LIMITED – CC-04
HAZARD IDENTIFICATION, RISK ASSESSMENT
& CONTROL MEASURES OF
CEC-CICI JV Electrical Installation/ Operations
1 4 3 2 1
Severity
4 - Catastrophic – Imminent dangers exist, hazard capable of causing death and illness on a wide scale.
3 - Critical – Hazard can result in serious illness, severe injury, and property and equipment damage.
2 - Marginal – Hazard can cause illness, injury or equipment damage, but the results would not be expected to be serious.
1- Negligible – Hazard will not result in serious injury or illness, remote possibility of damage beyond minor First-aid case.