Transportaand Highways Systems
Transportaand Highways Systems
Because of the benefits from compaction, contractors have built larger and heavier machines to
increase the amount of compaction of the soil. It was found that the Standard Compaction test
could not reproduce the densities measured in the field and this led to the development of the
Modified Compaction test.
1.1.2.2 Modified Compaction Test
The procedure and equipment is essentially the same as that used for the Standard test except that
5 layers of soil must be used. To provide the increased compactive effort (energy supplied equals
2072 kJ/m3) a heavier hammer and a greater drop height for the hammer are used. The key
dimensions for the Modified test are shown in the Table 1.2.
Table 1.2: Important dimensions for modified compaction test
Because Gs and γw are constants it can be seen that increasing dry density means decreasing
voids ratio and a more compact soil. In the test the dry density cannot be measured directly, what
are measured are the bulk density and the moisture content. From the definitions we have
This allows us to plot the variation of dry unit weight with moisture content, giving the typical
reponse shown in Figure 2 below. From this graph we can determine the optimum moisture
content, mopt, for the maximum dry unit weight, (γdry)max.
then a theoretical relationship between γdry and m for a given value of A can be derived as
follows:
If the percentage of air voids is zero, that is, the soil is totally saturated, then this equation
becomes
From this equation we see that there is a limiting dry unit weight for any moisture content and
this occurs when the voids are full of water. Increasing the water content for a saturated soil
results in a reduction in dry unit weight. The relation between the moisture content and dry unit
weight for saturated soil is shown on the graph in Figure 1.3. This line is known as the zero air
voids line.
Figure 1.3: Typical compaction curve showing no-air-voids line
It can be seen from this figure that the compaction curve is not a unique soil characteristic. It
depends on the compaction energy. For this reason it is important when giving values of (γ
dry)max and mopt to also specify the compaction procedure (for example, standard or modified).
There is a wide range of compaction equipment. For pavements some kind of wheeled roller or
vibrating plate is usually used. These only affect a small depth of soil, and to achieve larger
depths vibrating piles and drop weights can be used. The applicability of the equipment depends
on the soil type as indicated in the Table 1.4.
Table 1.4: Compaction equipment
2.3 Pipelines
Pipelines are an extremely important and extensive mode of land transport, although very rarely
appreciated or recognized by the general public, mainly because they are buried underground or
under the sea.
Two main products dominate pipeline traffic: oil and gas, although locally pipelines are
significant for the transport of water, and in some rare cases for the shipment of dry bulk
commodities, such as coal in the form of slurry.
Pipelines are almost everywhere designed for a specific purpose only, to carry one commodity
from one location to another. They are built largely with private capital and because the system
has to be in place before any revenues are generated, represent a significant capital commitment.
They are effective in transporting large quantities of products where no other feasible means of
transport (usually water) is available.
Pipeline routes tend to link isolated areas of production with major centers of refining and
manufacture in the case of oil, or major populated areas, as in the case of natural gas.
The routing of pipelines is largely indifferent to terrain, although environmental concerns
frequently delay approval for construction.
Geo-political factors play a very important role in the routing of pipelines that cross
international boundaries. Pipelines from the Middle East to the Mediterranean have been routed
to avoid Israel, and new pipelines linking Central Asia with the Mediterranean are being routed
in response to the ethnic and religious mosaic of the republics in the Caucasus.
Pipeline construction costs vary according to the diameter of the pipe and increase proportionally
with the distance and with the viscosity of the fluid (need for pumping stations). Operating costs
are very low, however, and as mentioned above, pipelines represent a very important mode for
the transport of liquid and gaseous products. One major disadvantage of pipelines is the inherent
inflexibility of the mode. Once built (usually at great expense), expansion of demand is not
easily adjusted to. There exist specific limits to the carrying capacity. Conversely, a lessening of
supply or demand will produce a lowering of revenues that may affect the viability of the system.
Land Usage
Transport planning cannot be isolated from land use planning. This is illustrated in the figure
below.
Hourly Patterns
The observed trend is that there are two peak periods during weekdays (Monday to Friday), one
in the morning (7.30-8.30 am) and one in the evening (4.00-5.00 pm), whereas on weekends
there is only one peak (12.30-1.30 pm) in the early afternoon, when people begin to go for
shopping, visits or recreational trips. This hourly pattern is fairly consistent throughout the year.
The actual pattern, however, may vary from place to place.
Daily Patterns
The traffic volumes remain consistent for weekdays and weekends throughout the year, except
for variations on special days, e.g. environmental sanitation days, election days, feast days,
public holidays, etc. Traffic volume studies should not be conducted on such days.
Directional Distribution
This is very important in the planning of a highway. The actual distribution to be used for design
purposes can only be determined by field measurements. Directional distribution (in percentages)
for any specific road is relatively stable and does not change materially from year to year. Hence,
relationships established on the basis of current traffic movements are also applicable to future
movements.
On the other hand, in the structural design of pavements (flexible or rigid), only the volume of
the commercial vehicles (i.e. those with an unladen weight of 1,500 kg, i.e. 1.5 tonnes, or more)
e.g. heavy buses, trucks, etc. that will use the road during its design life is considered. This is
because it is felt that the loads imposed by cars do not contribute significantly to the structural
damage caused to road pavements by traffic.
Another important component of the traffic stream which must be taken care of is the pedestrian
component. Measures must be taken to ensure the safety of pedestrians and to determine the
effect of pedestrian movement on the ease of movement of vehicles, or the effect of vehicle flow
on the ease of movement of pedestrians.
Then, x = q(ta + t)
and y = q(tw – t)
Therefore, q = 60 (x + y) (veh/hr)
ta + tw
and t = tw – y = x – ta (minutes)
q q
For example, if the flow to be estimated is flow AB, then x = xBA, ta = tBA, while tw = tAB. So
also, if the flow to be estimated is flow BA, then x = xAB, ta = tAB, while tw = tBA.
Example:
Six runs were made in each direction along a two-way highway between X and Y. Flows were
measured both with and against the moving car and the following notes obtained.
Flow Y to X:
x y ta tw q (veh/hr) t
(minutes)
401 1 11 12 1048.70 11.94
360 4 10 13 949.57 12.75
419 2 12 12 1052.50 11.89
397 1 9 9 1326.67 8.95
406 3 13 13 948.35 12.81
412 6 10 11 1194.29 10.71
Mean values 1085.93 11.51
qYX = 1090 veh/hr
vYX = (6.4) (60)/11.51 = 33.4 km/h
3.1.3 SPEED STUDIES
There are many types of speed in connection with highway planning. Those of most interest are:
Spot speed, Running speed, and Journey speed.
Cum. Freq., %
Methods of Measurement:
i. Registration Number Method
Observers with synchronized watches stay at both ends of the test section and note the
time a vehicle passes them.
ii. Elevated Observer Method
Here the road section has to be relatively short so that the vehicles remain within sight of
the elevated observer. This method is useful in city streets. It also has the advantage that
any vehicle delays can be noted. The disadvantage is that suitable observation points are
difficult to secure.
iii. Moving Car Observer Method
This is the same method already described under “Volume Studies”. We use the
formulas:
For the stream flow,
q = 60 (x + y) (veh/hr)
ta + tw
and for the flow journey time,
t = tw – y = x – ta (minutes)
q q
Then, Journey speed, v = distance/journey time = l/t.
Methods of Measurement:
Delay studies are carried out separately at particular locations or in conjunction with studies
determining running and journey speeds, e.g. the elevated observer method but most especially
the moving car observer method, which is most useful in determining the cause and extent of
delay encountered en route.
Sampling Techniques
It is not possible to interview all vehicles and so sampling may be done in one of three ways:
(a) Stopping a fixed no. of vehicles out of a certain no. in order to get a certain percentage,
e.g. stopping three vehicles and allowing the next nine to proceed to get a 25%-by-
vehicle sample.
(b) Stopping all vehicles that arrive at the site during a pre-determined period of time, e.g
stopping all vehicles every alternate half-hour in order to get a 50% by time sample.
(c) After completing an interview, the very next vehicle but one is stopped and others
allowed to proceed until the interview with that vehicle is again completed. In this way,
the interviewer is able to work at a constant rate, traffic delays are kept to a minimum,
and good sampling percentages are obtained (higher in light traffic and lower in heavy
traffic).
Disadvantages:
(a) Results are unreliable because no. of cards returned may be small.
(b) Results may be heavily weighted in favour of facilities of particular interest to motorists
in certain areas.
(c) Results may be distorted because returns from through-trippers will be especially low and
unrepresentative.
(d) Results may be distorted because office workers will more likely return postcards than
manual workers.
Advantages:
(i) All data are obtained at once for the chosen day of travel.
(ii) Untrained personnel can be used to hand out or send the cards by post.
(iii) There is little interference to traffic at congested road locations.
Disadvantage:
(a) Because of large manpower requirements, its use is limited to single highway facilities or
to small survey areas with few exits and entrances. All observation sites must be manned
simultaneously (at the same time) and continuously throughout the day.
Advantage:
(a) The path of each vehicle can be traced through the survey area by having intermediate
observers note the colour/shape of the tag on each vehicle. This could help in
determining the need for a by-pass.
b. The base is the most important and normally the thickest layer of the flexible pavement
on which the surfacing rests. It is the main load-spreading layer of the pavement. It bears the
burden of distributing the applied surface loads to ensure that the bearing capacity of the sub-
grade is not exceeded. It should therefore be built from high quality material capable of
withstanding high shearing stresses imposed from the surface loads. It will normally consist of
either
(i) crushed stone or gravel
(ii) gravelly soils
(iii) decomposed rock
(iv) sands, or
(v) sand-clays stabilized with cement, lime or bitumen
c. The sub-base is the secondary load-spreading layer underlying the base. It may or may
not be present in a pavement depending on the purpose for which it is to be used. Its function
may be examined from a number of aspects:
1. The sub-base helps to distribute the applied loads to the sub-grade. Its stresses are
less than those of the base. Therefore the materials can be of lower quality than those of
the base but must always be stronger than the sub-grade.
2. A coarse-grained material in the sub-base acts as a drainage layer to pass to the
highway drainage system any moisture which falls during construction or which enters
the pavement after construction
3. When we have a fine-grained (clayey) sub-grade soil, a granular sub-base may be
provided.
(i) to carry constructional traffic and act as a foundation for subsequent layers
(ii) to act as a cut-off blanket to prevent moisture from migrating upward from the
sub-grade
(iii) to act as a cut-off blanket to prevent the infiltration of sub-grade material into
the pavement.
The material used will depend on the purpose of the sub-base and the grading of the sub-
grade soil. It will normally consist of unprocessed natural gravel, gravel-sand or gravel-
sand-clay.
d. The sub-grade is the upper layer of the natural soil over which the pavement is being
built. It may be the undisturbed local material exposed by excavation or soil excavated
elsewhere and placed into an embankment. In either case it is compacted during
construction to give added stability and, where very weak soils are encountered, the sub-
grade may be improved by mixing in an imported better soil or a small amount of a
stabilizing agent.
(i) to know the number of commercial vehicles that will use the road when it is first opened
to traffic. This is based on the results of classified traffic counts taken on existing routes
along the corridor through which the new road will run. Seasonal traffic counts may be
conducted to provide more reliable data. When there are no existing roads in the area,
traffic estimates can be made on the basis of potential land use and other factors. For
new roads in residential and associated developments, it is common for accurate data not
to be available. The initial values to be assumed are then taken from tables (Table 1 of
the handout).
(ii) to forecast the annual growth rate, r, of this traffic. For developed countries, r is usually
taken between 3% and 6%, while for developing countries, r is between 6% and 15% and
may vary considerably from year to year, region to region and road to road. It is possible
for the growth rate to be 0% for certain specialized roads, e.g. those leading to refineries,
factories, etc. In the absence of any information, a growth rate of 4% is assumed.
(iii) to determine what the design life of the pavement should be. In the developed countries,
the design life is often taken as 20 years. However, a shorter design life (often 10 years)
is chosen for road pavements in developing countries because there is a tendency for the
percentage of heavy goods vehicles to reduce in these developing economies with time,
apart from the considerable variation in the traffic growth rates from year to year. In
those circumstances, long-term forecasting of traffic is very difficult.
A second reason for choosing a shorter design life when the traffic growth rate is high is that it is
rarely economic to build a road pavement strong enough to carry the traffic that will be using it
twenty years or so in the future when this may be as much as ten times as great as the initial
traffic. In such cases it is recommended that the pavement design is based on a ten-year design
life and that a form of construction is chosen that can readily be strengthened, normally by
adding a bituminous overlay when the growth in traffic requires it.
This approach, a form of “stage construction”, can be applied to most roads outside urban areas.
In towns the restrictions on road surface levels due to fixed access levels to buildings, drainage
arrangements, etc may make substantial overlaying impracticable.
STEP 2: ESTIMATING THE EQUIVALENT NO. OF STANDARD AXLES USING THE
ROAD OVER THE DESIGN LIFE
The deterioration of road pavements caused by traffic results from both the magnitude of the
individual wheel (or axle) loads and the no. of times these loads are applied.
(a) If the axle-load distribution of a typical sample of the commercial vehicles that will use the
road is known together with an estimate of the numbers of each axle load to be carried during
the design life of the pavement, then the equivalence factors given in Table 2 of the handout
(according to Liddle’s formula) are used as multipliers to obtain the equivalent number of
standard 8200 kg (18000 lb) axles to be catered for in the design.
Finally, the following formula is used to take into account a growth rate for any or all of the axle
loads:
Let Ax = no. of axles/day for a particular year, year x
Ao = no. of axles/day at the time of traffic count. (This is taken as the axles/day for the first
year of the design life of the pavement, i.e. A1 = A0.)
r = annual growth rate; this is generally taken as 0.04 or 4% in the absence of information to
the contrary. Usually, the regional growth rates for comparable or similar facilities are
employed.
x = number of years from the year of construction to the year for which the number of axles
per day is required.
Then, Ax = Ao (1 + r)x – 1
Evaluating, we have A1 = A0, A2 = A0 (1 + r), A3 = A0 (1 + r)2, A4 = A0 (1 + r)3, etc.
To obtain the cumulative no. of axles of any one category during the design life, the no. of axles
per day for each year over the design life is computed using the formula above. This is
multiplied by 365 (to obtain the no. of axles throughout the particular year) and summed to give
the cumulative no. of axles over the design life.
When the growth rates differ from year to year, the above method is the only practicable one.
When we have a constant growth rate over the design life, the following two methods can also be
used in getting the cumulative no. of axles. Firstly, it could be read from special charts such as
the one given in Fig. 1 of the handout. Secondly, we could apply the formula as derived below:
As seen above, Ax = Ao (1 + r)x – 1
This is a geometric sequence with:
first term a = A0
and common ratio R = 1 + r
Sum of first n terms of such geometric series is given by:
S = a Rn – 1
R–1
Sn = Ao (1 + r)n –1 = Ao (1 + r)n – 1
1+ r–1 r
where n is the design life.
4.2.1.1 Road Note 31 (RN31) Method of Design for Bitumen-Surfaced Roads in Tropical or
Sub-Tropical Countries
RN31 design method is developed for the developing countries. The chart in RN31 (fig. 2 of the
handout) has been designed on the basis that a standard thickness of road base, with a variable
thickness of sub-base to allow for the different sub-grade strengths, is the most economical
design for flexible pavements with light commercial vehicle flows as in developing countries.
Note that the sub-base CBR must be 25% or more. Therefore, no sub-base is required if the sub-
grade CBR is 25% or more. A minimum thickness of 100 mm of sub-base is to be used with
sub-grade having CBR from 8 to 24%. For flexible pavements required to carry up to 0.5 million
standard axles in one direction over a design life of 10 years or more, a base thickness of 150
mm with a double surface dressing will be adequate.
If it is desired to provide at the time of construction a pavement capable of carrying from 0.5 to
2.5 million standard axles in one direction over the design life, there are three options or choices.
(i) Either a 150 mm thick base with double surface dressing. The sub-base thickness is
determined from the continuous lines, same as for cumulative traffic from 0 to 0.5 million
standard axles.
(ii) Or a 150 mm base with a 50 mm bituminous surfacing. The sub-base thickness is
determined from the broken lines.
(iii) Or a 200 mm base with a double surface dressing. The sub-base thickness is determined
from the broken lines.
Note that in options (ii) and (iii) the sub-base thickness is slightly reduced.
In general, for roads which will carry not more than 300 commercial vehicles per day (in both
directions) at the time of construction, the most economical solution will be to choose the
double surface dressing on the 150 mm base initially, and to add the 50 mm bituminous
surfacing some years later.
The design chart has been drawn up on the assumption that one of the following base materials,
used in the tropics for the great majority of bituminous surfaced roads, will be used:
(i) mechanically-stable natural gravel or crushed gravel
(ii) crushed rock
(iii) cement or lime stabilized soil
(iv) bitumen-stabilized sand
When the traffic loading is beyond that covered by RN31, RN29 can be used with success in
tropical countries.
Example 4.1
Given that the existing traffic flow per day and the equivalent standard axle factor are as shown
in the table below and the CBR and design life are 4% and 10 years, respectively. Design the
flexible pavement (Flexible bituminous surface).
Table: Traffic flow and ESA factor
Commercial Vehicle Existing traffic flow/day ESA factor
Heavy truck 20 4.80
Medium truck 150 4.62
Light truck 50 1.00
Large bus 100 1.00
Solution
Commercial Vehicle Existing traffic ESA factor Existing Annual ESA
flow/day ESA/day
(1) (3) (4) × 365
(2) (4) = (2)×(3)
Heavy truck 20 4.80 96 35040
Medium truck 150 4.62 693 252945
Light truck 50 1.00 50 18250
Large bus 100 1.00 100 36500
Total Annual ESAs 342735
Cummulative Standard Axle for the design period is determined using the formula below:
Cummulative ESA =
=
=
=
= 4114533.676
= 4.1 × 106
Using the Road Note 31:
Traffic Class = T5
Subgrade Strength Class = S2
Provide
200mm Granular capping layer or selected subgrade fill
275mm Granular subbase
175mm Granular roadbase
50mm flexible bituminous surface
Traffic Analysis
For the purpose of structural design, the loads imposed by private cars do not contribute
significantly to the structural damage caused to road pavements by traffic. Therefore, only the
number of commercial vehicles and their axle-loadings are considered. Normally, the heavy
commercial vehicles operate on the outermost lane (the slow lane). Hence, the procedure
provides designs applicable to this lane. These designs will be used over the whole carriageway
width.
For various initial intensities of commercial traffic, Fig 4.5 gives the cumulative number of
commercial vehicles carried by each slow lane for design lives up to 40 years. Fig 4.5 (a), (b), (c)
and (d) are for annual growth rates of 3, 4, 5 and 6 percent respectively.
If the initial traffic intensities are greater than 2500 commercial vehicles per day in each
direction (the maximum shown in Fig 4.5), the cumulative number of commercial vehicles
carried by the design lane can be estimated by extrapolation from the given curves. However, if
the traffic data lead to the cumulative total of more than 90 million commercial vehicles to be
carried by the design lane during the design period, a value of 90 millions should be adopted
because the road is likely to be saturated.
The number of commercial vehicles carried by the design lane is then converted to a number of
axles. The average number of axles per commercial vehicle varies with the type of road as shown
in Table 4.7. The number of commercial axles has to be expressed as equivalent number of
18,000-pound axles (standard axle). Table 4.7 also gives the number of standard axles per
commercial axle and the factor that must be applied to the cumulative number of commercial
vehicles on the design lane to derive the cumulative number of standard axles for use in the
design.
Figure 4.5: Relations between cumulative number of commercial vehicles carried by design
lane and design life
Table 4.7: Conversion factors to be used to obtain the equivalent number of standard axles
from the number of commercial vehicles.
Subgrade
The strength of the subgrade is a principal factor in determining the thickness of the pavement.
The strength of the subgrade is assessed on the CBR scale. Road Note 29 recommended that the
water table should be prevented from rising to within 600 mm of the finished subgrade level.
This may be done by sub-soil drainage or by raising the finished subgrade level by means of an
embankment.
Subbase
The required thickness of subbase is determined from the cumulative number of standard axles to
be carried and the CBR of the subgrade using Fig 4.6. In the case that CBR of the subgrade is
less than 2 percent (the lowest value given in Fig 4.6), an additional 150 mm of subbase, above
the requirement for CBR 2 percent, should be used.
For cumulative traffic of less than 0.5 million standard axles, the minimum CBR of the subbase
should be 20 percent. For cumulative traffic in excess of 0.5 million standard axles, the minimum
CBR of the subbase should be 30 percent. For stabilized subbase, it can be assumed the CBR of
30 percent.
If the CBR of the subgrade is in excess of the minimum requirement for the subbase, no subbase
is required. Where subbase is required the minimum thickness that should be laid are 80 mm
where the cumulative traffic is less than 0.5 million standard axles and 150 mm where the traffic
is in excess of that value.
Base
Road Note 29 suggested the base materials as summarized in Table 4.8. The thicknesses required
for each of the base materials are determined by the use of Fig 4.7 or Fig 4.8, in terms of
cumulative number of standard axles to be carried.
To use the charts, it should be noticed the difference in English and American terminology.
“Roadbase” would be “Base course” in American and “Basecourse” would be “Binder course”.
Surfacing Course
The thickness of surfacing in terms of the cumulative number of standard axles to be carried can
be determined by Fig 4.7 and Fig 4.8 depending on the type of base material used. RoadNote 29
recommended the surfacing course material to be varied with the cumulative traffic to be carried
and the details are given in Table 4.9.
The surfacing is intended to be laid in two courses, except where the cumulative traffic is less
than 0.5 million standard axles. The thicknesses of surfacing course are indicated in Table 4.9.
For cumulative traffic of over 11 million standard axles the minimum thickness of surface course
plus binder course is 100 mm. For additional surfacing thickness over 100 mm shown in Fig 4.7
and Fig 4.8
Table 4.9: Bituminous surfacing materials as recommended by Road Note 29
Figure 4.6. Thickness of subbase.
Figure 4.7: Lean concrete, soil cement and cement-bound granular base courses: minimum
thickness of surfacing and base course
Figure 4.8: Wet-mix and dry-bound macadam base course: minimum thickness of
surfacing and base course.
4.3 Analytical Method of Flexible Pavements Design
The theoretical approach for designing flexible pavements uses fundamental physical properties
and theoretical model of each pavement material to predict the stresses, strains and deflections
due to load on the pavement. The thicknesses and composition of pavement materials are
designed so that the stresses, strains and deflections do not exceed the capabilities of any of the
materials.
Some of the advantages of the analytical method as compared to empirical methods are as
follows.
The analytical method is more theoretical. It is based on mechanistic responses on
pavement materials to the applied loads. Provided that the material properties and
material model are correct, the pavement can be designed correctly and confidently
anywhere and any environment condition.
Pavements can be designed according to any available materials. In the empirical
approach, the procedures are limited only to certain pavement materials for which they
were developed.
The analytical approach can cater any magnitude of wheel loads and frequencies while
the empirical method is valid only for the wheel loads and traffic intensities that it has
experienced during the experimental processes.
For certain traffic condition, a pavement can be designed into various patterns. This helps
the engineers to select the most optimum one. The empirical method is limited only one
or two patterns of pavement structure.
Since the damage of pavement can be predicted, therefore the maintenance strategies can
be easily obtained.
By the advent of computer, the analysis and design can be performed quickly.
The main disadvantage is that the analytical approach is still required a great deal of researches
in order to develop the relationships between loads and pavement responses as well as the
models to predict pavement distresses based on these responses. Moreover, because of
complexity of the method, computer is necessary.
Contraction joints
These are to limit tensile stresses induced in the pavement due to contraction or shrinkage of the
concrete and to prevent or control cracking. They are also constructed transverse to the road
centre-line. They are also to be provided with load-transfer devices (dowel bars). When the
pavement is reinforced, the mesh is not carried through the joints. The reinforcing is used to
control cracking between the contraction joints.
There are two main types of contraction joints: butt joints and dummy joints. Butt joints are
normally used on road schemes which utilize the alternate-bay method of slab construction.
Dummy joints are a deliberate groove which is placed in a slab in order to form a vertical plane
of weakness and thus induce a controlled crack. Dummy joints may also be constructed by
sawing the concrete after it has slightly hardened.
Warping joints
Also known as hinge joints, warping joints are simply breaks in the continuity of the concrete
which allow a small amount of angular movement to occur between adjacent slabs, thus limiting
the stresses due to restrained warping. Their main usage is for longitudinal jointing purposes,
though they may also be used as transverse joints. Longitudinal joints are used in highway
pavements to relieve curling and warping. In one lane-at-a-time construction, the longitudinal
joints are used to ensure load transfer and the pavements are tied together with tie bars.
In contrast to expansion and contraction joints, appreciable changes in joint width are prevented
at warping joints. This is done by either continuing the reinforcing steel through each joint or by
utilizing tie bars to draw the sides of the joint together.
Dummy warping joints are the same as dummy contraction joints except that the tie bars are not
lubricated to allow sliding to occur. The tie bars do not act as load-transfer devices but only to
bond both slabs together. Load transference is provided by the interlocking of the aggregate
particles at the face of the joints. In the tongue-and-groove type of warping joint, the slabs are
held together by the tie bars and load transference is provided by the tongue-and-groove
interlock.
Construction joints
These are needed when fresh concrete mixes are placed next to hardened concrete. Examples are
night joints transversely across the pavement at the end of a day’s job, or longitudinal lane joints
or edge joints when full width is not placed in the same pass.
Dowels
Dowel bars are to be plain steel bars with yield strength not less than 240 MPa and 500 mm long.
Dowels should strength with one end free from burrs. Appropriate dowel diameter, for slab
thickness of 200 – 250, is 25 mm.
Dowels at a spacing of 300 mm should be installed at transverse contraction joints where
appropriate. Dowels must be securely held parallel to each other, to the road centerline and to the
centerline of the surface of the finished pavement.
Tie Bars
Tie bars prevent separating of the pavement at longitudinal joints. Ties bars are to be 16 mm
diameter, 500 mm long and have yield strength of 400 MPa. Place centrally in the joint at
spacing 600 mm.
Subgrade
Road Note 29 categorized the subgrade based on its qualities in to three groups as given in Table
6.10. As in design of flexible pavements, Road Note 29 recommended that the water table should
be prevented from rising to within 600 mm of the finished subgrade level. This may be done by
sub-soil drainage or by raising the finished subgrade level by means of an embankment.
Subbase
The minimum thickness of subbase recommended for the three types of subgrade is also given in
Table 6.10.
Where heavy construction vehicles have to operate over the prepared sub-base laid on weak or
normal subgrades only, the sub-base should be strengthened as follows:
CBR 4%: Additional 150 mm of sub-base
CBR 4%: Additional 80 mm of sub-base
Table 6.10: Classification of subgrades for concrete roads and minimum thicknesses of
subbase required as recommended by Road Note 29
4.5.3 Concrete slab
The required thickness for reinforced and unreinforced concrete slab in terms of the cumulative
number of standard axles to be carried for the three types of subgrades is determined by the chart
shown in Fig 6.7. The designs given by this chart are based on a minimum compressive strength
for concrete of 28 MPa at 28 days.
Figure 6.7: Thickness of concrete slab as recommended by Road Note 29
The cumulative number of standard axles to be carried by each slow lane of the pavement is
estimated from the initial commercial traffic, growth rate and design life, using the method as for
flexible pavements.
4.6 Reinforcement
The minimum weight of reinforcement required in relation to the cumulative no. of standard
axles is given in a chart in terms of weight of long mesh reinforcement and area of steel per unit
width of pavement.
(i) The reinforcement should have 60 mm cover. This could be reduced to 50 mm if
slab thickness 150 mm
(ii) The reinforcement should terminate at least 40 mm and not more than 80 mm
from the edge of the slab and from all joints except longitudinal joints.
(iii) At the transverse overlap of reinforcing mats the first transverse wire of one mat
should lie within the last complete mesh of the previous mat and the overlap
should not be less than 450 mm. No overlap will be needed longitudinally
between mats.
(iv) When deformed bar reinforcement is used, the transverse overlap of the bars
should not be less than 40 bar diameters.
(v) To span longitudinal joints (when constructing a two-or three-lane carriageway
widths in one operation), reinforcing mats having 8 mm diameter at 200 mm
centres may be used in place of tie bars. The 8 mm wires must span at least 500
mm either side of the longitudinal joints.
4.6.1 Reinforcement design procedure
The purpose of reinforcing steel in rigid pavements is not to prevent cracking of the concrete, but
to hold tightly closed any cracks that do occur in such manner that the load carrying capacity of
the slab is preserved.
In jointed pavements the amount of steel is governed by the spacing of contraction joints. In case
of continuously reinforced pavements, sufficient steel is provided to eliminate the need for
contraction joints.
Joints
(a) Spacing of joints in reinforced concrete slabs:
The recommended maximum spacing of joints in relation to the actual weight of reinforcement
used is shown in one of the charts. Every third joint should be an expansion joint, the
remainder being contraction joints. Reinforcement must be discontinuous at both contraction
and expansion joints.
Longitudinal joints should be provided to ensure that the slabs are not more than 4.5m wide.
(b) Spacing of joints in unreinforced concrete slabs:
For slabs > 200 mm thick, Expansion joint spacing = 60m
For slabs < 200 mm thick, Expansion joint spacing = 40m
Intermediate contraction joints are then placed at 5m intervals.
Tied warping joints may be substituted for some of the sliding contraction joints, but not
more than three such warping joints may be used in succession.
Longitudinal joints should be provided so that the slabs are not more than 4.5 m wide.
(c) Details of joints in concrete slabs:
(i) Expansion joints to be provided with joint filler 25 mm thick.
(ii) All joints should be provided with a groove to accommodate a sealing material
the most important function of which is to keep out grit, the groove being filled
with sealing compound to 5 mm below the surface of the concrete.
(iii) To ensure complete formation of contraction and longitudinal joints, the
combined depth of groove and fillet should be ¼ to 1/3 of the thickness of the
slab.
(iv) Adequate means of load transference should be provided at all joints in concrete
pavements of 150 mm or greater thickness. All expansion and contraction joints
should have sliding dowel bars placed at 300 mm centres and half the length of
the bars should be coated with a bond-breaking compound. The bars in expansion
joints only should be provided with a cap at the debonded end, containing a
thickness of 25 mm of compressible material to allow the joint to open and close.
(v) Longitudinal joints should have tie bars 12 mm in diameter by 1m long at 600
mm centres.
Examples
1. Reinforced concrete slab
A reinforced concrete pavement design is required for a road to carry 2200 commercial vehicles
per day (sum in both directions) at the time of construction with a growth rate of 5%. The
subgrade has a CBR of 2%. Construction traffic will require to use the base. The design life is
to be 20 years.
Solution
(a) Traffic
ADT = 1100 comm. vehs. per day in each direction
r = 5%
Cumulative no. of comm. vehs. = 12.5 million
Cum. no. of std. axles = 12.5 x 1.08 = 13.5 million
(b) Subgrade
CBR = 2%
Classified as “weak”.
(c) Sub-base
Minimum requirement = 150 mm
Additional requirement for construction traffic = 150 mm
Total sub-base thickness = 300 mm
(d) Slab thickness
For weak subgrade, thickness = 222 + 25 = 247 mm for a loading of 13.5 mil. standard
axles
This is rounded upwards to 250 mm
(e) Reinforcement
Min. wt of reinforcement required for the traffic = 3.8 kg/m2
Next standard wt. of reinforcement = 4.34 kg/m2 (selected)
(f) Joint spacing
Corresponding to 4.34 kg/m2 reinforcement, joint spacing = 27.5m
Expansion joints are built at spacings of 3 x 27.5 = 82.5m.
Contraction joints will be two in between at 27.5m spacing.
If constructed in hot weather, the expansion joints may also be replaced with contraction
joints.
Example
The following parameters were given for the design of a four lane highway:
Average daily traffic in one direction = 7429 vehicles
Percent of commercial vehicles = 28.32%
Annual growth rate = 5%
Equivalent factor for commercial vehicles = 0.45
Design the joint plain unreinforced pavement using the Road Note 29 method. Assume the
average number of standard axle per commercial vehicle = 1
Solution
Number of commercial vehicle in the design lane per day = 7429 × 0.2832 × 0.45
= 946 vehicles
Number of commercial vehicle in the design lane per year = 946 × 365 = 345290 vehicles
Number of commercial vehicles during the design period is calculated as follows:
=
= 11417359.14
= 11.4 × 106