Tunnel Load Rating Examples - A Supplement To The Reference Guide For Load Rating of Tunnel Structures
Tunnel Load Rating Examples - A Supplement To The Reference Guide For Load Rating of Tunnel Structures
The National Tunnel Inspection Standards (NTIS, 23 CFR 650.513(g)) require States and
Federal agencies to “[R]rate each tunnel's safe vehicular load-carrying capacity in accordance
with the Sections 6 or 8, AASHTO Manual for Bridge Evaluation (incorporated by reference, see
§ 650.517(b)(1)).” However, the AASHTO Manual for Bridge Evaluation (MBE) lacks specific
information on the load rating of tunnels. In addition, Section 5.4 of FHWA’s Tunnel
Operations, Maintenance, Inspection, and Evaluation (TOMIE) Manual, published in 2015 only
provides limited information. As a result, FHWA published the Reference Guide for Load Rating
of Tunnel Structures in 2019.
This report is intended to be used as a supplement to that Reference Guide. It presents two
practical examples of load rating for actual, in-service tunnel structures. The examples are based
on the information contained within the Reference Guide and the computations are presented in
similar detail as the load rating examples included in the Reference Guide.
Subject matter experts from several State DOTs and FHWA provided technical review of this
report. Their advice, counsel and contributions during the preparation of this report are greatly
appreciated.
The contents of this document do not have the force and effect of law and are not meant to bind
the public in any way. This document is intended only to provide clarity to the public regarding
existing requirements under the law or agency policies.
ii
3.1 STRUCTURE DATA .................................................................................................................. 97
3.1.1 Materials ............................................................................................................................... 97
3.1.2 Dimensions ........................................................................................................................... 98
3.1.3 Example Notes ...................................................................................................................... 98
3.1.4 Rating Approach/Assumptions .............................................................................................. 99
3.2 STEEL ROOF GIRDER .............................................................................................................. 99
3.2.1 Load Calculations ................................................................................................................. 99
3.2.2 Structural Analysis .............................................................................................................. 102
3.2.3 Resistance Calculations ....................................................................................................... 104
3.2.4 LRFR Rating Calculations................................................................................................... 109
REFERENCES.................................................................................................................................... 111
iii
LIST OF FIGURES
iv
Figure 31. Illustration. Live Load Placement for Maximum Moment. ...................................... 103
Figure 32. Illustration. Live Load Placement for Maximum Shear. .......................................... 103
Figure 33. Illustration. Load Placement. .................................................................................. 103
Figure 34. Illustration: Plastic Neutral Axis Offset Dimensions. .............................................. 107
Figure 35. Illustration. Bracket Details. ................................................................................... 109
v
LIST OF TABLES
vi
Table 32. Maximum Moment (kip-ft) & Corresponding Shear (kip) & Axial (kip). ................... 88
Table 33. Minimum Moment (kip-ft) & Corresponding Shear (kip) & Axial (kip). .................... 88
Table 34. Maximum Shear (kip) & Corresponding Moment (kip-ft) & Axial (kip). ................... 89
Table 35. Maximum Axial (kip) & Corresponding Moment (kip-ft) & Shear (kip). ................... 89
Table 36. Load Factors. ............................................................................................................. 94
Table 37. HL-93 Inventory Level Rating Factors....................................................................... 94
Table 38. HL-93 Operating Level Rating Factors. ..................................................................... 94
Table 39. EV-3 Rating Factors. ................................................................................................. 95
Table 40. Building Performance Ratio. ...................................................................................... 95
Table 41. Moment Load Placement Dimensions. ..................................................................... 103
Table 42. Shear Load Placement Dimensions. ......................................................................... 104
Table 43. Unfactored Girder Critical Forces. ........................................................................... 104
Table 44. Short Term Composite Properties. ........................................................................... 105
Table 45. Long Term Composite Properties. ........................................................................... 106
Table 46. Load Factors. ........................................................................................................... 110
Table 47. Girder Resistance and Rating Factors....................................................................... 110
vii
LIST OF ABBREVIATIONS AND SYMBOLS
viii
CHAPTER 1 - INTRODUCTION
The purpose of this non-binding Supplement to the voluntary FHWA Reference Guide for Load
Rating of Tunnel Structures (Guide), created by the Federal Highway Administration (FHWA),
is to present two practical examples of real, in-service tunnel structures. The examples are based
on the information contained within the Guide, and computations are presented in similar details
as the load rating examples included in the Guide. The ratings are provided for LRFR only. The
examples are rated for the HL-93 and EV vehicles. Additionally, a nominal permit load is
applied and rated for Example 1. For each example, one cross-section with one set of parameters
(e.g. dead loads, soil parameters, etc.) is rated. Repetitive hand calculations are shown once in
detail (equations) with the subsequent results summarized in tables. Elements from the original
drawings and inspection reports (where applicable) are used in the examples where legible and
useful. Supplemental sketches are developed as necessary in a similar style as the Guide. Where
actual dimensions or properties are unclear or unavailable, reasonable approximations are made.
The results of the two examples may be used to validate the load ratings in the records of the
tunnels. Unless otherwise specified, all references refer to the voluntary Guide (FHWA 2019),
the non-binding MBE 3rd Edition (AASHTO 2018) (see Section 1.2 for the components and
editions incorporated by reference in the Federal regulations), or the TOMIE Manual (FHWA
2015a) [23 CFR 650.517(c)(1)].
• Chapter 2 covers the load rating of Example 1 – Circular Tunnel Liner with Invert
Structures.
• Chapter 3 contains the load rating of Example 2 – Box Tunnel Roof Girder.
National Tunnel Inspection Standards (NTIS) [23 CFR 650.513(g)]. The NTIS requires
“tunnel owners to establish a program for the inspection of highway tunnels” (Federal Register,
July 14, 2015, 80 FR 41350) to maintain an inventory, and to provide inspection findings to
FHWA as well as make corrective actions to critical issues found during inspection. This
document ultimately sets the rules and regulations regarding tunnel inspection and evaluation.
Federal regulation at 23 CFR 650.513(g) provides the regulations regarding the load rating of
tunnels. The NTIS incorporates, by reference, the Specifications for the National Tunnel
Inventory (SNTI) [23 CFR 650.517((c)(2)] and TOMIE Manual [23 CFR 650.517(c)(1)]. Refer
to the paragraph on the MBE below for components and editions incorporated by reference into
the Federal regulations.
9
Specifications for the National Tunnel Inventory (SNTI) (FHWA 2015b) [23 CFR 650.517
(c)(2)]. Developed in coordination with the NTIS, the SNTI provides the specifications and
coding data required to be submitted to the National Tunnel Inventory (similar to the National
Bridge Inventory (NBI)). Details are provided in each chapter of the SNTI regarding how to log
information for each item’s code, and how the Engineer decides which codes are applicable for
the tunnel at hand. Section 2 provides general information about the tunnel, where Section 2.7
provides the current load rating information. Section 3 discusses the specific tunnel elements,
with Section 3.2 (structural) and Section 3.3 (civil) being the most relevant. Section 4 provides
an index of inventory items and elements while Section 5 provides an example tunnel coding that
helps readers understand the inspection coding process and can be back-referenced to the rest of
the SNTI for further understanding. There are no references to any load rating process in the
SNTI.
AASHTO Manual for Bridge Evaluation (MBE) (AASHTO 2018). This voluntary edition of
the MBE provides procedures for determining “the physical condition, maintenance needs, and
load carrying capacity” for bridges. MBE Chapter 6 through Chapter 8 are of interest because
they present the concepts of load rating for vehicular live loads. In particular, Chapter 6
describes non-binding criteria for load rating and posting of bridges and informed several of the
load rating concepts presented in the Guide. The most current edition at the time of publication
of the Guide is the 3rd Edition. Subsequent references to the MBE in this document are relevant
to the voluntary 3rd Edition of the MBE. The portions and editions of the MBE incorporated into
the Federal regulations by reference in the NTIS, which are binding, are Sections 6 and 8 of the
2nd Edition, 2011 [23 CFR 650.517(b)(1)], the 2011 Interim Revisions to Section 6 [23 CFR
650.517(b)(2)], the 2013 Interim Revisions to Section 6 [23 CFR 650.517(b)(3)], the 2014
Interim Revisions to Section 6 [23 CFR 650.517(b)(4)], and the 2015 Interim Revisions to
Section 6 [23 CFR 650.517(b)(5)].
AASHTO LRFD Bridge Design Specifications, 8th Edition (BDS) (AASHTO 2017a) [23
CFR 625.4(d)(1)(v)]. Concepts such as standard loads, load factors, material resistance, and
resistance factors that are used in the Guide and the MBE are taken directly from the LRFD
BDS. The document represents an agreement among owners for the proper design of highway
bridges and is maintained by AASHTO.
AASHTO LRFD Road Tunnel Design and Construction Guide Specifications, 1st Edition
(LRFDTUN) (AASHTO 2017b). The non-binding LRFDTUN provides specifications for
design, evaluation, and rehabilitation of highway tunnels and is maintained by AASHTO.
FHWA Memorandum: Load Rating for the FAST Act’s Emergency Vehicles (FHWA
2016). This voluntary and non-binding memorandum provides explanations of the ratings for the
10
emergency vehicles enacted by the Fixing America’s Surface Transportation Act (FAST Act) [23
CFR 650.313(c)].
The FHWA Reference Guide for Load Rating of Tunnel Structures (Guide) (FHWA 2019)
is voluntary, non-binding reference guide created by the FHWA to illuminate the technical
aspects for the load rating of tunnel structures. It provides practical and representative step-by-
step examples of load rating that meets the FHWA’s general load rating guidance. It also
provides technical details and breadth appropriate to explain the load rating specifications in the
non-binding AASHTO MBE (AASHTO 2018) and the FHWA TOMIE Manual (FHWA 2015a)
[23 CFR 650.517(c)(1)]. A set of examples illustrate the specifications, procedures, and methods
for load rating.
The two examples in this Supplement illustrate how to load rate structural components of tunnels
that support roadway live loads, including invert slabs, walls, and other supporting members as
well as tunnel liners where applicable, that support live load from nearby highways.
Example 1 – The first example is located on the west coast of the United States. The tunnel is a
single, large diameter circular bored tunnel with a concrete liner. Internally, there are two levels
of traffic, the lower supported by an invert slab and the upper by a rigid frame. The tunnel liner
is comprised of precast reinforced concrete segments. The actual tunnel is located a distance
below the surface that is more than the diameter of the tunnel, which puts it outside the live load
zone of influence limits for culverts per the MBE (maximum of 8 feet or culvert width). Per
discussions with the FHWA, it will be assumed the tunnel is closer to the surface for the
purposes of this example. The invert slab, rigid frame structure, and tunnel liner will be rated for
this example. The invert slab will be analyzed by hand as a one-way prestressed slab on simple
supports and rated for shear and moment. The rigid frame will be analyzed with a simple 2D
analysis and rated for shear, moment, and thrust at controlling locations. The tunnel liner will be
modeled in Plaxis to determine forces in the liner due to earth loads and surface live loads. Based
on geotechnical information, a representative soil profile will be selected. The street surface
above the tunnel will be located a distance less than the tunnel diameter in order to be within the
zone of influence. Traffic above will be assumed to travel normal to the tunnel. The ring segment
reinforcement will be checked for bending, shear and thrust. The joints between sections will be
checked against crushing, shear, and the formation of a mechanism (bending overcoming thrust
pre-compression and opening joint).
Example 2 – The second example is located on the east coast of the United States. The tunnel is
one of several adjacent boxes with steel roof girders connected by shear-only steel bracket
connections to support walls. The tunnel supports a transverse roadway directly above. The
simply supported composite steel tunnel roof girder will be rated for this example. Forces will be
determined using hand calculations. The tunnel roof girder will be rated for moment and shear.
The capacity of the shear connection will be investigated as well.
11
1.4.2 Assumptions
The following general assumptions were used in the development of the examples and final
document:
• The document is entirely separate and acts as a supplement to the Guide with a separate
report number supplied by the FHWA.
• The examples are based on the information contained within the Guide.
• The examples are in a similar format as the ones in the Guide.
• The ratings are provided for LRFR only. The Guide adequately demonstrates the
difference between LRFR and LFR with parallel calculations in the examples; the
purpose of the examples is to apply the methodology to actual structures.
• The examples are rated for the HL-93 and EV vehicles. Additionally, a nominal permit
load is applied and rated.
• For each example, one cross-section with one set of parameters (e.g. dead loads, soil
parameters, etc.) is rated.
• Repetitive hand calculations are shown once in detail (equations) with the subsequent
results summarized in tables.
• Elements from the original drawings and inspection reports (where applicable) are used
in the examples where legible and useful. Supplemental sketches are developed as
necessary in a similar style as the Guide.
1.4.3 Approximations
12
CHAPTER 2 - EXAMPLE 1 – CIRCULAR TUNNEL LINER, RIGID FRAME, & SLAB
Example 1 presents a bored tunnel with an internal, reinforced concrete frame and a prestressed
bottom slab. The internal roadway is a bi-level, reinforced concrete frame. The bottom roadway
surface consists of a prestressed concrete invert slab. The tunnel is also subjected to surface loads
influencing the tunnel liner. The tunnel is subjected to vertical dead loads, earth loads, and live
loads as well as lateral earth, building surcharge and live load surcharge. The tunnel is rated with
the LRFR method for the design vehicles (HL-93 Inventory and Operating) and emergency
vehicles (EV-2 and EV-3) at the legal load limit.
This example will perform the following steps to rate this reinforced concrete box tunnel:
1. Structure data
2. Example notes
3. Rating approach/assumptions
4. Load application
5. Structural analysis
6. Resistance calculations
2.1.1 Materials
Materials are known, otherwise MBE Articles 6A5.2.1 and 6A5.2.2 may be used. Soil
parameters were randomly selected for the example. Full soil descriptions and evaluation should
be performed for actual tunnel ratings so accurate soil parameters can be obtained. This example
also assumed wet tunnel construction conditions and a 5% soil volume loss.
13
2.1.2 Dimensions
See Figure 1 for the tunnel cross-section geometry and dimensions. The elements rated in this
example are outlined in the figure.
Source: FWHA
Figure 1. Illustration. Cross-Section Showing Tunnel Geometry.
14
2.1.3 Example Notes
• Rating is performed only at maximum shear and moment locations. Typical ratings
include evaluation at all tenth points and other sectional or material change locations.
• LRFR evaluation is performed for a 1-foot wide strip (perpendicular to direction of traffic
inside the tunnel and parallel to the direction of traffic above the box tunnel).
• The pavement on the ground above has approximately the same unit weight as the soil
and is therefore included with the soil vertical loads (that is, gravel pavement surface).
• Compacted gravel fill acts along the sides of the tunnel with soil parameters of = 32°
and = 117 pcf. Additionally, the tunnel is partially submerged in ground water.
15
• LRFR live load ratings are evaluated for HL-93 design loading (Truck or Tandem), the
EV-2 and EV-3 emergency vehicles (FHWA Memo), and a permit truck shown in Figure
2 (for the internal frame and prestressed bottom slab only).
10 kip
18 kip
18 kip
23 kip
23 kip
23 kip
21 kip
21 kip
21 kip
21 kip
21 kip
9.0' 4' 4' 4' 4' 10.0' 4' 4' 4' 4'
Source: FHWA
Figure 2. Illustration. Permit Truck.
#6 @ 6"
#8 @ 6"
#8 @ 6"
#8 @ 6" #6 @ 6"
#6 @ 6"
#6 @ 6"
Source: FHWA
Figure 3. Illustration. Reinforcing Steel Details of Internal Frame.
Dead load components include the self-weight of the concrete internal frame and barriers on the
frame. These loads are described in MBE Article 6A.5.12.10.1 and LRFD BDS Article 3.5.1.
wc = 0.145 kcf + 0.005 kcf = 0.150 kcf LRFD BDS Table 3.5.1-1 and Article C3.5.1
The self-weight of the frame is applied to the model by including self-weight on the geometry
detailed in Figure 1. A 233 plf barrier load is applied on top of the frame at each side of the top
roadway.
A 10 psf fire protection load was applied to the interior surface of the upper roadway as indicated
in the Original Construction Plans (OCPs), this includes the upper walls and the underside of the
16
upper roadway. In addition to the fire protection load, 10 psf utility loads were applied to the
upper roadway surface along with the horizontal walkway surface slabs to the left side of the
internal frame supporting the upper roadway. Additional utility loads of 220 plf and 200 plf were
applied to the center of the middle and lower of these walking surfaces. Details of these loads
can be seen in Figure 5.
This internal frame has no wearing surfaces applied and therefore were not included in the load
calculations.
Air pressures were applied to the Egress Areas, roadways and Extraction Duct as shown in
Figure 1. ±21 psf was applied to the Egress Area, ±10 psf was applied to the roadways and -68
psf was applied to the Extraction Duct, according to the OCPs.
2.2.1.4 Temperature, TU
A temperature range of ±20 degrees was applied to the structure as a whole. This load was
modelled by applying the Temperature tool within the structural analysis program.
Creep and shrinkage is a displacement based force and needs to be modelled in the program as a
temperature variation. LRFD BDS Article 5.4.2.3.1 specifies the creep and shrinkage
displacement is calculated as “c” times “L”. The temperature range can then be backed out of
the temperature displacement equation. This temperature is then input into the structural analysis
program to determine the creep and shrinkage forces. Per Article 5.4.2.3.1, in the absence of
more accurate data, the shrinkage coefficient may be assumed to be 0.0005 after one year of
drying. The coefficient of thermal expansion, α, is specified in LRFD BDS Article 5.4.2.2
cL = = TL
0.0005 = 6.0e−6 T
T = 83.4 F
A 100 psf pedestrian live load is applied to both the Egress Path Corridor and Utility Corridor
floor slabs. A 60 psf pedestrian live load is applied to the Ceiling Slab.
The internal frame is a reinforced concrete frame and behaves similarly to the concrete deck of a
slab bridge. The distribution of axle loads based on an equivalent strip width, E, to cast-in-place
slabs acting perpendicular to the direction of traffic is provided in LRFD BDS Table 4.6.2.1.3-1,
where S is the span length. Per the LRFD BDS, separate distribution factors are computed for the
17
positive and negative moments in the roadway slab using a span, S, of 36 feet. The live load
applied to the walls is dependent on the forces imparted to them due to the fixed end moments
from the roadway slab. As such, this example determines the live load forces in the walls based
on the equivalent strip width, E, computed for negative moments in the slab, ESlab-.
Since the design strip is transverse to the direction of traffic, the wheel loads are included in the
live load evaluation; however, the lane load is not included per LRFD BDS Article 3.6.1.3.3. The
maximum number of trucks to be placed on the structure is obtained by taking the roadway width
and dividing by a 12-foot lane, per LRFD BDS Article 3.6.1.1.1, resulting in two possible trucks
to be placed parallel. This results in axle loads that are placed transversely such to produce
maximum forces at the critical locations, identified at mid-span and wall-slab connection.
Maximum connection forces were obtained by placing the first axle load 2 feet from the edge of
the driving surface per LRFD BDS Article 3.6.1.3.1. The second truck is placed such that there is
4 feet between wheel placements. Maximum positive moment is obtained when the centerline of
the span is midway between the center of gravity of loads and the nearest concentrated load. Live
load placement is shown in Figure 4.
Wheel loads for unit, or 1-foot, analysis widths are determined by multiplying the equivalent unit
width wheel load, P, by the appropriate impact factor (IM) and multiple presence factor (MPF).
The equivalent wheel load is determined by dividing the full wheel load by the equivalent strip
width, E, over which the axle load is distributed. However, if the axle spacing is less than the
equivalent strip width, E, then multiple axles can load the same unit-width analysis strip. In these
cases, the applied load is not simply the full wheel load divided by E; the overlap of axle loads
should be considered. For positive bending, the ESlab+ width of 21.97 feet exceeds the axle
spacing of the HL-93 Truck (14-foot spacing), HL-93 Tandem (4-foot spacing), both EV
vehicles (15-foot for EV-2 and 15- and 4-foot for EV-3), and the permit truck (4- to 10-foot
spacings). For negative bending and the walls, the ESlab- width of 13.00 feet exceeds the axle
spacing of the HL-93 Tandem, EV-2 vehicle (rear axle) and the permit truck. The unit width
wheel load, P, is computed below using equivalent axle loads where required. For a detailed
discussion of modified equivalent widths and figures showing the HL-93 and EV vehicle axle
configurations, refer to Section 9.2.4.1 of the Reference Guide for Load Rating of Tunnel
Structures (FHWA, 2019). Refer to Figure 2 for the permit truck axle configuration.
First, compute P for various axle configurations using the roadway slab positive bending
equivalent slab width, ESlab+, to determine the controlling load for each rating vehicle:
18
HL-93 Design Truck:
32 kip
PHL 93−Truck1 =
2 wheels 16 k/wheel
= = 0.73
( ESlab+ ) 21.97 ft
32 kip + 32 kip
PHL93−Truck 2 = 2 wheels =
32
= 0.89
k/wheel
( ESlab+ 2 + 14 + ESlab+ 2 ) 35.97 ft
25 kip
PHL 93−Tandem1 =
2 wheels 12.5 k/wheel
= = 0.57
( ESlab+ ) 21.97 ft
25 kip + 25 kip
=
2 wheels 25 k/wheel
PHL93−Tandem 2 = = 0.96
( ESlab+ 2 + 4 + ESlab+ 2 ) 25.97 ft
k/wheel
PHL93−Tandem+ = max ( PHL93−Tandem1 , PHL93−Tandem 2 ) = 0.96
ft
EV-2:
33.5 kip
PEV 2−1 =
2 wheels 16.75 k/wheel
= = 0.76
( ESlab+ ) 21.97 ft
19
EV-3:
31 kip
PEV 3−1 =
2 wheels 15.5 k/wheel
= = 0.71
( ESlab+ ) 21.97 ft
31 kip + 31 kip
=
2 wheels 31 k/wheel
PEV 3−2 = = 1.19
( ESlab+ 2 + 4 + ESlab+ 2 ) 25.97 ft
Permit Truck:
As stated, all the permit truck axle spacings are less than ESlab+; therefore, all 11 axle load
possibilities should be considered. The calculations follow the format as above and P
varies from 0.48 to 1.64 over the 11 permutations. The calculation for the controlling 10-
axle configuration is shown below.
21 + 21 + 21 + 21 + 21 + 23 + 23 + 23 + 18 + 18
= = 105 = 1.64 k/wheel
2 wheels
PPermit +
( ESlab+ 2 + 4 + 4 + 4 + 4 + 10 + 4 + 4 + 4 + 4 + ESlab+ 2 ) 63.97 ft
Next, compute P for various axle configurations using the roadway slab negative bending
equivalent slab width, ESlab-, which also applies to the walls, to determine the controlling load for
each rating vehicle:
ESlab-;is less than the HL-93 Truck axle spacings; therefore, only one configuration is
computed.
32 kip
=
2 wheels 32 k/wheel
PHL 93−Truck − = = 1.23
( ESlab+ ) 13.00 ft
HL-93 Design Tandem:
25 kip
PHL 93−Tandem1 = 2 wheels
=
25
= 0.96
k/wheel
( ESlab+ ) 17.00 ft
20
25 kip + 25 kip
=
2 wheels 50 k/wheel
PHL93−Tandem 2 = = 1.47
( ESlab+ 2 + 4 + ESlab+ 2 ) 17.00 ft
k/wheel
PHL 93−Tandem− = max ( PHL93−Tandem1 , PHL93−Tandem 2 ) = 1.47
ft
EV-2:
ESlab-;is less than the EV-2 axle spacing; therefore, only one configuration is computed.
33.5 kip
=
2 wheels 33.5 k/wheel
PEV 2− = = 1.29
( ESlab+ ) 13.00 ft
EV-3:
ESlab-;is less than the front EV-3 axle spacing; therefore, only two configurations are
computed.
31 kip
PEV 3−1 =
2 wheels 31 k/wheel
= = 1.19
( ESlab+ ) 13.00 ft
31 kip + 31 kip
=
2 wheels 62 k/wheel
PEV 3−2 = = 1.82
( ESlab+ 2 + 4 + ESlab+ 2 ) 17.00 ft
k/wheel
PEV 3− = max ( PEV 3−1 , PEV 3−2 ) = 1.82
ft
Permit Truck:
Similar to the positive bending calculations, all the permit truck axle spacings are less
than ESlab-. P varies from 0.81 to 1.91 over the 11 permutations. The calculation for the
controlling 10-axle configuration is shown below.
21 + 21 + 21 + 21 + 21 + 23 + 23 + 23 + 18 + 18
PPermit − = 2 wheels = 105 = 1.91 k/wheel
( ESlab+ 2 + 4 + 4 + 4 + 4 + 10 + 4 + 4 + 4 + 4 + ESlab+ 2 ) 55.00 ft
21
6' 4' 6' 2'
Right
Connection
6' 2'
Mid-Span
13.50' 6'
Left
Connection
2' 6'
Source: FHWA
Figure 4. Illustration. Live Load Placement for Internal Frame.
Single trucks are amplified by a multiple presence factor, MPF, of 1.2 while the two truck effects
utilize a multiple presence factor of 1.0 per LRFD BDS Table 3.6.1.1.2-1. For this example,
MBE Article 6A.4.4.3 is used to determine the dynamic impact factor, IM, of 1.33 for all
vehicles. Additionally, from the equivalent wheel load calculations, it can be seen that the HL-93
tandem will control over the HL-93 truck, and the EV-3 vehicle controls over the EV-2.
A frame analysis procedure is applied for the internal frame model with beam-column elements
based on gross section properties. All the load effects and member resistances are calculated
22
using this 1-foot wide strip representation. Structural analysis of the internal frame is based on a
frame model with moment resisting connections between the slab and the wall joints. The frame
is assumed to be pinned where the concrete frame connects to the tunnel liner, except at the top
walls where they are assumed to be free to vertically translate with respect to the liner. A P-Delta
analysis is also included to account for secondary effects. Although not shown in this example,
consideration for slenderness in the walls may be required in accordance with LRFD BDS
Article 5.6.4.3 [23 CFR 625.4(d)(1)(v)]. The applied loads are shown in Figure 5, and Table 1
through Table 18 provide the resulting force effects.
Source: FHWA
Figure 5. Illustration. Internal Frame Tunnel Applied Loads.
23
The LRFD Road Tunnel Design and Construction Guide Specifications, 1st Edition (AASHTO,
2017b), Table 3.4-1 identifies the applicable minimum and maximum load factors for each load
specified above. These minimum and maximum load factors are matched with the appropriate
load direction and summed to identify the critical design forces, including moments, shears, and
axial forces. The live load factors for the HL-93 are identified in Table 3.4-1, and the live load
factor for the EV vehicles is 1.3 as identified in the FHWA Emergency Vehicle Memorandum
(FHWA, 2016) and the live load factor for the permit vehicle was identified as 1.3 from MBE 3 rd
Edition (AASHTO, 2018) Table 6A.4.5.4.2a-1, corresponding to unlimited crossings, mixed
with traffic, two or more lanes, ADTT greater than 5000, and a permit weight factor ratio
(GVW/AL) greater than 3.
2.94
Span Point
2.10
2.0
2.04
Slab
1.10 3.10
Right Wall
Span Point
Span Point
Left Wall
1.497
3.0
1.0
Source: FHWA
Figure 6. Illustration. Member Identifiers and Directions.
24
Figure 6 shows the span point identification for the tunnel frame. The whole number represents
the member identification while the 10ths number indicates the percentage along the span length.
The forces were factored to produce controlling Strength I (or Strength II for permit loads) as
well as Service I load combinations. These resulting unfactored forces are given in Table 1
through Table 18 and the member identifiers and directions are shown in Figure 6.
25
Table 3. Left Wall Moment (kip-ft).
Sp Pt DC AP+ AP- TU+ TU- CR&SH
1.0 0.00 0.00 0.00 0.00 0.00 0.00
1.1 0.80 -0.06 0.02 -0.40 0.40 -1.68
1.2 1.60 -0.08 0.03 -0.81 0.81 -3.36
1.3 2.41 -0.07 0.05 -1.21 1.21 -5.04
1.4 3.21 -0.07 0.07 -1.61 1.61 -6.72
1.497 2.75 -0.09 0.09 -1.71 1.71 -7.13
1.6 -0.71 -0.05 0.05 -1.53 1.53 -6.37
1.7 -4.17 -0.13 0.13 -1.34 1.34 -5.61
1.8 -7.63 -0.14 0.14 -1.16 1.16 -4.85
1.9 -11.09 -0.09 0.09 -0.98 0.98 -4.08
1.10 -14.65 -0.04 0.10 -0.79 0.79 -3.30
26
Table 6. Right Wall Moment (kip-ft).
Sp Pt DC AP+ AP- TU+ TU- CR&SH
3.0 0.00 0.00 0.00 0.00 0.00 0.00
3.1 1.64 0.00 0.09 -0.33 0.33 -1.38
3.2 3.28 0.00 0.15 -0.66 0.66 -2.77
3.3 4.92 0.00 0.18 -1.00 1.00 -4.15
3.4 6.56 -0.01 0.19 -1.33 1.33 -5.53
3.5 8.20 -0.01 0.18 -1.66 1.66 -6.92
3.6 9.84 -0.01 0.14 -1.99 1.99 -8.30
3.7 11.48 -0.01 0.07 -2.32 2.32 -9.68
3.8 13.12 -0.02 0.01 -2.65 2.65 -11.07
3.9 14.76 -0.14 0.01 -2.99 2.99 -12.45
3.10 16.40 -0.28 0.01 -3.32 3.32 -13.83
27
Table 9. Slab Moment (kip-ft).
Sp Pt DC AP+ AP- TU+ TU- CR&SH
2.0 -3.77 -0.09 0.02 -0.01 0.01 0.03
2.04 -23.88 -0.05 0.05 -0.49 0.49 -2.06
2.2 -1.78 -0.04 0.04 -0.06 0.06 -0.14
2.3 7.83 -0.03 0.03 -0.25 0.25 1.03
2.4 14.24 -0.02 0.02 -0.53 0.53 2.21
2.5 17.28 -0.02 0.02 -0.81 0.81 3.38
2.6 17.18 -0.02 0.01 -1.09 1.09 4.56
2.7 13.92 -0.03 0.00 -1.37 1.37 5.73
2.8 7.53 -0.04 0.00 -1.66 1.66 6.91
2.94 -4.08 -0.01 0.27 -3.16 3.16 13.18
2.10 -16.40 -0.01 0.28 -3.32 3.32 13.83
Unfactored live load envelopes, including PL, HL-93, EVs, and Permit are presented in Table 10
through Table 18.
28
Table 11. Left Wall Shear Live Load (kip).
Sp Pt PL HL-93 Max HL-93 Min EV Max EV Min Permit Max Permit Min
29
Table 13. Right Wall Axial Live Load (kip).
HL-93 HL-93 Permit Permit
Sp Pt PL EV Negative EV Positive
Negative Positive Negative Positive
3.0 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
3.1 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
3.2 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
3.3 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
3.4 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
3.5 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
3.6 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
3.7 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
3.8 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
3.9 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
3.10 0.02 -4.82 0.00 -5.97 0.00 -6.26 0.00
30
Table 15. Right Wall Moment Live Load (kip-ft).
HL-93 HL-93 Permit Permit
Sp Pt PL EV Negative EV Positive
Negative Positive Negative Positive
3.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3.1 -0.01 0.00 1.90 0.00 2.36 0.00 2.47
3.2 -0.03 0.00 3.81 0.00 4.71 0.00 4.94
3.3 -0.04 0.00 5.71 0.00 7.07 0.00 7.42
3.4 -0.05 0.00 7.61 0.00 9.42 0.00 9.89
3.5 -0.06 0.00 9.51 0.00 11.78 0.00 12.36
3.6 -0.08 0.00 11.42 0.00 14.14 0.00 14.83
3.7 -0.09 0.00 13.32 0.00 16.49 0.00 17.31
3.8 -0.10 0.00 15.22 0.00 18.85 0.00 19.78
3.9 -0.11 0.00 17.13 0.00 21.20 0.00 22.25
3.10 -0.13 0.00 19.03 0.00 23.56 0.00 24.72
31
Table 17. Slab Shear Live Load (kip).
HL-93
Sp Pt PL HL-93 Min EV Max EV Min Permit Max Permit Min
Max
2.0 0.81 0.11 0.03 0.14 0.03 0.14 0.05
2.04 0.02 5.99 0.82 7.42 0.86 7.78 1.27
2.2 0.02 4.35 0.82 5.38 0.86 5.65 1.27
2.3 0.02 3.10 0.24 3.83 0.25 4.02 0.37
2.4 0.02 2.94 0.34 3.64 0.36 3.82 0.53
2.5 0.02 1.02 0.51 1.26 0.53 1.32 0.79
2.6 0.02 1.98 0.82 2.45 0.86 2.57 1.27
2.7 0.02 2.49 0.42 3.09 0.44 3.24 0.65
2.8 0.02 3.47 0.34 4.30 0.36 4.51 0.53
2.94 0.02 4.82 0.34 5.97 0.35 6.26 0.52
2.10 0.02 4.82 0.34 5.97 0.35 6.26 0.52
The depth, analysis section width, and reinforcement for each of the critical sections are
tabulated below in Table 19.
32
Table 19. Critical Section Data.
Depth Width Bar Bar Spacing Cover
Section
(in) (in) Number (in) (in)
Concrete Properties:
f’c = 4.0 ksi
∝1 = 0.85 LRFD BDS 5.6.2.2
β1 = 0.85 if f’c ≤ 4.0 ksi LRFD BDS 5.6.2.2
λ = 1.0 (normal weight concrete) LRFD BDS 5.4.2.8
γ3 = 0.67 (AASHTO M31 Grade 60) LRFD BDS 5.6.3.3
γ1 = 1.6 LRFD BDS 5.6.3.3
Modulus of rupture:
f r = 0.24 f 'c = 0.24(1.0) 4.0 = 0.480 ksi LRFD BDS 5.4.2.6
Moment Resistance:
Determine equivalent area of reinforcing bar:
As _ bar b 0.44(12.00)
As = = = 0.884 inch 2
s 6.0
Determine distance of the extreme compression fiber to the centroid of the reinforcement:
diabar 0.75
ds = h − − clr = 16.00 − − 2.00 = 13.63 inches
2 2
33
Determine distance from the equivalent stress block for tension controlled, non-
prestressed tension reinforcement only:
As f y 0.884(60)
a= = = 1.30 inches LRFD BDS Eq. 5.6.3.1.1-4 and 5.6.2.2
0.85 f 'c b 0.85(4.0)(12.00)
a 1.30
1 = 0.85 c = = = 1.53 inches LRFD BDS 5.6.2.2
1 0.85
ds 13.63
s = c − 1 = 0.003 − 1 = 0.024 0.005
c 1.53 LRFD BDS 5.5.4.2, 5.6.2.1
f = 0.90
Axial Resistance:
Walls need to be checked for axial thrust and flexural interaction. Check flexure/axial
interaction using the largest factored HL-93 Inventory axial load in the wall to check
applicability:
Minimum Steel:
Determine minimum reinforcement, beginning with the section modulus:
bh 2 12.00(16.00) 2
Sc = = = 512 inch 3 LRFD BDS 5.6.3.3
6 6
The cracking moment equation simplifies to the following (only monolithic sections and
no prestress forces), where fr is the modulus of rupture of concrete per LRFD BDS
Article 5.4.2.6:
34
1 ft
M cr = 3 1 f r Sc = 0.67(1.6)(0.480)(512)
12 inch LRFD BDS Eq. 5.6.3.3-1
= 21.95 kip-ft
Since fMn > Mcr, minimum reinforcement at this section is satisfied.
Shear Resistance:
Critical section for shear is dv from the face of the support in accordance with LRFD
BDS 5.7.3.2.
For this example, conservatively combine the largest factored HL-93 Inventory forces
along the wall (points 1.00 to 1.10 in Figure 6) to compute the minimum shear resistance.
Concurrent results along the length of the wall could be used to obtain more refined
results when rating factors are below 1.00:
The shear resistance of the walls needs to be evaluated using LRFD BDS 5.7.3.3. Shear
factors and need to be calculated since the member thickness is not less than 16
inches and there is no shear reinforcement. The maximum aggregate size, ag, is set to
0.75 inches.
M u Vu d v
LRFD BDS 5.7.3.4.2
60.55(12) = 726.00 kip-in 9.00(12.98) = 116.82 kip-inch
Mu
+ 0.5 N u + Vu
s = v
d
Es As
LRFD BDS Eq. 5.7.3.4.2-4
60.55(12)
+ 0.5(28.28) + 9.00
= = 0.0031
12.98
0.884(29000)
0 s 0.006
= 29 + 3500 s = 29 + 3500(0.0031) = 39.85o LRFD BDS Eq. 5.7.3.4.2-3
35
sx = dv h − 2cl − db = 12.98 in 16 − 2(2) − 0.75 = 11.25 inch
Where cl is the clear cover and the smaller #6 bar diameter is assumed on each face;
1.38
sxe = 12 in sx 80 inch
ag + 0.63
LRFD BDS Eq. 5.7.3.4.2-7
1.38
sxe = 12 in 11.25 80 in 12.00 inch
0.75 + 0.63
4.8 51
=
(1 + 750 s ) ( 39 + sxe )
LRFD BDS Eq. 5.7.3.4.2-2
4.8 51
= = 1.44
1 + 750(0.0031) 39 + 12.00
Vn = v 0.0316 f c' 0.25 f c' bv d v
= 0.90 0.0316(1.44) 4.0 0.25(4.0) 12(12.98) LRFD BDS 5.7.3.3
= 12.76 kip
The following LRFD BDS checks have not been performed for this example but should be
checked for actual rating calculations: regions requiring transverse reinforcement (5.7.2.3) and
longitudinal reinforcement checks (5.7.3.5) [23 CFR 625.4(d)(1)(v)].
Moment Resistance:
Determine equivalent area of reinforcing bar:
As _ bar b 0.785(12.00)
As = = = 1.571 inch 2
s 6.0
Determine distance of the extreme compression fiber to the centroid of the reinforcement:
diabar 1.00
ds = h − − clr = 16.00 − − 2.00 = 13.50 inches
2 2
Determine distance from the equivalent stress block for tension controlled, non-
prestressed tension reinforcement only:
36
As f y 1.571(60)
a= = = 2.31 inches LRFD BDS Eq. 5.6.3.1.1-4 and 5.6.2.2
0.85 f 'c b 0.85(4.0)(12.00)
a 2.31
1 = 0.85 c = = = 2.72 inches LRFD BDS 5.6.2.2
1 0.85
ds 13.50
s = c − 1 = 0.003 − 1 = 0.012 0.005
c 2.72 LRFD BDS 5.5.4.2, 5.6.2.1
f = 0.90
Axial Resistance:
It was shown in Section 1 above that axial thrust can be neglected for the left wall.
Minimum Steel:
Determine minimum reinforcement, beginning with the section modulus:
bh 2 12.00(16.00) 2
Sc = = = 512 inch 3 LRFD BDS 5.6.3.3
6 6
The cracking moment equation simplifies to the following (only monolithic sections and
no prestress forces), where fr is the modulus of rupture of concrete per LRFD BDS
Article 5.4.2.6:
1 ft
M cr = 3 1 f r Sc = 0.67(1.6)(0.480)(512)
12 inch LRFD BDS Eq. 5.6.3.3-1
= 21.95 kip-ft
Since fMn > Mcr, minimum reinforcement at this section is satisfied.
Shear Resistance:
Moment Resistance:
Determine equivalent area of reinforcing bar:
As _ bar b 0.44(12.00)
As = = = 0.884 inch 2
s 6.0
Determine distance of the extreme compression fiber to the centroid of the reinforcement:
diabar 0.75
ds = h − − clr = 16.00 − − 2.00 = 13.63 inches
2 2
Determine distance from the equivalent stress block for tension controlled, non-
prestressed tension reinforcement only:
As f y 0.884(60)
a= = = 1.30 inches LRFD BDS Eq. 5.6.3.1.1-4 and 5.6.2.2
0.85 f 'c b 0.85(4.0)(12.00)
a 1.30
1 = 0.85 c = = = 1.53 inches LRFD BDS 5.6.2.2
1 0.85
ds 13.63
s = c − 1 = 0.003 − 1 = 0.024 0.005
c 1.53 LRFD BDS 5.5.4.2, 5.6.2.1
f = 0.90
Axial Resistance:
Walls need to be checked for axial thrust and flexural interaction. Check flexure/axial
interaction using the largest factored HL-93 Inventory axial load in the wall to check
applicability:
38
0.1c f c' Ag = 0.1(0.7)(4.0)(16)(12) = 53.76 kip
N u = 19.54 kip LRFD BDS 5.6.4.5
0.1 f Ag Nu Neglect Axial Thrust
c c
'
Minimum Steel:
Determine minimum reinforcement, beginning with the section modulus:
bh 2 12.00(16.00) 2
Sc = = = 512 inch 3 LRFD BDS 5.6.3.3
6 6
The cracking moment equation simplifies to the following (only monolithic sections and
no prestress forces), where fr is the modulus of rupture of concrete per LRFD BDS
Article 5.4.2.6:
1 ft
M cr = 3 1 f r Sc = 0.67(1.6)(0.480)(512)
12 inch LRFD BDS Eq. 5.6.3.3-1
= 21.95 kip-ft
Since fMn > Mcr, minimum reinforcement at this section is satisfied.
Shear Resistance:
Critical section for shear is dv from the face of the support in accordance with LRFD
BDS 5.7.3.2.
Determining the nominal shear resistance. For this example, conservatively combine the
largest factored HL-93 Inventory forces along the wall (points 3.00 to 3.10 in Figure 6) to
compute the minimum shear resistance. Concurrent results along the length of the wall
could be used to obtain more refined results when rating factors are below 1.00):
The shear resistance of the walls needs to be evaluated using LRFD BDS 5.7.3.3. Shear
factors and need to be calculated since the member thickness is not less than 16
inches and there is no shear reinforcement.
39
M u Vu d v 42.99(12) = 515.88 kip-inch
LRFD BDS5.7.3.4.2
4.78(12.98) = 62.04 kip-inch
Mu
+ 0.5 N u + Vu
s = v
d
Es As
LRFD BDS Eq. 5.7.3.4.2-4
515.88
+ 0.5(19.54) + 4.78
= = 0.0021
12.98
0.884(29000)
0 s 0.006
= 29 + 3500 s = 29 + 3500(0.0021) = 36.35o LRFD BDS Eq. 5.7.3.4.2-3
4.8 51
=
(1 + 750 s ) ( 39 + sxe )
LRFD BDS Eq. 5.7.3.4.2-2
4.8 51
= = 1.86
1 + 750(0.0021) 39 + 12.00
Vn = v 0.0316 f c' 0.25 f c' bv d v
= 0.90 0.0316(1.86) 4.0 0.25(4.0) 12(12.98) LRFD BDS 5.7.3.3
= 16.48 kip
The following LRFD BDS checks have not been performed for this example but should be
checked for actual rating calculations: regions requiring transverse reinforcement (5.7.2.3) and
longitudinal reinforcement checks (5.7.3.5) [23 CFR 625.4(d)(1)(v)].
40
Spacing of rebar: s = 6.0 inch
Flexural resistance factor: f = TBD LRFD BDS 5.5.4.2
Moment Resistance:
The reinforcement and factored moment resistance are the same as calculated for Section
3 above.
Axial Resistance:
It was shown in Section 3 above that axial thrust can be neglected for the left wall.
Minimum Steel:
It was shown in Section 3 above that the minimum steel reinforcement is met.
Shear Resistance:
Moment Resistance:
Determine equivalent area of reinforcing bar:
As _ bar b 0.785(12.00)
As = = = 1.571 inch 2
s 6.0
Determine distance of the extreme compression fiber to the centroid of the reinforcement:
diabar 1.00
ds = h − − clr = 18.00 − − 2.00 = 15.50 inches
2 2
Determine distance from the equivalent stress block for tension controlled, non-
prestressed tension reinforcement only:
As f y 1.571(60)
a= = = 2.31 inches LRFD BDS Eq. 5.6.3.1.1-4 and 5.6.2.2
0.85 f 'c b 0.85(4.0)(12.00)
a 2.31
1 = 0.85 c = = = 2.72 inches LRFD BDS 5.6.2.2
1 0.85
41
ds 15.50
s = c − 1 = 0.003 − 1 = 0.014 0.005
c 2.72 LRFD BDS 5.5.4.2, 5.6.2.1
f = 0.90
Axial Resistance:
Slab need to be checked for axial thrust and flexural interaction using the largest factored
HL-93 Inventory axial load in the wall to check applicability:
Minimum Steel:
Determine minimum reinforcement, beginning with the section modulus:
bh 2 12.00(18.00) 2
Sc = = = 648 inch 3 LRFD BDS 5.6.3.3
6 6
The cracking moment equation simplifies to the following (only monolithic sections and
no prestress forces), where fr is the modulus of rupture of concrete per LRFD BDS
Article 5.4.2.6:
1 ft
M cr = 3 1 f r Sc = 0.67(1.6)(0.480)(648)
12 inch LRFD BDS Eq. 5.6.3.3-1
= 27.79 kip-ft
Since fMn > Mcr, minimum reinforcement at this section is satisfied.
Shear Resistance
The shear depth, dv, is calculated in accordance with LRFD BDS 5.7.3.2.
42
0.72h 0.72(18) = 12.96
d v = max 0.9d = 0.9(15.50) = 13.95 = 14.35 inches LRFD BDS 5.7.2.8
d − a 15.50 − 2.31 = 14.35
2 2
Determining the nominal shear. For this example, conservatively combine the largest
factored HL-93 Inventory forces along the slab (points 2.00 to 2.10 in Figure 6) to
compute the minimum shear resistance. Concurrent results along the length of the slab
could be used to obtain more refined results when rating factors are below 1.00:
The shear resistance of the slab needs to be evaluated using LRFD BDS 5.7.3.3. Shear
factors and need to be calculated since there is no shear reinforcement.
Mu
+ 0.5 N u + Vu
s = v
d
Es As
LRFD BDS Eq. 5.7.3.4.2-4
975.24
+ 0.5(2.76) + 16.61
= = 0.0019
14.35
1.571(29000)
0 s 0.006
= 29 + 3500 s = 29 + 3500(0.0019) = 35.65o LRFD BDS Eq. 5.7.3.4.2-3
sx = d v h − ( cltop + clbot ) −
(d b ,top + db ,bot )
= 18 − ( 2.50 + 2.00 ) −
( 0.75 + 1.00 ) = 12.625 inch
2 2
Where cl is the clear cover;
1.38
sxe = 12 in sx 80 inch
ag + 0.63
LRFD BDS Eq. 5.7.3.4.2-7
1.38
sxe = 12 in 12.625 80 in 12.625 inch
0.75 + 0.63
43
4.8 51
=
(1 + 750 s ) ( 39 + sxe )
4.8 51
= = 1.96 LRFD BDS Eq. 5.7.3.4.2-2
1 + 750(0.0019) 39 + 12.625
The following LRFD BDS checks have not been performed for this example but should be
checked for actual rating calculations: regions requiring transverse reinforcement (5.7.2.3) and
longitudinal reinforcement checks (5.7.3.5) [23 CFR 625.4(d)(1)(v)].
Moment Resistance:
Determine equivalent area of reinforcing bar:
As _ bar b 0.785(12.00)
As = = = 1.571 inch 2
s 6.0
Determine distance of the extreme compression fiber to the centroid of the reinforcement:
diabar 1.00
ds = h − − clr = 18.00 − − 2.50 = 15.00 inches
2 2
Determine distance from the equivalent stress block for tension controlled, non-
prestressed tension reinforcement only:
As f y 1.571(60)
a= = = 2.31 inches LRFD BDS Eq. 5.6.3.1.1-4 and 5.6.2.2
0.85 f 'c b 0.85(4.0)(12.00)
a 2.31
1 = 0.85 c = = = 2.72 inches LRFD BDS 5.6.2.2
1 0.85
44
ds 15.00
s = c − 1 = 0.003 − 1 = 0.014 0.005
c 2.72 LRFD BDS 5.5.4.2, 5.6.2.1
f = 0.90
Axial Resistance:
It was shown in Section 5 above that axial thrust can be neglected for the left wall.
Minimum Steel:
Determine minimum reinforcement, beginning with the section modulus:
bh 2 12.00(18.00) 2
Sc = = = 648 inch 3 LRFD BDS 5.6.3.3
6 6
The cracking moment equation simplifies to the following (only monolithic sections and
no prestress forces), where fr is the modulus of rupture of concrete per LRFD BDS
Article 5.4.2.6:
1 ft
M cr = 3 1 f r Sc = 0.67(1.6)(0.480)(648)
12 inch LRFD BDS Eq. 5.6.3.3-1
= 27.79 kip-ft
Since fMn > Mcr, minimum reinforcement at this section is satisfied.
Shear Resistance:
45
The slab right connection details are the same as the left connection details (Section 6); therefore,
the factored moment and shear resistances are the same.
The structural condition of the internal frame tunnel is satisfactory and the system factor falls
under the category for "All Other Girder Bridges and Slab Bridges." Therefore:
Resistance factors are based on LRFD BDS Section 5 and specified in the calculations of Section
2.2.3 of this document.
The equation for calculating the rating factor is based on MBE Equation 6A.4.2.1-1, which has
been simplified for the load types being applied.
C DC DC DW DW EV EV EH EH ES ES
RF = MBE Eq. 6A.4.2.1-1
LL ( LL + IM )
Table 20 through Table 24 shows the results of the overall capacity based on MBE Equation
6A.4.2.1-2 as well as the rating load factors based on MBE Equation 6A.4.2.1-1. It is also noted
that negative moments are designated with a negative sign as well as corresponding negative
moment capacities. It is imperative to coordinate positive and negative moments and shears
when calculating the rating factor. For this example, shear forces were taken as positive as a
simplification because controlling component shear loads acted on the rating sections in the same
direction. Ratings are performed at the critical section defined in LRFD BDS 12.11.5.2 for
flexure and 5.7.3.2 for shear. Consequently, the critical moment section (xcr for moment) is at the
wall to slab interface and the critical shear (xcr for shear) is at a distance dv from the inside face
of the wall or slab. A summary of these locations are:
46
Shear @ 5-7: Roadway Slab at dv from inside face of Left Wall based on review
of tenth point total factored forces
Maximum and minimum load factors are selectively used to obtain the maximum absolute value
of the force effects. The selected load factors are shown in Table 20. Note that a minimum load
factor of 0.00 for CR and SH is defined in case actual forces are less than computed; therefore,
any beneficial effects of CR and SH will not be counted. Additionally, the design truck controls
the HL-93 ratings and the EV-3 controls the EV ratings. The moments, shears and respective
capacities are in kip-ft and kip in Table 21 to Table 24.
47
Table 23. EV-2 and EV-3 Rating Factors.
Force Section xcr (in) DC AP+ AP- TU+ TU- CR&SH PL EV C RF
Moment 1 109.50 2.74 -0.09 0.09 -1.71 1.71 -7.13 -0.92 6.28 51.59 5.79
Moment 2 210.96 -13.21 -0.06 0.09 -0.87 0.87 -3.62 1.10 -24.08 -87.26 2.10
Moment 3&4 178.00 15.61 -0.21 0.01 -3.16 3.16 -13.17 -0.12 22.42 51.59 1.05
Moment 5 259.20 17.17 -0.02 0.01 -1.09 1.09 4.56 -0.10 29.11 101.4 1.95
Moment 6 24.00 -21.37 -0.05 0.05 -0.44 0.44 -1.84 -0.44 -21.70 -97.86 2.38
Moment 7 424.00 -12.61 -0.01 0.28 -3.27 3.27 13.63 0.12 -14.23 -97.86 4.35
Shear 1&2 198.02 1.99 0.05 0.05 0.11 0.11 0.44 0.25 3.79 12.76 1.83
Shear 3&4 16.02 1.05 0.00 0.05 0.21 0.21 0.89 0.01 0.16 16.84 65.13
Shear 5-7 38.35 4.06 0.00 0.00 0.08 0.08 0.33 0.02 6.77 19.1 1.54
48
2.3 PRESTRESSED BOTTOM SLAB
Prestressed Slab
(a)
32'
31' Span
14½ PS Slab
49
The prestressed bottom slab is a 14 ½-inch slab spanning 32 feet with a 12-inch bearing on each
end resulting in an effective span of 31 feet. The PS slab is comprised of 7 ksi concrete, (26)-
0.60 inch diameter, AASHTO Grade M203 Low Relaxation strands for each 8 foot slab with #4
shear bars at 12 inches on center in both transverse and longitudinal directions. The reinforcing
steel is grade 60 steel. Adjacent precast slabs are connected via shear keys and therefore transfer
forces between them.
The slab is exposed to self-weight, air pressure, and live load. Other forces such as TU are
neglected due to the simply supported boundary conditions of the PS slab. Creep and Shrinkage
as well as prestressing forces are accounted for in the capacity calculations
Dead load components include the self-weight of the concrete prestressed slab. Prestressed
forces are accounted for in the capacity calculations.
Use a unit weight, wc, of 0.150 kcf for reinforced concrete. The self-weight of the slab is applied
to the model by including self-weight on the geometry detailed in Figure 7.
The prestressed slab has a 2-inch asphalt overlay with a unit weight of 140 pcf. This produces a
load pressure of 23.33 psf. However, since this is a known specified load applied during initial
construction with field verification as opposed to an allowance for a future overly, the wearing
surface will be included in the Dead Load Component, DC loads for this example, such that a
strength load factor of 1.25 is applied per MBE 6A.2.2.3.
Air pressure was applied to the roadway of ±10 psf, according to the original construction plans.
2.3.1.4 Temperature, TU
No temperature loads were applied since this prestressed slab behaves as a simply supported
slab.
Creep and shrinkage is accounted for in the prestress losses within the capacity calculations.
The live load travels perpendicular to the span of the prestressed slab. The distribution of axle
loads based on an equivalent strip width, E, to cast-in-place slabs acting perpendicular to the
direction of traffic is provided in LRFD BDS Table 4.6.2.1.3-1, where S is the span length of 31
feet.
50
E pos = 26.0 + 6.6S
ESlab + = 26.0 + 6.6(31) = 230.60 inches = 19.22 feet
Since the design strip is transverse to the direction of traffic, the wheel loads are included in the
live load evaluation; however, the lane load is not included per LRFD BDS Article 3.6.1.3.3. The
maximum number of trucks to be placed on the structure is obtained by taking the roadway width
and dividing by a 12-foot lane per LRFD BDS Article 3.6.1.1.1 resulting in two possible trucks
to be placed parallel. This results in axle loads that are placed transversely such to produce
maximum forces at the critical locations, identified at mid-span and end of span. Maximum end
forces (shear) were obtained by placing the first axle load 2 feet from the barrier per LRFD BDS
Article 3.6.1.3.1. The second truck is placed such that there is 4 feet between wheel placements.
Maximum positive moment is obtained when the centerline of the span is midway between the
center of gravity of loads and the nearest concentrated load. Live load placement is shown in
Figure 8.
Wheel loads for unit, or 1-foot, analysis widths are determined by multiplying the equivalent unit
width wheel load, P, by the appropriate impact factor (IM) and multiple presence factor (MPF).
The equivalent wheel load is determined by dividing the full wheel load by the equivalent strip
width, E, over which the axle load is distributed. Calculate the wheel loads in the same manner
as the internal frame. Refer to Section 2.2.1.7 for a detailed discussion.
32 kip
PHL 93−Truck1 =
2 wheels 16 k/wheel
= = 0.83
( ESlab+ ) 19.22 ft
32 kip + 32 kip
PHL93−Truck 2 = 2 wheels =
32
= 0.96
k/wheel
( ESlab+ 2 + 14 + ESlab+ 2 ) 33.22 ft
25 kip
PHL 93−Tandem1 = 2 wheels 12.5
= = 0.65
k/wheel
( ESlab+ ) 19.22 ft
51
25 kip + 25 kip
=
2 wheels 25 k/wheel
PHL93−Tandem 2 = = 1.08
( ESlab+ 2 + 4 + ESlab+ 2 ) 23.22 ft
k/wheel
PHL 93−Tandem+ = max ( PHL93−Tandem1 , PHL93−Tandem 2 ) = 1.08
ft
EV-2:
33.5 kip
PEV 2−1 =
2 wheels 16.75 k/wheel
= = 0.87
( ESlab+ ) 19.22 ft
EV-3:
31 kip
PEV 3−1 =
2 wheels 15.5 k/wheel
= = 0.81
( ESlab+ ) 19.22 ft
31 kip + 31 kip
=
2 wheels 31 k/wheel
PEV 3−2 = = 1.34
( ESlab+ 2 + 4 + ESlab+ 2 ) 23.22 ft
Permit Truck:
All the permit truck axle spacings are less than ESlab+; therefore, all 11 axle load
possibilities should be considered. The calculations follow the format as above and P
varies from 0.55 to 1.72 over the 11 permutations. The calculation for the controlling 10-
axle configuration is shown below.
52
21 + 21 + 21 + 21 + 21 + 23 + 23 + 23 + 18 + 18
= = 105 = 1.72 k/wheel
2 wheels
PPermit +
( ESlab+ 2 + 4 + 4 + 4 + 4 + 10 + 4 + 4 + 4 + 4 + ESlab+ 2 ) 61.22 ft
Mid-Span
10.50' 6'
End-Span
2' 6'
Source: FHWA
Figure 8. Illustration. Live Load Placement on Slab.
Single trucks are amplified by a multiple presence factor, MPF, of 1.2 while the two truck effects
utilize a multiple presence factor of 1.0 per LRFD BDS Table 3.6.1.1.2-1. For this example,
MBE Article 6A.4.4.3 is used to determine the dynamic impact factor, IM, of 1.33 for all
vehicles.. Additionally, from the equivalent wheel load calculations, it can be seen that the HL-
93 tandem will control over the HL-93 truck and the EV-3 vehicle controls over the EV-2 for
this example.
A beam analysis is applied for the bottom slab. All the load effects and member resistances are
calculated using this 1-foot wide strip representation. The slab is assumed to be simply supported
and therefore can be evaluated with simple hand calculations or by a structural analysis program.
For the purpose of this example, a structural analysis program was used for simplicity.
The LRFD Road Tunnel Design and Construction Guide Specifications, 1st Ed. (AASHTO,
2017b), Table 3.4-1 identifies the applicable minimum and maximum load factors for each load
specified above. Since the slab is simply supported, only maximum load factors were necessary
to produce critical design forces. The live load factors for the HL-93 is identified in Table 3.4-1,
and the live load factor for the EV vehicles is 1.3 as identified in the FHWA Emergency Vehicle
Memorandum and the live load factor for the permit vehicle is identified as 1.3 from MBE 3rd
Edition Table 6A.4.5.4.2a-1, corresponding to unlimited crossings, mixed with traffic, two or
more lanes, ADTT greater than 5000, and a permit weight factor ratio (GVW/AL) greater than 3.
The forces were factored to produce controlling Strength I (or Strength II for permit loads) as
well as Service I and Service III load combinations. These resulting unfactored forces are given
in Table 25 and Table 26. Note shears are shown as absolute values.
53
Table 25. Slab Shear Forces (kip).
Sp Pt DC AP HL-93 EV Permit
1.0 3.45 0.16 3.89 5.22 6.20
1.1 2.76 0.13 3.15 4.22 5.02
1.2 2.07 0.10 2.46 3.29 3.91
1.3 1.38 0.06 1.95 2.61 3.10
1.4 0.69 0.03 0.28 0.37 0.44
1.5 0.00 0.00 0.28 0.37 0.44
1.6 -0.69 -0.03 -0.28 -0.37 -0.44
1.7 -1.38 -0.06 -1.95 -2.61 -3.10
1.8 -2.07 -0.10 -2.46 -3.29 -3.91
1.9 -2.76 -0.13 -3.15 -4.22 -5.02
1.10 -3.45 -0.16 -3.89 -5.22 -6.20
Span Point
1.0
1.10
Prestressed Slab
Source: FHWA
Figure 9. Illustration. Slab Direction.
Figure 9 shows the span point identification for the prestressed slab. The whole number
represents the member identification while the 10ths number indicates the percentage along the
span length.
54
2.3.3 Resistance Calculations
Modulus of rupture:
f r = 0.24 f 'c = 0.24(1.0) 7.0 = 0.635 ksi LRFD BDS 5.4.2.6
Moment Resistance:
As _ PS n 0.217(26)
As = = = 0.705 in 2 /ft
bslab 8
Determine distance of the extreme compression fiber to the centroid of the reinforcement:
55
Eccentricity of prestressing steel:
h 14.50
e = ds − = 11.00 − = 3.75 inches
2 2
Modulus of Elasticity:
c = 0.140 + 0.001 f 'c = 0.140 + 0.001(7.0) = 0.147 kcf LRFD BDS Table 3.5.1-1
ci = 0.140 + 0.001 f 'ci = 0.140 + 0.001(5.6) = 0.1456 kcf LRFD BDS Table 3.5.1-1
Section Properties:
Aps f j ( I x + e2 Ac ) − eM SW Ac
f pES =
Aps ( I x + e2 Ac ) + Ac I x Eci / E p
0.705(202.5)(3049 + 3.752 174) − 3.75(23.95 12)(174)
= = 6.82 ksi
0.705(3049 + 3.752 174) + 174(3049)(4492) / (28,500)
56
f pi = f pj − pES = 202.5 − 6.82 = 195.68 ksi
Pi = f pi Aps = 195.68(0.705) = 138 kip
Elastic gains are neglected for this example for conservatism. Long term losses are calculated
utilizing the Approximate Method as defined in LRFD BDS Article 5.9.3.3. These losses assume
the specimens were cured with 70% humidity.
f pR = 2.4 ksi
h = 1.7 − 0.01RH = 1.7 − 0.01(70) = 1.0
5 5
st = = = 0.76
1 + f ci 1 + 5.6
'
10.0 f pj Aps h st
f pT = + 12 h st + f pR
Ac
10.0(202.5)(0.705)(1.0)(0.76)
= + 12(1.0)(0.76) + 2.4 = 17.76 ksi
174
Allowable concrete stresses after losses are per LRFD BDS Table 5.9.2.3.2a-1 and Table
5.9.2.3.2b-1. Note compression is represented by negative (-) and tension is represented by
positive (+).
HL-93 stresses:
M NC = 26.7 kip-ft
M C = 1.3 kip-ft
M LL = 30.2 kip-ft
57
Top of section stresses:
M LL = 40.4 kip-ft
M LL (40.4)(12)
f LL , EV = − =− = −1.153 ksi
Sx 420.5
M LL (40.4)(12)
f LL, EV = = = 1.153 ksi
Sx 420.5
M LL = 48.0 kip-ft
M LL (48.0)(12)
f LL , Permit = − =− = −1.370ksi
Sx 420.5
M LL (48.0)(12)
f LL, Permit = = = 1.370ksi
Sx 420.5
58
2.3.3.5 Ultimate Flexural Resistance
The ultimate moment strength for one foot strip of the prestressed slab is calculated below
conservatively ignoring the additional capacity due to the minimal area of non-prestressed
tension (or compression) reinforcement. The following calculations are outlined in LRFD BDS
Eq. 5.6.3.1.1-1 and Eq. 5.6.3.1.1-4. The flexural resistance factor, which is based on a tension-
controlled section, is calculated in accordance with LRFD BDS 5.6.2.1 & 5.5.4.2.
Aps f pu 0.705(270)
c= = = 3.47 in
0.85 f 1b + kAps f pu / d p
c
'
0.85(7.0)(0.7)12 + 0.28(0.705)270 /11.00
ds 11.00
s = c − 1 = 0.003 − 1 = 0.0065 0.005 f = 1.0
c 3.47
kc 0.28 3.47
f ps = f pu 1 − = 270 1 − = 246.15 ksi
ds 11.00
a 2.43 1 ft
M n = f Aps f ps d s − = 1.0(0.705)(246.15) 11.00 − = 142 kip-ft
2 2 12 in
The minimum steel per LRFD BDS 5.6.3.3 should be checked to ensure minimum strength is
achieved. Since the composite and non-composite section is the same, the second term within the
brackets becomes zero and can therefore be neglected.
− Pe Pe e −125.4 125.4(3.75)
f cps = − = − = −1.84 ksi
Ac Sx 174 420.5
S
M cr = 3 ( 1 f r + 2 f cps ) S x − M dnc c − 1
Snc
1 ft
= 1.0 (1.6 0.635 + 1.11.84 ) 420.5 = 107 kip-ft
12 in
M n M cr OK
Critical section for shear is dv from the face of the support in accordance with LRFD BDS
5.7.3.2.
59
0.72h 0.72(14.50) = 10.44
d v = max 0.9d = 0.9(11.00) = 9.90 = 10.44 inches LRFD BDS 5.7.2.8
d − a 11.00 − 2.43 = 9.79
2 2
Applied shears and moments at the section of interest located a distance dv from the face of the
support are used to determine the nominal shear resistance. It was revealed that the shear
resistance is significantly larger than any of the live load shears; therefore, for simplicity and
conservatism, the maximum shear resistance will be based on the maximum shear force due to
the critical live load of HL-93 Inventory. The maximum shear force and moment is:
The shear resistance of the slab needs to be evaluated using LRFD BDS 5.7.3.3. Shear factors
and need to be calculated per LRFD BDS Article 5.7.3.4.2. #4 shear reinforcement is provided
on 12-inch centers along the span and 16.5-inch centers in the direction of traffic and therefore
can be included in the shear resistance.
12
Av f y dv cot ( 29 ) 0.196 (60)(10.44) cot(29)
16.5
Vs = = = 10.96 kip
s 12
Vn = v Vc + Vs = 0.90 50.28 + 10.96 = 55.12 kip
The following LRFD BDS checks have not been performed for this example but should be
checked for actual rating calculations: regions requiring transverse reinforcement (5.7.2.3);
detailing of transverse reinforcement (5.7.2.4); minimum shear reinforcement (5.7.2.5); and
longitudinal reinforcement checks (5.7.3.5).
60
2.3.4 LRFR Rating Calculations
The structural condition of the prestressed slab is satisfactory and the system factor falls under
the category for "All Other Girder Bridges and Slab Bridges." Therefore:
Resistance factors are based on LRFD BDS Section 5 and specified in the calculations of Section
2.3.3 of this document.
The equation for calculating the rating factor is based on MBE Equation 6A.4.2.1-1, which has
been simplified for the load types being applied.
C DC DC DW DW EV EV EH EH ES ES
RF = MBE Eq. 6A.4.2.1-1
LL ( LL + IM )
Table 28 shows the results of the overall capacity based on MBE Equation 6A.4.2.1-2 as well as
the load rating factors based on MBE Equation 6A.4.2.1-1. Maximum and minimum load factors
are selectively used to obtain the maximum absolute value of the force effects. The load factors
for strength limit states are as shown in Table 27. In Table 28, the load effects are unfactored
having a unit of kip-ft or kip for moment and shear, respectively.
HL-93 HL-93
EV
Max/Min DC AP Inventory Operating Permit
Legal
Level Level
Max 1.25 1 1.75 1.35 1.3 1.3
Min 0.9 N/A N/A N/A N/A N/A
61
For prestressed concrete, rating for stresses at Service limit states is optional per MBE Table
6A.4.2.2-1 at the legal load level (EV vehicle at Service-III limit state) and permit load level
(permit truck at Service-I limit state) but may be included upon the owners request. However,
Service-III limit state ratings for the design load (HL-93) at the Inventory level are applicable for
prestressed concrete. Per MBE Table 6A.4.2.2-1, the dead load factor (DC and AP) is 1.00 and
the live load factor is 0.80. Per LRFD BDS 5.9.2.3.2, tensile stresses in prestressed slabs apply to
the Service-III limit state (LRFD BDS 5.9.2.3.2b). Using the factored stresses and stress limits
calculated in Section 2.3.3.4, compute the HL-93 Inventory level rating factor for tensile stress
on the bottom face of the slab:
This example considers a circular bored tunnel with a precast segmental reinforced concrete
lining. An earth pressure balance tunnel boring machine (EPB TBM) was used to excavate the
tunnel and install the lining. The internal diameter is 52 feet and the liner segment thickness is 2
feet. A typical cross-section of the tunnel is presented in Figure 10.
For the purpose of performing a load rating of the liner, the crown of the tunnel is assumed to be
only 20 feet below the at-grade roadway. In reality, such a large diameter tunnel in shallow soft
ground is unlikely.
Source: FHWA
Figure 10. Illustration. Tunnel Cross-Section.
62
Underground conditions were modeled after the north portal area of the tunnel, where the tunnel
is relatively shallow and is not fully submerged. A submerged tunnel at such shallow depths
would experience instability due to buoyancy. As illustrated in Figure 11, soils were simplified
into two representative layers including Recent Granular Deposits (RGD) above the tunnel and
glacial Till-Like Deposits (TLD) surrounding and beneath the tunnel. The yellow color
represents the RGD (upper 15 feet) and the bluish color represents the TLD (below 15 feet).
In this analysis, the only structural component subject to load rating analysis is the tunnel liner.
Structure demands used in the example calculations are assumed to come from: self-weight of
the structure or dead load component (DC); vertical earth loads (EV); horizontal earth loads
(EH); at-grade building surcharge (BS); and live loads (LL).
Two-Dimensional (2D) Finite Element (FE) analysis is used to determine structural demands in
the form of moment, shear, and axial forces along the tunnel liner. The commercially-available
FE software Plaxis 2D (2019) is used for this example. A 2D model is generated which includes
the structural elements surrounded by a continuum representing the soil, allowing the model to
account for effects of soil-structure-interaction (SSI).
2.4.1 Materials
Concrete and section properties are listed below. In order to include the liner as a linear elastic
plate element in the FE model, an effective moment of inertia was assumed (FHWA, 2009). The
effective moment of inertia is significantly lower than the gross value of a 2-foot thick segment
because it accounts for the joints in between the precast liner segments. It should be recognized
that this effective moment of inertia is only an approximation; the actual structural behavior of a
precast segmental liner with bolted connections would be more complex and is beyond the scope
of this geotechnical analysis example.
I eff = I j + I g ( 4 / n )
2
FHWA-NHI-10-034 Equation 10-11
63
2.4.1.3 Example Notes
• This cross-section is fictitious and is only for the purpose of demonstrating the principles
of using FE models to perform analysis to aid in rating tunnels.
• Live loading on the ground surface over the tunnel may increase force effects and is
therefore included in the load rating analysis.
• Dead loads from the roadway and other structures interior to the liner are included in the
analysis.
• In general, if the surface roadway passing over the tunnel has an overlay, sidewalk, or
other loads, they should be included in the dead load analysis for tunnel load rating. This
example assumes that these items are not included in the geometry of the tunnel.
• While not assumed here, any other mechanical (including dynamic equipment loads) and
architectural systems supported by the tunnel should be included in the dead load.
• The liner is modeled in this example with the approximated effective moment of inertia
described above.
• The load rating evaluation is performed for a 1-foot wide strip of tunnel and surrounding
soil (parallel to the direction of traffic above the tunnel).
• Pavement has approximately the same unit weight as the soil and is therefore included
with the soil vertical loads.
• Groundwater is assumed to be 10 feet above the tunnel invert, and is included in the FE
model accordingly. The location of groundwater is shown in Figure 11.
• In this example, the HL-93 Truck, Tandem, EV-2, and EV-3 live loads are considered.
All relevant live loads may be considered in an actual load rating analysis.
• There are no signs of distress or deterioration as the tunnel construction was recently
completed; therefore, the tunnel is considered to be in satisfactory physical condition.
• Structural demands are calculated by performing 2D FE analysis including the soil and
structure.
A 2D plane strain model was developed to assess the load demands on the tunnel due to dead
loads, earth pressures, and live loads. The model is illustrated in Figure 11, representing a 1-foot
wide strip (into the page) of the tunnel and surrounding soil. Structural elements are used to
represent the tunnel and continuum elements are used to represent the soil. Interface elements are
included around the outside of the tunnel to simulate the interaction between the soil and
structure. Model length units are feet, and force units are kips.
64
Source: FHWA
Figure 11. Illustration. 2D Plane Strain FE Model of Tunnel Cross-Section. Length Units
are in Feet.
The tunnel liner is modeled with linear-elastic curved plate (i.e., shell) elements (Plaxis, 2019),
which are used to model slender structures in the ground with a significant flexural rigidity (EI)
and normal stiffness (EA). The assumption of linear-elastic structural behavior is expected to be
sufficient for load rating purposes, where loading is restricted to typical service-type conditions.
However, after the FE analysis is completed, the resulting structural demands should be checked
against capacities to verify this assumption.
Properties are assigned to the liner based on the structure data listed in Section 2.4.1. The
assigned properties are listed in Table 29 and Table 30. In the 1-foot wide plane strain model,
structure properties are defined per foot of model width. Plate elements have zero thickness,
while the actual tunnel liner is 2 feet thick. The plate elements are modeled along the centerline
of the actual tunnel liner elements, with a diameter of 54 feet. The liner weight is based on the
actual liner thickness of 2 feet times the unit weight of 0.155 kcf for the high strength reinforced
concrete. The tunnel is centered horizontally at an X coordinate of zero feet. The tunnel crown is
at a Y coordinate of -20 feet (20 feet below grade), and the invert is as -74 feet (74 feet below
grade).
E A Ieff
(ksf) (ft2/ft) (ft4/ft)
767,232 2 0.107
65
Table 30. Plane Strain Model Inputs.
EA EIeff Weight, w
(kip/ft) (kip-ft2/ft) (kip/ft/ft)
The model soil domain surrounding the tunnel (Figure 11) has overall dimensions of 400 feet in
width (X coordinates of -200 feet to +200 feet), and 200 feet in depth (Y coordinates of +0 to -
200 feet). In soil-structure interaction (SSI) modeling, overall dimensions should be sufficiently
large such that they do not significantly influence the model response and the results of interest.
The soil dimensions were determined for this example by first starting with an initial assumption
with relatively small dimensions and running the model to determine the structure forces
(moment, shear, and axial). Then, the dimensions were increased incrementally and the model
was re-run until the forces became insensitive to further increases.
2.4.2.3 FE Mesh
Fifteen-node triangular continuum elements were used to discretize the soil domain and the plate
elements have five nodes per adjacent triangular continuum element as shown in Figure 12.
Plaxis (2019) generates the mesh automatically based on the settings and adjustments selected by
the user. Similar to selecting the domain size, the fineness of the mesh should be selected such
that it does not significantly influence the model response and the results of interest. An
appropriate mesh was selected for this example by comparing the results for different mesh sizes.
66
(A) 15-node triangle (B) 5-node plate
Source: FHWA
Figure 12. Illustrations. Node distribution for (Plaxis 2019): a) 15-node triangular
continuum element and b) 5-node plate element.
The soil domain in the FE model is described by constitutive models (stress-strain relationships)
and soil properties which are assigned by the user. Actual stress-strain behavior of soil tends to
involve significant variability and uncertainty. In order to address this variability in SSI analyses
and ensure a reliable load rating, a range of soil properties may need to be considered.
Accordingly, sets of Upper and Lower Estimate (UE and LE) soil parameters (listed in Table 31)
were used in this example for the Recent Granular Deposits (upper 15 feet) and Till-Like
Deposits (below 15 feet).
The Mohr-Coulomb (Plaxis, 2019) linear elastic-perfectly plastic model is used to approximate
nonlinear soil behavior in this example. Five parameters are typically considered to define the
Mohr-Coulomb model for each soil type, including: unit weight, friction angle ( ), cohesion
intercept (c), Young’s modulus (E), and Poisson’s ratio (). An advanced feature was also used
to allow for increasing soil stiffness with depth based on a sixth input parameter (Eincr). As
indicated in Table 31, the value for Young’s modulus was defined at the top of the layer (Etop)
and limited to a maximum value (Emax).
The at-rest earth pressure coefficient (K0) is used to define the initial horizontal stress conditions
in the model. In FE analysis of underground structures, K0 can have a significant impact, because
it significantly influences horizontal earth pressures. Construction sequencing may also affect
horizontal earth pressures in FE models, which do not always exactly simulate reality. In order to
account for variability, uncertainty, and potential effects of construction, a relevant range of K0
should be considered in the load rating analysis.
67
The Recent Granular Deposits are modeled after loose to dense sandy soils encountered near the
ground surface. These recent deposits are normally consolidated, with K0 assigned as 1-sin()
based on the Plaxis (2019) default recommendation. It is noted that the Recent Granular Deposits
are only located above the tunnel crown (Figure 11), so the K0 value in this layer does not have
as significant an impact as the Till-Like Deposits surrounding the tunnel.
Glacial till tends to be over-consolidated, strong, and stiff. In this example, the Till-Like
Deposits were modeled as primarily coarse grained, with relatively high values and stiffness
parameters. Lower and Upper Estimate K0 values of 0.5 and 1.0, respectively, were considered in
order to cover a typical range of over-consolidated conditions in such materials.
Unit
Etop Einc Emax Poisson
Soil Type Wt. (deg) c (ksf) K0 4
(ksf) 1 (ksf/ft) 2 (ksf) 3 ’s Ratio
(pcf)
Recent Granular
Deposits 105 30 0.1 500 25 875 0.3 0.50
Lower Estimate
Recent Granular
Deposits 125 36 0.1 1,000 50 1,750 0.3 0.41
Upper Estimate
Till-Like Deposits
125 36 0.1 1,000 300 8,500 0.35 0.50
Lower Estimate
Till-Like Deposits
145 42 0.1 2,000 600 17,000 0.35 1.00
Upper Estimate
Notes:
1. Etop = Young’s modulus at top of layer.
2. Einc = Rate of change of stiffness with depth below top of layer.
3. Emax = Maximum value for E (no further increase with depth beyond this value).
4. K0 = At-rest earth pressure coefficient.
A soil-structure interface is included around the outside perimeter of the tunnel with strength
equal to two-thirds (0.67) that of the adjacent soil. The interface limits the amount of stress that
can be transferred between the structure and the soil. Small circles with a minus sign inside them
graphically indicate the interface around the perimeter of the tunnel in Figure 11 and in later
figures.
Permanent loads including the dead weight of the tunnel (DC), vertical earth pressures (EV), and
horizontal earth pressures (EH) are generated automatically in the model based on the assigned
structure and soil properties. Dead load reactions from the internal tunnel structures such as the
roadway boxes (Figure 10) are applied as downward point loads acting on the corbels, as
illustrated in Figure 13. Loads of 15.6 kip/ft (kips per foot model width) and 12.3 kip/ft are
applied to the left and right corbels, respectively. The corbels are included as linear elastic
continuum elements with concrete stiffness in order to distribute the point loads over their
contact area with the tunnel liner.
68
Source: FHWA
Figure 13. Illustration. Close-Up View of Tunnel in FE Model.
Live loads are applied as downward distributed loads on the surface of the model (Figure 13).
Surface traffic is assumed to be moving in the direction from right to left across the tunnel.
Based on AASHTO BDS Article 3.6.1.2.5, a tire contact length (lt) of 10 inches is assumed along
the direction of traffic. In order to consider various vehicle positions above the tunnel and find
the most critical location, a distributed load with a length of approximately 10 inches was placed
(but not always activated) at every foot on-center from X = -30 feet to X = +30 feet (lighter
arrows in Figure 13). Vehicle loads are simulated by activating the distributed loads at wheel
locations above the tunnel for various vehicle positions. For instance, the two activated loads
(dark arrows) in Figure 13 represent HL-93 Tandem loading, which consists of a pair of wheel
loads spaced at 4 feet.
The four live loads included in this example for demonstration purposes are the HL-93 Truck
and HL-93 Tandem loads, EV-2, and EV-3. The HL-93 Truck consists of an 8-kip load, and two
32-kip loads, each spaced at 14 feet. The HL-93 Tandem consists of two 25-kip loads spaced at 4
feet, as mentioned above. EV-2 consists of a 24-kip load and a 33.5-kip load spaced at 15 feet.
EV-3 includes a 24-kip wheel load followed by a 15-ft spacing and a pair of 31-kip loads spaced
at 4 feet. Lane loads for the HL-93 Tandem and Truck loads were not applied, refer to Section
2.4.2.5.1 for a discussion.
Axle loads will distribute outward laterally as they pass downward through the fill until they
reach the tunnel. This leads to lower magnitude pressures (spread out over a larger area) on the
tunnel than at the ground surface. Distribution transverse to the tunnel’s longitudinal axis (to the
left and right in Figure 13) will occur automatically in the 2D model. However, the 2D plane
69
strain model cannot automatically account for the distribution along the tunnel’s longitudinal
direction (in and out of the page in Figure 13).
The guidelines in LRFD BDS Article 3.6.1.2.6 were used to account for the distribution along
the tunnel’s longitudinal direction as follows:
• For traffic running transverse to the tunnel’s longitudinal axis (crossing over the tunnel),
and wheel load distribution along the tunnel’s longitudinal direction,
wt 0.06 Di 20 0.06(648)
sw − − 6− −
H int-t = 12 12 = 12 12 = 0.95 feet LRFD BDS Eq. 3.6.1.2.6b-1
LLDF 1.15
Where:
sw = 6 feet
wt = 20 inches
Di = 54 feet (648 inches)
LLDF = 1.15 LRFD BDS Table 3.6.1.2.6a-1
• Conservatively assume H = 20 feet above the tunnel (H = 20 feet at the crown and H > 20
feet away from the crown).
• The length of the distributed axle loads in the model is 0.84 feet (approx. 10 inches / 12
inches per foot).
The above magnitudes are assigned to the appropriate discrete distributed load in the model to
simulate each wheel. For instance, to simulate HL-93 Tandem loading at the arch mid-span as
illustrated in Figure 13, the distributed loads centered at X-coordinates -2 feet and +2 feet were
activated and assigned a magnitude of 0.88 ksf. All other distributed loads were left unactivated.
70
As mentioned previously, lane loading was not applied with the HL-93 vehicles. LRFD BDS
Article 3.6.1.2.6a discusses the use of axle loads only for buried structures. However, for larger
tunnel structures, lane loading should be considered unless it is negligible. In the case of this
example, comparing the pressure due to the lane loading, pland, at the top of the tunnel (under 20
feet of fill) with the soil pressure at that depth, psoil, shows it is negligible (less than 1% of soil
load):
psoil = soil H = (0.125 kcf )(20) = 2.50 ksf ? plane = 0.02 ksf
Per LRFD BDS Article 3.6.2.2, the dynamic load allowance at depth of 20 feet is 0% (no
increase in wheel loads). Additionally, per LRFD BDS Article 3.6.1.2.6a, the single lane
multiple presence factor of 1.20 should be applied to traffic parallel to the span (perpendicular to
longitudinal direction of tunnel). The 1.20 factor is applied to the FE results prior to computing
load factors.
Live load placements need to be considered in order to capture the maximum and minimum
force envelopes. Influence lines can sometimes be used to determine placement of live loads.
However for more complex SSI analyses, alternative methods may be more appropriate.
A relatively simple, but time consuming method is to consider all relevant vehicle locations one
at a time in separate FE analyses. Figure 14 presents an example for the HL-93 Truck at one
specific location. The three activated loads (dark arrows) can be moved incrementally to any
other position. Structural demands can be compared for each load position in order to identify the
maximum demands.
71
Source: FHWA
Figure 14. Illustration. Live Load Application for HL-93 Truck at One Location.
Alternatively, a moving load analysis can be performed to identify the critical load location.
Moving load analysis is more complex, but can save time if performed by an experienced
modeling professional. A moving load analysis is demonstrated in Example 4 of the Reference
Guide for Load Rating of Tunnel Structures (FHWA, 2019) using the Dynamics feature of Plaxis
(2019). Moving load analyses were performed to determine the location of each live load that
results in the maximum moment in the tunnel liner (at the crown) for this example.
Structural dead loads and earth pressures are generated automatically in the FE model. As a
result, it is not possible to apply a load factor directly to the EV or EH loads. It is possible to
apply load factors to live loads in the FE model. However, for consistency with the handling of
permanent loads, load factors were not applied to live loads in the FE analysis. Therefore, the FE
model results are for unfactored permanent and live loads. Load factors should be applied to the
resulting demands later in the load rating procedure.
72
2.4.2.7 Volume Loss
During earth pressure balanced tunnel boring machine (EPB TBM) tunnel construction, there is
typically a small volume of soil that is over-excavated in excess of the theoretical volume of the
excavation, leading to ground or volume loss. This volume loss can lead to ground settlements at
the surface and can also impact the tunnel liner forces. Volume loss is typically lumped into
three groups (FHWA, 2009): face loss, shield loss, and tail loss. Face loss consists of ground
movements into the shield face. Shield loss occurs between the cutting edge and the shield tail,
due in part to the small amount of overcut that occurs for maneuverability. Tail loss occurs
behind the tail as the ground support mechanism moves to the liner itself and the grout that fills
the annular space between the cut and the liner. In the tunneling industry, the volume loss (i.e.,
amount of over-excavation) is typically expressed as a percentage of the tunnel size.
EPB TBMs are able to minimize the magnitude of volume loss by applying pressure to the tunnel
face, minimizing the overcut, and grouting the tail void (FHWA, 2009). However, the volume
loss is not likely to be eliminated entirely. Ultimately, the amount of volume loss is dependent on
the quality of workmanship during construction. As a result, it is good practice to consider a
range of volume loss in the load rating analysis in order to address this uncertainty. However, if
ground loss levels were measured and recorded during the construction of a tunnel, a more
precise value can be used for the load rating.
Modern EPB TBM techniques have significantly reduced the ground loss on recent projects. For
example, the LA Metro Regional Connector, Sao Paulo Metro Line 4, Heathrow Airside Road
Tunnel, and Madrid South Bypass M-30 Tunnels have reported ground loss in the range of 0.1%
to 0.4% for tunnel diameters of approximately 20 to 50 feet (Metro, 2019).
Volume loss is applied in this example using the line contraction feature in Plaxis (2019). The
circumference of the liner plate element is reduced to achieve the specified volume loss. As such,
it is a simplification of the actual volume loss mechanism described above. In this example, two
volume loss scenarios are considered as lower and upper bounds in order to address uncertainties
and numerical simplifications: zero volume loss; and 0.5% volume loss.
FE analyses were performed for the following scenarios to address uncertainties discussed in the
previous sections:
The load rating analysis for this example was based on the highest structure demands from these
four scenarios.
73
2.4.3 FE Analysis Procedure
The FE analysis was performed in phases in order to consider a realistic construction sequence
and to separately evaluate demands under permanent loads only as well as permanent plus live
loads. An initial phase was performed with level ground conditions (without the tunnel present)
to generate stresses in the ground prior to the start of construction, as illustrated in Figure 15.
Vertical stresses were generated based on the assigned soil unit weights, and horizontal stresses
were generated based on a K0 procedure (horizontal stress = vertical stress times K0). The
following staged construction phases were performed next:
Tunnel Construction (Figure 16): Excavate tunnel, activate liner and interface, and dewater
inside tunnel by setting soil clusters inside tunnel to dry.
Volume Loss (not shown): Activate the line contraction to apply the volume loss (for scenarios
that include non-zero volume loss).
Interior Dead Loads (Figure 17): Activate corbels and point loads representing the dead load
from the structures inside the tunnel lining. All unfactored permanent loads (DC, EV, and EH)
are accounted for at the end of this phase, with the exception of the building surcharge which is
discussed in Section 2.4.4.1.2.
Live Loads (Figure 13 and Figure 14): Activate vehicle live load. All unfactored permanent
loads and live loads (DC, EV, EH, and LL) are accounted for at the end of this phase, with the
exception of the building surcharge which is discussed in Section 2.4.4.1.2.
Source: FHWA
Figure 15. Illustration. Generate Stresses Under Original Level Ground Condition.
74
Source: FHWA
Figure 16. Illustration. Excavate Tunnel, Activate Liner and Interface, Dewater Inside.
Source: FHWA
Figure 17. Illustration. Activate Corbels and Apply Interior Structure Dead Loads.
All of the analysis phases listed above were performed for each of the four sensitivity scenarios
described in Section 2.4.2.8.
75
2.4.4 FE Analysis Results
Results are presented in the following sections for use in the load rating analysis in the form of
moment, shear, and axial force plots along the liner. The results are plotted as a function of the
angle from the horizontal, with zero degrees being at the right-most point on the liner (3 o’clock
position), 90 degrees at the crown (12 o’clock position), and 270 degrees at the invert (6 o’clock
position), as illustrated in Figure 18. Axial compression loads are negative.
Source: FHWA
Figure 18. Illustration. Convention Used for Angle from Horizontal to Present the Results.
Results of the analysis including all of the permanent loads except for the building surcharge are
presented in Figure 19 for each of the four sensitivity scenarios described in Section 2.4.2.8.
76
Source: FHWA
Figure 19. Analysis Results. Permanent Loads Without the Building Surcharge.
77
2.4.4.1.2 With Building Surcharge
The presence of large buildings at the surface above the tunnel was considered by applying a
vertical surcharge of 7 ksf across a width of 84 feet centered about the tunnel centerline, as
illustrated in Figure 20. The 7 ksf is a defined building load prescribed within the project
parameters. Based on the assumption that the buildings were in place before the tunnel, the
building surcharge was activated prior to tunnel excavation and construction. Results of the
analysis including all of the permanent loads plus the building surcharge are presented in Figure
21 for each of the four sensitivity scenarios described in Section 2.4.2.8.
It should be noted that for tunnels at this depth below soil, building loads as shown in Figure 20
and live loads over the top are not coincident. As a result, the ratings are not calculated including
the building surcharge. At increased depths where adjacent building surcharges would overlap
with overhead vehicular traffic, the live load effects would be nonexistent.
Source: FHWA
Figure 20. Illustration. Building Surcharge Included at the Ground Surface.
78
Source: FHWA
Figure 21. Analysis Results. Permanent Loads Including the 7 ksf Building Surcharge.
79
2.4.4.2 Structure Demands due to Permanent and Live Loads
Live load analysis results are presented in this section. The results indicate that the impacts of
surface live loads on the tunnel liner are relatively small, and the difference between each vehicle
is hardly noticeable. As explained in Section 2.4.2.5.1, the wheel loads are distributed
horizontally through the overlying soil before reaching the tunnel, which significantly lessens
their impact on the liner as compared with the weight of the soil itself.
The deformed mesh and liner moments for the HL-93 Tandem live load plus permanent loads
(excluding the building surcharge) are illustrated in Figure 22 for the LE with 0.5% volume loss
scenario. Moment, shear, and axial force diagrams are presented in Figure 23 for each of the four
sensitivity scenarios described in Section 2.4.2.8.
81
2.4.4.2.2 HL-93 Truck
The deformed mesh and liner moments for the HL-93 Truck live load plus permanent loads
(excluding the building surcharge) are illustrated in Figure 24 for the LE with 0.5% volume loss
scenario. Moment, shear, and axial force diagrams are presented in Figure 25 for each of the four
sensitivity scenarios described in Section 2.4.2.8.
Source: FHWA
Figure 24. Analysis Results. Permanent Loads + HL-93 Truck (No Building Surcharge).
82
Source: FHWA
Figure 25. Analysis Results. Permanent Loads + HL-93 Truck (No Building Surcharge).
83
2.4.4.2.3 EV-2
The deformed mesh and liner moments for the EV-2 live load plus permanent loads (excluding
the building surcharge) are illustrated in Figure 26 for the LE with 0.5% volume loss scenario.
Moment, shear, and axial force diagrams are presented in Figure 27 for each of the four
sensitivity scenarios described in Section 2.4.2.8.
84
Source: FHWA
Figure 27. Analysis Results. Permanent Loads + EV-2 (No Building Surcharge).
85
2.4.4.2.4 EV-3
The deformed mesh and liner moments for the EV-3 live load plus permanent loads (excluding
the building surcharge) are illustrated in Figure 28 for the LE with 0.5% volume loss scenario.
Moment, shear, and axial force diagrams are presented in Figure 29 for each of the four
sensitivity scenarios described in Section 2.4.2.8.
86
Source: FHWA
Figure 29. Analysis Results. Permanent Loads + EV-3 (No Building Surcharge).
87
2.4.4.3 Critical Forces
The critical load forces were extracted from the shear, moment and axial force diagrams.
Factored loads were reviewed around the perimeter to find the maximum load locations. The
load combination and location for the maximum and minimum moments, shears and axial forces
are identified and the subsequent forces are extracted and reported in Table 32 through Table 35.
These loads are unfactored. Live load results were obtained by subtracting the demands due to
permanent loads only in Section 2.4.4.1 from the corresponding permanent plus live load
demands in Section 2.4.4.2. Live load values in the following tables include the 1.20 single lane
multiple presence factor.
The maximum moment shown in Table 32 was obtained when subjected to the LE-Contraction
soil condition at 90° with respect to Figure 18, which occurs at the top of the tunnel. Positive
moment causes tension on the inside face of the tunnel liner (in the absence of axial
compression). It can be seen that the shear is effectively zero at this location and the live load
components of the moment and axial thrust is small in relation to dead load.
Table 32. Maximum Moment (kip-ft) & Corresponding Shear (kip) & Axial (kip).
Perm
Force Perm Truck Tandem EV-2 EV-3
+Bldg
Moment 20.95 74.80 0.82 0.89 0.61 0.96
Shear 0.02 0.10 0.00 0.00 0.00 0.01
Axial -27.91 -116.23 -0.71 -0.50 -0.48 -0.71
The minimum moment as shown in Table 33 was obtained when subjected to the UE-
Contraction soil condition at 354° with respect to Figure 18, which occurs at the right side of the
tunnel and is further from the surface than the positive moments above. It can be seen that shear
live load forces at this location are essentially zero. Although this location is the maximum
factored negative (or minimum) moment location, only negligible live loads moments, which are
positive, exist there. To compare against the maximum positive moments above, maximum
negative live load moments from around the perimeter are shown in Table 33 to envelope the
results. The maximum negative live load moments occur in the LE-Contraction soil condition at
52°. It will be shown later the reinforcement is the same on both faces and the concrete cover on
each face is similar (2 inches on outside versus 1.5 inches on inside) so the larger positive
moments above will control the rating. As such, no negative moment rating factors will be
calculated.
Table 33. Minimum Moment (kip-ft) & Corresponding Shear (kip) & Axial (kip).
Perm
Force Perm Truck Tandem EV-2 EV-3
+Bldg
Moment* -15.93 -12.47 -0.27 -0.27 -0.21 -0.32
Shear 0.07 -2.73 0.02 0.01 0.01 0.02
Axial -31.94 -72.06 -0.82 -0.64 -0.57 -0.77
*Note: Live load moments are minimums from entire perimeter.
88
The location of maximum factored shear, whether it be positive or negative, as shown in
Table 34 was obtained when subjected to the LE-No Contraction soil condition at 245° with
respect to Figure 18, which is located near the bottom of the tunnel liner at the left corbel. It can
be seen that live load forces (moment, shear or axial) at this location are essentially zero. This
location, at the bottom of the tunnel is not influenced by live load above. Other locations do have
live load shears but they are not the maximum factored shear location. It will be shown later, that
the shear capacity is much greater than the factored maximum shear (1.35 times dead load) so
ratings will not be calculated. The shear resistance will be conservatively based on maximum
positive or negative moments and axial thrust to ensure capacity envelopes all possible
combinations. For reference, the maximum HL-93 Truck shear is ±0.12 kips for the LE-
Contraction soil condition on either side of the tunnel crown (90°).
Table 34. Maximum Shear (kip) & Corresponding Moment (kip-ft) & Axial (kip).
Perm
Force Perm Truck Tandem EV-2 EV-3
+Bldg
Moment -5.50 1.23 0.06 0.05 0.04 0.06
Shear 4.00 4.83 0.03 0.03 0.02 0.03
Axial -93.99 -143.16 -0.06 -0.01 -0.04 -0.07
The minimum axial thrust (negative axial load) as shown in Table 35 was obtained when
subjected to the UE-No Contraction soil condition at 270° with respect to Figure 18, which is
located at the bottom of the tunnel. As expected, there are no factored axial tension forces in the
liner. For similar reasons to the maximum shear location above, it can be seen that live load
forces (shear or axial) at this location are essentially zero. This location, at the bottom of the
tunnel is not influenced by live load above. Similar to the minimum (negative) moment location,
the maximum factored thrust location is not subjected to compression live load. The live load
values show in Table 35 are the maximum values around the perimeter to envelope the results.
The maximum live load axial thrust is for the LE-Contraction soil condition on the left and right
sides of the tunnel. It will be shown later, that the axial capacity is much greater than the factored
maximum axial thrust (1.35 times dead load) so ratings will not be calculated.
Table 35. Maximum Axial (kip) & Corresponding Moment (kip-ft) & Shear (kip).
Perm
Force Perm Truck Tandem EV-2 EV-3
+Bldg
Moment -0.43 1.64 0.02 0.01 0.01 0.02
Shear -0.07 -0.07 0.00 0.00 0.00 0.00
Axial* -175.57 -195.19 -1.32 -1.06 -0.92 1.35
*Note: Live load thrusts are minimums from entire perimeter.
The tunnel liner was constructed from 24-inch thick precast concrete sections that are 77.86
inches wide at the outside. These sections have 2 inches of clear to the ASTM A496 deformed
steel wire size D-31 transverse bars on the outside face and 1.5 inches on the inside face. The
89
size D-30 longitudinal bars, which resist the bending moments, are inside the transverse
reinforcement. Structural resistances are calculated assuming the 16 longitudinal bars in each
section equally resist the force demands in that precast section. This results in 2.47 bars per
linear foot of the tunnel liner. The deformed steel wire size D-30 longitudinal bars have a
diameter of 0.618 inch while the size D-31 transverse bars have a diameter of 0.628 inch. These
sections are constructed utilizing 7.0 ksi concrete and 75 ksi reinforcing steel.
Concrete Properties:
f’c = 7.0 ksi
∝1 = 0.85 LRFD BDS 5.6.2.2
β1 = 0.70 for f’c = 7.0 ksi LRFD BDS 5.6.2.2
λ = 1.0 (normal weight concrete) LRFD BDS 5.4.2.8
γ3 = 0.75 (AASHTO M31 Grade 75) LRFD BDS 5.6.3.3
γ1 = 1.6 LRFD BDS 5.6.3.3
Modulus of rupture:
f r = 0.24 f 'c = 0.24(1.0) 7.0 = 0.635 ksi LRFD BDS 5.4.2.6
Moment Resistance:
Determine equivalent area of reinforcing bar:
As = As _ bar No.Bar = 0.300(12"/ 4.87" bar spacing) = 0.740 inch 2
Determine distance of the extreme compression fiber to the centroid of the reinforcement:
diabar 0.618
ds = h − − dtrans − clr = 24.00 − − 0.628 − 2.00 = 21.06 inches
2 2
Determine distance from the equivalent stress block for tension controlled, non-
prestressed tension reinforcement only:
90
As f y 0.740(75)
a= = = 0.78 inches LRFD BDS Eq. 5.6.3.1.1-4 and 5.6.2.2
0.85 f 'c b 0.85(7.0)(12.00)
a 0.78
1 = 0.7 c = = = 1.11inches LRFD BDS 5.6.2.2
1 0.7
ds 21.06
s = c − 1 = 0.003 − 1 = 0.054 0.005
c 1.11 LRFD BDS 5.5.4.2, 5.6.2.1
f = 0.90
Accounting for the level of applied axial compression at the location of maximum
factored moment in the equation above would not shift the strain out of the tension-
controlled zone.
The calculation of moment resistance conservatively ignores the presence of axial thrust, which
generally increase the moment resistance up to the levels of axial compression present in the
analysis. This can be seen in Figure G6A-1 in Appendix G6A of the MBE (AASHTO, 2018). If
the resulting moment ratings were inadequate, the refined moment-axial interaction procedure
could be employed. However, as can be seen in the figure, very high loads of axial compression
may reduce the moment resistance.
Axial Resistance:
Tunnel liner need to be checked for axial thrust and flexural interaction. Check
flexure/axial interaction:
Since the axial forces associated with the maximum factored moments (permanent dead
load plus live load) do not exceed 0.1cfc’Ag, the axial thrust can be neglected.
Furthermore, at the locations where the dead load effects are approaching this limit, the
live load moment effect is approaching zero; as a result, the load rating can be neglected
when axial forces are in excess of this limit.
Minimum Steel:
Determine minimum reinforcement, beginning with the section modulus:
91
bh 2 12.00(24.00)2
Sc = = = 1152 inch 3 LRFD BDS 5.6.3.3
6 6
The cracking moment equation simplifies to the following (only monolithic sections and
no prestress forces):
1 ft
M cr = 3 1 f r Sc = 0.75(1.6)(0.635)(1152)
12 inch LRFD BDS Eq. 5.6.3.3-1
= 73.15 kip-ft
Since fMn > Mcr, minimum reinforcement at this section is satisfied
The shear resistance of the liner is also evaluated. The liner does have shear bars dispersed
through the precast sections. However, for the purpose of simplification, only the concrete shear
capacity will be utilized for the shear resistance. If the resistance is not sufficient with just the
concrete shear resistance, the shear bars can be included in the resistance calculations.
Determining the nominal shear resistance involves the use of the applied shears and moments at
the section of interest. To envelope the possible combinations of forces, use the non-concurrent
maximum factored HL-93 Inventory loadings.:
M u = 29.85 kip-ft
Vu = 5.38 kip
Nu = 236.96 kip
The shear resistance of the liner needs to be evaluated using LRFD BDS 5.7.3.3. Shear factors
and need to be calculated since the member thickness is not less than 16 inches and the shear
steel is not being considered in the resistance calculations.
M u Vu dv
LRFD BDS5.7.3.4.2
29.85(12) = 358.2kip-in 5.38(20.67) = 111.2 kip-inch
92
Mu
+ 0.5 N u + Vu
s = v
d
Es As
LRFD BDS Eq. 5.7.3.4.2-4
358.2
+ 0.5(239.96) + 5.38
= = 0.0066
20.67
0.740(29000)
0 s 0.006
= 29 + 3500 s = 29 + 3500(0.006) = 50.00 o
4.8 51
=
(1 + 750 s ) ( 39 + sxe )
LRFD BDS Eq. 5.7.3.4.2-2
4.8 51
= = 0.88
1 + 750(0.006) 39 + 18.63
Vn = v 0.0316 f c' 0.25 f c' bv d v
= 0.85 0.0316(0.88)(1.0) 7.0 0.25(7.0) 12(20.67) LRFD BDS 5.7.3.3
= 15.51 kip
It can be seen that even with very conservative calculation of shear resistance using non-
concurrent loads and ignoring shear reinforcement, the resistance is significantly higher than the
maximum factored HL-93 Inventory shear force. The following LRFD BDS checks have not
been performed for this example but should be checked for actual rating calculations: regions
requiring transverse reinforcement (5.7.2.3) and longitudinal reinforcement checks (5.7.3.5) [23
CFR 625.4(d)(1)(v)].
The structural condition of the tunnel liner is satisfactory and the system factor falls under the
category for "All Other Girder Bridges and Slab Bridges." Therefore:
Resistance factors are based on LRFD BDS Section 5 and specified in the calculations of Section
2.4.5 of this document.
The equation for calculating the rating factor is based on MBE Equation 6A.5.12.4-1, which has
been simplified for the load types being applied.
C DC DC DW DW EV EV EH EH ES ES
RF = MBE Eq. 6A.5.12.4-1
LL ( LL + IM ) LS LS
Table 37 though Table 39 show the results of the overall capacity based on MBE Equation
6A.5.12.4-2 as well as the rating factors based on MBE Equation 6A.5.12.4-1. Ratings are
performed at the critical section. As discussed in Section 2.4.4.3, only ratings for maximum
positive moment will be calculated. It was shown that the total factored loads and low levels of
live load forces indicate the negative moment, shear and axial loads do not need to be
investigated.
Maximum and minimum load factors are selectively used to obtain the maximum absolute value
of the force effects. Dead loads and earth loads are not able to be de-coupled due to the nature of
the FEM. Therefore, a conservative load factor of 1.35 is used for all permanent loads. This load
factor is the larger of the DC, EV and EH load factors. The live load factor for the EV vehicles is
2.0 as identified in the FHWA Emergency Vehicle Memorandum (FHWA, 2016) for buried
structures. The load factors used are shown in Table 36. The moments, shears and their
corresponding capacities in Table 37 to Table 39 are in kip-ft and kip, respectively. The load
effects are unfactored, but the capacities are factored resistances. Note that Table 39 is for the
EV-3 vehicle because it controls over EV-2.
94
Table 39. EV-3 Rating Factors.
Section Perm. Live Load Capacity R.F.
Mpos 20.95 0.96 86.02 30.07
The rating factors are all well above 1 indicating that the tunnel liner is sufficient for all the
evaluated live loads. In addition, it is observed that the live load effects induce a minor effect on
the tunnel liner force demands in relation to permanent loads.
The flexural and shear resistance of the joints between panels around the circumference of the
liner are not investigated in this example but should be reviewed for an actual rating. This
includes resistance to crushing and opening of the joint under axial thrust and bending. In
addition to the thrust due to external loads, the panels are attached to each other with torqued
bolts creating additional compression across the joint providing additional resistance to joint
opening. The shear resistance of the interface also needs to be investigated. Shear is resisted
through friction and steel guide rods and the previously mentioned bolts.
A structural adequacy evaluation under a 7 ksf building load is investigated at other locations in
addition to the rating of the liner under live load effects. This loading does not include a live load
effect and therefore cannot produce a rating factor; however, a performance ratio can be
evaluated by dividing the resistance by the demand. This ratio will therefore correlate in the
same manner as the rating factor in which a ratio greater than 1 indicates adequate strength while
a ratio less than 1 indicates insufficient strength. The moments, shears and their corresponding
capacities in Table 40 are in kip-ft and kip, respectively. The permanent loads including the
building load are factored per Table 36 and the capacities are factored resistances.
The performance ratio is greater than 1, indicating this tunnel liner has sufficient resistance to
support the 7 ksf building load when not subjected to concurrent live load at this depth below the
surface.
95
96
CHAPTER 3 - EXAMPLE 2 – BOX TUNNEL ROOF GIRDER
Example 2 presents a double cell tunnel consisting of simply supported, composite, steel roof
girders supported by walls and a slab-on-grade bottom slab. The roof girder supports surface
roadway loads. The lower roadway slab is on-grade and therefore does not need to be rated. The
walls are soldier pile tremie concrete walls, which resist the lateral earth loads and the vertical
loads from the roof girders. The tunnel roof girder is subjected to vertical dead loads, earth loads
and live loads. It is assumed that little or no lateral loads are imparted to the roof girders due to
the simple shear connections of the girders to the soldier piles. The box tunnel roof girder is rated
with the LRFR method for the design vehicles (HL-93 Inventory and Operating Level) and
emergency vehicles (EV-2 and EV-3) at the legal load level.
This example will perform the following steps to rate this composite steel roof girder:
1. Structure data
2. Example notes
3. Rating approach/assumptions
4. Load application
5. Structural analysis
6. Resistance calculations
3.1.1 Materials
Materials are known, otherwise use MBE Articles 6A5.2.1 and 6A5.2.2. Soil parameters were
randomly selected for the example. Full soil descriptions and evaluation should be performed for
actual tunnel ratings so accurate soil parameters can be obtained. This example also assumed dry,
or drained, soil above the roof girder.
97
3.1.2 Dimensions
32 kip
32 kip
8 kip
14'-30' 14'
Ground Surface
4.0' Fill Depth
12" Slab with Stay-In-Place Forms
60.77'
Simply Supported Steel Composite Girder
Source: FHWA
Figure 30. Illustration. Cross-Section Showing Tunnel Geometry.
• This cross-section has been selected from this project as representative to demonstrate
rating of the tunnel roof girder under external loading.
• The live load carrying member considered in this example is the simply supported
composite steel I- girder.
• If the roadway above the tunnel has overlay or sidewalk loads, they should be included in
the dead load analysis. This example assumes that these items are not included in the
geometry of this roof girder.
• The focus of this example is LRFR.
• This example focuses on the load rating of a critical and typical roof girder. A section
taken near the ends of the tunnel would need to account for increases in loading due to
edge of slab effects. Additionally, critical connection details may need to be rated in a
full rating project.
• The rating Engineer should review the record drawings and inspection reports carefully to
properly identify the support condition (pinned, expansion, fixed). Typical conditions,
assumed for this example are simply supported conditions for the roof girder.
• Rating is performed only at maximum shear and moment locations. The capacity of the
bracket is also evaluated. Typical ratings include evaluation at all tenth points and full
connection evaluation.
98
3.1.4 Rating Approach/Assumptions
The roof girder is subject to self-weight, air pressure, soil/pavement, and live load. There is no
wearing surface applied and is therefore neglected in this analysis. Other forces such as TU are
neglected due to the simply supported boundary conditions of the composite girder.
Dead load components include the self-weight of the reinforced concrete slab, steel girder and
stay-in-place (SIP) forms.
This tunnel assumed no wearing surfaces were applied and therefore were not included in the
load calculations.
99
3.2.1.3 Vertical Earth Pressure, EV
H 4.0
Fe = 1 + 0.20 = 1 + 0.2 = 1.013 LRFD BDS Eq. 12.11.2.2.1-1
Bc 60.77
Where H is the fill depth of 4 feet and Bc is the supported width of 60.77 feet.
The live load travels parallel to the span of the steel girder over a 4 feet fill and therefore the
wheel load distributes through the earth fill. The transverse live load distribution should be
calculated in accordance to LRFD BDS Article 3.6.1.2.6b for traffic parallel to span. The LLDF
is specified as 1.15 from LRFD BDS Table 3.6.1.2.6a-1.
H = 4.0 ft
wt 0.06 D j 20 0.06(60.77 12)
sw − − 6− −
H int = 12 12 = 12 12 LRFD BDS Eq. 3.6.1.2.6b-1
LLDF 1.15
= 0.598 ft
The effective width the load is distributed over can be calculated by LRFD BDS Eq. 3.6.1.2.6b-3
since H is greater than Hint.
wt D 20 60.77 12
ww = + sw + LLDF ( H ) + 0.06 i = + 6.0 + 1.15(4.0) + 0.06 = 15.913 ft
12 12 12 12
The longitudinal live load distribution should be calculated in accordance to LRFD BDS Article
3.6.1.2.6b for traffic parallel to the span. Compute the distribution widths for the various axle
spacings of the HL-93 and EV vehicles (4’ for HL-93 Tandem and EV-3 vehicle, 14 feet for HL-
93 Truck, and 15’ for EV-2 and EV-3 vehicles). Note the HL-93 Truck produces the critical
force effects when the rear axle is at 14-foot spacing. Additionally, where ratings are adequate,
the longitudinal distribution of wheel loads may conservatively and conveniently be ignored by
applying the axle point loads directly to the beam.
100
lt 10
sa − 4−
H int − p (4') = 12 = 12 = 2.754 ft
LLDF 1.15 LRFD BDS Eq. 3.6.1.2.6b-4 & 5
l 10
lw = t + sa + LLDF ( H ) = + 4 + 1.15(4) = 9.43 ft
12 12
lt 10
sa − 14 −
H int − p (14') = 12 = 12 = 11.449 ft
LLDF 1.15 LRFD BDS Eq. 3.6.1.2.6b-4 & 5
lt 10
lw = + LLDF ( H ) = + 1.15(4) = 5.43 ft
12 12
lt 10
sa − 15 −
H int − p (15') = 12 = 12 = 12.319 ft
LLDF 1.15 LRFD BDS Eq. 3.6.1.2.6b-4 & 5
l 10
lw = t + LLDF ( H ) = + 1.15(4) = 5.43 ft
12 12
Each axle load is distributed over the transverse and longitudinal areas and normalized over the
girder spacing. For calculation simplicity, a unit load pressure is calculated then multiplied by
the axle loads of the various vehicles.
This distributed load (axle) per length along the girder can then be multiplied by the various axle
loads. However, the live load also needs to be multiplied by the dynamic allowance for buried
structures specified in LRFD BDS Article 3.6.2.2 and a single multiple presence factor of 1.2 as
specified in LRFD BDS Article 3.6.1.1.2. For this example, a multiple presence factor of 1.0 was
used for the EV legal loads based on MBE Article 6A5.12.10.3 for buried structures with traffic
traveling parallel to the span. Where the axle loads are 14 feet or 15 feet, the axle loads shall be
distributed over 5.43 feet. When the axle spacing is 4 feet, the axle loads shall be combined and
distributed over 9.43 feet.
I.M. = 33(1.0 − 0.125DE ) 0% = 33(1 − 0.125 4) = 16.5% LRFD BDS Eq. 3.6.2.2-1
101
0.377 axle
PHL 93−Truck = (8 kip/axle) (1.165)(1.2) = 0.776 klf per girder
5.43 ft
0.377 axle
PHL 93−Truck = ( 32 kip/axle ) (1.165)(1.2) = 3.106 klf per girder
5.43 ft
0.377 axle
PHL 93−Tandem = (2) ( 25 kip/axle ) (1.165)(1.2) = 2.795 klf per girder
9.43 ft
0.377 axle
PEV 2 = ( 24 kip/axle ) (1.165)(1.0) = 1.941 klf per girder
5.43 ft
0.377 axle
PEV 2 = ( 33.5 kip/axle ) (1.165)(1.0) = 2.710 klf per girder
5.43 ft
0.377 axle
PEV 3 = ( 24 kip/axle ) (1.165)(1.0) = 1.941 klf per girder
5.43 ft
0.377 axle
PEV 3 = (2) ( 31 kip/axle ) (1.165)(1.0) = 2.888 klf per girder
9.43 ft
For this example, only axle loads are applied based on MBE Article 6A5.12.10.3 for reinforced
concrete box culverts,. However, this is a steel roof girder with a span in excess of 60 feet;
therefore, it is prudent to include the lane load for HL-93 ratings. As a result, the distribution of
the lane load also needs to be determined, assuming the load distributes at a 1.15 factor as
specified in LRFD BDS Table 3.6.1.2.6a-1. Therefore, the bottom width of the load application
at the structure is 1.15 times wider than the width at the ground surface.
A beam analysis is utilized for the structural analysis. All the load effects and member
resistances are calculated using the tributary, one-dimensional analysis. The composite girder is
assumed to be simply supported and therefore can be evaluated with simple hand calculations or
by a structural analysis program.
The maximum moment can be obtained by positioning the axles such that the centerline of the
span is midway between the center of gravity of the load and the nearest wheel load, as depicted
in Figure 31. The maximum shear is obtained when the axle loads are placed adjacent to the end
of the span, as depicted in Figure 32.
102
C.L.span
P1 P2 P3
C.G.load
Source: FHWA
Figure 31. Illustration. Live Load Placement for Maximum Moment.
P1 P2 P3
Source: FHWA
Figure 32. Illustration. Live Load Placement for Maximum Shear.
Using this load placement theory, the distributed dead and live loads are placed on the beam as
depicted in Figure 33.
x1 w1 x2 w2 x3 w4 x4
60.77'
Source: FHWA
Figure 33. Illustration. Load Placement.
Where the variables xi and wi are defined in Table 41. Results show the Tandem controls the HL-
93 loading due to the convergence of the axle load effects over such a concentrated portion of the
girder.
Table 41. Moment Load Placement Dimensions.
LRFD Road Tunnel Design and Construction Guide Specifications, 1st Ed. Table 3.4-1 identifies
the applicable minimum and maximum load factors for each load specified above. Since the
girder is simply supported, only maximum load factors were necessary to produce critical forces.
The live load factors for the HL-93 are identified in Table 3.4-1; however, the live load factor for
the EV vehicles are 2.0 as identified in the FHWA Emergency Vehicle Memorandum. The forces
are given in Table 43.
The depth, analysis section width, and reinforcement for each of the critical sections are
tabulated below in Table 44 and Table 45.
Non-Composite Section:
105
Long Term Properties (assume 3n=24.0):
The plastic moment of the composite section is calculated in accordance to LRFD BDS Article
D6.1. To accomplish this, the rolled W36x280 is discretized into top flange, web and bottom
flange areas.
b ft = b fb = 16.595 inches
t ft = t fb = 1.57 inches
D =33.38 inches
tw = 0.885 inches
The relative magnitudes of these plastic forces are compared as outlined in LRFD BDS Table
D6.1-1. This reveals this example is Case II. The corresponding plastic section properties are
then calculated.
106
Pt + Pw + Pc Ps 1303 + 1477 + 1303 = 4082 2938 kip
t P + P − Ps 1.57 1477 + 1303 − 2938
Y = c w t + 1 = + 1 = 0.69 inches
2 Pc 2 1303
P
M p = c Y 2 + ( tc − Y ) + Ps d s + Pw d w + Pd
t t
2
2tc
1303 1 ft
= 0.69 + (1.57 − 0.69 ) + 2938 6.69 + 1477 17.57 + 1303 35.05
2 2
2 1.57 12 inch
= 7648 kip-ft
D p = Y + ts = 0.69 + 12 = 12.69 inches
Source: FHWA
Figure 34. Illustration: Plastic Neutral Axis Offset Dimensions.
The section has been determined to be compact for composite positive flexure per LRFD BDS
Article 6.10.6.2.2. The plastic depth is compared against the total depth to ensure the concrete
deck will not crush prior to steel plastic capacity is reached per LRFD BDS Article 6.10.7.12.
Since the plastic compressive depth is greater than 10% of the total depth and this is a simply
supported section, the plastic moment capacity needs to be determined per LRFD BDS Eq.
6.10.7.1.2-2.
Dp 12.69
f M n = f M p 1.07 − 0.7 = 1.0 ( 7648 ) 1.07 − 0.7 = 6783 kip-ft
Dt 48.52
107
3.2.3.6 Shear Resistance
The shear resistance also needs to be determined. The maximum shear force of this simply
supported girder is within the end panel of the girder. Therefore, tension field action cannot be
included in the shear resistance of the girder.
The slenderness of the web first needs to be determined to calculate the shear buckling
coefficient per LRFD BDS Article 6.10.9.3.2. The panel length, do, is 15.19 feet since the cross
frames with transverse stiffeners are located at quarter points of the span.
D 33.38
= = 37.72
tw 0.885
k =5
Ek 29000 5
1.12 = 1.12 = 60.32
Fy 50
Since the web slenderness ratio, D/tw, is less than the web compact limit, C=1.0. Therefore, the
shear resistance is the plastic shear limit per LRFD BDS Article 6.10.9.3.3.
The bracket connection needs to be rated along with the girder capacities. The bracket buckling
resistance is often prudent to rate along with the connection resistance. However, for simplicity
of this example, the weld connection will only be shown as that is the controlling limit state on
this particular bracket plate.
The bracket is composed of 3~8-inch x 21-inch vertical plates with vertical ½-inch fillet welds
on both sides of each plate. The weld is composed of E70 electrodes.
It can be seen that the capacity of the bracket exceeds the shear capacity of the girder; therefore,
the girder will control the ratings.
108
Source: FHWA
Figure 35. Illustration. Bracket Details.
The structural condition of the steel girder is satisfactory and the system factor falls under the
category for "All Other Girder Bridges and Slab Bridges." Therefore:
The equation for calculating the rating factor is based on MBE Equation 6A.4.2.1-1, which has
been simplified for the load types being applied.
C DC DC EV EV
RF = MBE Eq. 6A.4.2.1-1
LL ( LL + IM )
Table 47 shows the results of the overall capacity based on MBE Equation 6A.4.2.1-2 as well as
the rating factors based on MBE Equation 6A.4.2.1-1. Maximum and minimum load factors are
selectively used to obtain the maximum absolute value of the force effects. The load factors used
are shown in Table 46. Moments, shears and their corresponding capacities in Table 47 are in
kip-ft and kip, respectively.
109
Table 46. Load Factors.
Emergency
Earth
HL-93 LL HL-93 LL Vehicle,
DC Load,
Inventory Operating EV LL
EV
Legal
1.25 1.35 1.75 1.35 2.00
110
REFERENCES
AASHTO. (2017a). AASHTO LRFD Bridge Design Specifications, 8th Edition, LRFD-8.
American Association of State Highway and Transportation Officials, Washington, DC.
AASHTO. (2017b). LRFD Road Tunnel Design and Construction Guide Specifications, 1st
Edition, LRFDTUN-1. American Association of State Highway and Transportation Officials,
Washington, DC.
AASHTO. (2018). Manual for Bridge Evaluation, 3rd Edition. American Association of State
Highway and Transportation Officials, Washington, DC.
FHWA. (2004). FHWA Road Tunnel Design Guidelines, FHWA-IF-05-023. Federal Highway
Administration, Washington, DC.
FHWA. (2009). Technical Manual for Design and Construction of Road Tunnel—Civil
Elements, FHWA-NHI-10-034. Federal Highway Administration, Washington, DC.
FHWA. (2013). Information: Load Rating of Specialized Hauling Vehicles. Federal Highway
Administration, Washington, DC.
FHWA. (2015a). Specifications for the National Tunnel Inventory, FHWA-HIF-15-006. Federal
Highway Administration, Washington, DC.
FHWA. (2016). Memorandum: Load Rating for the FAST Act’s Emergency Vehicles. Federal
Highway Administration, Washington, DC.
FHWA. (2019). Reference Guide for Load Rating of Tunnel Structures, FHWA-HIF-19-010.
Federal Highway Administration, Washington, DC.
Los Angeles County Metropolitan Transit Authority (Metro). (2019). Westside Purple Line
Extension, Section 3, Structure Impact Assessment Report for Tunnels and Cross Passages.
Prepared by ALDEA, November 26.
111