Estimation Class 10 First Terminal
Estimation Class 10 First Terminal
Group A
Choose the best alternative to the given questions and write in answer sheet. [9*1=9]
A) m B) m2 C) m3 D) m4
A) m B) m2 C) m3 D) m4
4) What is volume of rectangular trench having length, width, and depth 75m, 15m and 3m
respectively?
thickness of wall
A) thickness of wall B) C) 2∗(thickness of wall) D) none
2
1
A) Amean = ∗( A 1+ A 2+ 4∗Am)
6
1
B) Amean = ∗( A 1+ A 2+4∗Am)
3
1
C) Amean = ∗( A 1+ A 2+ Am)
3
1
D) Amean = ∗( A 1+ A 2+ Am)
6
thickness of wall
A) thickness of wall B) C) 2∗(thickness of wall) D) none
2
Group B
11) Write down different type of estimate and explain any three of them.
12) What are three different formulas used in quantity calculation of regular trench. Write in brief.
13) What are different methods used in building estimate. Explain long wall-short wall and centerline
method.
14) Draw the section of wall showing roof to foundation and show different item.
Group C
f) Brickwork in superstructure with parapet and deduction for Door and Windows [3]