Structure installation-JSA Rev.01
Structure installation-JSA Rev.01
JOB LOCATION (Plant): STC-Jubail Utilities Park & Pilot Plants Project AREA: WAREHOUSE: STC-J project area
RESPONSIBIL
BASIC STEP POTENTIAL HAZARDS MITIGATION PLAN STATUS
ITY
Page 1 of 11
STC-Jibail Utilities Park & Pilot Plants Project
Job supervisor must conduct toolbox talk to all people involve in the job prior to
5.1 Safe job executing
start and explain to them all the safety point in the method that could be applied
5. Mobilization of steel procedure not discussed
and the safety precaution to be taken; Construction
structure materials to site
using trailer /boom truck Manager
5.2 Collapse and fall of 5.2.1 Ensure that the bed guard is installed;
material during transport 5.2.2 Secure load with minimum of two lashing or dog chain strap;rachet binder
Page 2 of 11
STC-Jibail Utilities Park & Pilot Plants Project
Page 3 of 11
STC-Jibail Utilities Park & Pilot Plants Project
Page 4 of 11
STC-Jibail Utilities Park & Pilot Plants Project
13.2.1 Wear proper hand gloves during alignment and drilling of steel structure;
13.2.2 Use electric drill side handle to control the drill machine;
13.2 Hand & Finger injury
13.2.3 Keep hands off from line of fire;
13.2.4 Use center punch to guide the drill bit if necessary.
13.3 Fall of alignment & Secure the hand tools / drill machine with rope to prevent from falling to the
fitting tools ground.
Page 5 of 11
STC-Jibail Utilities Park & Pilot Plants Project
Page 6 of 11
STC-Jibail Utilities Park & Pilot Plants Project
Page 8 of 11
STC-Jibail Utilities Park & Pilot Plants Project
Page 10 of 11
STC-Jibail Utilities Park & Pilot Plants Project
Comment: …………………………………………………………………………………………………
…………………………………………………………………………………………………………………..
…………………………………………………………………………………………………………………..
…………………………………………………………………………………………………………………..
…………………………………………………………………………………………………………………..
Page 11 of 11