0% found this document useful (0 votes)
14 views

CIVE1211 L4 CompSlab 2019

Uploaded by

mar629346
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views

CIVE1211 L4 CompSlab 2019

Uploaded by

mar629346
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 35

CIVE1211 Steel Structures 2

Lecture 4 Composite slab design


Dr Rick Chan
Senior lecturer
School of Engineering

[email protected]

1
What is composite construction?
• “Composite steel-concrete construction” refers to structural strength is
achieved by steel & concrete acting together.
– Concrete resists compression and steel resists tension
• Most common form used in steel framed structures today.
• Consist of composite slab, beams, columns and joints
• Example: RMIT’s New Academic Street, Melbourne
• https://www.youtube.com/watch?v=n0TMqBTYJDs
• https://www.youtube.com/watch?v=uPBvdNvuJyY

2
Examples in Australia

3
Concreting in progress: steel deck is used as permanent formwork

4
Example in HK: Extension to MMW Building, CityU

Steel frame being installed on roof level.


Photo: Ricky Chan

5
RMIT University©yyyy School/Department/Area 5
RMIT University©yyyy
6
School/Department/Area

Steel sheets are being installed on steel frame.


Photo: Ricky Chan

Shear studs welded on top of beams


(through the sheet). Photo: Ricky Chan

6
RMIT University©yyyy
7
School/Department/Area

Steel sheets installation completes and


rebars are installed.
Photo: Ricky Chan

View under steel deck, showing


temporary support to beams &
slabs (props)
Photo: Ricky Chan

7
RMIT University©yyyy
8
School/Department/Area

Concreting with concrete pump.


Photo: Ricky Chan

8
Composite slabs
• Consists of a profiled steel deck (or sheet), reinforcements and concrete
• Profiled steel decks are “proprietary products” manufactured by steel
companies
• Comp. slabs are supported on steel beams, spanning in the direction of
deck (1-way spanning)

Re-entrant profile

Trapezoidal profile

9
Major steel deck suppliers in Australia
• Lysaght Bondek and Deckform
– http://www.lysaght.com/products/bondek

• Bluescope DeckForm
– http://www.steel.com.au/products/coated-steel/deckform-steel

• Stramit Condeck
– http://www.stramit.com.au/product-range/stramit-condeck-hp%C2%AE-composite-slab-system

• Fielders Kingflor
– http://fielders.com.au/products/flooring-solutions/kingflor-design-data/
• Disclaimer: For learning & teaching purpose we will use Lysaght Bondek

10
Lysaght Bondek (Australia) dimensions

Source:
https://professionals.lysaght.com/sites/default/files/LysaghtBondekDesign
andConstructionGuideJuly2016.pdf
11
Functions of steel sheet (or deck)
• a working platform for construction.
• formwork (shuttering) for the concrete slab (permanent formwork)
• bottom reinforcement for the slab – resist tension in positive moment
region

Composite construction in Melbourne

12
HK Steel Code requirements
• Material properties (Sec 10.4.1):
– Steel sheet yield strength < 550N/mm2
– Min. bare metal thickness = 0.7mm
– Concrete strength: C25 – C45
• Generally comp slabs are
constructed without props
• Reinforcement provided for
negative bending moment

Composite construction in Melbourne

13
HK Steel Code requirements: min slab thickness

14
Design for construction
• See Clause 10.4.4.2
• Steel sheets must be able to support
– Self weight, weight of wet concrete and reinforcement
– Construction loads
– Storage loads
• Basic construction load: 1.5kPa
• If span <3m, increase construction load to 4.5/Lp (kPa). Lp is the effective
span of slab.
• Storage load = 3.0kPa (but not co-existing with wet concrete)

15
Design for construction
• Load arrangement requirements:

16
Design for construction
• Criteria, see Cl. 10.4.4.3 and 10.4.4.4
• Ultimate Limit State
– Bending capacity
– Shear capacity
– Web crushing
– Combination of the above
• Serviceability Limit State
– Deflection limit: D <=Ds/10
• Typically capacities are thoroughly Strength of steel deck under testing
tested by manufacturers in http://www.newsteelconstruction.com
laboratories.

17
Composite slabs in composite stage
• This refers to the state when
concrete is hardened on steel sheet.
• Concrete resist compression and
steel (steel sheet) resists tension.
• The above only happens when
tension zone is in the bottom, i.e.
region of positive bending moment.
• In regions of negative (hogging)
moment the steel sheet has no
function and tension must be
resisted by reinforcements.

18
Simply supported slab (1 span)
• Consider a simple situation where
the composite slab is simply
supported and loaded with UDL as
shown
• Entire span is under positive
bending (or sagging) moment
Shear Force Diagram
• Concrete is stressed in
compression and steel sheet is
stressed in tension

Bending Moment Diagram

19
Composite slab in bending
• Shear connection between concrete and
steel is observed to be a crucial factor
• When a simply supported comp slab is
loaded, it may fail in 3 modes.
• Mode 1 – Bending (flexural) failure
• Mode 2 – Shear bond failure
• Mode 3 – Vertical shear failure
• Design criterion and capacity may be
determined by testing
• Standard testing procedure is described
in AS2327

20
Standard composite slab tests
• Described in 16.4 in HK code
• Longitudinal shear behavior (mr and kr) is determined experimentally.

21
Composite slab tests

22
Moment capacity by calculations:
Positive Moment
• Design flexural resistance
Described in 10.4.5.3.
• This calculation assumes full shear-
bond capacity below:

23
Continuous slab (>1 span)
• Composite slabs typical span over more than 2
supports, creating “continuous slabs”.
• Negative (hogging) moment over interior supports

Spanning over 2 interior


support is very common
~3x4=12m
(photo: Rick Chan)

24
Moment capacity by calculations:
Negative Moment
• Under hogging moment the steel deck is ineffective to take up tension
(because tension in on the top side)
• Tension is resisted by reinforcement bars
• The HK Steel Code does not provide design equations, users are refered to
HKCC.

25
Serviceability requirements
• See 10.4.5.4
• Deflection of composite slabs due to imposed load is Ls/360 or 20mm
whichever is less.
• Calculation is made using service load Wserv, which self-weight of slab is
excluded.

26
Detailing according to HK code
• The code has specific requirements on (1) Slab thickness, (2) arrangement of
reinforcement, (3) size of aggregates in concrete and (4) concrete cover.
• See 10.4.6
• Curtailment and lapping of reinforcement must conform to HK Concrete Code
• Construction details requirements in 10.4.7, particularly it ensure sufficient
bearing widths.

27
Manufacturers’ capacity tables
• Manufacturer’s catalogue provide capacity tables which engineers may choose
appropriate deck and concrete thickness according to project needs.
• Step 1: Estimate imposed (live) loads
• Step 2: Structural arrangement – simple, continuous?
– Top reinforcements are required to resist hogging (negative) moment above
supports. When bending moment is negative, the steel deck is in compression
zone, it has no structural strength.
– Additional reinforcement is required for fire resistance period: 60, 90, 120, 180,
240min.
– Span = spacing between supporting beams
• Step 3: Base on thicknesses in Step 2, determine requirements of temporary props
during construction.

28
Example on using span tables
Requirements
• Spacing between secondary
beams is 2.766m
• 6 span continuous
• Imposed load = 2.5kPa
• Superimposed dead load = 0.1kPa
• Fire resistance = 120min

29
Example on using span tables
• Assume we use Lysaght Bondek
https://professionals.lysaght.com/sites/default/files/LysaghtBondekDes
ignandConstructionGuideJuly2016.pdf

• Assume slab thickness = 120mm


conforming to 10.4.6(1)
• Concrete grade = C35
• Assume no props during
construction, and 0.75mm BMT
• Yield strength = 550N/mm2
• Note max. yield strength is
550N/mm2 and max sheet thickness
in HK is 0.70mm (Cl. 10.1.5)

30
• (Cl. 10.4.4.4) Deflection limit in construction stage: D <=Ds/10
• D <= 120/10=12mm
• Converts to Span/230.5
• Now, check formwork deflection: max. span for L/240 is only 2550mm.
• We must increase thickness of sheet to 1.0BMT

p.13 of Bondek Design Manual

31
• Next, for composite stage, check Interior Span Table
• Requires 210mm2/m reinforcement over support

32
• Next, for composite stage, check End Span Table
• Also requires 210mm2/m reinforcement over support

33
Converting 210mm2/m reinforcement = T10 and 300mmc/c (area is
260N/mm2)

34
• Detail as per manufacturer’s recommendation
• In addition, wire mesh for anti-crack purpose (shrinkage causes crack).
Requirement is 0.1% of cross sectional area of concrete (10.4.5.6)

35

You might also like