Method Statement For Installation of The CRAC Unit For
Method Statement For Installation of The CRAC Unit For
MEP Services
Contents:
1. Scope of Works.........................................................................................................................................4
2. References................................................................................................................................................5
3. Definition & Abbreviations.........................................................................................................................6
4. Personnel..................................................................................................................................................6
5. Resources Mobilization Plan.....................................................................................................................8
6.Equipment and Tools.................................................................................................................................9
7.Site Procedure...........................................................................................................................................9
8.Method Statement....................................................................................................................................10
8.1 Materials ....................................................................................................................................10
8.2 Installation Procedures…….……….………………………………………………………………………. 10
8.2.1 Storage / Protection .................................................................................................................10
8.2.2 Preparatory Work …………………………………………………………………………………….……11
8.2.3 Installation ……………………………………………………………………………………………….…11
8.2.4 Pre-Installation Operation Check ...............................................................................................22
9. Quality Assurance / Quality Control........................................................................................................22
10. Health and Safety / Risk Controls.........................................................................................................22
10.1 Personal Protective Equipment (PPE) Requirements ........................................................................22
10.2 Additional PPE / RPE Requirements..................................................................................................23
10.3 Personnel Training Certification .........................................................................................................23
10.4 Site Security........................................................................................................................................23
10.5 First Aid Facilities................................................................................................................................23
10.6 STAART Talks (Daily Briefing) ...........................................................................................................23
11. Environmental Measures.....................................................................................................................24
11.1 Waste Management........................................................................................................................24
11.2 Waste Water management……………………………………………………………………………..….24
11.3Noise Pollution……………………………………………………………………………………………………………………………..24
) REFERENCES:
• BS EN 15255 Energy Performance of buildings. Sensible room cooling load calculation
• CIBSE Guide B2 Ventilation and air conditioning part 1,2,3 & 5
• CIBSE Guide B HVAC Services
• ER Vol 6 - Section 13.2.3.5
• MAR Ref No.: M006-GDB-MEP-MAR-00193
• Approved Design Drawings
• Approved Technical Specifications
• Inspection & Test Pan ITP : M006-GDB-MEP-ITP-00055
• International Standards Involved:
o NFPA 90A- Installation of Air conditioning & Ventilation system.
o NFPA 70A – National Electrical code
o AMCA – Laboratory Method of testing fans for rating
o ASHRAE Standard 52-68 - American Society of Heating, Refrigerating, and Air-
Conditioning Engineers
o BS 746 – Gas Meter Union and adaptor
o NEMA – Motor and electrical installation
o ISO – Certification of International Organization for standardization
o BS CP 352 – Mechanical Ventilation and air conditioning in Buildings.
o QGEWC - Qatar General Electricity & Water Corporation
o QCDD & LPC Certified & UL Listed.
o CIBSE and BSRIA application guide
• Submittals :
• Relevant Material Approval Request
• Project Safety Plan M006-GDB-HSE-PLN-00001
• Project Environmental Plan M006-GDB-EMS-PLN-00001.
• Project Quality Plan M006-GDB-QMS-PLN-00002
• Sustainability Management Plan M006-GDB-SUS-PLN-00001
• GSAS Design Assessment Standard – Railways
• GSAS Construction Assessment Standard
• Design / Installation /Combined Service Drawings
• QA/QCEngineer/Inspectors
Identify the Projects Specific Quality Requirements, Develop the Project Specific Quality,
Inspection and Test Plan (ITP), Operational and Control procedures, Mechanism and Forms
and ensure effective implementation of Method Statement & ITP. Responsible for the work of
entire Quality Assurance, Quality control and inspection programs on site. Produces all quality
related documents and necessary quality reports as requested by ALYSJ JV and the client in
relation to this work. To coordinate in formalizing the Method Statement with the Site Engineers
to describe the job specific quality control work for each stage / activity.
• HSSEManager
Responsible for entire HSE matters and preparing Risk Assessment (RA) in line with method
statements for particular activity. Liaison with Engineer and Engineer’s Assistant for HSE
issues. Monitoring the HSE requirements as per Project Specifications and
Engineer/Engineer’s Assistant requirements.
• SafetyEngineer(Officer)
Ensure that all workers have a safe working place, advice safe system of work and provide
adequate instructions, training and supervision to enable employees to work in safety. Carry
out site survey on daily basis to ensure that the HSE methods of working are in operation &
that all regulations are being observed. Report, determine & analyse the cause of any accident
or dangerous occurrence and recommend measures for preventing recurrence.
• Environmental Manager
Responsible for entire environmental matters and preparing Environmental Risk Assessment
(ERA) in line with method statements for particular activity. Liaison with Engineer and
Engineer’s Assistant for environmental issues. Monitoring the environmental requirements as
per Project Specifications and Engineer/Engineer’s Assistant requirements.
• Environmental Engineer
Monitoring works implementation as per project’s environmental requirements. Advice for
environmentally sound operations and provide adequate instructions, training and supervision
to enable employees to work avoiding environmental impacts. Carry out site survey on daily
basis to ensure that the environmental mitigations measures of working are in operation & that
all regulations are being observed. Report, determine & analyse the cause of any
environmental incidence and recommend measures for preventing recurrence.
• Surveyor
Chief surveyor will be in-charge of the survey department and responsible for entire survey
works. He will lead the survey team and will coordinate with all the concerned parties and
ensure survey works is in time and with proper quality. The surveyor will be responsible for all
survey work and will report to chief surveyor.
• Site Engineer
Adheres to the Project specific method statements, procedures, quality requirements and
inspection programs and HSE instructions to get the activities performed to Client’s satisfaction
with full coordination with the HSE and Quality personnel.
• Foreman/Work Supervisor
Responsible for daily activities and resources (labour, machinery, material etc.) are effectively
utilized and monitored in order to achieve HSE and Quality requirements.
• Workforce(Labour)
Carry out their work under direct supervision by their Foreman and Charge Hand and under
instruction from the Site Engineer to ensure all works are undertaken in a safe manner. The
workforce to attend a daily Tool Box Talks and morning task briefs prior to starting any new
works, EHS (Environmental Health Standard) plans and Policies. The workforce shall receive
a full Project briefing and site rules induction prior to commencing any work on site.
5) RESOURCESMOBILIZATION PLAN:
Prior site mobilization careful planning and preparation as per works programme will be
implemented. These include appropriation of sufficient number of staffs and labour’s, equipment,
materials, site offices and facilities/services. Actual mobilization to site is dependent on accessibility
to site and availability of space allocations. Contractor will have to advise ALYSJ the schedule and
requirements for site mobilization. Meanwhile, ALYSJ after a thorough study and careful planning
must confirm immediately with contractor the schedule requirements in order to mobilize within
sufficient period of time. Appropriate and sufficient temporary services such as power, lighting,
waters, communications, ventilations, lifting cranes, trolleys, working areas, scaffolding shall be
provide by ALYSJ.
7) SITE PROCEDURE
It is of crucial importance that the works are conducted in accordance with all design criteria. When
work is ready to be inspected the Site Supervisor and QC inspector inspect the works as per this
method statement and Test Pan (ITP). If any deviation, corrections will be requested to rectify. It is
checked and submitted to ALYSJ JV by Subcontractor Site Team.
8) METHOD
STATEMENT
8.1 Materials
All material delivered to the site must be according to the make and relevant model numbers
approved by consultant and client. All materials when delivered will be first inspected by the
store in charge/site in charge, to check that it is in accordance with the site requirement, the
approved design and material qualification and also that it is free from any damage caused
during transportation to site. Delivery documentation shall be checked for completeness.
Defective or damaged materials shall either be returned to their supplier’s facility or stored on
site at a suitable quarantine location. The inward inspection of materials will be carried in
accordance with relevant QA/QC procedure. Materials should be kept in a location and
condition according to the MSDS recommendations before and after the material inspections.
No materials will be permitted to enter the works locations without being inspected on arrival to
the site.
The unloading of CRAC units and its related materials will be carried out at site using a
crane/forklift. Whenever a crane is used, a licensed operator under project safety rules and
regulations will operate it. If a crane is not available at site, the materials will be manually
unloaded at the job site. It should be noted that the materials used in this work are of valuable
nature and that they shall be stored in secure location and access to these materials shall be
strictly controlled.
The make of materials used at site shall conform to the requirement of approved material
submittal. The materials used at site shall conform to the requirement of approved site
environmental plan.
8.2 Installation Procedure
8.2.1 Storage / Protection:
CRAC UNIT and Accessories shall be unloaded with care to avoid any damages. If they
are shipped in packs or pallets, each pack of pallet shall be lifted individually with suitable
lifting equipment. Every precaution shall be taken to preserve their cleanliness before
installation. Store in accordance with manufacturer’s instructions, properly protected from
construction activities and weather conditions – As recommended by manufacturer it is
from 20-50 o C (Degree Celsius). Keep the equipment in upright position with proper
covering until the installation of designated location at site.
Follow proper Guidelines and Instruction manual from manufacturer while unloading and shifting of
the CRAC UNIT.