100% found this document useful (2 votes)
231 views

Basis of Design

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
231 views

Basis of Design

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 71

PROJECT AND LOCATION CLIENT DOCUMENT NO.

PROVISION OF
SN-057-T-N-0017-00
REPLACEMENT/UPGRADING OF LIQUID
METERING AND SOLID SULFUR JOB NUMBER Rev. SHEETS / OF
WEIGHING SCALE AT MELLITAH C/047/MCX/23 P1 Page 1/70
COMPLEX

Mellitah Oil & Gas B.V – Mellitah Complex


Sabratha Libya
SENSIA DOCUMENT NO.
4017109-A23-001 Rev. 1

BASIS OF DESIGN - METERING, SAMPLING &


CONTROL PACKAGE

P1 15/04/24 Issued for Comment JM MJD BH


Rev Date Description Prepared Verified Approved
PROJECT AND LOCATION CLIENT DOCUMENT NO.

PROVISION OF REPLACEMENT/UPGRADING
SN-057-T-N-0017-00
OF LIQUID METERING AND SOLID SULFUR
WEIGHING SCALE AT MELLITAH COMPLEX JOB NUMBER Rev. SHEETS / OF

C/047/MCX/23 P1 Page 2/70


Mellitah Oil & Gas B.V – Mellitah Complex
Sabratha Libya
SENSIA DOCUMENT NO.
4017109-A23-001 Rev. 1

Rev. Para. Revision Description

P1 Issued for Comment

Page 2 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 3/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

TABLE OF CONTENT
1. INTRODUCTION ...............................................................................................................7
1.1 Project Overview and Background ...................................................................... 7
1.2 Scope Of the Document ...................................................................................... 8
2. GENERAL .........................................................................................................................9
2.1 Definitions .......................................................................................................... 10
2.2 Acronyms ........................................................................................................... 10
2.3 System of measurement .................................................................................... 12
2.4 Field location and environmental data ............................................................... 14
2.4.1 General .............................................................................................. 14
2.4.2 Design Temperatures for Equipment and Piping............................... 14
2.4.3 Relative humidity ............................................................................... 14
2.4.4 Air barometric pressure ..................................................................... 15
2.4.5 Wind .................................................................................................. 15
2.4.6 Basic Wind Speed & Exposure for Structural Design ........................ 15
2.4.7 Rain and snow ................................................................................... 16
2.5 Utilities available ................................................................................................ 16
2.6 Project life .......................................................................................................... 16
3. STANDARDS ..................................................................................................................17
3.1 International codes and standards .................................................................... 17
3.2 Eni standard and general specifications ............................................................ 17
4. PROCESS DESIGN DATA .............................................................................................18
4.1 Operating & Design conditions .......................................................................... 18
5. MAIN ASSUMPTIONS ....................................................................................................21
5.1 H2S Levels ........................................................................................................ 21
5.2 Hammering/Vibration issues .............................................................................. 22
5.3 Corrosion/erosion of existing systems ............................................................... 23
5.4 Pipeline Mixing for Sampling ............................................................................. 24
5.5 Pump Types used on Sampling Systems .......................................................... 25
6. PROCESS DESIGN CRITERIA ......................................................................................26
6.1 Equipment and Lines ......................................................................................... 26

Page 3 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 4/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

6.2 Piping design ..................................................................................................... 26


6.3 Instrument Tubing & Fittings .............................................................................. 26
6.3.1 Instrument Tubing ............................................................................. 26
6.3.2 Instrument Fittings ............................................................................. 27
6.3.3 Pressure Take off positions ............................................................... 27
6.4 Painting .............................................................................................................. 27
7. FLOW MEASUREMENT DESIGN CRITERIA ................................................................28
8. PIPING & LAYOUT DESIGN CRITERIA ........................................................................30
8.1 Bypass ............................................................................................................... 30
8.2 Metering ............................................................................................................. 30
8.3 Sampling & Analysis .......................................................................................... 31
9. INSTRUMENT AND CONTROL DESIGN CRITERIA.....................................................33
9.1 Metering Control System Scope of Work .......................................................... 33
9.2 Flow Computer System 1 .................................................................................. 35
9.2.1 Summary ........................................................................................... 35
9.2.2 Flow Computers ................................................................................ 35
9.2.3 Propane 4E-220-JM-001 Hardware Arrangement ............................. 36
9.2.4 Butane 4E-220-JM-002 Hardware Arrangement ............................... 36
9.2.5 Condensate 4E-220-JM-003 Hardware Arrangement ....................... 37
9.2.6 Software Applications system 1 ........................................................ 38
9.2.7 Metering Panel .................................................................................. 41
9.2.8 Design Summary ............................................................................... 41
9.2.9 Panel Layout ..................................................................................... 43
9.3 Flow Computer System 2 .................................................................................. 44
9.3.1 Summary ........................................................................................... 44
9.3.2 Flow Computers ................................................................................ 44
9.3.3 El Feel 85-220-JM-007 Hardware Arrangement................................ 45
9.3.4 Wafa 85-220-JM-009 Hardware Arrangement .................................. 45
9.3.5 Crude Oil Export 85-220-JM-008 Hardware Arrangement ................ 46
9.3.6 Hardware Arrangement ..................................................................... 47
9.3.7 Software Applications system 2 ........................................................ 48
9.3.8 Metering Panel .................................................................................. 52

Page 4 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 5/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

9.4 Metering Supervisory Computer ........................................................................ 53


9.4.1 MSC Hardware .................................................................................. 53
9.4.2 MSC Software Functionality .............................................................. 53
10. MATERIAL DESIGN CRITERIA .....................................................................................56
11. MECHANICAL DESIGN CRITERIA ...............................................................................56
12. ELECTRICAL DESIGN CRITERIA .................................................................................57
12.1 Instrument Cable ............................................................................................... 57
12.2 Cable Glands ..................................................................................................... 57
12.3 Cable Support .................................................................................................... 57
12.4 Cable Segregation ............................................................................................. 58
12.5 Junction Boxes .................................................................................................. 59
12.6 Ingress Protection .............................................................................................. 59
12.7 Certification ........................................................................................................ 59
13. HSE DESIGN CRITERIA ................................................................................................60
13.1 General .............................................................................................................. 60
13.2 Firefighting Equipment ....................................................................................... 60
13.3 Risk Assessment ............................................................................................... 60
13.3.1 HAZID Session .................................................................................. 60
13.3.2 HAZOP Session ................................................................................ 61
14. CIVIL DESIGN CRITERIA ..............................................................................................62
14.1 Earthwork .......................................................................................................... 62
14.1.1 Site Preparation ................................................................................. 62
14.1.2 Destruction Procedure for existing concrete...................................... 62
14.1.3 Excavation ......................................................................................... 63
14.1.4 Backfilling around structure ............................................................... 63
14.1.5 Concrete work specifications ............................................................. 63
14.1.6 Project specifications ......................................................................... 64
14.1.7 Reinforcement ................................................................................... 64
14.1.8 Fabrication and Installation of formwork ............................................ 65
14.1.9 Embedded items ............................................................................... 65
14.1.10 Placement and concreting ................................................................. 66
14.1.11 Stripping of forms: Cast in place concrete works .............................. 67

Page 5 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 6/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

14.1.12 Curing and protecting of concrete ..................................................... 67


14.1.13 Concrete surface repair ..................................................................... 67
15. APPENDIX 1 - INTERNATIONAL CODES AND STANDARDS ....................................68
16. APPENDIX 2 - ENI STANDARDS AND GENERAL SPECIFICATIONS ........................69

SN to add Para. for Material Selection Criteria

Page 6 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 7/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

1. INTRODUCTION
1.1 Project Overview and Background
The Mellitah Plant receives crude oil, gas and associated condensate from Wafa and El-
Feel by pipeline. Both inputs are metered by separate independent systems. Oil is
processed to remove water and entrained gas before being sent to the storage tanks.
Stored oil is exported to tankers via the oil export metering system (4E-220-JM-008).
Condensate and LPG is received at the Mellitah plant from Wafa and NC41 via separate
pipelines.
The Wafa product is a mix of crude oil and NGL (LPG, C5+ and oil), NC41 product is
condensate only. Wafa product is processed to separate; stabilised oil, propane and
butane then metered and stored in separate tanks. The oil is exported from the oil storage
tanks mentioned in the previous paragraph. Propane and butane are exported separately
via independent metering systems.
NC41 condensate is treated at the plant to stabilise and stored in allocated condensate
tanks. The stored condensate is exported via an export metering system. Gas is received
at the plant from Wafa and the Sabratha platform via pipeline.

Figure 1 - Mellitah Complex

Mellitah Oil & Gas B.V. (COMPANY) intends to up-grade/replace the existing fiscal
Metering systems of Mellitah Complex to the most suitable metering system to increase
the accuracy and reliability and decrease the uncertainty.
The objective of the COMPANY is to improve the existing metering system (fiscal) by
providing new or by calibration/upgrading the existing metering system in compliance with
latest technology & in accordance with International Standards.

Page 7 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 8/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

1.2 Scope Of the Document


Scope of this document is to provide the main data, assumptions and design criteria for
the replacement/upgrading of the Liquid metering, prover, sampling systems and solid
sulphur weighing scale at Mellitah complex. The following major items are covered under
the scope:

• Export Propane Metering and Sampling, 4E-220-JM-001 (Note 1)


• Export Butane Metering & Sampling, 4E-220-JM-002 (Note 1)
• Export Condensate Metering & Sampling 4E-220-JM-004 (Note 1)
• El Feel reception Crude Oil Metering & Sampling 85-220-JM-007 (Note 2)
• Crude Oil Export Metering & Sampling 85-220-JM-008 (Note 1)
• Wafa reception Crude Oil Metering & Sampling 85-220-JM-009 (Note 2)
• Solid Sulphur Weighing Scales 6E-632-WQA-651
• Export Propane Metering Bypass Loop 4E-220-JM-001 (Note 3)
• Export Butane Metering Bypass Loop 4E-220-JM-002 (Note 3)
• Export Condensate Metering Bypass Loop 4E-220-JM-004 (Note 3)
• El Feel reception Crude Oil Metering Bypass Loop 85-220-JM-007 (Note 4)
• Crude Oil Export Metering Bypass Loop 85-220-JM-008 (Note 3)
• Flow Computer System 1 will contain the following metering:
• Propane Metering (4E-220-JM-001)
• Butane Metering (4E-220-JM-002)
• Condensate Metering (4E-220-JM-004)
• Small Volume Prover
• Flow Computer System 2 will contain the following metering:
• El feel Metering (85-220-JM-007)
• Wafa Oil Metering (85-220-JM-009)
• Crude Oil Export Metering (85-220-JM-008)
• Small Volume Prover
• Metering Supervisory Computer:
• Providing supervisory functions for all of the above metering
• Wazen Oil Site Work

Page 8 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 9/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

Notes:
1. Replacement Metering Skid and Sampling System.
2. Upgrade of the existing Metering System and new Sampling System
3. Temporary Bypass Loop
4. Permanent Bypass Loop
Information initially supplied by MOG and subsequently gathered and verified through
multiple site visits are considered in generating this document. Document 4017109-A22-
001-02 (SN-057-T-Z-0004-00) MCX Site Survey Report (Sensia & SGS) is critical in
defining the final design.

2. GENERAL

Page 9 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 10/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

2.1 Definitions

COMPANY Mellitah Oil & Gas BV


CONTRACTOR Sensia UK Limited
LOCATION Mellitah Complex, Libya
PROJECT Provision of replacement/upgrading of liquid metering and solid
sulphur weighing scales at Mellitah complex.

2.2 Acronyms
AC Alternating Current
API American Petroleum Institute
BVS Block Valve Station
BDV Blowdown Valve
CCTV Closed Circuit TV
CPU Central Processing Unit
CR Control Room
DC Direct Current
DI Digital Input
DO Digital Output
DPDT Double Pole Double Throw
ESD Emergency Shut Down
F&G Fire and Gas system
FEED Front End Engineering Design
FO Flow Orifice
FOC Fiber Optic Cable
HMI Human Machine Interface
HP High Pressure
HVAC Heating Ventilation Air Conditioning
IP ICSS Mechanical protection Integrated Control and Safety System
LAN Local Area Network
LCP Local Control Panel
LGCS Local Gas Compressor Station
LED Light Emitting Diode
LP Low Pressure

Page 10 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 11/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

LV Low Voltage
MFA Manual Fire Alarm push button
MAOP Maximum Allowable Operating Pressure
MAOT Maximum Allowable Operating Temperature
MGCS Mellitah Gas Compressor Station
MOT Maximum Operating Temperature
OCS Operator Control Station
P&ID Piping and Instrumentation Diagram
PC Personal Computer
PCS Process Control System
PLC Programmable Logic Controller
PSD Process Shutdown
PSV Pressure Safety Valve
PVC Polyvinyl Chloride
RTD Resistance Temperature Detector
RTU Remote Terminal Unit
SCADA Supervisory Control and Data Acquisition System
SDV Shut-Down Valves
SI International System of Units
SPDT Single Pole Double Throw
UPS Uninterruptible Power Supply
WAT Wax Appearance Temperature
XLPE Cross-linked Polyethylene

Page 11 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 12/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

2.3 System of measurement


The official language of the Project is English.
The units of measurement to be used within the Project will be as per the following table.
Concerning the system of units, in principle the SI measurement system will be applied. All
derived units (multiple, sub-multiple or combination) may also be used.

However, the following reference conditions and specific selections will be used.

REFERENCE TEMPERATURE °C PRESSURE BARA


Standard Conditions 15 1
Normal Conditions 0 1

QUANTITY NAME OF UNIT SYMBOL


Amount of substance kilogram mole kmol
Capacity cubic meters m3
Concentration, mass parts per million, mass ppm w
Concentration, volume parts per million, volume ppm v
Current ampere A
Density Kilograms per cubic metre kg/m3
Density API Gravity ° API
Density Specific Gravity Sp.Gr.
Electric current Ampère A
Electric potential Volt V
Force Newton N
Frequency hertz Hz
Gas and vapour flowrate (vol.) Standard cubic metres per hour Sm3/h
Gas and vapour flowrate (vol.) Standard cubic metres per day Sm3/d
Illuminance lux lx
Insulation thickness millimeters mm
Length meters m
Length millimeters mm
Liquid flowrate (mass) kilograms per hour kg/h
Liquid flowrate (volume) litres per hour l/h
Liquid flowrate (volume) cubic metres per hour m3/h
Mass kilogram kg
Molecular weight kilogram per kilogram mole kg/kmol

Page 12 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 13/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

Noise decibel dB(a)


Piping nominal diameter inches NPS
Piping standardisation ASME
Piping thickness schedule SCH
Plane angle degree deg
Plane angle minute '
Plane angle second "
Power kilowatt kW
Pressure Bar bar
Pressure Pound square inch Psi
Radiation intensity Watt per square metre W/m2
Resistance Ohm Ω
Resistivity Ohm metre Ω/m
Speed - angular degrees per second deg/s
Speed – linear metres per second m/s
Speed - rotating revolutions per minute rpm
Stress Newton per square millimetre N/mm2
Temperature degree Celsius °C
Temperature Kelvin K
Time second s
Time minute min
Time hour h
Viscosity - dynamic centi-Poise cP
Viscosity - kinematic centi-Stocks cSt
Voltage volts V

Page 13 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 14/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

2.4 Field location and environmental data

2.4.1 General
Installation Type Coastal, Suitable for Offshore
environment
Atmosphere Tropical
Ambient Temperature 2.5 to 50.2°C
Soil Temperature (depth 1.5m) 6 to 30°C
Relative Humidity 26 to 97%
Solar Radiation Systems supplied with sun shades
Control Room Safe Area/Clean
Earthquake Not considered

2.4.2 Design Temperatures for Equipment and Piping


T Annual cumulative
frequency of non-
exceedance:
Wet bulb design temperature er: 28° C 99.99%
Dry bulb design temperature for cooling 44° C 99.99%
tower:
Design temperature for air coolers: 44° C 99.99%
Design max. temperature for cold insulation: 44° C 99.99%
Design dew point temperature: 24.7° C 99.6%
Design min. temperature for hot insulation: 3° C 99.99%
Annual probability
of non-
exceedance
Dry bulb design temperature for electrical 50° C 99.8%
rating:

2.4.3 Relative humidity


• Minimum value: 26%
• Maximum value: 97%
• Design values for:
• air fans, compressors and blowers: 60%
• insulation thermal calculations: 70%

Page 14 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 15/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

2.4.4 Air barometric pressure


• Min: 936.7 hPa
• Max: 963.4 hPa

2.4.5 Wind

The frequency distribution of winds is the following:


• From EAST & E-N-E: 58%
• From WEST & W-S-W: 22%
• From NORTH: 18%
• From SOUTH: 2%

Therefore, the direction of prevailing wind is from EAST (angle sector 80° +
100°).

2.4.6 Basic Wind Speed & Exposure for Structural Design

The Uniform Building Code requires the basic wind speed for structural
design to be taken as the greater of:
• the "fastest-mile wind speed associated with an annual probability of 0.02
measured at 10 meters above grade"
• the 70 mph (112.7 km/h) minimum value set forth in Table 16-F of UBC.

Statistical evaluation of Zuara wind records of ten years indicates that the
latter value should be assumed as basic wind speed.

Notwithstanding the above, the Basic Wind Speed to be taken for Mellitah
shall be:
• 145 km/h and
• qs = 1.0 kN/m2 is the corresponding wind stagnation pressure.

The exposure shall be taken as "C" (flat and generally open terrain extending
0.81 km or more in any direction).

Wind erosion due to sandstorms has not been considered.

Page 15 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 16/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

2.4.7 Rain and snow


• Maximum rainfall recorded in 10 minutes: Not available.
• Maximum rainfall recorded in 1 hour: Not available.
• Maximum rainfall recorded in 12 hours: Not available.
• Maximum rainfall recorded in 24 hours: 51mm.
• Maximum snow depth: N/A
• Design intensity duration curve for sewer design 1=18.47 (t/60)
• Design snow load: N/A
• Run off coefficients:
• Roofs: 1
• Paved floors: 0.85
• Greens: 0.20

2.5 Utilities available


Electrical (single phase) 230V AC, 50 Hz
Electrical (3 phase) 400V AC, 50 Hz
DC Voltage 24V DC
Instrument Air Supply 5 barg minimum (12 barg maximum)

2.6 Project life


The project life is typically 25 years.

Page 16 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 17/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

3. STANDARDS
The following standards and specifications are considered in the design of the scope for
this project. Additional client specifications supplied after P.O. may also be considered if
necessary.

3.1 International codes and standards


For the applicable International Codes and Standards, see APPENDIX 1.

3.2 Eni standard and general specifications


For ENI Standards and General Specifications, see APPENDIX 2.

3.3 the NOC code

3.4 Other project Specifications reference

Page 17 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 18/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

4. PROCESS DESIGN DATA


4.1 Operating & Design conditions
The following summary of process data details the design limits for the project. They have
been collated from site supplied information and subsequent independent spot
samples/analysis. Design tolerances of ±0.5% for density and ±5% for viscosity has also
been added to determine a suitable operating range.

Notes:

1. Noted from ENI report J-63-M-O-0002-00 W L G P Wafa Plants Coastal Plant


Operating manual that condensate pump operating flow is 2800 m3h. The design is
being evaluated considering the 4700 m3/h indicated by off takers as operating flow
rate and maximum operating capacity of pumps (5600m3/h).

2. Minimum allowable operating pressures during flowing conditions for each of the lines
refers to the mainline pressure immediately upstream of the metering skids inlet
headers. The values (in orange) have been calculated based on many factors such as
estimated pressure drop across the metering skids, maximum RVP values advised and
minimum suction pressures required for the sampling pumps to operate safely.

Page 18 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 19/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

3. Maximum allowable operating pressures during flowing conditions for each of the lines
refers to the mainline pressure immediately upstream of the metering skids inlet
headers. The values (in orange) have been calculated to ensure that the sampling
pumps cannot exceed the stated design pressures even in a dead head fault condition.

4. Minimum design temperatures (where omitted from the data supplied by MOG in
orange) have been selected based on piping/equipment limits.

5. Max Operating temperatures: The values (where omitted from the data supplied by
MOG in orange) have been calculated as the maximum permissible operating
temperatures for these lines. For the Propane and Butane lines this value is based on
generic PT curves for (R600a / R-290) to ensure that the fluids remain liquified and
within the stated design pressures.

6. This data is collated from site supplied information and subsequent independent spot
samples/analysis. Design tolerances of -0.5% have been added to determine a suitable
minimum operating value for density.

7. This data is collated from site supplied information and subsequent independent spot
samples/analysis. Design tolerances of +0.5% have been added to determine a
suitable maximum operating value for density.

8. This data is collated from site supplied information and subsequent independent spot
samples/analysis. Design tolerances of -5% have been added to determine a suitable
minimum operating value for viscosity.

9. This data is collated from site supplied information and subsequent independent spot
samples/analysis. Design tolerances of +5% have been added to determine a suitable
maximum operating value for viscosity.

10. This data is collated from site supplied information and subsequent independent spot
samples/analysis. Design tolerances of -2% have been added to determine a suitable
minimum operating value for RVP.

11. This data is collated from site supplied information and subsequent independent spot
samples/analysis. Design tolerances of +2% have been added to determine a suitable
maximum operating value for RVP. The values defined for Propane and Butane
represent the maximum vapor pressure at the given maximum operating temperature.

12. All cells in yellow are not applicable.

13. Metering Skid Overrange capacities:

The systems currently have and overrange capability based on the maximum operating
flowrate versus the design flowrate as follows:

Page 19 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 20/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

Propane 4E-220-JM-001 - +22%

Butane 4E-220-JM-002 - +26%

Condensate 4E-220-JM-004 - +30%

El Feel 85-220-JM-007 - +12%

Crude Oil Export 85-220-JM-008 - +38%

Wafa Crude Oil 85-220-JM-009 - +240%

Normally a system overrange is around 10 to 30%. During detail design the Crude Oil
Export & Wafa Crude Oil systems will be re-evaluated to see if the design can be
optimised.

Page 20 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 21/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

5. MAIN ASSUMPTIONS
The main assumptions are reported in following paragraphs (some of these items have
previously been discussed in the site survey report):
• H2S Levels
• Hammering/Vibration issues
• Corrosion/erosion of existing systems
• Pipeline Mixing for Sampling

• Pump Types used on Sampling Systems

5.1 H2S Levels


The H2S existence and potential leak was discussed with different relevant MOG
departments including Health and Safety, Environment, Fire and Gas and operations.
Several random readings were recorded at different plant locations during the site survey.
There are multiple H2S monitors installed at different locations around the MOG gas plant.
These monitors are set to alarm at when the H2S concentration reach 10 ppm. MOG safety
procedures are to evacuate the plant if the H2S concentration reaches 15 ppm.
All random readings recorded during the site survey using certified H2S gas detector were
below 0.2 ppm.
There was one incident of H2S leak in April 2010 when the gas flare was switched-off
because of fuel gas failure during this incident the H2S recorded was around 1300PPM.
To minimize the equipment corrosion and increase the systems life span the new metering
skids to be designed for an offshore environment.
This design for offshore would involve using marine environment instruments housings,
Stainless steel cable trays and Stainless steel Junction boxes. In addition, all equipment
will have a good quality offshore coating system with good quality checks during
production.

It should be noted that good onsite maintenance activities are also


crucial to the lifespan of the equipment with paint touch ups being
carried out as and when required.

In addition to the above NACE MR0175 / ISO 15156 requirements will be applied. (where
possible).

Page 21 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 22/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

5.2 Hammering/Vibration issues


(Condensate 4E-220-JM004 & Crude Oil Export 85-220-JM008)
This was investigated during the site visit in an attempt to determine the source of the
issues. Both skids had the same issue which occurred during ramp-up.

A thorough investigation was carried out on the following:


a. Inspection of the skid foundations.
b. Inspection of the off-skid supports upstream and downstream of the skid
c. Inspection of the skid supports
d. Review of the current operating procedures

The Crude oil system consists of qty 4 x 33% streams in a duty standby configuration. The
system design flowrate is 6600m3/hr which equates to 2200 m3/hr per stream. The startup
flowrate requested by the off-taker at 10,000bbl/hr (1590m3/hr)
From the information received by the system operators and by evaluating all process data
and upstream piping arrangement it was concluded that the source of hammering and
vibration is the high differential pressure across the streams flow control valves FCV’s
caused by very high flowrate.
The export pumps recycle line and FCV are too small even when fully open there are still
very high flow passing to the metering skid. During the start of tanker loading (ramping-up)
when the flowrate requested by the off-taker is around 10,000 bbls/hr (1590m3/hr) only
one stream is partially opened by the FCV at 35% open. The high flowrate from the export
pump will create very high back pressure across the FCV which in return lead to the high
vibration witnessed by the end user.

To eliminate the vibration, it is important to control the flow and pressure upstream the
metering skid by increasing the flow to pump recycling line and discharge tank.
One solution is to increase the size of the main recycle line FCV as well as the introduction
of pressure control valves at the new metering skid.
Also, the new metering system operation procedure should allow the system to start up
gradually and increase the flow low then build up gradually. Then at around 80% of the
max stream flow the next stream should open up as the flow increases. This practice would
avoid hammer and vibration.

Page 22 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 23/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

5.3 Corrosion/erosion of existing systems


During the site survey, a section of pipe was cut from an operating stream on the
Condensate Skid 4E-220-JM-004 for metallurgical analysis. This was due to concerns
regarding the high levels of H2S advised by the client.
It should be noted however that no H2S was found in the sample taken to the SGS
laboratory.
The material was sent to the SGS accredited laboratory for analysis. This included
chemical analysis and Microexamination.
The material was confirmed as API 5L Grade B pipe. The pipe was tested as 12” sch 40
with a wall thickness of 10.3mm and a corrosion allowance of 3mm.
The Microexamination showed the wall thickness to be 8.85 to 8.8mm. This would indicate
a corrosion of up to 1.45mm. However, API 5L pipe has a wall thickness tolerance for pipe
wall between 4 to 25mm of +0.15t to -0.125t. The minus value equates to – 1.3mm.
Therefore, the pipe from the manufacturer could have a minimum wall thickness of 10.3 -
1.3mm = 9mm. This means the corrosion could be between 0.15mm (9-8-85) and 1.45mm.
Sensia advise the corrosion/erosion inside the pipe sample tested is acceptable based on
the duration installed and the corrosion allowance of 3mm.

Page 23 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 24/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

5.4 Pipeline Mixing for Sampling


The pipeline mixing requirements are governed by the Manual of Petroleum Measurement
Standards Chapter 8.2 (API8.2) / ISO3171 sampling standards. Upon receipt of detailed
process properties (as detailed in section 4.1) we have now carried out detailed mixing
calculations to AnnexA of these sampling standards.
API8.2 Describes pipeline water dispersion as:

“The ratio of water concentration at the top of a horizontal


pipe C1 to that at the bottom C2 is used.
C1
A C1/C2 ratio of 0.9 to 1.0 indicates very good dispersion
while a ratio of 0.4 or smaller indicates poor dispersion with
a high potential for water stratification. C2

Calculations giving less than 0.7 should not be considered


reliable as coalescence of water droplets invalidates the
prediction technique.”

The following table summarises the results of these mixing sizing calculations:
Pump
Minimum C1/C2 Line Size Pump Power
Flowrate
Crude Oil Export 0.9 32” 212m3/hr 55kW
Wafa 0.9 12” 51m3/hr 30kW
El Feel 0.9 24” 92m3/hr 55kW
Condensate 0.74 26” 212m3/hr 55kW
Generally, Sensia will aim to size the mixing to achieve a C1/C2 ratio of 0.9 where possible.
In the case of Condensate above, due to the extremely low viscosity and density of the
fluid coupled with the large diameter of pipe section it is not possible to reach this figure,
however it is within the acceptable range as defined by API8.2 above.
The Condensate system will be further optimised to operate at the maximum operating
flowrate (as defined in section 4.1) to reduce the sampling uncertainty at maximum
flowrate.
The Propane and Butane systems do not require pipeline mixing. The Fast loop pumps on
each of these lines will be sized for a flowrate of 4-6m3/hr and will be fitted with 5.5kW
motors.

Page 24 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 25/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

5.5 Pump Types used on Sampling Systems


The pumps selected for use on the sampling packages shall be ASME/ISO standard
pumps.
The pumps are a magnetically coupled / seal less type pump and offer a distinct advantage
over traditional mechanically sealed pumps, especially in applications where H2S is
present.

Sensia have a long-proven track record of using this type of magnetically coupled / seal
less pump in Oil + Gas applications worldwide and it is our preferred choice over
mechanical sealed pump designs.
Mechanical seal pumps require complicated seal support systems, so by using the seal
less design the system is simplified and has much lower maintenance requirements /
longer service intervals.
The main wetted materials of construction for the pumps shall be stainless steel (casing
and impellor), Alloy C276 (containment shroud/shell) with silicon carbide internal bearings.
The design pressure of the pumps shall be 18.9 bar which is in accordance with the project
process data (see section 4.1)
The pumps shall be sized according to the required duty, as summarised in section 5.4

Page 25 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 26/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

6. PROCESS DESIGN CRITERIA


6.1 Equipment and Lines
Design pressure for all supplied equipment and lines shall be defined according to the
process conditions as defined in section 4.1

6.2 Piping design


All piping shall be designed in accordance with ASME B31.3
All supplied process piping will comply to the following Snamprogetti Piping classes:
• CA1BY (CS) shall be used on CL150 RF systems.
• EA1DY (LTCS) shall be used on CL300 RF systems.

Due to the possible presence of H2S, all piping components shall comply with NACE
MR0175 where possible.
Stress calculation report for piping shall be issued for MOG
All pressure retaining parts/assemblies shall be hydrotested at 1.5 times the design
pressure (minimum) for a minimum of 30 minutes. A hydro test procedure shall be provided
to cover this activity.
"SN to add Para. Tie-ins to existing Facilities
6.3 Instrument Tubing & Fittings
All instrumentation installation will be in accordance with the recommendations of BS 6739
“Instrumentation in process control systems: installation design and practice”. except
where otherwise specified by the customer.

6.3.1 Instrument Tubing

All tubing should be stainless steel to ASTM A269 TP316 and use stainless-
steel double ferrule compression fittings.

All tube cuts shall be deburred and cleaned ensuring any swarf/debris is
removed prior to installation.

All tube bends shall be formed using the correct size of hand tube bender.

Impulse lines shall be kept to a practical minimum length. The maximum


unsupported tubing length is 500mm. Tubing can be supported in cable tray
where needed. Plastic anti-corrosion type tube clamps with steel bolts shall
be used at regular intervals as spot supports.

Page 26 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 27/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

6.3.2 Instrument Fittings

All fittings shall be of Swagelok manufacture. Sizes shall be metric, 6mm or


10mm. Material of construction shall be 316/316L stainless steel.

All compression fittings will be installed in compliance with the manufacturers’


instructions. Personnel used for installation of these fittings shall have
undergone fitting and installation training and be in possession of a valid
certificate.

All threads (where possible) shall be NPT, sealed with liquid PTFE sealant,
PTFE tape shall not be used.

Instrument tube/fittings shall not be painted or coated.

6.3.3 Pressure Take off positions


Pipe Orientation Type Position
Horizontal Liquid Side or Bottom
Gas Top
Vertical Any Side

6.4 Painting
Painting of fabricated process pipework will be as per Client Paint System No. 004
(Uninsulated) and system No. 009 (Insulated). from 20000E05 (Ref 27591.ENG.CPI.STD)
- Protective Coatings. Coating systems chosen will be suitable for an off-shore
environment.

"Paragraph shall be added for Thermal insulation "Cold &Hott

Page 27 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 28/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

7. FLOW MEASUREMENT DESIGN CRITERIA


The metering systems and Bypass lines are designed in accordance with the Process
Data, Environmental conditions, ENI Specifications, NOC Measurement Codes and
international standards as identified in this document.

The systems been optimised since the bid phase and the configurations are as follows:

4E-220-JM-001 Propane Metering –

[ Duty N + standby 1 ] + [ master meter ] + [ Autosampler ], and a spare master meter for
calibration rotation.

All meters / master meters are Coriolis.

4E-220-JM-002 Butane Metering –

[ Duty N + standby 1 ] + [ master meter ] + [ Autosampler ] , and a spare master meter for
calibration rotation.

All meters / master meters are Coriolis.

4E-220-JM-004 Condensate Metering –

[ Duty N + standby 1 ] + [ master meter ] + [ Autosampler ] , and a spare master meter for
calibration rotation.

The Duty + standby Meters are Sensia SVM Ultrasonic Flow Meters. The Master Meter is
a Turbine Flow Meter.

A mobile Common Small Volume Prover is used to calibrate the master meter. The
stream meters are calibrated against the master meter.

85-220-JM-007 El Feel Crude Oil Metering –

[ Duty N + standby 1 ] + [ master meter ] + [ Autosampler ] , and a spare master meter for
calibration rotation.

Page 28 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 29/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

The Duty + standby Meters are Sensia SVM Ultrasonic Flow Meters. The Master Meter is
a Turbine Flow Meter.

A mobile Common Small Volume Prover is used to calibrate the master meter. The
stream meters are calibrated against the master meter.

85-220-JM-008 Crude Oil Export Metering –

[ Duty N + standby 1 ] + [ master meter ] + [ Autosampler ] , and a spare master meter for
calibration rotation.

The Duty + standby Meters are Sensia SVM Ultrasonic Flow Meters. The Master Meter is
a Turbine Flow Meter.

A mobile Common Small Volume Prover is used to calibrate the master meter. The
stream meters are calibrated against the master meter.

85-220-JM-009 Wafa Crude Oil Metering

[ Duty N + standby 1 ] + [ master meter ] + [ Autosampler ] , and a spare master meter for
calibration rotation.

All meters / master meters are Coriolis.

Page 29 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 30/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

8. PIPING & LAYOUT DESIGN CRITERIA


All piping systems will follow the P&ID and General arrangement drawings. The piping will
be designed in accordance with ASME B31.3.

8.1 Bypass

The bypass systems are designed to be installed around the existing skids which are being
upgraded or replaced.

The layouts will be designed and orientated to be easily installed on site whilst minimising
any site pipework modifications.

The systems will be designed taking into account piping design code requirements,
metering code requirements, access for operation, access for maintenance, access for
removal of equipment and environmental & process loadings.

Working environment requirements (ergonomics) will also be considered in the designs.

The system line sizes will be designed considering the process conditions, velocities,
pressure drops, noise and vibrations.

8.2 Metering

The metering systems are designed to be installed into existing skids which are being
upgraded or to be installed as new skids into the existing pipework.

The layouts will be designed and orientated to be easily installed on site whilst minimising
any site pipework modifications.

The systems will be designed taking into account piping design code requirements,
metering code requirements, access for operation, access for maintenance, access for
removal of equipment and environmental & process loadings. Final Design shall meet all
Company requirement
Working environment requirements (ergonomics) will also be considered in the designs.

The system line sizes will be designed considering the process conditions, velocities,
pressure drops, noise and vibrations.

Page 30 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 31/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

8.3 Sampling & Analysis


All piping systems for the sampling package shall be sized to provide optimum velocities
required to maintain sufficient turbulence to prevent water dropout.
The sampling packages can be broken down into 2 main types of system:

Fast Loop Sampling System CoJetix Sampling System


This applies to the systems NOT This applies to the systems
requiring pipeline mixing: requiring pipeline mixing:
• Butane • Condensate
• Propane • Crude Oil Export
• Wafa
• El Feel
All systems that require pipeline
mixing shall be sized in accordance
with ISO3171 Annex A

Common features
The sampling cabinet layouts shall be kept consistent (where possible) across all systems
to provide a common layout to provide operators with a more familiar feel.
To facilitate with this, all of the pipework contained within the sampling and analysis
cabinets shall be designed using class 300lb piping system regardless of whether the
system is 150 or 300lb. In the case of a 150lb system the pipe work would be uprated to
300lb.
The WIOM monitors shall not be fitted to the Butane/Propane systems but the pipe work
shall remain standard and these connections blinded off using blind flanges.
Dual density meters are supplied for the Crude oil and condensate systems, a single
density meter is supplied for Propane and Butane systems.
The sample receiver types used will be selected based on vapor pressure.
For high vapor pressure applications, the constant pressure cylinder (CPC) shall be used,
this is a piton balanced receiver which uses a pre-charge gas to maintain the sample at a
high pressure to prevent any gas breakout.
For low vapor pressure applications, the atmospheric type of receiver (PR) shall be used.

Page 31 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 32/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

System Receiver Type Volume (Litres)


Propane CPC 1
Butane CPC 1
Condensate CPC 4
El Feel PR 18
Wafa PR 18
Crude Oil Export PR 18

The pumps and related interconnecting pipework shall be designed 150 or 300lb according
to the system design pressure. The layout of these arrangements shall be kept similar
where possible.

Page 32 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 33/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

9. INSTRUMENT AND CONTROL DESIGN CRITERIA

The basis for design in relation to the metering control system for the Mellitah Complex
Metering Upgrade is detailed in the following sections of this document. The full design
details will be provided in the functional design specification (FDS) for the metering
control system.
Based on the revised system requirements, the scope of work for the control system is
understood to be as follows:

Metering Package name Description


Package
4E-220-JM-001 Propane Metering Skid New three stream Coriolis metering
skid with inline sample probe. Coriolis
master meter for proving.
4E-220-JM-002 Butane Metering Skid New three stream Coriolis metering
skid with inline sample probe. Coriolis
master meter for proving.
4E-220-JM-004 Condensate Metering New four stream USM metering skid
Skid with CoJetix system. Turbine master
meter for proving.
85-220-JM-007 El feel Metering Skid New two stream USM metering skid
with CoJetix system. Turbine master
meter for proving.
85-220-JM-008 Crude Oil Export Metering New four stream USM metering skid
Skid with CoJetix system. Turbine master
meter for proving.
85-220-JM-009 Wafa Metering Skid New two stream Coriolis metering
skid with CoJetix system. Coriolis
master meter for proving.
Small Volume Prover One common mobile prover will be
supplied to prove Condensate, Wafa
and Crude oil skids.

9.1 Metering Control System Scope of Work


The scope of supply will be broken down into two separate flow computer systems, which
will share a common Metering Supervisory Computer, as follows:
• Flow Computer System 1 will contain the following metering:
o Propane Metering (4E-220-JM-001)
o Butane Metering (4E-220-JM-002)
o Condensate Metering (4E-220-JM-004)
o Small Volume Prover

Page 33 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 34/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• Flow Computer System 2 will contain the following metering:


o El feel Metering (85-220-JM-007)
o Wafa Oil Metering (85-220-JM-009)
o Crude Oil Export Metering (85-220-JM-008)
o Small Volume Prover
• Metering Supervisory Computer:
o Providing supervisory functions for all of the above metering

Each flow computer system will be supplied in a stand-alone metering panel each located
in separate sub-buildings. Computer system 1 will be located in Area R1 and will contain
flow computers for metering Butane 4E-220-JM-001, Propane 4E-220-JM-002 and
Condensate 4E-220-JM-004. Computer system 2 will be located in Area Q2 and will
contain flow computers for metering El Feel 85-220-JM-007, Wafa 85-220-JM-009 and
Crude Oil 85-220-JM-008. The new panels will be installed in place of the existing
Daniels metering panels on site.
The Metering Supervisory Computer will be supplied in a free standing server rack, to be
located in the Main Control Room. Desk mount operator workstations and printers will be
provided to access the MSC software.

Page 34 of 70
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 35/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

9.2 Flow Computer System 1

9.2.1 Summary

Metering Flow Computer MSC Sampling


Package
Propane Metering Seven new S600+ The existing DMS+ One InSpec
(4E-220-JM-001) flow computers will will be removed and Controller will be
be supplied. Two per replaced with a new integrated with the
metering stream TruST MSC located TruST MSC.
(Duty/Standby) and in the Main Control
one Master Meter. Room.
Butane Metering Seven new S600+ One InSpec
(4E-220-JM-002) flow computers will One common Controller will be
be supplied. Two per duty/standby TruST integrated with the
metering stream Metering TruST MSC.
(Duty/Standby) and Supervisory
one Master Meter. Computer will be
Condensate Nine new S600+ supplied to handle One InSpec
Metering flow computers will all supervisory Controller will be
(4E-220-JM-004) be supplied. Two per functions. integrated with the
metering stream TruST MSC.
(Duty/Standby) and
one Master Meter.
Small Volume One new S600+ flow Sampling not
Prover computer will be applicable.
supplied for the
mobile prover.

All sampling I/O and functionality will be handled by InSpec Controllers, sampling however
can be initiated and controlled from the metering supervisor system (TruST).
A new 4 bay Rittal style metering panel will be supplied to house all of the above listed flow
computers and InSpec controllers for system 1.

9.2.2 Flow Computers


A total of twenty four S600+ flow computers will be supplied for Flow Computer System 1,
based on redundant flow computers per stream, in a duty/standby configuration plus
dedicated flow computers for the Master Meters for each skid. A separate flow computer
will be supplied with the application for the Small Volume Prover which will be used for
proving the Condensate master meter. New S600+ flow computers will replace the existing
S600 flow computers which are installed on site.

4017109-A23-001-01 35
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 36/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

The existing system handles valve control via ADAM Modules, however with the supply of
new S600+ flow computers these signals will be handled by the designated S600+ stream
flow computer.

9.2.3 Propane 4E-220-JM-001 Hardware Arrangement


Each flow computer will be supplied with the following hardware arrangement:

Flow Computer Quantity New Hardware


Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
1&2: • 1 x P152 CPU Board
Propane Metering • 1 x P153 Keypad/LCD
Stream 1 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
3&4: • 1 x P152 CPU Board
Propane Metering • 1 x P153 Keypad/LCD
Stream 2 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
5&6: • 1 x P152 CPU Board
Propane Metering • 1 x P153 Keypad/LCD
Stream 3 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 7: 1 S600+ Flow Computer Base Unit, complete with:
Propane Metering • 1 x P152 CPU Board
Master Meter • 1 x P153 Keypad/LCD
• 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board

9.2.4 Butane 4E-220-JM-002 Hardware Arrangement

Flow Computer Quantity New Hardware


Flow Computer 8&9: 2 S600+ Flow Computer Base Unit, complete with:
Butane Metering • 1 x P152 CPU Board
Stream 1 • 1 x P153 Keypad/LCD
• 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
10&11: • 1 x P152 CPU Board
Butane Metering • 1 x P153 Keypad/LCD
Stream 2 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board

4017109-A23-001-01 36
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 37/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

Flow Computer 2 S600+ Flow Computer Base Unit, complete with:


12&13: • 1 x P152 CPU Board
Butane Metering • 1 x P153 Keypad/LCD
Stream 3 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 14: 1 S600+ Flow Computer Base Unit, complete with:
Butane Metering • 1 x P152 CPU Board
Master Meter • 1 x P153 Keypad/LCD
• 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board

9.2.5 Condensate 4E-220-JM-003 Hardware Arrangement

Flow Computer Quantity New Hardware


Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
15&16: • 1 x P152 CPU Board
Condensate • 1 x P153 Keypad/LCD
Metering Stream 1 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
17&18: • 1 x P152 CPU Board
Condensate • 1 x P153 Keypad/LCD
Metering Stream 2 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
19&20: • 1 x P152 CPU Board
Condensate • 1 x P153 Keypad/LCD
Metering Stream 3 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
21&22: • 1 x P152 CPU Board
Condensate • 1 x P153 Keypad/LCD
Metering Stream 4 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 23: 1 S600+ Flow Computer Base Unit, complete with:
Condensate • 1 x P152 CPU Board
Metering Master • 1 x P153 Keypad/LCD
Meter • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board
Flow Computer 24: 1 S600+ Flow Computer Base Unit, complete with:
Small Volume • 1 x P152 CPU Board
Prover – Mobile • 1 x P153 Keypad/LCD
Prover • 1 x P144 I/O Board

4017109-A23-001-01 37
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 38/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• 1 x P148 Mezzanine Board


• 1 x P154 Prover Board

9.2.6 Software Applications system 1


The following new flow computer applications will be developed for Flow Computer System
1:
• Configuration 1 – Single Stream, Liquid Coriolis Metering
• Configuration 2 – Liquid Coriolis Master Meter Application
• Configuration 3 – Single Stream, Liquid USM Metering
• Configuration 4 – Liquid Turbine Master Meter Application
• Configuration 5 – Small Volume Prover Application
The first configuration will be loaded into all stream flow computers for the Propane and
Butane systems. The second configuration will be loaded into the two master meter flow
computers for Propane and Butane. The third configuration will be loaded into all stream
flow computers for the Condensate system. The fourth configuration will be loaded into the
master meter flow computers for Condensate. The fifth configuration will be loaded into the
small volume prover flow computer.
The following I/O is to be handled by each unique flow computer application:

Flow Computer Required I/O


Configuration 1: Stream I/O Signals:
All flow
computers • Coriolis Flow Rate (Single Pulse)
running the • Coriolis Diagnostics (Modbus RS-485)Kindly add also
single stream • Coriolis Density (4-20mA)
Flow control valve position
Coriolis • Stream Pressure (4-20mA)
(4-20mA input)
application • Stream Temperature (4-20mA)
(Propane & • Fast Loop Pressure (4-20mA) Flow control valve fault (DI)

Butane) • Fast Loop Temperature (4-20mA)


• Fast Loop Flow Rate (4-20mA)
• Fast Loop WIO Meter (4-20mA)
• Flow Control Valve (4-20mA Output)
• Mass Flow Rate (4-20mA Output)
• Standard Volume Flow Rate (4-20mA Output)
• Fast Loop Densitometer A (Frequency)
• Fast Loop Densitometer B (Frequency)
• Stream Inlet MOV – Open Command (DO)
• Stream Inlet MOV – Close Command (DO)

4017109-A23-001-01 38
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 39/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• Stream Inlet MOV – Open Status (DI)


• Stream Inlet MOV – Closed Status (DI)
• Stream Inlet MOV – Local/Remote Status (DI)
• Stream Inlet MOV – Fault (DI)
• Stream Outlet MOV – Open Command (DO)
• Stream Outlet MOV – Close Command (DO)
• Stream Outlet MOV – Open Status (DI)
• Stream Outlet MOV – Closed Status (DI)
• Stream Outlet MOV – Local/Remote Status (DI)
• Stream Outlet MOV – Fault (DI)
• MM Offtake MOV – Open Command (DO)
• MM Offtake MOV – Close Command (DO)
• MM Offtake MOV – Open Status (DI)
• MM Offtake MOV – Closed Status (DI)
• MM Offtake MOV – Local/Remote Status (DI)
• MM Offtake MOV – Fault (DI)
• Prover Raw Pulse Bus (Pulse Output)
Configuration 2: Master Meter I/O Signals:
All flow
computers • Coriolis Flow Rate (Single Pulse)
running the • MM Stream Pressure (4-20mA)
Master Meter • MM Stream Temperature (4-20mA)
Kindly add also
application • MM Stream Filter DP (4-20mA)
• Fast Loop Pressure (4-20mA) Flow control valve position
(Propane &
Butane) • Fast Loop Temperature (4-20mA) (4-20mA input)
• Fast Loop Flow Rate (4-20mA) Flow control valve fault (DI)
• Fast Loop WIO Meter (4-20mA)
• Flow Control Valve (4-20mA Output)
• Mass Flow Rate (4-20mA Output)
• Standard Volume Flow Rate (4-20mA Output)
• Fast Loop Densitometer A (Frequency)
• Fast Loop Densitometer B (Frequency)
• MM Stream Outlet MOV – Open Command (DO)
• MM Stream Outlet MOV – Close Command (DO)
• MM Stream Outlet MOV – Open Status (DI)
• MM Stream Outlet MOV – Closed Status (DI)
• MM Stream Outlet MOV – Local/Remote Status (DI)
• MM Stream Outlet MOV – Fault (DI)
• SVP Offtake MOV – Open Command (DO) (Condensate only)
• SVP Offtake MOV – Close Command (DO) (Condensate only)
• SVP Offtake MOV – Open Status (DI) (Condensate only)
• SVP Offtake MOV – Closed Status (DI) (Condensate only)
• SVP Offtake MOV – Local/Remote Status (DI) (Condensate only)
• SVP Offtake MOV – Fault (DI) (Condensate only)
Configuration 3: Stream I/O Signals:

4017109-A23-001-01 39
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 40/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

All flow • USM Flow Rate (Single Pulse)


computers • USM Diagnostics (Modbus RS-485)
running the • Stream Pressure (4-20mA)
single stream • Stream Temperature (4-20mA)
USM application • Fast Loop Pressure (4-20mA) Kindly add also
(Condensate) • Fast Loop Temperature (4-20mA) Flow control valve position
• Fast Loop WIO Meter (4-20mA) (4-20mA input)
• Flow Control Valve (4-20mA Output) Flow control valve fault (DI)
• Mass Flow Rate (4-20mA Output)
• Standard Volume Flow Rate (4-20mA Output)
• Stream Inlet MOV – Open Command (DO)
• Stream Inlet MOV – Close Command (DO)
• Stream Inlet MOV – Open Status (DI)
• Stream Inlet MOV – Closed Status (DI)
• Stream Inlet MOV – Local/Remote Status (DI)
• Stream Inlet MOV – Fault (DI)
• Stream Outlet MOV – Open Command (DO)
• Stream Outlet MOV – Close Command (DO)
• Stream Outlet MOV – Open Status (DI)
• Stream Outlet MOV – Closed Status (DI)
• Stream Outlet MOV – Local/Remote Status (DI)
• Stream Outlet MOV – Fault (DI)
• MM Offtake MOV – Open Command (DO)
• MM Offtake MOV – Close Command (DO)
• MM Offtake MOV – Open Status (DI)
• MM Offtake MOV – Closed Status (DI)
• MM Offtake MOV – Local/Remote Status (DI)
• MM Offtake MOV – Fault (DI)
Prover Raw Pulse Bus (Pulse Output)

Configuration 4: Master Meter I/O Signals:


All flow
computers • Turbine Flow Rate (Dual Pulse)
running the • MM Stream Pressure (4-20mA)
Master Meter • MM Stream Temperature (4-20mA)
application • MM Stream Filter DP (4-20mA) Kindly add also
• Fast Loop Pressure (4-20mA) Flow control valve position
• Fast Loop Temperature (4-20mA) (4-20mA input)
• Fast Loop Flow Rate (4-20mA) Flow control valve fault (DI)
• Fast Loop WIO Meter (4-20mA)
• Mass Flow Rate (4-20mA Output)
• Standard Volume Flow Rate (4-20mA Output)
• Flow Control Valve (4-20mA Output)
• Fast Loop Densitometer A (Frequency)
• Fast Loop Densitometer B (Frequency)
• MM Stream Outlet MOV – Open Command (DO)

4017109-A23-001-01 40
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 41/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• MM Stream Outlet MOV – Close Command (DO)


• MM Stream Outlet MOV – Open Status (DI)
• MM Stream Outlet MOV – Closed Status (DI)
• MM Stream Outlet MOV – Local/Remote Status (DI)
• MM Stream Outlet MOV – Fault (DI)
• SVP Offtake MOV – Open Command (DO) (El Feel and Crude oil
export only)
• SVP Offtake MOV – Close Command (DO) (El Feel and Crude oil
export only)
• SVP Offtake MOV – Open Status (DI) (El Feel and Crude oil
export only)
• SVP Offtake MOV – Closed Status (DI) (El Feel and Crude oil
export only)
• SVP Offtake MOV – Local/Remote Status (DI) (El Feel and Crude
oil export only)
SVP Offtake MOV – Fault (DI) (El Feel and Crude oil export only)
Configuration 5: Small Volume Prover I/O signals:
Flow computer • Raw Pulse Input
running the • Prover Ready (DI)
Small Volume • Prover Run Command (DO)
Prover • Prover Detector Switch 1 (DI)
application • Prover Detector Switch 2 (DI)
• Prover Pressure (4-20mA)
• Prover Temperature (4-20mA)
• Prover Outlet MOV – Open Command (DO)
• Prover Outlet MOV – Close Command (DO)
• Prover Outlet MOV – Open Status (DI)
• Prover Outlet MOV – Closed Status (DI)
• Prover Outlet MOV – Auto/Manual Status (DI)
• Prover Outlet MOV – Fault (DI)

9.2.7 Metering Panel


A new four bay Rittal metering panel for Flow Computer System 1 will be supplied to house
the S600+ flow computers and InSpec controllers. The panel will be built according to
Swinton Technology’s general panel specification.

9.2.8 Design Summary


A summary of the new metering panel is detailed below:

Component Description
Manufacturer Type Rittal Series

Dimensions 3,200 mm x 800 mm x 2,100 mm (W, D, H)


Plinth Yes included (100 mm) with absorption pads.

4017109-A23-001-01 41
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 42/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

Access Rear access to internal components.


Flow computer Redundant 24 Volts.
supply
Ingress Protection IP54.
Cable entry bottom entry.
Cable type Low smoke zero halogen.
Internal light and Internal panel light fitted with a micro-switch or PIR sensor. A G-
power outlet type BSI1363 UK power socket installed with RCD protection as
standard.
PSU 6 x 24 Volt diode in an ‘OR’ arrangement.
Anti-condensation No.
heater
Ventilation Dust filters, louvers, dual ventilation fans.

The following key design notes also apply to the metering panel:
• All major equipment, such as flow computers, will be screwed into position to
provide a secure installation.
• Panel front plates are 2mm painted steel, and internally stiffened to prevent bowing.
• Removable gland plates will be installed with an earth stud and strap.
• Standard Rittal equipment is provided with eye lifting bolts, no special lifting frame
or equipment is provided.
• All equipment is to be wired completely; all wires will be numbered with interlocking
ferules, and all ends will be fitted with crimped lugs.
• Panel trunking will have a minimum of 20% spare capacity and spare terminals will
be provided to terminate all spare cores.

The cable colors of the FCs redundant network must differ; e.g., Network A should
be red, while Network B should be green.

4017109-A23-001-01 42
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 43/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

9.2.9 Panel Layout


The metering panel will be supplied with the following general arrangement: new drawing

Pictured – Flow Computer System 1 Metering Panel General Arrangement

4017109-A23-001-01 43
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 44/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

9.3 Flow Computer System 2

9.3.1 Summary

Metering Flow Computer MSC Sampling


Package
El Feel Metering Five new S600+ flow The existing DMS+ One InSpec
(85-220-JM-007) computers will be will be removed and Controller will be
supplied. Two per replaced with a new integrated with the
metering stream TruST MSC located TruST MSC.
(Duty/Standby) and in the Main Control
one Master Meter. Room.
Wafa Oil Metering Five new S600+ flow One InSpec
(85-220-JM-009) computers will be One common Controller will be
supplied. Two per duty/standby TruST integrated with the
metering stream Metering TruST MSC.
(Duty/Standby) and Supervisory
one Master Meter. Computer will be
Crude Oil Export Nine new S600+ supplied to handle One InSpec
(85-220-JM-008) flow computers will all supervisory Controller will be
be supplied. Two per functions. integrated with the
metering stream TruST MSC.
(Duty/Standby) and
one Master Meter.
Small Volume One new S600+ flow Sampling not
Prover computer will be applicable.
supplied.

All sampling I/O and functionality will be handled by InSpec Controllers, sampling however
can be initiated and controlled from the metering supervisor system (TruST).

9.3.2 Flow Computers


A total of twenty flow computers will be supplied for Flow Computer System 2, based on
redundant flow computers per stream in a duty/standby configuration. A dedicated flow
computer will be supplied as a Master Meter for each skid. A separate flow computer will be
supplied with the application for the Small Volume Prover which will be used for proving the
El Feel and Crude Oil Export master meters. New S600+ flow computers will replace the
existing S600 flow computers which are installed on site.
The existing system handles valve control via ADAM Modules, however with the supply of
new S600+ flow computers these signals will be handled by the designated S600+ stream
flow computer.

4017109-A23-001-01 44
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 45/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

9.3.3 El Feel 85-220-JM-007 Hardware Arrangement


Each flow computer will be supplied with the following hardware arrangement:

Flow Computer Quantity New Hardware


Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
1&2: • 1 x P152 CPU Board
El Feel Metering • 1 x P153 Keypad/LCD
Stream 1 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
3&4: • 1 x P152 CPU Board
El Feel Metering • 1 x P153 Keypad/LCD
Stream 2 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
5&6: • 1 x P152 CPU Board
El Feel Metering • 1 x P153 Keypad/LCD
Stream 3 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 7: 1 S600+ Flow Computer Base Unit, complete with:
El Feel Metering • 1 x P152 CPU Board
Master Meter • 1 x P153 Keypad/LCD
• 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board

9.3.4 Wafa 85-220-JM-009 Hardware Arrangement

Flow Computer Quantity New Hardware


Flow Computer 8&9: 2 S600+ Flow Computer Base Unit, complete with:
Wafa Metering • 1 x P152 CPU Board
Stream 1 • 1 x P153 Keypad/LCD
• 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
10&11: • 1 x P152 CPU Board
Wafa Metering • 1 x P153 Keypad/LCD
Stream 2 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
12&13: • 1 x P152 CPU Board
Wafa Metering • 1 x P153 Keypad/LCD
Stream 3 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board

4017109-A23-001-01 45
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 46/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

Flow Computer 14: 1 S600+ Flow Computer Base Unit, complete with:
Wafa Metering • 1 x P152 CPU Board
Master Meter • 1 x P153 Keypad/LCD
• 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board

9.3.5 Crude Oil Export 85-220-JM-008 Hardware Arrangement

Flow Computer Quantity New Hardware


Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
15&16: • 1 x P152 CPU Board
Crude Oil Export • 1 x P153 Keypad/LCD
Metering Stream 1 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
17&18: • 1 x P152 CPU Board
Crude Oil Export • 1 x P153 Keypad/LCD
Metering Stream 2 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
19&20: • 1 x P152 CPU Board
Crude Oil Export • 1 x P153 Keypad/LCD
Metering Stream 3 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
21&22: • 1 x P152 CPU Board
Crude Oil Export • 1 x P153 Keypad/LCD
Metering Stream 4 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 23: 1 S600+ Flow Computer Base Unit, complete with:
Crude Oil Export • 1 x P152 CPU Board
Metering Master • 1 x P153 Keypad/LCD
Meter • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board
Flow Computer 24: 1 S600+ Flow Computer Base Unit, complete with:
Small Volume • 1 x P152 CPU Board
Prover – Mobile • 1 x P153 Keypad/LCD
Prover • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board

4017109-A23-001-01 46
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 47/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

9.3.6 Hardware Arrangement


Each flow computer will be supplied with the following hardware arrangement:

Flow Computer Quantity New Hardware


Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
1&2: • 1 x P152 CPU Board
El Feel Metering • 1 x P153 Keypad/LCD
Stream 1 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
3&4: • 1 x P152 CPU Board
El Feel Metering • 1 x P153 Keypad/LCD
Stream 2 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 5: 1 S600+ Flow Computer Base Unit, complete with:
El Feel Metering • 1 x P152 CPU Board
Master Meter • 1 x P153 Keypad/LCD
• 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board
Flow Computers 2 S600+ Flow Computer Base Unit, complete with:
6&7: • 1 x P152 CPU Board
Wafa Oil Metering • 1 x P153 Keypad/LCD
Stream 1 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 8&9: 2 S600+ Flow Computer Base Unit, complete with:
Wafa Oil Metering • 1 x P152 CPU Board
Stream 2 • 1 x P153 Keypad/LCD
• 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 10: 1 S600+ Flow Computer Base Unit, complete with:
Wafa Oil Metering • 1 x P152 CPU Board
Master Meter • 1 x P153 Keypad/LCD
• 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
11&12: • 1 x P152 CPU Board
Crude Oil Export • 1 x P153 Keypad/LCD
Stream 1 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
13&14: • 1 x P152 CPU Board
Crude Oil Export • 1 x P153 Keypad/LCD

4017109-A23-001-01 47
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 48/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

Stream 2 • 1 x P144 I/O Board


• 1 x P148 Mezzanine Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
15&16: • 1 x P152 CPU Board
Crude Oil Export • 1 x P153 Keypad/LCD
Stream 3 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 2 S600+ Flow Computer Base Unit, complete with:
17&18: • 1 x P152 CPU Board
Crude Oil Export • 1 x P153 Keypad/LCD
Stream 4 • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
Flow Computer 19: 1 S600+ Flow Computer Base Unit, complete with:
Crude Oil Export • 1 x P152 CPU Board
Master Meter • 1 x P153 Keypad/LCD
• 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board
Flow Computer 20: 1 S600+ Flow Computer Base Unit, complete with:
Small Volume • 1 x P152 CPU Board
Prover – Mobile • 1 x P153 Keypad/LCD
Prover • 1 x P144 I/O Board
• 1 x P148 Mezzanine Board
• 1 x P154 Prover Board

9.3.7 Software Applications system 2


The following flow computer applications will be used for Flow Computer System 2:
• Configuration 1 – Single Stream, Liquid Coriolis Metering
• Configuration 2 – Liquid Coriolis Master Meter Application
• Configuration 3 – Single Stream, Liquid USM Metering
• Configuration 4 – Liquid Turbine Master Meter Application
• Configuration 5 – Small Volume Prover Application
The first configuration will be loaded into all stream flow computers for the WAFA Crude Oil
system. The second configuration will be loaded into the master meter flow computers for
WAFA Crude Oil. The third configuration will be loaded into all stream flow computers for
the El Feel and Crude Oil Export systems. The fourth configuration will be loaded into the
master meter flow computers for El Feel and Crude oil Export. The fifth configuration will be
loaded into the small volume prover flow computer.
The following I/O is to be handled by each unique flow computer application:

4017109-A23-001-01 48
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 49/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

Flow Computer Required I/O


Configuration 1: Stream I/O Signals:
All flow
computers • Coriolis Flow Rate (Single Pulse)
running the • Coriolis Diagnostics (Modbus RS-485)
single stream • Coriolis Density (4-20mA)
Coriolis • Stream Pressure (4-20mA) Please add:
application • Stream Temperature (4-20mA) Flow control valve position
(WAFA) • Fast Loop Pressure (4-20mA) (4-20 mA Input)
• Fast Loop Temperature (4-20mA) Flow control valve fault (DI)
• Fast Loop Flow Rate (4-20mA)
• Fast Loop WIO Meter (4-20mA)
• Flow Control Valve (4-20mA Output)
• Mass Flow Rate (4-20mA Output)
• Standard Volume Flow Rate (4-20mA Output)
• Fast Loop Densitometer A (Frequency)
• Fast Loop Densitometer B (Frequency)
• Stream Inlet MOV – Open Command (DO)
• Stream Inlet MOV – Close Command (DO)
• Stream Inlet MOV – Open Status (DI)
• Stream Inlet MOV – Closed Status (DI)
• Stream Inlet MOV – Local/Remote Status (DI)
• Stream Inlet MOV – Fault (DI)
• Stream Outlet MOV – Open Command (DO)
• Stream Outlet MOV – Close Command (DO)
• Stream Outlet MOV – Open Status (DI)
• Stream Outlet MOV – Closed Status (DI)
• Stream Outlet MOV – Local/Remote Status (DI)
• Stream Outlet MOV – Fault (DI)
• MM Offtake MOV – Open Command (DO)
• MM Offtake MOV – Close Command (DO)
• MM Offtake MOV – Open Status (DI)
• MM Offtake MOV – Closed Status (DI)
• MM Offtake MOV – Local/Remote Status (DI)
• MM Offtake MOV – Fault (DI)
• Prover Raw Pulse Bus (Pulse Output)
Configuration 2: Master Meter I/O Signals:
All flow
computers • Coriolis Flow Rate (Single Pulse)
running the • MM Stream Pressure (4-20mA)
Master Meter • MM Stream Temperature (4-20mA)
application • MM Stream Filter DP (4-20mA)
(WAFA) • Fast Loop Pressure (4-20mA)
• Fast Loop Temperature (4-20mA)
• Fast Loop Flow Rate (4-20mA)

4017109-A23-001-01 49
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 50/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• Fast Loop WIO Meter (4-20mA) Please add:


• Flow Control Valve (4-20mA Output) Flow control valve position
• Mass Flow Rate (4-20mA Output) (4-20 mA Input)
• Standard Volume Flow Rate (4-20mA Output)
Flow control valve fault (DI)
• Fast Loop Densitometer A (Frequency)
• Fast Loop Densitometer B (Frequency)
• MM Stream Outlet MOV – Open Command (DO)
• MM Stream Outlet MOV – Close Command (DO)
• MM Stream Outlet MOV – Open Status (DI)
• MM Stream Outlet MOV – Closed Status (DI)
• MM Stream Outlet MOV – Local/Remote Status (DI)
• MM Stream Outlet MOV – Fault (DI)
• SVP Offtake MOV – Open Command (DO) (Condensate only)
• SVP Offtake MOV – Close Command (DO) (Condensate only)
• SVP Offtake MOV – Open Status (DI) (Condensate only)
• SVP Offtake MOV – Closed Status (DI) (Condensate only)
• SVP Offtake MOV – Local/Remote Status (DI) (Condensate only)
• SVP Offtake MOV – Fault (DI) (Condensate only)
Configuration 3: Stream I/O Signals:
All flow
computers • USM Flow Rate (Single Pulse)
running the • USM Diagnostics (Modbus RS-485)
single stream • Stream Pressure (4-20mA) Please add:
USM application • Stream Temperature (4-20mA) Flow control valve position
(EL Feel & • Fast Loop Pressure (4-20mA) (4-20 mA Input)
Crude Oil • Fast Loop Temperature (4-20mA)
Flow control valve fault (DI)
Export) • Fast Loop WIO Meter (4-20mA)
• Flow Control Valve (4-20mA Output)
• Mass Flow Rate (4-20mA Output)
• Standard Volume Flow Rate (4-20mA Output)
• Stream Inlet MOV – Open Command (DO)
• Stream Inlet MOV – Close Command (DO)
• Stream Inlet MOV – Open Status (DI)
• Stream Inlet MOV – Closed Status (DI)
• Stream Inlet MOV – Local/Remote Status (DI)
• Stream Inlet MOV – Fault (DI)
• Stream Outlet MOV – Open Command (DO)
• Stream Outlet MOV – Close Command (DO)
• Stream Outlet MOV – Open Status (DI)
• Stream Outlet MOV – Closed Status (DI)
• Stream Outlet MOV – Local/Remote Status (DI)
• Stream Outlet MOV – Fault (DI)
• MM Offtake MOV – Open Command (DO)
• MM Offtake MOV – Close Command (DO)
• MM Offtake MOV – Open Status (DI)

4017109-A23-001-01 50
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 51/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• MM Offtake MOV – Closed Status (DI)


• MM Offtake MOV – Local/Remote Status (DI)
• MM Offtake MOV – Fault (DI)
Prover Raw Pulse Bus (Pulse Output)

Configuration 4: Master Meter I/O Signals:


All flow
computers • Turbine Flow Rate (Dual Pulse)
running the • MM Stream Pressure (4-20mA) Please add:
Master Meter • MM Stream Temperature (4-20mA) Flow control valve position
application • MM Stream Filter DP (4-20mA) (4-20 mA Input)
(EL Feel & • Fast Loop Pressure (4-20mA) Flow control valve fault (DI)
Crude Oil • Fast Loop Temperature (4-20mA)
Export) • Fast Loop Flow Rate (4-20mA)
• Fast Loop WIO Meter (4-20mA)
• Mass Flow Rate (4-20mA Output)
• Standard Volume Flow Rate (4-20mA Output)
• Flow Control Valve (4-20mA Output)
• Fast Loop Densitometer A (Frequency)
• Fast Loop Densitometer B (Frequency)
• MM Stream Outlet MOV – Open Command (DO)
• MM Stream Outlet MOV – Close Command (DO)
• MM Stream Outlet MOV – Open Status (DI)
• MM Stream Outlet MOV – Closed Status (DI)
• MM Stream Outlet MOV – Local/Remote Status (DI)
• MM Stream Outlet MOV – Fault (DI)
• SVP Offtake MOV – Open Command (DO) (El Feel and Crude oil
export only)
• SVP Offtake MOV – Close Command (DO) (El Feel and Crude oil
export only)
• SVP Offtake MOV – Open Status (DI) (El Feel and Crude oil
export only)
• SVP Offtake MOV – Closed Status (DI) (El Feel and Crude oil
export only)
• SVP Offtake MOV – Local/Remote Status (DI) (El Feel and Crude
oil export only)
SVP Offtake MOV – Fault (DI) (El Feel and Crude oil export only)
Configuration 5: Small Volume Prover I/O signals:
Flow computer • Raw Pulse Input
running the • Prover Ready (DI)
Small Volume • Prover Run Command (DO)
Prover • Prover Detector Switch 1 (DI)
application • Prover Detector Switch 2 (DI)
• Prover Pressure (4-20mA)
• Prover Temperature (4-20mA)
• Prover Outlet MOV – Open Command (DO)

4017109-A23-001-01 51
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 52/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• Prover Outlet MOV – Close Command (DO)


• Prover Outlet MOV – Open Status (DI)
• Prover Outlet MOV – Closed Status (DI)
• Prover Outlet MOV – Auto/Manual Status (DI)
• Prover Outlet MOV – Fault (DI)

9.3.8 Metering Panel


A new four bay Rittal metering panel for Flow Computer System 2 will be supplied to house
the S600+ flow computers and InSpec controllers.
The panel design will be designed as previously described for Flow Computer System 1
The metering panel for Flow Computer System 2 will be wired to suit the requirements of El
Feel, Wafa Oil, and Crude Oil Export metering. The following panel general arrangement
shows the intended layout of the flow computers:

Pictured – Flow Computer System 2 Metering Panel General Arrangement

4017109-A23-001-01 52
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 53/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

9.4 Metering Supervisory Computer


A new TruST Metering Supervisory Computer will be supplied to replace the existing DMS+
systems. The new MSC will be located in the Main Control Room and provide supervisory
functions for both Flow Computer System 1 and Flow Computer System 2.

9.4.1 MSC Hardware


The following hardware will be supplied for the Metering Supervisory Computer:

Item Qty. Description


1. 2 Rack mount Metering Supervisory Computer (Dell server)
2. 1 Engineering Workstation (KVM)
3. 6 Ethernet Switches (2 in system 1 metering panel, 2 in system 2
metering panel and 2 in server rack)
4. 6 Terminal Servers (2 in system 1 metering panel, 2 in system 2
metering panel and 2 in server rack)
5. 4 Desk Mount Operator Workstation PC (Dell)
6. 4 Desk Mount Monitor, Keyboard and Mouse
7. 2 B&W Laser Printer
8. 1 Server Rack – Dimensions: 800mm x 800mm x 2,100mm (W, D, H)
Note: model numbers will be detailed in the FDS.

The new MSC servers will operate in a duty/standby arrangement. A new rack-mount
monitor and keyboard with in-built KVM will also be supplied as an Engineering
Workstation, to provide access to both servers for maintenance purposes.
A single bay server rack will be supplied for the Main Control Room to house the Metering
Supervisory Computers, two Ethernet switches and two terminal servers
Four new desk-mounted Operator Workstation PCs will also be provided for user access to
the TruST MSC software, all to be located in the Main Control Room.
Modbus Serial data links will be provided and configured to transfer data from the metering
supervisory to the EMMS, DCS and IAS. The MSC will be capable of receiving commands
from the DCS, where the DCS shall supervise the flow computer/prover control and load
the flow quantities. The data maps will be detailed in the FDS.

9.4.2 MSC Software Functionality


The key functions to be provided by TruST for the Mellitah Complex include:
• Display live data for each stream including gross volumetric flow rate, standard
volumetric flow rate, mass flow rate, temperature, pressure and density.
The FO (the connection between the substations and the control room) shall be checked and verified. If it needs to be
replaced, it is the contractor responsibility as agreed.

4017109-A23-001-01 53
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 54/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• Provide customised dynamic mimic displays with live updating values and graphic
symbols.
• Provide a comprehensive alarm/event system including printing of alarm/event data
and archive of these alarms/events to the disk-based database.
• Redundant Modbus TCP/IP communication links to each S600+ flow computer, for
the upload/download of metering data.
• Automatic generation of current and period end reports for each flow computer.
• On demand viewing and printing (to printer) of archived reports and current reports.
• Audit/event logging facility for process data changes and operator actions/events
detected by TruST.
• Long term storage of the historic archive event data.
• User configurable trending package, capable of trending relevant process data for
fault finding purpose.
• Totalisation of daily data, including generation of station totals.
• Provide monitoring and control of the CoJetix sampling systems via
communications with InSpec controllers.
• Provide manual and automatic line control (stream switching) for each metering
station.
• The system will allow batching functionality which will include for monitoring a start
or stop commands issued by an operator in line with Daniels procedure
“Operational Procedure for Mellitah JM 008 Export Batch Metering System rev 4”.
The start command will place the system into a monitoring state where once flow
begins all totals will be accumulated into batch totals. When the stop command is
issued the batch monitoring will end and a batch report will be produced containing
all accumulated totals whilst in the batch monitoring state. The supervisory system
has no automatic control functionality over starting/stopping the batch in terms of
opening and closing valves or FCVs. There is no provision included for
automatically ramping up the flow at the start of the batch or ramping down the flow
at the end of the batch this is all operator controlled.
• Security – Multi-level password protected user interface.
• Efficient polling allowing only changing data to be processed, using shared memory
inter-program communication.
• Modbus Serial data links to transfer data to the EMMS, DCS and IAS. It is assumed
that identical data will be provided by TruST on all links.

4017109-A23-001-01 54
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 55/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• The metering control system does not included for interfacing to the Sulfur
Totalizing Belt Scale it is understood that this is handled separately by a local
controller which is interfaced directly to the DCS.
• The metering supervisory and control system will be engineered and tested to the
agreed design as defined in the approved Functional Design Specification and
signal lists which will be issued separately to this document.

To provide all the required maintenance software for the system components, for example USM condition
based monitoring and Coriolis meter verification software, Flow computer software, MOV software and ect.
loaded into a single laptop.

4017109-A23-001-01 55
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 56/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

10. MATERIAL DESIGN CRITERIA


Material selection will be carried out, based on the process and environmental conditions,
in accordance with the project Material Selection Philosophy Document. (Separate
document)
This will take into account all information gathered during the site visits including H2S,
External Corrosion, Internal Corrosion, vibration, hammering.
The requirements of NACE MR0175 / ISO 15156 will be applied (where possible)

11. MECHANICAL DESIGN CRITERIA


Primary structural members shall be steel channel sections to BS EN 10025-1:2004 S275JR,
BS EN 10025-1:2004 S355 or similar.

Secondary steelwork may use RHS or RSA sections of equivalent material grade to the
primary members as appropriate to the application.

Structural Steel, where applicable, will be welded to BS EN ISO 15614-1:2004 to a pre-


approved set of standard Weld Procedures with 3rd Party endorsed Procedure Qualification
Records.

NDT will be 100% Magnetic Particle Inspection of main structural joints and all lifting points
to BS EN 1290:1998 with acceptance to BS EN ISO 5817:2014.

Note that NDE Procedures shall be approved by a PCN Level III Technician.

NDE operators shall be PCN Level II.

All Inspection, Non-Destructive Testing (NDT), Testing activities, including all third-party
review, witnessing and inspection would be in accordance with an agreed Inspection and
Test Plan and/or code requirements. All will be carried out at our works or nominated local
fabricators.

Material test certification in accordance with BS EN10204 type 3.1, and with full material
traceability will be provided for main load bearing structural steel, including skid lifting lugs.

Sunshields for the metering systems have been included.

Sunshield to cover the SVP is also included while not in operation.

Nozzle / Quill will exceed the requirements of PD IEC/TR 61831:2011 for vortex shedding
and bending moments.
Installing a new isolation valve in R1 area

4017109-A23-001-01 56
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 57/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

12. ELECTRICAL DESIGN CRITERIA


12.1 Instrument Cable
Instrument cable construction will be in line with the client specifications 11591E01 Rev01,
20047E03 Rev 03, and 20048E04 Rev04.

12.2 Cable Glands


Glands installed within hazardous areas shall be certified for the hazardous area
classification, the required IP rating, and the equipment that they terminate into.
Sealing washers will be fitted to all glands.
Where the enclosure entry is not threaded then both serrated washers and back nuts shall
be used.
Shrouds shall not be fitted to cable.
The material of construction shall be brass.

12.3 Cable Support


Cable is to be run, wherever possible, on cable tray unless otherwise specified.
Deep-channel stainless steel 316 Unistrut or equivalent complete with PVC capping and end
caps may be installed where cables must be run from the cable tray route to the instrument.
The cables will be adequately supported and clamped at intervals not exceeding 450mm on
horizontal run or not more than 250mm on vertical run.
Cable tray shall be provided in 316 stainless steel.
Cables shall be run in neat looms side by side and crossovers avoided. In cases where
crossovers do occur, bridging cable tray should be used at 90° to each other.
Where cable tray is cut to facilitate cable entry/exit, plastic/rubberised protective edging is to
be added to the edges of the tray to protect the cables.

Earthing system

4017109-A23-001-01 57
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 58/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

12.4 Cable Segregation


Whenever possible, cables should be segregated in compliance with BS 6739 Section 15.13
as shown in the table below.
Classification Instrument Cable Classifications
Category
1 Instrument power and control wiring (above 50 V). This group includes
AC and DC power supplies and control signals, including emergency
shut‑down control circuits.
Any cable having a total loading of more than 10 A should be regarded
as a power cable and be excluded from this classification.
2 High level signal wiring (5 V to 50 V DC). This group includes digital
signals, alarm signals, shut‑down signals and high-level analogue
signals, e.g. 4 mA to 20 mA.
3 Low level signal wiring (below 5 V DC). This group includes temperature
signals and low analogue signals, e.g. analyser measuring circuits.
4 Communications signals. This group includes fieldbuses, ethernet and
other digital communication systems such as CAN‑based systems, and
analogue/digital hybrids.

Only conductors carrying signals of the same category should be contained within any one
multicore/multipair cable.
In each classification, a further segregation should be made to ensure that conductors
forming part of intrinsically safe circuits are contained within multicore/multipair cables
reserved solely for such circuits.

All I.S cables must be segregated by at least 50mm from non I.S. cables unless at least one
of the cables has earthed armour or shielding.

Classification Recommended minimum


Category spacing
1 to 2 200mm
2 to 3 300mm
1 to 3 300mm
1 to 4 300mm
2 to 4 300mm
3 to 4 300mm

4017109-A23-001-01 58
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 59/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

12.5 Junction Boxes


Junction boxes shall be 316 SS with minimum ingress protection rating of IP66 and shall be
certified in accordance with section 12.7.
Separate junction boxes will be provided for different signals and voltage levels (if applicable)
as follows:
• Valve Control and Indication
• I.S. / Non I.S.
• Analogue Signals
• Digital Signals
• Densitometer frequency signals

12.6 Ingress Protection


Ingress Protection of electrical equipment will be BS EN 60529:1992 IP 66 – except pump
motor (IP55 min)
Ingress Protection of Sampling / Analysis cabinets are designed to be equivalent to or better
than IP33 – however, no certification will be provided.

12.7 Certification
This classifies the areas of the plant into the following zones for the purpose of purchasing
electrical, instrument, and mechanical equipment:
• Zone 0: That part of a hazardous area in which a flammable atmosphere is
continuously present or present for long periods;
• Zone 1: That part of a hazardous area in which a flammable atmosphere is likely to
occur in normal operation;
• Zone 2: That part of a hazardous area in which a flammable atmosphere is not likely
to occur in normal operation and, if it occurs, will exist only for a short period.
An unclassified area not included in the above categories will be non-hazardous.
All electrical/electronic field instruments shall be suitable and ATEX certified for installation
hazardous area Zone 1 IIB T3 minimum, except for the Sulphur weigh belt scales which will
be certified for Zone 21 ATEX.
For the R1 area (Propane, Butane and Condensate) the electrical equipment will be ATEX
certified suitable for Zone 1 Gas Group IIA Temperature Class T4 (or better), where
applicable. Certified Ex’e’.
For the Q2 area (Elfeel, Crude Export and Wafa) the electrical equipment will be ATEX
certified suitable for Zone 1 Gas Group IIB Temperature Class T4 (or better), where
applicable. Certified Ex’d’.

4017109-A23-001-01 59
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 60/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

13. HSE DESIGN CRITERIA


13.1 General

The details of the HSE scope of work related to this project will be defined in the Project HSE
Plan:

SN-057-G-Q-0002-00 - Project HSE Plan

SN-057-G-Q-0003-00 - Wazen - Construction HSE Plan

Working Environment aspects of the equipment will be considered also.

13.2 Firefighting Equipment


The fire protection system of the new facilities will be determined according to fire hazards,
nature of the equipment, layout and manning level and taking into account the existing
firefighting capabilities.
The followings portable fire protection system will be foreseen, where necessary, if not
already installed in the plant:
• hand-held and/or wheeled dry chemical extinguishers;
• hand-held and/or wheeled carbon dioxide extinguishers.

13.3 Risk Assessment


During the current Project Phase development, risk assessment sessions will be managed
in order to evaluate the risk related to the pipeline installation and related to interferences
with existing plants. Only existing areas affected by the new installations will be studied.
General safety criteria and requirements will be described on HSE Philosophy that will be
issued.

13.3.1 HAZID Session

The overall intent of an HAZID study is to assist in demonstrating that the risks
associated with all the identified hazards shall be managed during the whole
activity and will be reduced to an acceptable level by:
• Checking the design for project development and consider whether any
external or internal cause, may generate a hazard to people working on the
installation and/or to the general public, and/or a damage to the Assets
and/or impacts to environment or reputation.

4017109-A23-001-01 60
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 61/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• Checking whether the precautions and safeguards incorporated in the


project development are sufficient to either prevent the hazard occurring or
mitigate the severity of any consequence to an acceptable level.
• Identifying and implementing additional precautions or safeguards to
manage all the hazards not sufficiently incorporated during the design
phase.

Dedicated documentation will be Issued: HAZID Term of Reference and HAZID


Report.

13.3.2 HAZOP Session

HAZOP study is a formal systematic critical examination to the process and


engineering intentions of new or existing facilities to assess the hazard potential
of mal-operation or malfunction of individual items of equipment and the
consequential effects on the facility as a whole.

The purpose of the HAZOP studies shall be to identify possible deviations from
the intended process and utility operating parameters, and any subsequent
hazards or operability problems associated with those deviations.

A HAZOP session(s) will be conducted prior to production of any of the new


systems. The HAZOP will be facilitated/chaired by a qualified body deemed
neutral to the project. This may include personnel from our parent companies
SLB/Rockwell.

HAZOP Recommendations will be recorded and numbered sequentially, clearly


identifying any required action, which will be included in the HAZOP Report.

4017109-A23-001-01 61
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 62/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

14. CIVIL DESIGN CRITERIA


14.1 Earthwork
The earthwork is divided to site preparation, surveying, excavation, filling and compacting of
soil material.

14.1.1 Site Preparation

Prior to commencing any excavation work, the contractor shall establish a


horizontal and vertical survey, record existing ground elevations and stake the
location of trenches and foundations to be excavated.

The Contractor shall prepare the site for construction by clearing, removing and
disposing of all items not indicated on the Drawings to remain or so defined by
the Engineer.

The Contractor shall obtain relevant excavation and road cutting permits as
required prior to commencing work.

14.1.2 Destruction Procedure for existing concrete

Existing concrete shall be demolished and transferred to local borrow sites


using dump trucks, the destruction phase shall take place in site as soon as the
temporary bypass for the condensate, butane and propane has been
accomplished and put into work.

The destruction process shall be made according to the following procedure.


• Executing a site survey and marking the boundaries of the foundations to
be destructed.
• Planning for the destruction method according to the site conditions and
access as well as the existence of any objects that may be affected by
method used.
• Isolating the area of work according to HSE requirements and putting all
necessary signs and fencing to secure the perimeter.
• Issuing all necessary permits for the start of the demolishing process.
• Use of cable and pipe detectors to check for any hidden obstacles below
the surface prior to the excavation works.
• Excavating the surrounding soil along the perimeter of the foundations for
all the skids using mini excavator supported by the use of manpower with
hand‐shovels at sensitive locations or any uncertain spots during the
excavation process.

4017109-A23-001-01 62
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 63/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• After isolating the foundation from its perimeter, the destruction of the
foundation could be started by splitting the foundation and crushing the
concrete to small segments, using different methods according to the site
condition and the environment, the method for demolishing the concrete
foundation shall be done according to ACIPRC‐555‐01.
• All crushed segments of the demolished foundations shall be cleared off
site by loading onto dump‐trucks and transferred to the closest borrow‐pits.

14.1.3 Excavation
• Excavation of existing soils shall be performed according to the lengths,
widths and depths shown on the drawings or such further dimensions as
may be directed by the Engineer.
• Excavation shall be carried out, if possible, by use of backhoe machine.
Else it would be done by the aid of air powered jackhammer and hand
shovels.
• The bottom face of the hole shall be levelled at the desired depth.
• All unsuitable and excessive materials of soil shall be immediately
removed, loaded and transported off site area to approved dumps
according to local regulations.

14.1.4 Backfilling around structure

Sides of concrete sump tank shall be backfilled using suitable backfill material.
Materials conforming to the requirements should be placed and compacted in
layers having a maximum thickness of 300mm measured before compaction.
Backfill material shall be moistened according to the optimum water content to
provide maximum density.

14.1.5 Concrete work specifications

This section consists of performing all operations necessary for casting of


concrete and reinforced concrete in accordance with the specifications,
drawings and Engineer’s instructions.

SN to add Soils Data

4017109-A23-001-01 63
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 64/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

14.1.6 Project specifications

The civil works for the construction of the new skid foundations and by‐pass
foundations shall be according to the following specifications and regulations.
• ACI‐304R Guide for Measuring, Mixing, Transporting and Placing Concrete
• ACI‐117 Standard Specifications for Tolerances for Concrete Construction
and Materials
• ACI‐ 304.2R Placing Concrete by Pumping Methods
• ACI‐ 308 Standard Practice for Curing Concrete
• ACI 308R Guide Lines for Curing Concrete
• ACI ‐347 Guide to Formwork for Concrete
• ACI – 301‐99 Specification for Structural Concrete
• ACI‐ 309R Guide for Consolidation of Concrete
• Project Drawings Issued for Construction (IFC)
• Contractor HSE Plan.

14.1.7 Reinforcement
• The reinforcing materials shall be as per technical specifications and IFC
drawings and shall be inspected and accepted by Client/ Consultant.
• Reinforcing steel shall be handled with care and stored properly.
• Reinforcement shall be free from loose scale, rust, oil, grease or any other
material that may impair the bond between the concrete and reinforcement.
• Welding on rebars shall not be permitted for assembling of reinforcement.
• All rebars will be cold bent in accordance with ACI ‐318M.
• Care should be taken to avoid any damage to the coated rebars during
shipment, handling, fabrication, and placement.
• All reinforcing bars shall be placed in accurately with the correct cover and
shall fix securely in positions as shown on the drawings.
• Clear cover to the main reinforcement shall be in accordance with IFC
drawings.
• Plastic or mortar spacers shall be used for reinforcement cover.
• Approved rustproof binding wire shall be used.
• All intersections of the regular reinforcement shall be securely tied with
wire. Tie wire ends shall be bent in a way that they do not protrude into the
concrete cover zone.

4017109-A23-001-01 64
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 65/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

• Splices of reinforcing bars shall be as shown on the IFC Drawings or the


approved shop drawings.

14.1.8 Fabrication and Installation of formwork


• Form work shall be done in accordance with ACI‐347.
• It is proposed to use timber formwork for all the works. The main panel of
the formwork will be made of laminated plywood board. Lesser thickness
can be used for minor items.

In any case, it shall be made to withstand the concrete pressure.


• The main panels will be stiffened using Aluminium beam and or timber
beams along the length and width of planks according to the site conditions.
• Steel soldiers will be used to hold the panels together where the form height
is more than 1.5m.
• There will be props supporting the beams or soldiers. The props shall be of
push type so that the verticality of the formwork can be maintained by
adjusting them.
• The space between faces of the formwork can be adjusted by using steel
tie rods running through the PVC sleeves and cone end. They are screw
type so that spacing can be adjusted. There shall be tie rods run through
PVC holes shall be grouted after curing with approved materials.
• The formwork will be inspected before every casting to ensure that it is as
per the IFC.

14.1.9 Embedded items


• All the embedded items will be procured / fabricated prior to concreting and
fixed to formwork. The position of all embedded item shall be verified.
• The supervisor will cross check all the embedded item prior to submitting a
WIR to the QC. The QC Inspector will inspect the form work and raise WIR
to Client/Consultant.
• The plumpness of the Anchor bolt shall be checked and make sure it is
within the tolerance limit.
• When templates are used for the positioning of the inserts, they will be
screwed on to the main body of the form or held in position by the
supporting elements. In any case a rigid positioning of the template will be
ensured.
• Rebar and formwork WIR must be accepted by Client/Consultant Engineer
and release should be get from other discipline prior to start the concrete
pouring for any structure.

4017109-A23-001-01 65
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 66/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

14.1.10 Placement and concreting

Concreting will be carried out by using the approved design mix and that
specified for the structure. The concrete from approved Batch Plant only will be
used for all concreting works.
• Concrete when deposited to site shall have a temperature of not less than
5°C and not more than 28°C. If the ambient temp of the steel is more than
35°C, the forms and reinforcement will be sprayed with water just prior to
placing of concrete.
• Assurance shall be made no sustaining water inside the form work prior to
concreting.
• Once the concrete truck arrived at the site, all the required inspection and
testing shall be done by the approved Third‐party inspector and the QC
Inspector. The slump and cylinder test samples shall be taken.
• During concrete pouring, needle type vibrator shall be used to consolidate
the concrete.
• Sufficient number of vibrators shall be available at site based on the
quantity of concrete. Concrete testing shelter will be built on site for
concrete testing.
• In case of mass concrete pouring, the concreting will be done
uninterrupted, so that the cold joints are avoided. However, in case of slabs
/ paving, appropriate pre‐approved construction joints will be provided.
• Reinforcement, inserts, embedded part, formed expansion and contraction
joints shall be not disturbed during concrete placement.
• Except in case of columns, concrete shall be not dropped into place from a
height exceeding 2 meters otherwise trucking or chutes will be used.
• Concrete surface shall be finished by skilled and approved Masons.
• Control joints, if any, will be cut immediately after the concrete got
hardened.
• Joints not specified on the design drawings, shall be in accordance with
ACI 301 – 05.
• After concreting and before setting of concrete, the foundation and other
connection points (especially but not limited to anchor bolts) are checked
by surveyor to confirm their location, orientation, elevation and condition.
• Immediately after placement, protect concrete from premature drying or
excessively hot or cold temperatures, and mechanical injury per ACI 301‐
2010, Sec 5.3.6.5 requirements.

4017109-A23-001-01 66
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 67/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

14.1.11 Stripping of forms: Cast in place concrete works

Stripping of forms shall be done very carefully to avoid damaging the surface of
concrete.

14.1.12 Curing and protecting of concrete


• Curing and protection of concrete shall be done accordance with ACI‐
308.308R.
• Curing water and compound as per project specifications. The saturated
burlaps shall be covered with a plasticized sheet vapor barrier, minimum
0.15 mm in thickness and shall be kept in contact with the concrete surface
at all times.
• On concrete surfaces which are to be waterproofed shall not be used curing
compound.

14.1.13 Concrete surface repair


• Remedial treatment/Repair shall be carried out immediately to concrete
surface after client/consultant inspection.
• Before Concrete repair, surface shall be cleaned of dirt, laitance, corrosion
or other contamination with wire brush and rinse surface and allow to dry.
• For areas patched with epoxy mortar, shall remove broken and soft
concrete 6mm deep.
• Exposed structural, shrinkage and settlement cracks of concrete shall be
repaired by approved epoxy injection method.
• For patching honeycombs, approved epoxy mortar or cementitious grout
shall be used with trowel to repair concrete surface. Bonding agent shall be
applied to concrete surface before repair.
• Curing shall be done as per repair material manufacturer
recommendations.

As agreed there will be maintenance activities including electrical, instrument, civil, and mechanical shall
be considered here as per company standard and specification (technical offer sections 6.18 & 6.20).

4017109-A23-001-01 67
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 68/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

15. APPENDIX 1 - INTERNATIONAL CODES AND STANDARDS

International Standards

API MPMS, Ch. 4 Proving Systems


API MPMS, Ch. 5.3 Measurement of Liquid Hydrocarbons by Turbine Meters
API MPMS, Ch. 5.8 Measurement of Liquid Hydrocarbons by Ultrasonic Flow
Meters
ISO 3171 Petroleum Liquids - Automatic Pipeline Sampling. (1988)
API MPMS, Ch.8.2 Automatic Sampling of Petroleum and Petroleum
Products’. (Also published as ASTM-4177) (1995)
ASTM D4177 Standard Practice for Automatic Sampling of Petroleum
and Petroleum Products
IP Part VI, Section 2 Automatic Sampling of Liquids from Pipelines’. (1986)
OIML R117-1 Dynamic measuring systems for liquids other than water
Part 1: Metrological and technical requirements
IEC 79-10 Electrical Apparatus for Explosive Gas Atmospheres Part
10 Classification of Hazardous Areas
API RP 505 Recommended Practice for Classification of Locations for
Electrical Installations at Petroleum Facilities Classified
as Class 1, Zone 0, Zone 1, Zone 2
IP 15 Model Code of Safe Practice in the Petroleum Industry
Part 15 Area Classification Code for Petroleum
Installations
Libya NOC Measurement Libyan Hydrocarbon's National Code for Dynamic &
Code Static Measurement Systems
Libya NOC GES J.02 Flow Instruments
Libya NOC GES J.26 Metering and Proving System
Libya NOC GES Z.07 Oil / Gas Metering Stations

4017109-A23-001-01 68
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 69/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

16. APPENDIX 2 - ENI STANDARDS AND GENERAL SPECIFICATIONS


Doc No. Rev Title

27550E01 01 CIVIL WORKS SITE CLEARING AND EXCAVATION


27575E01 01 CIVIL WORKS FOUNDATION PILES
06798E00 00 INSTRUMENTATION ELECTRIC AND FIBER OPTIC CABLES
11591E01 01 INSTRUMENT BULK MATERIALS
20047E03 03 REQUIREMENTS FOR THE INSTALLATION OF INSTRUMENTATION
20048E04 04 INSTRUMENTATION GENERAL DESIGN REQUIREMENTS
28030E00 00 FLOW METERS INSTRUMENTS FUNCTIONAL REQUIREMENTS
FUNCTIONAL REQUIREMENTS FOR ON-OFF VALVES, ACTUATORS, LOCAL
28034E00 00
CONTROL PANELS AND ACCESSORIES
MINIMUM TECHNICAL CONTENT OF DOCUMENTS FOR INSTRUMENTATION,
28680E00 00 AUTOMATION AND TELECOMMUNICATION DISCIPLINES FOR EACH
PROJECT DEVELOPMENT PHASE
PROTECTIVE COATING, GALVANIZING AND METALLIZING FOR INTERNAL
20000E05 05 AND EXTERNAL SURFACES OF OFFSHORE AND ONSHORE STRUCTURES
AND RELATED COMPONENTS
20552E01 01 MAINTENANCE OF COATED SURFACES
29000E00 00 PAINTING AND COATINGS FOR OFFSHORE AND COASTAL STRUCTURES
29008E00 00 QUALIFICATION REQUIREMENTS FOR PAINTING SYSTEMS
TECHNICAL DOCUMENT IDENTIFICATION AND TITLE BLOCKS
20189E03 03
(IDENTIFICATION TABLES)
MANAGEMENT AND APPROVAL OF TECHNICAL DOCUMENTATION
27608E01 01
DELIVERABLES AND REQUIREMENTS OF CONTRACTORS AND VENDORS

TECHNICAL DOCUMENTATION REQUIRED DURING THE FACILITIES


27700E06 06
PROJECT DEVELOPMENT PHASE – DETAILED LIST & REQUIREMENTS
28081E00 00 STANDARD RULES FOR AS-BUILT PREPARATION
MINIMUM TECHNICAL CONTENT OF DOCUMENTS FOR INSTRUMENTATION,
28680E00 00 AUTOMATION AND TELECOMMUNICATION DISCIPLINES FOR EACH
PROJECT DEVELOPMENT PHASE
MG-HSEQ-Q-P-254 A1 CORPORATE PROJECT FINAL HANDOVER DOCUMENTATION
02776E03 03 GENERAL SPECIFICATION FOR FIELD WELDING OF PIPELINES
20367E04 04 WELD CODE FOR WELDING PROCEDURE AND EXAMINATION
23025E04 04 DESIGN OF OFFSHORE PIPELINES

FACILITIES CONSTRUCTION QUALITY CONTROL AND MECHANICAL


27951E03 03
COMPLETION SPECIFICATION

28907E00 00 CARBON STEEL PIPELINES FOR ONSHORE AND OFFSHORE PIPELINES

4017109-A23-001-01 69
PROJECT AND LOCATION DOCUMENT NR.

SN-057-T-N-0017-00
C-047-MCX-23
MELLITAH COMPLEX JOB NUMBER REV. SHEETS / OF

C-047-MCX-23 P1 70/70
CONTRACTOR LOGO SENSIA DOCUMENT NUMBER

4017109-A23-001

MELLITAH OIL & GAS B.V.


LIBYAN BRANCH
BASIS OF DESIGN - METERING, SAMPLING & CONTROL PACKAGE

4017109-A23-001-01 70

You might also like