Media Converter Sample TDS
Media Converter Sample TDS
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All previous cover pages are
hereby superseded and are to be destroyed.
CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 DEFINITIONS
5.0 RESPONSIBILITIES
6.0 EQUIPMENT
7.0 PROCEDURE
8.0 ATTACHMENTS
Project Name
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
INSTALLATION OF LIGHTNING PROTECTION SYSTEM Page 4 of 10
1.0 PURPOSE
This method statement is applicable for Installation Lightning protection system and its accessoiries in all
applicable areas for the Project.
2.0 SCOPE
Supply , installation & Testing of the Lightning protection system for all applications in line with project
requirments.
3.0 REFERENCE
Latest Approved shop drawings for the Lightning protection system.
Specifications
BS EN 62305, Parts 1 to 4, Protection Against Lighting
Project Quality Plan
Material Approval
4.0 DEFINITIONS:
5.0 RESPONSIBILITIES:
6.0 EQUIPMENT:
A. Tools: B. Materials
Drilling Machine
Tool Box 25X3mm Bare Copper Tape
TC030
Sprit Level DC Tape Clips CP210
Measuring Tape Square clamps CT105
Ladders / Scaffoldings U bolt rod clamp Type A,
Hammer Type E (CR105, CR320)
Hacksaw Frame and Blade Air Terminal RA250
Earth Resister Tester. Earth Pits.
Cutter.
Safety requirements tools such as safety shoes, safety helmet, safety glasses, fluorescent vest, and
safety gloves to ensure maximum ability of safe work and dust mask when required.
7.0 PROCEDURE
Check all material delivered to site is inspected properly by QA/QC Engineer and check if it is stored properly as
per manufacturer’s recommendations.
MIR shall be raised for the inspection of materials, Lightning Protection System materials, received at site to the
Consultant Engineer.
Work shall be carried out by the site staff under strict supervision and guidance of the concerned Supervisors /
Foremen / Engineers.
The QA/QC Engineer shall check all the installations as per the Installation Check list.
WIR shall be prepared by QA/QC Engineer and will be submitted to Consultant for their inspection and
approval.
QA/QC Engineer shall coordinate with other contractors and arrange inspection for installation to the
CONSULTANT Engineer.
QA/QC Engineer is responsible for all installation activities for getting the work inspected and approved by
Consultant Engineer.
On receipt of the Lightning Protection System materials at site necessary precautions shall be taken for
unloading, shifting and storage, as follows:
Material shall be stored in a covered / dry space at all the time to avoid being damaged.
All materials received at site shall be inspected and ensured that the materials are as per approved material
Project Name
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
INSTALLATION OF LIGHTNING PROTECTION SYSTEM Page 6 of 10
submittal.
Any discrepancies, damage etc., found will be notified and reported for further action.
Material found not suitable for site use will be removed from site immediately.
Civil clearance for the working area perior to start the work of the system.
The correct materials shall be ascertained from approved shop drawings and material submittals before
installation.
The installation of the lighting protection will be as per approved shop drawings and as per manufacturer
recommendation and project specification as shown in Figure #.1.
Figure #1
Connections between ground rods and structural steel columns shall be made with heavy duty Class II
copper conductor.
Connection of the Earth pits will as per agreed with Consultant and as per manufacturer recommendation
and project specification. See below Figure #2. For the Earth pit connection details.
Project Name
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
INSTALLATION OF LIGHTNING PROTECTION SYSTEM Page 7 of 10
Figure #.2
All earth pits for the lighting protection has to be tested by checking the continuity of the earth pits and the
final Air terminal connected in the roof and all the results has to be recorded in the attached testing sheet.
In the roof make sure to Mark the location of the tape as per approved layout drawing.
Check the distance between clips in horizontal route shall not be more than 1000mm and in vertical route
shall be 500mm if applicable as shown in figure #. 3.
Figure #3
Project Name
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
INSTALLATION OF LIGHTNING PROTECTION SYSTEM Page 8 of 10
All mechanical and electrical equipment on the roof shall be bonded to the lightning protection system as
required.
A minimum of 2400 mm copper electrode shall be provided with each down conductor separately.
However, the Specialist Lightning Protection Installer shall submit the calculation for deciding the number
of earth rods in each earth pit. Wherever the soil resistivity is low (typically below <20 Ω /m), the
Specialist Lightning Protection Installer must use either copper rods or stainless steel rods to ensure the
longitivity of the earth termination network.
Measure the resistance of the complete installation and submit for review to the CONSULTANT.
The complete Lightning Protection System measured at any point, should not exceed 10 ohms. With the
test clamp disconnected, the resistance of each individual earth should be no more than ten times the
number of down conductors in the complete system. as per Specifications.
The terminated head of each electrode shall be located in a light weight inspection pit. If clear earth is not
available, then the Specialist Lightning Protection Installer has to install the earth pit inside the building
using double flange earth electrode seals.
Test clamps shall be provided in each inspection pit to allow for testing and commissioning.
Concrete inspection pits with cover shall be installed flush with finished floor level and be fully accessible.
All metallic parts protruding outside the extended air termination network shall be connected to the air
termination using suitable clamps at every floor wherever the horizontal conductor is applied.
Make sure that the air terminal network layout to be coordinated with the mechanical equipment on the
roof.
This air terminal shall be installed at a suitable separation distance so that the partial lightning current
doesn’t flow through the equipment as per manufacturer recommendation, project specification and
approved shop drawing. Refer to Figure #3 & Table #.1 for the length/height of the Air terminal.
Schedule #1
Submit WIR when the installation of Lightning Protection System is completed to the Consultant.
8.0 ATTACHMENTS
Project Name
TITLE Ref. No. :
METHOD STATEMENT FOR REV. No. 0
Date :
INSTALLATION OF LIGHTNING PROTECTION SYSTEM Page 9 of 10