Test C
Test C
The number of occupants, their function, and the occupancy schedules for the building would be noted in
which document?
B The Cx Report
Notes:
See the Further Explanation in the prerequisite for the different document types and what each includes
(too extensive to include here). Test-takers should be familiar with the content that goes into each of the
following:
OPR
BOD
Cx Plan
CFR
Question 2 of 100
A technology firm is deciding on a location to build a new data center. Which of the following sites would
be most appropriate?
C Land with a plant species from the State threatened species list
Notes:
The 'developed site' would be most appropriate because the site was already developed. A previously
developed site doesn't have to meet the same requirements for LT Credit Sensitive Land Protection The
other answer choices fail to meet the requirements of the credit.
Sites cannot have endangered species on them and meet the requirements.
The undeveloped land near the stream must be more than 50 feet (not 41 feet) from the stream.
The land near the wetland must be more than 50 feet away.
The tree nursery is not correct because the land is prime farmland.
Question 3 of 100
Which action must a project team take for implementation of the Integrative Process credit?
D Document how the analysis informed building and site design decisions in the project's OPR and
BOD
For the credit, a narrative must be included that documents how analyses informed design.
Notes:
Question 4 of 100
A project will include a unique manufacturing process resulting in non-regulated load savings. Which
statement is true regarding how these savings would be addressed in a whole building energy simulation?
D The non-regulated load is subtracted from both the baseline and design case model
Notes:
A non-regulated load is 'any building load, end-use or control which does not have an ASHRAE 90.1-2010
baseline modeling requirement that allows the load and use or control to be modeled differently in the
Question 5 of 100
Regional priority credits are specific to:
Each LEED project type may have different impacts so each rating system has its own RP credits.
For example a warehouse may not have high priority for indoor water use if there are not a lot of
occupants.
Question 6 of 100
When installing artificial lighting, which light source will approximate natural light?
B A light source with a ratio of average ceiling illuminance to work surface illuminance that does not
exceed 1:10
C Task lighting
Notes:
Option 2 Lighting Quality of EQ Interior Lighting has eight strategies. Understand the methodology behind
each of these strategies, which are listed in the Behind the Intent section.
Question 7 of 100
A project team conducted a site inventory followed by a site analysis. Which actions exemplify design
decisions based on the site assessment?
A Using a soil analysis to locate community gardens
A site assessment includes a soil analysis, which could indicate where things get planted on the
site.
B Selecting a project site near a bicycle network that has at least 10 diverse uses
C Locating a functional entry within 1/4 mile (400 meters) of a bus stop
While the orientation of the building is effected by a site analysis, the location of functional entries
is probably not.
D Locating operable windows for occupants on the lee side of a building, away from pollution
sources
Building orientation is influenced by the climate features found from a site assessment.
Notes:
Some of the ways that a site assessment could influence the design are as follows:
Locating buildings based on view corridors, transportation infrastructure, and adjacent properties;
Incorporating natural ventilation by utilizing prevailing winds and seasonal wind patterns while also
Optimizing on-site rainwater management based on soil types and existing vegetation.
Question 8 of 100
An office has an open floor plan. Which element should be incorporated into the schematic design to
minimize solar heat gains while still admitting daylight?
A Exterior shading
This is the only choice that impacts both daylighting and minimizing solar heat gain.
This would help increase daylight in the interior but not minimize solar heat gains.
C Furniture selection
Furniture selection impacts interior daylighting but not minimizing solar heat gains.
This would help increase daylight in the interior but not minimize solar heat gains.
Notes:
Question 9 of 100
To be successful with MR Prerequisite Storage and Collection of Recyclables, who should assist in
providing input on space requirements and the best infrastructure required for collection?
B An architect
C A project owner
D Building occupants
Notes:
While the architect, owner, and occupants might assist with space requirements, only the waste
hauler/recycling provider can assist with the infrastructure required for collection. For example, if there
will be dumpsters in the back of the building, can the trucks get to and load them? If a compactor will be
Question 10 of 100
When designing for flexibility, project teams should focus on the portions of the building typically subject
to change, which include all of the following EXCEPT:
A Parking areas
B HVAC services
C Department layouts
D Movable furniture
Notes:
The credit focuses on the space plan, services, and movable items.
Question 11 of 100
For good acoustic design, designers would need to specify sound-absorbing treatments to address:
A Sound reinforcement
D Sound isolation
Question 12 of 100
In which ways can a project team influence change if a LEED project is not already located near a bicycle
network or a transit stop?
A By seeing if the local transit agency will commit to providing additional service the project
B By getting the local government to commit to striping bike lanes or lower the street speed limit
D By working with the county commission to add more traffic routes or lanes to the project
Notes:
Question 13 of 100
A project team for a school wants to increase the daylighting and views for students in classrooms. What
issue should be considered if the design team chooses to increase the amount of glazing?
C Increased glazing will decrease the opportunity for thermal comfort control
Notes:
More glazing results in less wall space and glazing can result in more heat gain and loss.
Question 14 of 100
Which type of project would require the project team to conduct a whole-building life-cycle assessment
for MR Credit Building Life-Cycle Impact Reduction?
Notes:
Question 15 of 100
How can a project team avoid errors and expenses in LEED documentation prior to submitting the project
for review?
B Require that each person assigned to a credit store their own documentation until submission
C Request that the USGBC LEED reviewer does a quality assurance review
D Verify that numeric values (FTE, site area, etc.) are consistent across credits
E Wait until the project is substantially complete before collecting material quantities
Notes:
Proofreading, checking numerical values for consistency across credits, and checking the application for
Question 16 of 100
A LEED BD+C: Healthcare project must meter how many water subsystems for WE Credit Water Metering?
A 7
The healthcare adaptation requires metering five subsystems in addition to the two subsystems
required for LEED BD+C: New Construction projects.
B 4
C 2
D 5
Question 17 of 100
Which information must a project team calculate in order to manage rainwater on site when the team has
determined natural land-cover conditions?
B The total runoff volume of just the developed areas on the site
All areas are included.
Both the natural land-cover volume and the runoff volume under post-developed conditions are
needed.
Notes:
Question 18 of 100
If a project team is going to use aerators without a WaterSense label in private lavatories as part of a
strategy to meet WE Prerequisite Indoor Water Use Reduction, which is the maximum flow rate allowed?
Question 19 of 100
The LEED project boundary may not include land that is owned by a party other than that which owns the
LEED project unless:
D The land is associated with and supports normal building operations for the LEED project building
The only exception to the LEED project boundary of land not owned by the project owner is land
that is associated with and supports normal building operations for the LEED project building.
Question 20 of 100
A new school project is being modeled for energy use. The baseline building project has an energy cost of
$225,282 / year. The proposed building has an energy cost of $129,750 / year. How much additional
energy must be saved to earn Innovation credit for exemplary performance for optimizing energy
performance?
A $8,098
B $24,239
C $17,109
D $21,614
Notes:
Remember, exemplary performance credits are earned through the Innovation credit.
The following minimum energy cost savings would earn Innovation credit
Option 1, New construction, major renovation, and core and shell projects can earn exemplary
In this example the project was a new school. The project must achieve at least a 54% energy savings:
Question 21 of 100
A school project will monitor CO2 concentrations and increase the ventilation of the building. The project
has mechanical ventilation. Which of the following spaces would need to be monitored to earn a point for
IEQ Credit Enhanced IAQ Strategies?
Notes:
The key to this credit is to know only densely occupied spaces are monitored. These spaces have 25 or
more people per 1,000 square feet. The only answer choice that met this criteria was the conference
room.
Question 22 of 100
Which action must a project team take to achieve WE Prerequisite Building-Level Water Metering?
D Install permanent water meters for any water subsystem consuming at least 10% of the project's
water use
Notes:
The building and grounds have to be metered for potable water use. The data must be shared with USGBC
The building water and the associated grounds water can either be metered together or separately.
Question 23 of 100
A mechanical engineer and architect are evaluating ventilation strategies for a school project in a dense
urban area. Which project information should they start with in order to inform their design decisions?
B Building form
C Building orientation
The quality of the outdoor air plays an important role in the ventilation strategy. For example, in a
location with poor outdoor air quality, natural ventilation is not a good choice and mechanical
ventilation would require attention to filtration.
Next to the outdoor air quality, the building form, orientation, and depth of the floor plate can
impact the different types of ventilation selected.
Question 24 of 100
Which systems need to be metered for individual energy use for EA Credit Advanced Energy Metering?
A Two space-cooling systems that each use 6% of the total annual consumption of the building
B Interior lighting that represents 13% of the total annual consumption of the building
D Two space-heating systems that run on opposite schedules and each use 4% of the total annual
consumption of the building
Notes:
If a project is pursuing the EA Credit Advanced Energy Metering, all energy end-uses that contribute at
Question 25 of 100
For a mixed-use office and residential project, which space qualifies as outdoor space for SS Credit Open
Space?
A An intensive green roof that is not physically accessible
C A bicycle network located within 100 yards (30 meters) of functional building entrance
Note athletic fields with turf grass DO count toward this credit, but there is a limit to how much
turf grass the project can have for the credit.
Outdoor space minimum: 30% of the total site area (including building footprint).
Of that 30%, 25% must be vegetated (not turf grass) or have an overhead vegetated canopy (such
as trees).
Notes:
Question 26 of 100
Which water-budget information provides enough data for use in the Discovery phase of water-related
systems?
A Data revealing that the building's indoor fixtures will use 10,000 gallons of water (37,854 liters)
Water budgets need to include indoor, outdoor, process, makeup water, and on-site supply water
offsets. This choice only has indoor water use.
B Data concluding that a rainwater collection system will supply 20,000 gallons (75,708 liters) of
water per year
This data is only the offset of the on-site supply. Water budgets need to include indoor, outdoor,
process, makeup water, and on-site supply water offsets.
C A week's worth of data showing that 5,000 gallons (18,900 liters) of water will be used
Water budgets are associated with a specific period of time (week, month, or year) and a quantity
of water (gallons or liters), both of which are included in this choice.
Water budgets need to include indoor, outdoor, process, makeup water, and on-site supply water
offsets.
Notes:
Question 27 of 100
A project team hired a water-treatment professional to analyze the makeup water for a cooling tower and
received the following results:
Which is the maximum number of cycles of concentration for this makeup water?
Notes:
To find this answer, divide the maximum allowable concentrations by the makeup water concentrations for
each parameter.
Question 28 of 100
A general contractor is working on documenting the quantity of materials reuse for a project. If a salvaged
material came from on-site, how will the contractor determine the replacement value of the material?
A Using a comparable material in the local market, excluding labor and shipping
B Using a comparable material in the local market, including labor and shipping
Material reuse is based on the total cost of the materials and the total cost of any reused/salvaged
materials.
If a salvaged material came from on-site, the replacement value of the material is determined by
comparing the material to something available in the local market. Labor and shipping are excluded, as
Question 29 of 100
A project team member was not clear about the specifications for building materials, and a contractor
substituted a product with disclosure documentation for a product without disclosure documentation. The
replacement product has a Green Screen v1.2 Benchmark. How should the product be treated as it applies
to MR Credit Building Product Disclosure and Optimization - Material Ingredients?
A Exclude the product from both the disclosure and optimization options
C Include the product in both the disclosure option and the optimization option
D Exclude the product from the disclosure option and include it in the optimization option
Notes:
Each Building Disclosure and Optimization credit has an option for disclosure and another option for
optimization. Each option is worth 1 point, and projects can earn 2 points each for the credit.
Earning 1 point for Option 2 optimization is allowed without earning Option 1 disclosure for each credit.
In this scenario, the product does not have disclosure (because the product was substituted), but it does
have optimization by having the Green Screen v1.2 Benchmark which counts toward Option 2.
Question 30 of 100
Which first step must all projects take before attempting EA Prerequisite Minimum Energy Performance?
Notes:
Question 31 of 100
How can a project owner share building-level watering meter data with USGBC on a monthly basis?
Notes:
Project owners have two choices for sharing water use data:
Third-party data source. The project owner commits to providing water consumption data to USGBC and
acknowledges that USGBC will only accept the data in an approved third-party source or format.
USGBC- approved data template. The project owner commits to providing water consumption data to
USGBC and acknowledges that USGBC will only accept the data using ENERGY STAR's Portfolio Manager
Question 32 of 100
Which of the following would be classified as a private lavatory faucet?
'The Uniform Plumbing Code, International Plumbing Code, and the National Standard Plumbing
Code each define private as those fixtures in residences, hotel or motel guest rooms, and private
rooms in hospitals. All other applications are deemed to be public.' - USGBC
Question 33 of 100
For a LEED BD+C: School Project, which details will the project team need to show regarding pedestrian
access to the school for LT Credit Access to Quality Transit?
Project teams pursuing Option 2: Pedestrian Access need to delineate a walkshed boundary using
mapping software (GIS or CAD). The walkshed boundary varies based on the age or grade level of
the school. Points are earned based on the percentage of students in the boundary.
D Functional entries within a 1/4-mile (400 meter) walking distance of bus lines
Question 34 of 100
Which description is an example of extended producer responsibility?
A A ceiling tile manufacturer that takes back the product at the post-consumer stage of the
product's life cycle
B A manufacturer that works with raw materials suppliers to enhance the working conditions of
laborers
C A manufacturer that identifies, documents, and communicates information on the health, safety,
and environmental characteristics of chemical ingredients
Notes:
Question 35 of 100
A project team has decided to pursue LEED certification during early construction. Which statement is true
about the project's ability to achieve SS Prerequisite Construction Activity Pollution Prevention?
A Only those areas that are relevant to the site at the time of project registration must be followed
in the ESC Plan.
B The prerequisite does not apply, since construction has already begun.
C A compliant ESC plan must have been in place prior to construction to earn the prerequisite.
A project in the design phase may have to create or modify an ESC plan for certification.
A project in the construction phase that doesn't have a compliant ESC plan cannot be LEED-
certified, since the prerequisite can't be met.
Question 36 of 100
As an alternative refrigerant to HCFC a project team is considering HFC-410A. What is the trade-off to
when using HFC-410A in the HVAC&R system?
D May require more energy to achieve the same level of cooling as HCFC
It has a lower GWP but require more energy to achieve the same level of cooling.
Question 37 of 100
Energy-related research for the Integrative Process credit should include all EXCEPT which element?
A Site conditions
B Local climate
Public transportation proximity does not have a significant (if any) impact on the building's energy
use.
Question 38 of 100
The commissioning authority, with the help of the design team and contractors, is writing functional test
scripts for a new school building. Which order will the test scripts typically follow?
Test scripts typically follow the sequence of operations created by the engineers.
Question 39 of 100
An office park will contain 450 parking spaces. There will be 30 preferred parking spaces and 3 spaces for
van or carpools. The team wants to earn a point for Sustainable Sites Credit Heat Island Reduction by
placing parking underground. What should be done to earn the credit?
Notes:
Place a minimum of 75% parking spaces under cover. This project has a total of 450 parking spaces; all
other numbers are not relevant. To meet the requirements of this credit the project can place 338 parking
spaces under cover - underground will qualify since the ground does not contribute to the heat island
effect.
If the parking were covered by a material, that material would have to have an initial SRI of at least 39 or
Question 40 of 100
A project team is pursuing both LT Credit Reduced Parking Footprint and LT Credit Green Vehicles. Which
statement is true in order for the team to obtain both of these credits?
A Signage for carpool and vanpool vehicles and green vehicles may be combined if 5% of the total
parking capacity is reserved with this signage.
B Preferred parking spaces can be shared for carpools/vanpools and green vehicles.
C Enough preferred parking must be provided for both green vehicles and carpools/vanpools.
The spaces can't be double counted if the project team is pursuing both credits.
D Preferred parking is required for green vehicles only.
Notes:
Question 41 of 100
A client is assessing the value LEED certification for an office project in a suburban area. All of the
following are values and benefits of green building except:
Notes:
LEED-certified buildings cost less to operate, reducing energy and water bills by as much as 40%.
Businesses and organizations across the globe use LEED to increase the efficiency of their buildings,
freeing up valuable resources that can be used to create new jobs, attract and retain top talent, expand
LEED buildings have faster lease-up rates and may qualify for a host of incentives like tax rebates and
Question 42 of 100
A project in a dense location calculated a parking reduction for LT Credit Reduced Parking Footprint that
falls below the local code minimum design threshold. Which action should the project team take to earn
the credit?
This is the only choice that will reduce the actual number of parking spaces needed by the project
based on the local code. The other choices reduce the demand for spaces.
A Adequate parking
C Toilets
D Shower facilities
Notes:
When a school is providing the facilities (Options 1 and 2) the facility must have a separate entry and
access to toilets.
Question 44 of 100
When mapping the surrounding density within a 1/4 mile (400-meter) radius of the project site from the
site boundary, which details needs to be included in the calculations?
B Buildable land
C Types of buildings
E Parking garages
Notes:
On the map, identify the buildings in the area as either residential, non-residential, or mixed use.
Also include buildable land, which includes all of the land within that 1/4 mile except non-habitat space
such as parking garages, or public rights of way, and land that is excluded from development by law.
The project buildings are also not included in the surrounding density calculations (remember it is
Question 45 of 100
An indoor water use baseline case consists of which information?
A The amount of water used if the project used only code-compliant fixtures and fittings
The baseline comes from the fixtures and fittings flow rates as set by in EPAct 1992
B The amount of water used in all fixtures and fittings, minus any alternative water supplies
(graywater, rainwater, etc.)
C The amount of water used by the fixtures and fittings selected for the project
D The amount of water used if the project uses all WaterSense labeled fixtures
Question 46 of 100
The following items were removed from a renovation project and will not be reused. What item must be
included in the calculations for Materials and Resources Credit Construction and Demolition Waste
Management?
A Asbestos tiles
C Land-clearing debris
D Excavated soil
Notes:
The carpet would need to be included in the calculations for the total of all construction waste
management. If the carpet were recycled or donated it would be included in the percentage of
Excavated soil and land-clearing debris are excluded from the calculations.
Question 47 of 100
Qualified resources for EA Credit Green Power must have come online since which date?
Question 48 of 100
A project team reviews a project design and finds that the design does not comply with SR Credit Heat
Island Reduction using the standard non-roof/roof calculation due to the project having multiple roof
angles and materials that fall above and below the minimum SRI and SR values. Which action should the
project team take next?
A Use the weighted non-roof/roof calculation to see if the design will comply
B Submit a CIR for clarification on the how the roof angles can be calculated
Parking under cover is for Option 2. This question is asking about Option 1.
If after the project team finds that equation 1 and equation 2 don't yield the desired results, the
design needs to be addressed.
Notes:
Question 49 of 100
What products would be included in the threshold level of compliance for emissions and content standards
for low-emitting materials in an office project?
C Acoustic insulation
D Carpet pads
Flooring is included.
Notes:
Option 1 for the credit includes interior paints, coatings, adhesives, sealants, flooring, composite wood,
ceilings, wall, thermal and acoustic insulation, and furniture as applicable to the project's scope of work.
There are 7 categories. Points are awarded based on the number of compliant categories of products.
Question 50 of 100
For each of the Building Disclosure and Optimization credits, a project's structure and enclosure materials
may not constitute more than which percentage of the total value of compliant building materials?
A 20%
B 45%
C 30%
D 25%
Notes:
Once that 30% cap is reached, the value of the structure and enclosure materials cannot count toward the
cost of the compliant products. Their value is still included in the total product cost. This requirement is in
place to encourage the demand for sustainability for less expensive materials or materials.
Question 51 of 100
A company is building a distribution center near an airport. Which additional criteria, if present, would
earn the project LT Credit Surrounding Density and Diverse Uses?
A If the site is within a 1/2-mile (800 meters) driving distance to a freight line
This is correct. The maximum is 1 mile (1,600 meter) for a freight line and this site is within a 1/2
mile (800 meters). Remember questions won't always have identical values to the requirements
because they test real-world examples. Most projects don't have the exact minimum or maximum
distances of the requirements.
Highway on-ramps have a 1-mile (1,600 meter) limit, not 2 miles (3.2 km).
This is referring to Option 1 Development and Adjacency. For this option the project must:
Construct or renovate the project on a previously developed site that was used for industrial or
commercial purposes (2 points).
OR
Construct or renovate the project on a site that is both a previously developed and an adjacent
site. The adjacent sites must be currently used for industrial or commercial purposes (3 points).
Notes:
While the credit name is the same between different BD+C adaptations, the options are different for the
following project types:
For distribution centers Option 2 Transportation Resources, the site must be constructed or renovated on
a site that has at least two of the following:
● The site is within a 10-mile (16 kilometer) driving distance of a main logistics hub, defined as an
airport, seaport, intermodal facility, or freight village with intermodal transportation.
● The site is within a 1-mile (1600-meter) driving distance of an on-off ramp to a highway.
● The site is within a 1-mile (1600-meter) driving distance of an access point to an active freight rail line.
● The site is served by an active freight rail spur.
Question 52 of 100
A project team is setting the schedule to conduct air-quality testing for EQ Credit IAQ Assessment. Under
what circumstances must the tests occur?
B During normal occupied hours and while operating at a minimum outdoor airflow rate
Air-quality testing occurs after construction but before occupancy under normal operating
conditions.
C At any time as long as the ventilation system has increased ventilation by at least 30%
D On the weekend when the ventilation system is turned off
Question 53 of 100
A manufacturing plant will install solar car ports in the parking lot to generate onsite electricity. Skylights
will be placed every 40 ft. in the roof of the building for daylighting. The project team is discussing
strategies for Energy and Atmosphere Credit Green Power and Carbon Offsets. What would help achieve
this credit?
A The skylights
C RECs
Notes:
RECs can be purchased, or the green power can be purchased directly or indirectly.
Question 54 of 100
A project team in an area that receives extensive rainfall wants to install a rainwater cistern to supply 75%
of the water needed for irrigation for a LEED BD+C: Healthcare project. The landscape design would
include perennial plants and turf grass irrigated with overhead sprinklers. Which outcome would be the
result of this design?
A The project would earn two points for WE Credit Outdoor Water Use Reduction.
B The project would earn exemplary performance for WE Credit Outdoor Water Use Reduction.
C The project would not meet the requirements of WE Prerequisite Outdoor Water Use Reduction.
D The project would earn one point for WE Credit Outdoor Water Use Reduction.
Notes:
LEED v4 takes an 'efficiency first' approach for the following:
First, make the irrigation more efficient through plant selection and irrigation efficiency. This is necessary
to get to the first 30% reduction for the prerequisite. THEN additional reductions beyond 30% can be
More efficiency
Even if a project uses 100% rainwater for irrigation but has exclusively turf-grass and overhead sprinklers,
the project isn't going to meet the prerequisite. Remember 30% first for efficiency, then alternatives.
Question 55 of 100
Which of the following may earn a project IN Credit Innovation for Innovation?
B Achieving a higher certification level than the one set in the preliminary rating
Other than the higher certification, no other reward exists for a project earning more points than
originally planned for.
LEED does not award projects in any way for having a fully occupied building.
Notes:
Question 56 of 100
Which types of thermal comfort controls contribute to occupant productivity and comfort?
E Thermostats with fixed set-points that can only be adjusted by facility managers
Question 57 of 100
Nearly every credit in the LEED rating system has a direct or indirect impact on human health. Why would a
development firm want to convey this information to clients?
C To communicate green building is healthier and more enjoyable for individuals inside the
buildings leading to increased productivity
D To communicate how the LEED credits selected by the project team will play a vital role in
attracting tenants
Notes:
Question 58 of 100
EQ Prerequisite ETS Control prevents or minimizes exposure of environmental tobacco smoke to all of the
following except:
A Indoor surfaces
B Building occupants
Notes:
Question 59 of 100
A project team is reviewing a simple box energy model for a large commercial building dominated by
external loads. Which strategy can help decrease envelope loads?
A Increasing the insulating value of the glazing and window frame system
Notes:
Question 60 of 100
A warehouse project is located in an extremely arid climate. The project owner has a goal to increase
energy efficiency. Which action would most benefit this project?
A Permeable paving
C Envelope commissioning
Envelope commissioning should be considered where projects are in extreme climates or where
the building is envelope dominated.
D Low-sloped roofing
Notes:
Question 61 of 100
A project includes FSC certified wood costing $150,000 and that was extracted, manufactured, and
purchased 80 miles (128 km) from the project site. What value does the wood have toward MR Credit
Building Disclosure and Optimization - Sourcing of Raw Materials?
A $0
B $200,000
C $150,000
D $300,000
The wood meets a sustainability criteria and is within 100 miles (160 km) of the project, so it is
valued at 200% of cost.
Notes:
1. Sustainability
If the product meets multiple sustainability criteria, it doesn't count more toward the total (salvaged
Question 62 of 100
A project design will include bio retention areas, porous paving, rain gardens, and pervious decking.
Which type of strategies are these?
Question 63 of 100
A project team is working on three medical office buildings located on different sites in the same area.
Which statements are true regarding the construction waste management plan(s) required for the projects?
B The plan(s) must identify at least five types of materials to divert from landfills
D The plan(s) can include hazardous material removal in the project's total waste diversion
A hazardous material removal and disposal plan is required in a CWM plan; however, this doesn't
count toward the total waste diverted or as a separate waste stream (1 of 5 required).
Notes:
Question 64 of 100
A new construction major renovation project is working to convert an historic warehouse into a mixed-use
retail and office building. The project is trying to divert as much construction waste as possible from
landfills. The following is a construction waste management summary. How many points would the project
earn for Materials and Resources Credit Construction and Demolition Waste Management?
Waste Weight
----------------------------------------------
Excavated soil 50 tons
Crushed concrete reused on site 25 tons
Steel sent to a recycling center 1 ton
Wood sent to a recycling center 15 tons
Mixed waste sent to a landfill 25 tons
A 2
B 0
C 3
D 1
Notes:
-Crushed concrete
-Steel
-Wood
Mixed waste sent to the landfill does not count as diverted waste but is included in the calculation of the
41 / 66 = 62.1%
This is enough to earn one point for the credit because the diversion included 3 material streams and met
Question 65 of 100
What is the threshold for an sDA simulation?
A 1,000 lux of direct sunlight for more than 250 hours of the year between 8 AM and 6 PM local
time for a full calendar year
B 300 lux for 50% of the hours between 8 AM and 6 PM local time for a full calendar year
C 30 inches (750 mm) above the finished floor for the default workplane height
D 9 AM on the first equinox (March 21 or September 21) and 3 PM on the second equinox
Notes:
Question 66 of 100
A new school project fell behind schedule and the building flush out will need to occur while the teachers
are in the classrooms preparing for the start of the new school year. When must the flush-out period
occur if the teachers are in the school?
B At the start of occupancy each day, continuing until the last person leaves the building each day
D After the teachers leave each day, continuing until they arrive they next day
Notes:
For an occupied flush-out the flush-out must begin 3 hours prior to occupancy and continue during
occupancy. Occupancy cannot begin until at least 3,500 cu. ft. outside air / sq. ft. of floor area has been
introduced.
Question 67 of 100
Which special considerations would be part of the LEED project scope?
A Underground parking
B Daylight modeling
D An off-site amenity
Notes:
Off-site amenities or shared facilities off site are special considerations, since they fall outside of the LEED
project boundary.
Question 68 of 100
A site project has two landscaped sections: one that requires irrigation and one that does not because it is
Xeriscaped. How should the project team calculate the landscape water budget?
Zero landscape water consumption cannot be entered for any landscaped areas.
For projects in the U.S., WE Prerequisite Outdoor Water Use Reduction Option 2: Reduced Irrigation
requires using the Water Budget Tool.
D By making two separate calculations, one for the irrigation section and one for the unirrigated
area
This is correct. The calculations should be completed twice using the Water Budget Tool, and the
result will be the sum of the two calculations.
Notes:
Question 69 of 100
A project in a hot climate is considering attempting EA Credit Demand Response. Which actions will the
project team need to take in order to participate?
While this is one strategy to reduce demand, it isn't needed for the credit.
Projects must either participate at an existing demand response program for at least 10% of peak
demand or provide infrastructure to take advantage of future demand response autonomic pricing
programs.
Notes:
Question 70 of 100
For which part of the project design would a project team use tracer gas modeling for a 30-story Core and
Shell project?
B Increased ventilation
Exterior contamination prevention requires teams to design the project to minimize and control
the entry of pollutants into the building. Teams demonstrate this through computational fluid
dynamics modeling, Gaussian dispersal analysis, wind tunnel modeling, or tracer gas modeling.
Question 71 of 100
The project owner has designated you to hire the Enhanced Commissioning Authority for a 100,000 sq. ft.
retail center. What restrictions must you ensure the Commissioning Authority meets to qualify for LEED
credit?
Question 72 of 100
A project was registered in January of 2013. In April 2013 USGBC published Addenda for a credit the
project team is pursuing. What statements are true regarding this project?
A The project team must follow any addenda published prior to January, 2013
B The project team can choose to follow any addenda published after April, 2013
C The project team can choose to follow any addenda published prior to January, 2013
D The project team must follow any addenda published in April, 2013
Notes:
Project teams must follow Addenda published prior to their project's registration date. It's strongly
recommended that project teams also follow Addenda published after their registration date.
In this scenario the project must follow addenda prior to January 2013 and can choose to follow any
Question 73 of 100
A project team has purchased 7,500 SF (696 m2) of salvaged wood flooring from a barn at a cost of
$22,500. How can the reused materials be applied toward LEED credits?
A The cost of the flooring can be applied to MR Credit Building Life-Cycle Impact Reduction, Option
3 Building and Material Reuse; AND the cost of the flooring can be applied to MR Credit Building
Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2.
B The surface area of the flooring can be applied to MR Credit Building Life-Cycle Impact Reduction,
Option 3 Building and Material Reuse; AND the cost of the flooring can be applied to MR Credit
Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2.
C The surface area of the flooring can be applied to MR Credit Building Life-Cycle Impact Reduction,
Option 3 Building and Material Reuse; OR the cost of the flooring can be applied to MR Credit
Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2.
D The flooring cost can be applied ONLY to MR Credit Building Product Disclosure and Optimization
- Sourcing of Raw Materials.
Question 74 of 100
A project site contains a large greenfield area, a wetland, and an old parking lot. The new building design
will require building on more than the previously developed area. Which statement is true about the
project's ability to earn LT Credit Sensitive Land Protection?
A The credit can be earned if the project team preserves 30% of the total site area.
This is part of SS Credit Open Space. Don't confuse the requirements and percentages of these
two credits.
B The credit can be earned by not disturbing any sensitive land areas.
If the development footprint will extend beyond previously developed portions of the site, then
the team must pursue Option 2.
The project can earn the credit by building on the previously developed area and not disturbing
sensitive areas.
C The credit can be earned if the project does not build within 50 feet (15 meters) of the wetland.
Notes:
Question 75 of 100
Which is a key strategy for project teams to earn multiple points and credits for the MR Credits for
Building Product Disclosure and Optimization?
Materials that have lots of documentation and sustainable attributes can count toward multiple
credits.
For example in the EPD, credit Option 1 can be earned if materials have an EPD.
Question 76 of 100
A project team is working with school authorities, neighborhood agencies, and outside companies to
identify eligible facilities owned by other organizations that could be made accessible to students. Which
space would count toward SS Credit Joint Use of Facilities?
A A fast-food restaurant within a 1/4-mile (400 meter) walking distance of the main entrance of the
school
Notes:
The space must include direct pedestrian access from the school.
Question 77 of 100
A building owner is reviewing sites that could meet LT Credit Surrounding Density and Diverse Uses.
Which site would earn this credit?
A A site within 1/2 mile (800 meters) of 10 diverse uses accessible by automobile
B A site within 1/2 mile (800 meters) of a residential neighborhood with a density of 7 units per
acre net
This example only provides information on a single neighborhood, not the average
neighborhoods. Also there is no information on the nonresidential density.
C A site within 1/4 mile (400 meters) of two different metro bus lines
D A site in a community with an average combined density of 22,000 SF/acre in the correct density
radius
Notes:
Question 78 of 100
On which factor will a site's lighting design be based?
Prior to any design, the project team must determine what lighting zone the project is in and
justify why that lighting zone was selected.
Question 79 of 100
A project team that selects a high-priority site is likely to fulfill the requirements of which other credit?
The types of sites in LT Credit High-Priority Site are often previously developed, allowing the
project team to meet the requirements of Option 1 of LT Credit Sensitive Land Protection for
building on previously developed land.
Question 80 of 100
A project located in a rural area without a recycling program must take which action for MR Prerequisite
Storage and Collection of Recyclables?
A Separate, store, and collect all recyclables on site prior to sending the items to a landfill
B Submit a project narrative indicating why the project does not have to provide storage and
collection areas for recycling
The prerequisite applies to all projects even if recycling is not currently available in the area.
C Submit a floor plan indicating where the recycling areas might be placed in the future
The prerequisite requires a floor plan indicating where the recycling areas are, not where they
might go.
D Provide storage for recyclables to allow for participation in a future recycling service, should one
be established
The prerequisite applies to all projects even if recycling is not currently available in the area.
Notes:
Question 81 of 100
For mechanically ventilated spaces which design factor must the project team verify are included in order
to meet outdoor air requirements?
Question 82 of 100
Which of the following refrigerants has the least global warming potential?
A HCFC-123
While you don't need to memorize the entire table of ODP and GWP values, note that while HFCs
deplete less ozone, HCFC-123 causes less global warming than any HFC.
B CFC-11
C CFC-12
D HFC-23
Notes:
Question 83 of 100
A 500,000 SF (46,500 m2) mixed-use building pursuing LEED BD+C: New Construction includes office
space and residential space. The office space has 102 regular building occupants and 40 peak visitors.
The residential space has 30 units with 40 residents and 20 peak visitors. How many shower facilities are
required for LT Credit Bicycle Facilities?
A 2
B 1
C 31
D 0
Notes:
Showers need to be provided for commercial and institutional projects. Residential projects do not need
Since this is a mixed-use project with residential space, the residential component of this question can be
ignored.
1 shower/changing room for the first 100 regular building occupants and 1 shower for every 150 more.
They key here is regular building occupants. Visitors don't count in the calculation. The other point to
The office space has 102 regular building occupants. The first 100 require 1 shower. The next 150 require
Question 84 of 100
Orienting a building to take advantage of natural shading features of the site are likely to have which
results?
Maintaining the building would not be more or less hard in this circumstance.
The shading will also decrease the opportunities for daylighting, increasing the need for electric
lighting.
Notes:
Question 85 of 100
Which strategy would help a project team earn exemplary performance for SS Credit Heat Island Reduction
on a project with a zero-lot line and a low-sloped roof?
B Have 100% underground parking and install a vegetated roof on top of the building
For exemplary performance, a project must achieve both Option 1 and Option 2 of the credit, and
for Option 2, 100% of the parking must be under cover.
C Cover 100% of the building roof with a three-year aged SRI material of at least 64
D Cover 100% of the building roof with a material that has an initial SRI of 39
Question 86 of 100
A project team will not pursue points under WE Credit Indoor Water Use Reduction. Which information
should be documented by the MEP engineer for the prescriptive path of WE Prerequisite Indoor Water Use
Reduction?
A Occupancy usage-based calculations
If a project is using the prescriptive path and not pursuing any credits, the credit documentation
would include product cut sheets and fixture schedules showing that all fixtures are Water Sense
labeled or equivalent.
Question 87 of 100
Identifying at least one on-site, non-potable water source that could be used to offset water demand is
required for which credit?
D Integrative Process
For IP credit, discovery requires assessing and estimating potential non-potable water supply
sources.
For IP credit implementation, demonstrate how at least one non-potable water supply source was
used to offset at least two water demand components (indoor, outdoor, process).
That's key for IP credit: Using non-potable water sources is required for the implementation
component. That means for two of the water credits, the project will need to use at least one non-
potable water source for reductions.
Question 88 of 100
Which documentation do project teams need to submit for Integrative Process credit?
A A site assessment
Question 89 of 100
Project teams choosing on-site restoration for SS Credit Site Development - Protect or Restore Habitat
must restore which elements?
A Habitat
C Water buffers
E Soil
Notes:
Question 90 of 100
The use of the CBECS database may be needed in the following credits except:
Notes:
Several credits require the building's annual energy cost for the calculations. The energy cost can come
from the cost calculated in a whole building energy simulation or from the CBECS database.
Question 91 of 100
During the construction phase a contractor has painted a wall with high VOC paint. What is the process to
use to correct the error or submit information to qualify for Indoor Environmental Quality Credit, Low-
Emitting Materials?
A Include the volume of high VOC paint in both the baseline and design case VOC calculations
B Paint over the high VOC paint with an approved low VOC paint
C Subtract the high VOC paint from the design case calculations
Notes:
Question 92 of 100
A three-story retail project has a main entrance on the first level. The building has 420 parking spaces in
an attached three-story garage with an elevator on the second and third levels that allows access to the
main entrance. How many preferred parking spaces are required for LT Credit Green Vehicles, and where
should they be located?
B 7 preferred parking spaces nearest the main entrance and 7 preferred parking spaces nearest the
elevator on the second and third garage levels.
Notes:
If parking is provided on multiple levels of a facility, the preferred parking spaces should be located
B MEP
C Covered parking
E Roof assemblies
F Surface lots
Notes:
This credit requires all that all assessed materials include the complete building envelope and structure
Footings
Foundations
Structural walls
Structural floors
Ceilings
Structural parking
Question 94 of 100
Which design decisions can earn a project IN Credit for exemplary performance?
A Purchasing 50%, by cost, of the total value of permanently installed building products meet the
responsible extraction criteria
B Purchasing 95% of products that are extracted, manufactured, and purchased within 100 miles
(160 kilometers) of the project
This is the location valuation factor. There is no exemplary performance for this.
Notes:
Question 95 of 100
How do renewable energy systems reduce the environmental and economic harms associated with fossil-
fuel energy?
Notes:
Question 96 of 100
A residential building will include a common laundry room, postal area, and heated swimming pool. An
independent CxA has been hired to help the project achieve Energy and Atmosphere Credit Enhanced
Commissioning. What additional activities will the CxA be required for enhanced systems commissioning?
Notes:
There are several responsibilities only the CxA can complete for Enhanced Systems Commissioning. Some
items can be completed by the CxA or other members of the project team. The question specifically asks
for items that the CxA is required to perform. So the correct answers can only be performed by the CxA.
Training can be done by the CxA or other project team member, that is why it is not a correct answer - the
Question 97 of 100
Which elements are not covered under the LEED BD+C: Core and Shell rating system?
A Tenant fit-out
B Envelope
C HVAC system
FF&E are part of the LEED ID+C rating systems. Furniture is also addressed in LEED BD+C.
E Structure
Notes:
Structure
Envelope
HVAC System
Question 98 of 100
Which type of fixture is eligible for WaterSense labels?
A A tankless toilet
B A waterless urinal
C A composting toilet
Notes:
Water-using urinals
Showerheads
Tankless toilet
Composting toilet
Waterless toilet
Waterless urinal
Question 99 of 100
If the requirements described on a credit form do not match the rating system and/or reference guide
material, which action should a project team take next?
If a project team needs guidance on an issue before submitting for certification review, the project
CIR process is available to them. The project CIR will be determined by a GBCI Certification
Reviewer familiar with the project's specific circumstances. The advantage of a project CIR is that
the timeline for a ruling is relatively quick, and the project team can have certainty about the
applicability of their strategy early in the design or implementation process.
For assistance with broken prerequisite/credit forms and/or functionality within leedonline.com,
submit issues via the feedback button, found on every page in leedonline.com.
Requirements as described in the form do not match the rating system and/or reference guide
material or the project team member is having problems logging in, joining a team, or accessing
projects or credits.
This type of formal inquiry is relevant to many projects. These are examples of inquires that, after
receiving a project CIR, would also result in a LEED interpretation if the project team opted into
the LEED-interpretations process.
Notes:
A Glazing
B Light shelves
C Photovoltaic membranes
D Building fenestration
Notes:
Fenestration is any opening in a building's envelope, including windows, doors and skylights.
Building fenestration impacts occupant comfort by the quantity of heat let in from these openings.
Occupants closer to openings receiving direct sunlight will be warmer than those occupants who are
further away. These location differences affect both occupant comfort and the cooling load to make the
building comfortable.
Glazing affects the heat let into the building (occupant comfort and cooling load) and lighting. Light
shelves will help but the building fenestration will make a greater impact and is therefore a better choice.