Longest Path
Longest Path
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total Float 2023 2024
Duration
Oct N D Jan F M A M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D
CONSTRUCTION, COMPLETION & REMEDYING DEFECTS OF PROPOSED396 20-Nov-23
VILLA (G+1) 18-Dec-24 20-Nov-23
+ BOUNDARY WALL18-Dec-24 0 18-Dec-24, CONSTRUCTI
KEY DATES AND MILESTONES 396 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 18-Dec-24, KEY DATES A
CONTRACTUAL MILESTONES 396 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 18-Dec-24, CONTRACTUA
G1.GEN.1000 Project Commencement 0 20-Nov-23 20-Nov-23 0 Project Commencement
G1.GEN.1800 Project Handing Over 0 18-Dec-24 18-Dec-24 0 Project Handing Over
MOBILIZATION & SITE SUPERVISION 339 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 18-Dec-24, MOBILIZATION
MOBILIZATION 22 20-Nov-23 14-Dec-23 20-Nov-23 14-Dec-23 0 14-Dec-23, MOBILIZATION
G1.MOB.1100 Temporary Access roads & Signages 5 20-Nov-23 24-Nov-23 20-Nov-23 24-Nov-23 0 Temporary Access roads & Signages
G1.MOB.1200 Establishment of Site Offices with Facilities 12 25-Nov-23 08-Dec-23 25-Nov-23 08-Dec-23 0 Establishment of Site Offices with Facilities
G1.MOB.1400 Establishment of Welfare areas with facilities 15 28-Nov-23 14-Dec-23 28-Nov-23 14-Dec-23 0 Establishment of Welfare areas with facilities
SITE SUPERVISION & SECURITY 339 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 18-Dec-24, SITE SUPERV
G1.SS.1000 Supervision of Site 339 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 Supervision of Site
G1.SS.1100 Security of Site 339 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 Security of Site
G1.SS.1200 Project Duration (Working Days) 339 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 Project Duration (Working
ENGINEERING WORKS & PROCUREMENT 139 03-Aug-24 18-Dec-24 03-Aug-24 18-Dec-24 0 18-Dec-24, ENGINEERING
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total Float 2023 2024
Duration
Oct N D Jan F M A M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D
G1.C.SUB.GF.2700 Waterproofing for PCC 2 02-Feb-24 03-Feb-24 02-Feb-24 03-Feb-24 0 Waterproofing for PCC
G1.C.SUB.GF.2800 Reinforcement work for Tie Beam 3 03-Feb-24 06-Feb-24 03-Feb-24 06-Feb-24 0 Reinforcement work for Tie Beam
G1.C.SUB.GF.2900 Formwork / Shuttering for Tie Beam 2 05-Feb-24 06-Feb-24 05-Feb-24 06-Feb-24 0 Formwork / Shuttering for Tie Beam
G1.C.SUB.GF.3000 Casting Tie Beam 2 06-Feb-24 07-Feb-24 06-Feb-24 07-Feb-24 0 Casting Tie Beam
G1.C.SUB.GF.3100 Backfilling Up to SOG 2 08-Feb-24 09-Feb-24 08-Feb-24 09-Feb-24 0 Backfilling Up to SOG
GROUND FLOOR SLAB ON GRADE 18 10-Feb-24 01-Mar-24 10-Feb-24 01-Mar-24 0 01-Mar-24, GROUND FLOOR SLAB ON GRADE
G1.C.SUB.GF.3200 Ant termite treatment, Polythene and PCC work (SOG) 1 10-Feb-24 10-Feb-24 10-Feb-24 10-Feb-24 0 Ant termite treatment, Polythene and PCC work (SOG)
G1.C.SUB.GF.3300 Reinforcement work for SOG 3 12-Feb-24 14-Feb-24 12-Feb-24 14-Feb-24 0 Reinforcement work for SOG
G1.C.SUB.GF.3400 Formwork / Shuttering for SOG 2 13-Feb-24 14-Feb-24 13-Feb-24 14-Feb-24 0 Formwork / Shuttering for SOG
G1.C.SUB.GF.3500 Casting SOG 2 15-Feb-24 16-Feb-24 15-Feb-24 16-Feb-24 0 Casting SOG
G1.C.SUB.GF.3600 Curing of SOG 12 17-Feb-24 01-Mar-24 17-Feb-24 01-Mar-24 0 Curing of SOG
SUPER STRUCTURE 36 02-Mar-24 12-Apr-24 02-Mar-24 12-Apr-24 0 12-Apr-24, SUPER STRUCTURE
GROUND FLOOR LEVEL 36 02-Mar-24 12-Apr-24 02-Mar-24 12-Apr-24 0 12-Apr-24, GROUND FLOOR LEVEL
COLUMN & WALL 2 02-Mar-24 04-Mar-24 02-Mar-24 04-Mar-24 0 04-Mar-24, COLUMN & WALL
G1.C.SUP.GF.1300 Casting of Column & Walls 2 02-Mar-24 04-Mar-24 02-Mar-24 04-Mar-24 0 Casting of Column & Walls
COVER SLAB 34 05-Mar-24 12-Apr-24 05-Mar-24 12-Apr-24 0 12-Apr-24, COVER SLAB
G1.C.SUP.GF.1400 Formwork / Shuttering for Cover Slab & Stair 12 05-Mar-24 18-Mar-24 05-Mar-24 18-Mar-24 0 Formwork / Shuttering for Cover Slab & Stair
G1.C.SUP.GF.1500 Reinforcement work for Cover Slab & Stair 12 05-Mar-24 18-Mar-24 05-Mar-24 18-Mar-24 0 Reinforcement work for Cover Slab & Stair
G1.C.SUP.GF.1700 MEP Conduits in Cover Slab 7 11-Mar-24 18-Mar-24 11-Mar-24 18-Mar-24 0 MEP Conduits in Cover Slab
G1.C.SUP.GF.1800 DM Inspection for Casting of Cover Slab & Stair 2 19-Mar-24 20-Mar-24 19-Mar-24 20-Mar-24 0 DM Inspection for Casting of Cover Slab & Stair
G1.C.SUP.GF.1900 Casting of Cover Slab & Stair 2 19-Mar-24 20-Mar-24 19-Mar-24 20-Mar-24 0 Casting of Cover Slab & Stair
G1.C.SUP.GF.2100 De Shuttering of Ground Floor Cover Slab 6 06-Apr-24 12-Apr-24 06-Apr-24 12-Apr-24 0 De Shuttering of Ground Floor Cover Slab
FINISHES WORKS 189 13-Apr-24 19-Nov-24 13-Apr-24 19-Nov-24 0 19-Nov-24, FINISHES WORKS
GROUND FLOOR 189 13-Apr-24 19-Nov-24 13-Apr-24 19-Nov-24 0 19-Nov-24, GROUND FLOOR
COMMON 44 13-Apr-24 03-Jun-24 13-Apr-24 03-Jun-24 0 03-Jun-24, COMMON
BLOCK WORK & PLASTER 44 13-Apr-24 03-Jun-24 13-Apr-24 03-Jun-24 0 03-Jun-24, BLOCK WORK & PLASTER
G1.C.FIN.GF.1000 Block Works Layout 5 13-Apr-24 18-Apr-24 13-Apr-24 18-Apr-24 0 Block Works Layout
G1.C.FIN.GF.1100 Block Works 20 16-Apr-24 08-May-24 16-Apr-24 08-May-24 0 Block Works
G1.C.FIN.GF.1200 Plaster Preparation 5 09-May-24 14-May-24 09-May-24 14-May-24 0 Plaster Preparation
G1.C.FIN.GF.1300 Plaster Inc Sub Frames 20 11-May-24 03-Jun-24 11-May-24 03-Jun-24 0 Plaster Inc Sub Frames
WET AREA 20 15-Jul-24 06-Aug-24 15-Jul-24 06-Aug-24 0 06-Aug-24, WET AREA
FALSE CEILING 20 15-Jul-24 06-Aug-24 15-Jul-24 06-Aug-24 0 06-Aug-24, FALSE CEILING
G1.C.FIN.GF.2000 False Ceiling Suspension 20 15-Jul-24 06-Aug-24 15-Jul-24 06-Aug-24 0 False Ceiling Suspension
DRY AREA 105 20-Jul-24 19-Nov-24 20-Jul-24 19-Nov-24 0 19-Nov-24, DRYAREA
FALSE CEILING 15 20-Jul-24 06-Aug-24 20-Jul-24 06-Aug-24 0 06-Aug-24, FALSE CEILING
G1.C.FIN.GF.2100 False Ceiling Suspension 15 20-Jul-24 06-Aug-24 20-Jul-24 06-Aug-24 0 False Ceiling Suspension
DOOR & WINDOW 20 07-Aug-24 29-Aug-24 07-Aug-24 29-Aug-24 0 29-Aug-24, DOOR & WINDOW
G1.C.FIN.GF.2300 Door Fixing 20 07-Aug-24 29-Aug-24 07-Aug-24 29-Aug-24 0 Door Fixing
PAINT WORK 20 28-Oct-24 19-Nov-24 28-Oct-24 19-Nov-24 0 19-Nov-24, PAINT WORK
G1.C.FIN.GF.3400 Internal Paint Final Coat 20 28-Oct-24 19-Nov-24 28-Oct-24 19-Nov-24 0 Internal Paint Final Coat
1ST FLOOR 69 31-Aug-24 19-Nov-24 31-Aug-24 19-Nov-24 0 19-Nov-24, 1ST FLOOR
WET AREA 25 28-Sep-24 26-Oct-24 28-Sep-24 26-Oct-24 0 26-Oct-24, WET AREA
ACCESSORIES 25 28-Sep-24 26-Oct-24 28-Sep-24 26-Oct-24 0 26-Oct-24,ACCESSORIES
G1.C.FIN.1F.3000 Installation of Kitchen Units - Frames 12 28-Sep-24 11-Oct-24 28-Sep-24 11-Oct-24 0 Installation of Kitchen Units - Frames
G1.C.FIN.1F.3200 Installation of Kitchen Units - Panels 18 07-Oct-24 26-Oct-24 07-Oct-24 26-Oct-24 0 Installation of Kitchen Units - Panel
DRY AREA 69 31-Aug-24 19-Nov-24 31-Aug-24 19-Nov-24 0 19-Nov-24, DRYAREA
DOOR & WINDOW 20 31-Aug-24 23-Sep-24 31-Aug-24 23-Sep-24 0 23-Sep-24, DOOR & WINDOW
G1.C.FIN.1F.2500 Door Fixing 20 31-Aug-24 23-Sep-24 31-Aug-24 23-Sep-24 0 Door Fixing
PAINT WORK 20 28-Oct-24 19-Nov-24 28-Oct-24 19-Nov-24 0 19-Nov-24, PAINT WORK
Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total Float 2023 2024
Duration
Oct N D Jan F M A M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D
G1.C.FIN.1F.3400 Internal Paint Final Coat 20 28-Oct-24 19-Nov-24 28-Oct-24 19-Nov-24 0 Internal Paint Final Coat
MEP WORKS 50 04-Jun-24 31-Jul-24 04-Jun-24 31-Jul-24 0 31-Jul-24, MEP WORKS
GROUND FLOOR 50 04-Jun-24 31-Jul-24 04-Jun-24 31-Jul-24 0 31-Jul-24, GROUND FLOOR
MEP 2nd Fix 50 04-Jun-24 31-Jul-24 04-Jun-24 31-Jul-24 0 31-Jul-24, MEP 2nd Fix
HVAC 50 04-Jun-24 31-Jul-24 04-Jun-24 31-Jul-24 0 31-Jul-24, HVAC
G1.C.MEP.GF.2000 AC Ducting Work 30 04-Jun-24 08-Jul-24 04-Jun-24 08-Jul-24 0 AC Ducting Work
G1.C.MEP.GF.2100 FCU's Installation 30 04-Jun-24 08-Jul-24 04-Jun-24 08-Jul-24 0 FCU's Installation
G1.C.MEP.GF.2400 FCU's Valve Assembly 20 09-Jul-24 31-Jul-24 09-Jul-24 31-Jul-24 0 FCU's Valve Assembly
G1.C.MEP.GF.2500 Condensate Pipe lnstallation 20 09-Jul-24 31-Jul-24 09-Jul-24 31-Jul-24 0 Condensate Pipe lnstallation
G1.C.MEP.GF.2600 Copper Pipe lnstallation 20 09-Jul-24 31-Jul-24 09-Jul-24 31-Jul-24 0 Copper Pipe lnstallation
PROJECT CLOSEOUT & HANDING OVER 25 20-Nov-24 18-Dec-24 20-Nov-24 18-Dec-24 0 18-Dec-24, PROJECT CLO