Longest Path

Uploaded by

Aslam Mohammad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

Longest Path

Uploaded by

Aslam Mohammad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

PROPOSED VILLA and BOUNDARY WALL

Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total Float 2023 2024
Duration
Oct N D Jan F M A M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D
CONSTRUCTION, COMPLETION & REMEDYING DEFECTS OF PROPOSED396 20-Nov-23
VILLA (G+1) 18-Dec-24 20-Nov-23
+ BOUNDARY WALL18-Dec-24 0 18-Dec-24, CONSTRUCTI

GENERAL 396 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 18-Dec-24, GENERAL

KEY DATES AND MILESTONES 396 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 18-Dec-24, KEY DATES A
CONTRACTUAL MILESTONES 396 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 18-Dec-24, CONTRACTUA
G1.GEN.1000 Project Commencement 0 20-Nov-23 20-Nov-23 0 Project Commencement
G1.GEN.1800 Project Handing Over 0 18-Dec-24 18-Dec-24 0 Project Handing Over
MOBILIZATION & SITE SUPERVISION 339 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 18-Dec-24, MOBILIZATION
MOBILIZATION 22 20-Nov-23 14-Dec-23 20-Nov-23 14-Dec-23 0 14-Dec-23, MOBILIZATION
G1.MOB.1100 Temporary Access roads & Signages 5 20-Nov-23 24-Nov-23 20-Nov-23 24-Nov-23 0 Temporary Access roads & Signages
G1.MOB.1200 Establishment of Site Offices with Facilities 12 25-Nov-23 08-Dec-23 25-Nov-23 08-Dec-23 0 Establishment of Site Offices with Facilities
G1.MOB.1400 Establishment of Welfare areas with facilities 15 28-Nov-23 14-Dec-23 28-Nov-23 14-Dec-23 0 Establishment of Welfare areas with facilities
SITE SUPERVISION & SECURITY 339 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 18-Dec-24, SITE SUPERV
G1.SS.1000 Supervision of Site 339 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 Supervision of Site
G1.SS.1100 Security of Site 339 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 Security of Site
G1.SS.1200 Project Duration (Working Days) 339 20-Nov-23 18-Dec-24 20-Nov-23 18-Dec-24 0 Project Duration (Working
ENGINEERING WORKS & PROCUREMENT 139 03-Aug-24 18-Dec-24 03-Aug-24 18-Dec-24 0 18-Dec-24, ENGINEERING

ALUMINUM PERGOLA 139 03-Aug-24 18-Dec-24 03-Aug-24 18-Dec-24 0 18-Dec-24,ALUMINUM PE


G1.ENG.ALP.1000 Submission of PQ of subcontractor for Aluminum Pergola 11 03-Aug-24 16-Aug-24 03-Aug-24 16-Aug-24 0 Submission of PQ of subcontractor for Alumin
G1.ENG.ALP.1100 Approval of sub contractor forAluminum Pergola 11 16-Aug-24 29-Aug-24 16-Aug-24 29-Aug-24 0 Approval of sub contractor forAluminum Pe
G1.ENG.ALP.1200 Submission of Material 11 29-Aug-24 11-Sep-24 29-Aug-24 11-Sep-24 0 Submission of Material
G1.ENG.ALP.1300 ContractAgreement Preparation/Finalization 17 05-Sep-24 25-Sep-24 05-Sep-24 25-Sep-24 0 ContractAgreement Preparation/Finaliz
G1.ENG.ALP.1400 Approval of Material 11 11-Sep-24 25-Sep-24 11-Sep-24 25-Sep-24 0 Approval of Material
G1.ENG.ALP.1500 Submission of Shop Drawing 11 25-Sep-24 08-Oct-24 25-Sep-24 08-Oct-24 0 Submission of Shop Drawing
G1.ENG.ALP.1600 Approval of Shop Drawing by Consultant 11 08-Oct-24 21-Oct-24 08-Oct-24 21-Oct-24 0 Approval of Shop Drawing by Cons
G1.ENG.ALP.1700 Delivery of Material 60 21-Oct-24 18-Dec-24 21-Oct-24 18-Dec-24 0 Delivery of Material
CONSTRUCTION 292 15-Dec-23 19-Nov-24 15-Dec-23 19-Nov-24 0 19-Nov-24, CONSTRUCTION

SUBSTRUCTURE WORKS 67 15-Dec-23 01-Mar-24 15-Dec-23 01-Mar-24 0 01-Mar-24, SUBSTRUCTURE WORKS


GROUND FLOOR 67 15-Dec-23 01-Mar-24 15-Dec-23 01-Mar-24 0 01-Mar-24, GROUND FLOOR
EARTHWORK 25 15-Dec-23 12-Jan-24 15-Dec-23 12-Jan-24 0 12-Jan-24, EARTHWORK
G1.C.SUB.GF.1100 Excavation for Foundation 16 15-Dec-23 02-Jan-24 15-Dec-23 02-Jan-24 0 Excavation for Foundation
G1.C.SUB.GF.1200 Anti termite & Blinding for Foundation 2 03-Jan-24 04-Jan-24 03-Jan-24 04-Jan-24 0 Anti termite & Blinding for Foundation
G1.C.SUB.GF.1300 MEP Works below Grade Slab 4 05-Jan-24 09-Jan-24 05-Jan-24 09-Jan-24 0 MEP Works below Grade Slab
G1.C.SUB.GF.1400 Excavation & Leveling & Compaction for Footing 3 10-Jan-24 12-Jan-24 10-Jan-24 12-Jan-24 0 Excavation & Leveling & Compaction for Footing
FOOTING 10 13-Jan-24 24-Jan-24 13-Jan-24 24-Jan-24 0 24-Jan-24, FOOTING
G1.C.SUB.GF.1500 Ant termite treatment, Polythene and PCC work 2 13-Jan-24 15-Jan-24 13-Jan-24 15-Jan-24 0 Ant termite treatment, Polythene and PCC work
G1.C.SUB.GF.1600 Waterproofing for PCC 2 16-Jan-24 17-Jan-24 16-Jan-24 17-Jan-24 0 Waterproofing for PCC
G1.C.SUB.GF.1700 Reinforcement work for Footing 5 18-Jan-24 23-Jan-24 18-Jan-24 23-Jan-24 0 Reinforcement work for Footing
G1.C.SUB.GF.1800 Formwork / Shuttering for Footing 2 22-Jan-24 23-Jan-24 22-Jan-24 23-Jan-24 0 Formwork / Shuttering for Footing
G1.C.SUB.GF.1900 DM Inspection for Casting of Footing 1 24-Jan-24 24-Jan-24 24-Jan-24 24-Jan-24 0 DM Inspection for Casting of Footing
G1.C.SUB.GF.2000 Casting of Footing 1 24-Jan-24 24-Jan-24 24-Jan-24 24-Jan-24 0 Casting of Footing
NECK COLUMN & TIE BEAMS 14 25-Jan-24 09-Feb-24 25-Jan-24 09-Feb-24 0 09-Feb-24, NECK COLUMN & TIE BEAMS
G1.C.SUB.GF.2100 Reinforcement work for Neck Colum 2 25-Jan-24 26-Jan-24 25-Jan-24 26-Jan-24 0 Reinforcement work for Neck Colum
G1.C.SUB.GF.2200 Formwork / Shuttering for Neck Colum 2 25-Jan-24 26-Jan-24 25-Jan-24 26-Jan-24 0 Formwork / Shuttering for Neck Colum
G1.C.SUB.GF.2300 Casting Neck Column 2 26-Jan-24 27-Jan-24 26-Jan-24 27-Jan-24 0 Casting Neck Column
G1.C.SUB.GF.2400 Waterproofing for Neck Column & Footing 3 27-Jan-24 30-Jan-24 27-Jan-24 30-Jan-24 0 Waterproofing for Neck Column & Footing
G1.C.SUB.GF.2500 Back Filling Up to Tie Beam Level 2 31-Jan-24 01-Feb-24 31-Jan-24 01-Feb-24 0 Back Filling Up to Tie Beam Level
G1.C.SUB.GF.2600 Ant termite treatment, Polythene and PCC work (Below Tie Beam) 2 01-Feb-24 02-Feb-24 01-Feb-24 02-Feb-24 0 Ant termite treatment, Polythene and PCC work (Below Tie Beam)

Actual Work Summary Date Revision Checked Approved


Baseline Program Of Work - Rev 0
Remaining Work Page 1 of 3
Critical Remaining Work
Milestone
PROPOSED VILLA and BOUNDARY WALL

Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total Float 2023 2024
Duration
Oct N D Jan F M A M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D
G1.C.SUB.GF.2700 Waterproofing for PCC 2 02-Feb-24 03-Feb-24 02-Feb-24 03-Feb-24 0 Waterproofing for PCC
G1.C.SUB.GF.2800 Reinforcement work for Tie Beam 3 03-Feb-24 06-Feb-24 03-Feb-24 06-Feb-24 0 Reinforcement work for Tie Beam
G1.C.SUB.GF.2900 Formwork / Shuttering for Tie Beam 2 05-Feb-24 06-Feb-24 05-Feb-24 06-Feb-24 0 Formwork / Shuttering for Tie Beam
G1.C.SUB.GF.3000 Casting Tie Beam 2 06-Feb-24 07-Feb-24 06-Feb-24 07-Feb-24 0 Casting Tie Beam
G1.C.SUB.GF.3100 Backfilling Up to SOG 2 08-Feb-24 09-Feb-24 08-Feb-24 09-Feb-24 0 Backfilling Up to SOG
GROUND FLOOR SLAB ON GRADE 18 10-Feb-24 01-Mar-24 10-Feb-24 01-Mar-24 0 01-Mar-24, GROUND FLOOR SLAB ON GRADE
G1.C.SUB.GF.3200 Ant termite treatment, Polythene and PCC work (SOG) 1 10-Feb-24 10-Feb-24 10-Feb-24 10-Feb-24 0 Ant termite treatment, Polythene and PCC work (SOG)
G1.C.SUB.GF.3300 Reinforcement work for SOG 3 12-Feb-24 14-Feb-24 12-Feb-24 14-Feb-24 0 Reinforcement work for SOG
G1.C.SUB.GF.3400 Formwork / Shuttering for SOG 2 13-Feb-24 14-Feb-24 13-Feb-24 14-Feb-24 0 Formwork / Shuttering for SOG
G1.C.SUB.GF.3500 Casting SOG 2 15-Feb-24 16-Feb-24 15-Feb-24 16-Feb-24 0 Casting SOG
G1.C.SUB.GF.3600 Curing of SOG 12 17-Feb-24 01-Mar-24 17-Feb-24 01-Mar-24 0 Curing of SOG
SUPER STRUCTURE 36 02-Mar-24 12-Apr-24 02-Mar-24 12-Apr-24 0 12-Apr-24, SUPER STRUCTURE
GROUND FLOOR LEVEL 36 02-Mar-24 12-Apr-24 02-Mar-24 12-Apr-24 0 12-Apr-24, GROUND FLOOR LEVEL
COLUMN & WALL 2 02-Mar-24 04-Mar-24 02-Mar-24 04-Mar-24 0 04-Mar-24, COLUMN & WALL
G1.C.SUP.GF.1300 Casting of Column & Walls 2 02-Mar-24 04-Mar-24 02-Mar-24 04-Mar-24 0 Casting of Column & Walls
COVER SLAB 34 05-Mar-24 12-Apr-24 05-Mar-24 12-Apr-24 0 12-Apr-24, COVER SLAB
G1.C.SUP.GF.1400 Formwork / Shuttering for Cover Slab & Stair 12 05-Mar-24 18-Mar-24 05-Mar-24 18-Mar-24 0 Formwork / Shuttering for Cover Slab & Stair
G1.C.SUP.GF.1500 Reinforcement work for Cover Slab & Stair 12 05-Mar-24 18-Mar-24 05-Mar-24 18-Mar-24 0 Reinforcement work for Cover Slab & Stair
G1.C.SUP.GF.1700 MEP Conduits in Cover Slab 7 11-Mar-24 18-Mar-24 11-Mar-24 18-Mar-24 0 MEP Conduits in Cover Slab
G1.C.SUP.GF.1800 DM Inspection for Casting of Cover Slab & Stair 2 19-Mar-24 20-Mar-24 19-Mar-24 20-Mar-24 0 DM Inspection for Casting of Cover Slab & Stair
G1.C.SUP.GF.1900 Casting of Cover Slab & Stair 2 19-Mar-24 20-Mar-24 19-Mar-24 20-Mar-24 0 Casting of Cover Slab & Stair
G1.C.SUP.GF.2100 De Shuttering of Ground Floor Cover Slab 6 06-Apr-24 12-Apr-24 06-Apr-24 12-Apr-24 0 De Shuttering of Ground Floor Cover Slab
FINISHES WORKS 189 13-Apr-24 19-Nov-24 13-Apr-24 19-Nov-24 0 19-Nov-24, FINISHES WORKS
GROUND FLOOR 189 13-Apr-24 19-Nov-24 13-Apr-24 19-Nov-24 0 19-Nov-24, GROUND FLOOR
COMMON 44 13-Apr-24 03-Jun-24 13-Apr-24 03-Jun-24 0 03-Jun-24, COMMON
BLOCK WORK & PLASTER 44 13-Apr-24 03-Jun-24 13-Apr-24 03-Jun-24 0 03-Jun-24, BLOCK WORK & PLASTER
G1.C.FIN.GF.1000 Block Works Layout 5 13-Apr-24 18-Apr-24 13-Apr-24 18-Apr-24 0 Block Works Layout
G1.C.FIN.GF.1100 Block Works 20 16-Apr-24 08-May-24 16-Apr-24 08-May-24 0 Block Works
G1.C.FIN.GF.1200 Plaster Preparation 5 09-May-24 14-May-24 09-May-24 14-May-24 0 Plaster Preparation
G1.C.FIN.GF.1300 Plaster Inc Sub Frames 20 11-May-24 03-Jun-24 11-May-24 03-Jun-24 0 Plaster Inc Sub Frames
WET AREA 20 15-Jul-24 06-Aug-24 15-Jul-24 06-Aug-24 0 06-Aug-24, WET AREA
FALSE CEILING 20 15-Jul-24 06-Aug-24 15-Jul-24 06-Aug-24 0 06-Aug-24, FALSE CEILING
G1.C.FIN.GF.2000 False Ceiling Suspension 20 15-Jul-24 06-Aug-24 15-Jul-24 06-Aug-24 0 False Ceiling Suspension
DRY AREA 105 20-Jul-24 19-Nov-24 20-Jul-24 19-Nov-24 0 19-Nov-24, DRYAREA
FALSE CEILING 15 20-Jul-24 06-Aug-24 20-Jul-24 06-Aug-24 0 06-Aug-24, FALSE CEILING
G1.C.FIN.GF.2100 False Ceiling Suspension 15 20-Jul-24 06-Aug-24 20-Jul-24 06-Aug-24 0 False Ceiling Suspension
DOOR & WINDOW 20 07-Aug-24 29-Aug-24 07-Aug-24 29-Aug-24 0 29-Aug-24, DOOR & WINDOW
G1.C.FIN.GF.2300 Door Fixing 20 07-Aug-24 29-Aug-24 07-Aug-24 29-Aug-24 0 Door Fixing
PAINT WORK 20 28-Oct-24 19-Nov-24 28-Oct-24 19-Nov-24 0 19-Nov-24, PAINT WORK
G1.C.FIN.GF.3400 Internal Paint Final Coat 20 28-Oct-24 19-Nov-24 28-Oct-24 19-Nov-24 0 Internal Paint Final Coat
1ST FLOOR 69 31-Aug-24 19-Nov-24 31-Aug-24 19-Nov-24 0 19-Nov-24, 1ST FLOOR
WET AREA 25 28-Sep-24 26-Oct-24 28-Sep-24 26-Oct-24 0 26-Oct-24, WET AREA
ACCESSORIES 25 28-Sep-24 26-Oct-24 28-Sep-24 26-Oct-24 0 26-Oct-24,ACCESSORIES
G1.C.FIN.1F.3000 Installation of Kitchen Units - Frames 12 28-Sep-24 11-Oct-24 28-Sep-24 11-Oct-24 0 Installation of Kitchen Units - Frames
G1.C.FIN.1F.3200 Installation of Kitchen Units - Panels 18 07-Oct-24 26-Oct-24 07-Oct-24 26-Oct-24 0 Installation of Kitchen Units - Panel
DRY AREA 69 31-Aug-24 19-Nov-24 31-Aug-24 19-Nov-24 0 19-Nov-24, DRYAREA
DOOR & WINDOW 20 31-Aug-24 23-Sep-24 31-Aug-24 23-Sep-24 0 23-Sep-24, DOOR & WINDOW
G1.C.FIN.1F.2500 Door Fixing 20 31-Aug-24 23-Sep-24 31-Aug-24 23-Sep-24 0 Door Fixing
PAINT WORK 20 28-Oct-24 19-Nov-24 28-Oct-24 19-Nov-24 0 19-Nov-24, PAINT WORK

Actual Work Summary Date Revision Checked Approved


Baseline Program Of Work - Rev 0
Remaining Work Page 2 of 3
Critical Remaining Work
Milestone
PROPOSED VILLA and BOUNDARY WALL

Activity ID Activity Name Original Early Start Early Finish Late Start Late Finish Total Float 2023 2024
Duration
Oct N D Jan F M A M J Jul A S Oct N D Jan F M A M J Jul A S Oct N D
G1.C.FIN.1F.3400 Internal Paint Final Coat 20 28-Oct-24 19-Nov-24 28-Oct-24 19-Nov-24 0 Internal Paint Final Coat
MEP WORKS 50 04-Jun-24 31-Jul-24 04-Jun-24 31-Jul-24 0 31-Jul-24, MEP WORKS
GROUND FLOOR 50 04-Jun-24 31-Jul-24 04-Jun-24 31-Jul-24 0 31-Jul-24, GROUND FLOOR
MEP 2nd Fix 50 04-Jun-24 31-Jul-24 04-Jun-24 31-Jul-24 0 31-Jul-24, MEP 2nd Fix
HVAC 50 04-Jun-24 31-Jul-24 04-Jun-24 31-Jul-24 0 31-Jul-24, HVAC
G1.C.MEP.GF.2000 AC Ducting Work 30 04-Jun-24 08-Jul-24 04-Jun-24 08-Jul-24 0 AC Ducting Work
G1.C.MEP.GF.2100 FCU's Installation 30 04-Jun-24 08-Jul-24 04-Jun-24 08-Jul-24 0 FCU's Installation
G1.C.MEP.GF.2400 FCU's Valve Assembly 20 09-Jul-24 31-Jul-24 09-Jul-24 31-Jul-24 0 FCU's Valve Assembly
G1.C.MEP.GF.2500 Condensate Pipe lnstallation 20 09-Jul-24 31-Jul-24 09-Jul-24 31-Jul-24 0 Condensate Pipe lnstallation
G1.C.MEP.GF.2600 Copper Pipe lnstallation 20 09-Jul-24 31-Jul-24 09-Jul-24 31-Jul-24 0 Copper Pipe lnstallation
PROJECT CLOSEOUT & HANDING OVER 25 20-Nov-24 18-Dec-24 20-Nov-24 18-Dec-24 0 18-Dec-24, PROJECT CLO

DEMOBILIZATION 25 20-Nov-24 18-Dec-24 20-Nov-24 18-Dec-24 0 18-Dec-24, DEMOBILIZAT


G1.DM.1000 Demobilization of Offices & Welfare areas 24 20-Nov-24 17-Dec-24 20-Nov-24 17-Dec-24 0 Demobilization of Offices &
G1.DM.1100 Demobilization of Facilities & Utilities 20 26-Nov-24 18-Dec-24 26-Nov-24 18-Dec-24 0 Demobilization of Facilities

Actual Work Summary Date Revision Checked Approved


Baseline Program Of Work - Rev 0
Remaining Work Page 3 of 3
Critical Remaining Work
Milestone