Pert CPM

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views3 pages

Pert CPM

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Activity Precedes Duration of work (days)

a Clearing b,c 3
b Layout of plan d,e 1
c Purchasing of Materials e 1
d Excavation of foundation e 3
e Foundation steel works f 5
f Foundation concreting g,h 15
g Excavation of wall footing i 3
h Wall footing steel works i 10
i Wall footing concreting j
j Ground floor column steel works k 3
k Attachment of ground floor column forms and scaffoldings l 15
l Ground floor column concreting m 3
m Removal of ground floor forms and scaffoldings n 5
n Backfilling o 5
o Attachment of forms and scaffoldings for beams and slab p 7
p Beams and slab steel works q 5
q Ground floor electrical works r 7
r Ground floor beams and slab concreting s 3
s Removal of forms and scaffoldings from beams and slab t,ag 12
t Ground floor wall concreting u 7
u Ground floor doors and windows installation v 10
v Ground floor wall plastering w,x 10
w Ground foor glass and glazing works ab 2
x Flooring steel works y 3
y Ground floor concreting z,aa 7
z Ground floor tile works af 7
aa Ground floor plumbing works ac 6
ab Ground floor FDAS works ac 3
ac Balcony concreting ad 15
ad Balcony railing concreting ae 4
ae Attachment of composite aluminun metal cladding af 10
af Ground floor painting works end 7
ag Second floor column steel works ah 2
ah Attachment of forms and scaffolding for second floor columns ai 5
ai Second floor column Concreting an 7
aj Attachment of forms and scaffoldings for stairs ak 2
ak Stair steel works al 1
al Stair concreting am 2
am Attachment of metal railings an 2
an Removal of forms and scaffoldings from second floor columns ao 1
ao Roof beam steel works ap 2
ap Attachment of forms and scaffolding for second floor beams aq 2
aq Roof beam concreting ar 2
ar Removal of forms and scaffolding from second floor beams as 2
as Second floor wall concreting at,aw 7
at Second floor doors and windows installation au 1
au Second floor wall plastering av 5
av Second floor glass and glazing works bb 2
aw Ceiling works ax,ay,az 10
ax Second floor electrical works bb 2
ay Second floor FDAS works bb 2
az Second floor plumbing works bb 3
ba Second floor tile works bb 10
bb Built-up roofing concreting bc 4
bc Parapet concreting bd 2
bd Second floor painting works be 7
be Fixtures and furnishings end 3
Duration of work (days) forward backward
0 0
a 2 2 2
b 1 3 3
e 5 8 8
f 15 23 23
h 10 33 33
i 15 48 48
j 10 58 58
k 3 61 61
l 15 76 76
m 3 79 79
n 5 84 84
o 5 89 89
p 7 96 96
q 5 101 101
r 7 108 108
s 3 111 111
t 12 123 123
u 7 130 130
v 10 140 140
x 3 143 143
y 7 150 150
aa 6 156 156
ac 15 171 171
ad 3 174 174
ae 4 178 178
af 10 188 188

188
6.266667