According to metal temperature of turbine unit start up procedure may be cold start up, warm start
up or hot start up. Here cold start up procedure is described below:
COLD START UP STEP BY STEP PROCEDURE OF A COAL FIRED THERMAL POWER
PLANT:-
SITUATION:- AC POWER IS ON. NO EQUIPMENT IS RUNNING
The following are the main step to remember for taking action in details:-
1. Start ACW Pump → BACK Charge the CONDENSER & CW Pump Discharge lines for water
filling and air releasing. ( Time may be 25-30 Minutes).
2. Start CW PUMP.
5. Start AIR COMPRESSOR. If, not INSTRUMENTS & ACTUATORS WILL NOT WORK.
6. Line up boiler and deaerator storage tank to take water in boiler drum and deaerator storage tank.
8. Start BOILER DRUM Water Filling up to Normal Level and DEAERATOR STORAGE TANK &
HOTWELL up to normal level.
9. Taking auxiliary steam from side unit ( if available) start Deaerator initial heating system.
12. ESTABLISH air flow approx.30% to 40% maintaining furnace pressure between (-5) & (-10 mm
wc).
17. ESTABLISH GENERATOR SEAL OIL system & FEED hydrogen gas following the gas feeding
procedure.
23. AT DRUM Pressure approx. at 6 – 8 Kg/cm2 CLOSE STEAM SIDE DRAINS & VENTS except
START UP VENT.
24. At around 10 kg/cm2 main steam pressure WARM UP Main Steam (MS) LINE , then open the
Main steam stop valves.
25. At MAIN STEAM PRESSURE approx. 25 Kg/cm2, PUT Self APRDS system into SERVICE.
28. Charge HP-LP BYPASS system & then Close START UP VENT.
29. START DEAERATOR PEGGING STEAM FROM APRDS AND STOP DEAERATOR INITIAL
HEATING.
30. PUT two more LFO GUNS in CD Elevation, and achieve matching steam parameter for TURBINE
ROLLING e.g. STEAM Pressure = 35Kg/cm2, Temp. 3500 C. approx.. ).
32. Check X-criterias ( X1, X2 & X3) fulfilled and START TURBINE STEAM ROLLING AND
INCREASE SPEED TO 600 rpm gradually ( 200 rpm /min).
33. TURBINE SOAKING TO BE DONE FOR UNIFORM HEATING. Check criteria curves.
34. SATRT ONE PA FAN AND KEEP ONE MILL RUNNING WITHOUT FEEDER.
CLOSE ALL ISOLATORS FROM GENERATOR TO MAIN BUS ( 220 KV / 400 KV).
CLOSE FIELD BREAKER
PUT AVR - I / II AUTO ON
CHECK GENERATOT OUT VOLTAGE – 16.5 KV
PUT SYNCHROSCOPE – ON
MATCH INCOMING & RUNNING VOLTAGE, FREQUENCY AND PHASE SEQUENCE AND CLOSE GT
BREAKER
LOAD (MW) WILL BE approx.5%.
38. START COAL FEEDER & INCREASE COAL FEEDING. Monitor Steam Pressure & Temperature.
39. CUT-IN 2ND MILL & RAISE FEEDING with close monitoring with Total Air Flow, Steam Pressure
& Temperature.
LPH in SERVICE
Put UNIT AUX TRANSFORMER (UAT) in SERVICE
Change DEAERATER PEGGING steam FROM CRH source.
CHECK HPLP BY PASS system is CLOSED.
Try to STOP ALL Oil GUNS with careful monitoring with Flame Intensity.
Change over Feed Control System from LOW TO HIGH capacity VALVE