9 Wms-Method Statement For Water Prooping
9 Wms-Method Statement For Water Prooping
Return Code:
Code 1: APPROVED
Code 3: REJECTED
Reviewed by
Reviewed by Approved by
Rev. Rev. Date Issued by (Quality Checked By
(Safety Dept) Client
Dept)
Custom Statuses: Use custom statuses to track the progress of your waterproofing projects, such as "In Progress,"
"Completed," and "Pending Approval."
Custom Fields: Utilize custom fields to include important information specific to each project, such as project location,
client name, project start and end dates, and materials used.
Different Views: Access different views to visualize and organize your waterproofing projects. For example, use the "Project
Overview" view to get a high-level summary of all your projects, or the "Detailed Scope of Work" view to dive into the
specifics of each project.
3. References
Project Specifications-Protective Treatment for Concrete.
Health and Safety Plan
CEMP
General Lifting Plan
Baseline Schedule- Detailed
Material Submittal for Waterproofing System
This Method Statement shall be read in conjunction with the following Standards, Plans, and Documents; Project
Drawings
Logistics Plan, Health & Safety Plan Other Relevant Procedures
Manufacturer’s Instructions
4. Organization and Responsibilities
Project Manager: Supervise closely, the activities designated to them and ensure that all instructions and safety
procedures are followed and strictly adhered to. Supervise the work to ensure that technical, quality, safety, and purchase
order requirements are met; Attend daily site meetings and communicate his daily report with the Project/Site Engineer;
Participate in training and development of his subordinates; Organize with the Project/Site Engineer to ensure the
availability of plant, equipment, and labor to his designated work activities; Closely monitor the usage of consumable and
materials by his crew in order to minimize wastage; Assess craftsmanship of subordinates under his control.
Document Title Document Number:
Site Engineer: Supervise operations in accordance with the approved method statement for waterproofing, shop
drawings, specifications, material submittals, and schedules to achieve the acceptance of the project deliverables.
Supervisor: Supervise closely, the activities designated to them and ensure that all instructions and safety procedures are
followed and strictly adhered to.
Supervise the work to ensure that technical, quality, safety, and purchase order requirements are met; Attend daily site
meetings and communicate his daily report with the Project/Site Engineer; Participate in training and development of his
subordinates; Organize with the
Project/Site Engineer to ensure the availability of plant, equipment, and labor to his designated work activities; Closely monitor
the usage of consumables and materials by his crew in order to minimize wastage; Assess craftsmanship of subordinates under
his control.
5.Resources
Manpower
Site engineer
Civil Supervisor
HSE Engineer
Quality Engineer
6.0 Procedure
Setting out:
Dig around the foundation to expose the exterior walls. Check for cracks in the foundation walls and repair them. Apply a sealant
to the foundation walls to prevent water from seeping through. Apply a membrane to the foundation walls to provide more
protection.
Methodology:
a. Planning and Preparation:
Waterproofing System is divided into two phases which are the application of PVC T-Lock:
Membrane and application of Integra tank spray membrane. The T-Lock Keyed Pre-Formed Membrane (KPM) membrane is
applied before the concrete work start and the Spray membrane is applied after the concrete has attained the required criteria
for the application. The contractor shall execute the trial test section on the vertical and horizontal surface which shall
Document Title Document Number:
include details of construction and expansion joint, complete with protection system and approval before application to the
structure. The subcontractor team at the site shall be responsible to check all items of waterproofing system against the
sequence of construction starting from the laying of reinforcement bars for the base slab till the finishing of backfilling,
considering the following:
a. Subcontractor to arrange for 24/7 supervision of responsible representative at the site for Backfilling surveillance, installation
of protection board, and waterproofing repairs as required.
b. The subcontractor is to provide the Specific Organization Chart of the Supervision Team for the project.
c. The subcontractor is to sign a separate checklist as attached in Appendix F to check the waterproofing membrane during the
backfilling work application.
d. Documentation:
Maintain proper documentation of all Look for signs of water damage, cracks, deteriorated sealants, or areas of potential water
intrusion. Interior Assessment: Check the interior spaces for signs of water stains, dampness, or mold growth. Inspect
basements, crawl spaces, bathrooms, and any areas susceptible to moisture issues.
Report any deviations or issues to the relevant authorities and take corrective actions as necessary.
Safety Precautions:
The slope of ground drainage should meet the design requirements.
The base layer should have sufficient strength, be solid, flat, and not sandy, and the base layer should be free of
standing water and clear water.
Any impermeable layer/coating should never be applied on both faces of the wall as the wall must be allowed to
“breathe”.
A non-permeable finish or waterproof finish should not be applied on a wet wall, as it takes a long time to lose water
used during construction.
These include health hazards; such as asphalt fumes, lead, silica, and solvents; as well as safety hazards, such as falls
from elevation, awkward and heavy lifting, flammables, and power tools.
The contents in HEMP Register shall be disseminated within the crew by the shift supervisor / foreman, through
Toolbox Talk.
Any new hazards & controls identified with reference to site conditions change shall be briefed to the crew by the
supervisor / Foreman, prior to commencement of any activity.
Following control measures generally apply to all hazards that shall be adopted as a proactive measure in addition to
the specific controls identified in the HEMP Register:
Correct use & maintenance of tools and equipment.
Third party inspection/ calibration of all tools / tackles, JCB, Pock lain.
Deployment of trained & authorized persons for the job.
Conduct of toolbox talks prior to work commencement.
Provision of adequate warning signs, barricading, night lamps etc.
Adequate and effective supervision.
Use of necessary PPE.
Prevention of Inhalation of Toxic chemicals, Solvents.
First Aid facilities
Safe Storage System will be practiced & Handling is ensured by trained personnel only.
Appropriate PPEs (Rubber gloves etc.) shall be used while doing handling, cleaning activity.
The Crew in-charge shall ensure that crew members have ready access to the telephones for use
during emergencies and the emergency contact numbers are displayed in the site.
The emergency actions to follow to be disseminated to the work group through daily toolbox talk
and ensured of the understanding by one and all.
Extreme requirements, call for POLICE/Emergency Response Team / Ambulance assistance.
10.0 Attachments
Checklist of Waterproofing Work
Excavation
A-2.2/10-01-01 - Checklist for Excavation
Site Work
Activity
Document Title Document Number:
Site
Location/GRID
Date
Drawing Reference No.
Soil Investigation Report Ref.
No:
Refer to the Approved Work Method Statement for waterproofing work.
1 Are all the safety norms being covered as per HSEM process?
Yes No