OQ Protocol Unit 06
OQ Protocol Unit 06
) LIMITED
Operational Qualification
Personnel Involved in
Signature / Date Designation
Qualification Study
Muhammad ALI
ELECTICAL ENGINEER
Prepared By:
IMRAN KHAN
Manager Engineering
Reviewed By:
Checked By:
ZEESHAN
PRODUCATION OFFICER
APPROVED BY
Operational Qualification (OQ) should be performed after satisfactory compilation of the Installation Qualification (IQ).
Any Worst Case challenges to the HVAC System are defined and incorporated into the testing strategy and should be
mentioned in the Operational Qualification Report.
The SOP’s for the operation, maintenance, cleaning/ sanitization, calibration and safety must be available during Operational
Qualification.
2.0 Objective:
To established a documented evidence that the HVAC System operates according to predetermined design, functional and
operational specifications and suitable for intended purpose and will produce consistent and reliable results/ output.
3.0 Scope:
The scope of the activity of Operational Qualification of HVAC System is to ensure that,
i. The operation of the HVAC System is in accordance with the pre-determined specification provided either by the
manufacturer or the user specification/ requirements.
ii. To perform systematic check for the proper working of all major components of the HVAC System according to
predetermined checking criteria.
iii. To ensure availability of all the utilities according to requirement.
iv. To ensure the availability of the Standard Operating Procedure (SOP) including responsibilities, cleaning, operating,
calibration and maintenance procedures.
v. To establish the operational qualification report including observation, deviation encountered during qualification
study and impact of deviation, corrective action to be taken in response of any deviation and finally the conclusion
either the HVAC System qualifies its operation or not.
Any modification, fabrication or relocation of HVAC System which directly or indirectly affects the performance of the
Blistering or the quality of the product should be controlled and in accordance with the Change Control Procedure and it will
be required to re-qualify the HVAC System.
Minor changes or the changes have no direct impact of the in process or final product quality should be handled through the
system of the preventive maintenance program.
5.0 Responsibility:
6.0 Requirement:
i. Description of the HVAC System to be studied for OQ along with actual mechanism of work and functions.
ii. Actual results, the predetermined functional and operational specifications during rest conditions.
iii. Working mechanism of the major components.
iv. Specification of the supporting utilities.
v. Calibration results of the parameters that required calibration along with calibration frequency (if applicable).
vi. Environment, safety and health aspects (safety Features).
7.0 Operation/Procedure:
The HVAC System has the following parameters that required calibration;
Air Quantity Supplied
a. Measure the Air Velocity with the pre calibrated Climomaster (Velocity Meter) by proper positioning of the Hood for the
air supply diffuser.
b. Take measurement for a minimum of 05 seconds in one position and record the reading.
c. When air velocities fall below the lower limits (as per room requirements), the pre-filters should be checked / Cleaned
(as required) and replaced if exceptionally dirty. If the average air flow velocity is still below the lower limit, increase the
blower speed until the acceptance Criterion is met. When the blower speed control is turned to the maximum setting
and the average airflow velocity is below the recommended value, assess the need for the blower repair and filters
replacement.
d. If blower motor is repaired or filter replacement is necessary, repeat the above steps. Report all the results on the
certification report form.
Air Changes Per Hour Calculation
a. Using the above data of air quantity in cubic feet per minute (CFM), calculate the air changes per hour (ACH) of
individual rooms using the following equation.
Air Quantity (CFM)
Air Changes Per Hour (ACH) = x 60
Room Volume (Ft3)
Air Flow direction and Room Pressurization
a. After adjusting the individual air flow in the supply diffuser, monitor the differential pressure of each room using the
differential pressure gauge installed at the entrance of each room.
b. The differential pressure gauge of each of room should give negative pressure with respect to the adjacent corridor.
c. If the differential pressure is not as per requirement, adjust the air supply using dampers, fresh air supply in the unit and
return air from individual rooms.
Temperature & Humidity
a. Monitor and check the temperature and humidity of the rooms using the pre-calibrated Climomaster or hygrometer, by
holding the Probe in atmosphere for few seconds.
b. In case the Relative Humidity / Temperature are outside the predetermined limits adjust them with the adjustment of
steam or cooling coils.
10.0 Facilities:
The Operational Qualification of HVAC System will be performed in the Compression of General section in
production Department of FASSGEN PHARMACEUTICALS (PVT.) LTD. Hattar -Pakistan.
WASIF ENGINEER
Manufacturer For:
Local