SQRA Calculation Methodology USACE
SQRA Calculation Methodology USACE
RMC-TN-2018-01
1E-01
Annual Probability of Failure
1E-02
~, PFM
1E-03
' ', 1
Total
I'' ,, PFM
1E-04
' 2
I'' ,,
'
1E-05
', ,,
1E-06 '
1 10 100 1,000
Average Life Loss
US Army Corps
of Engineers ®
Institute for Water Resources
Risk Management Center
Form Approved
REPORT DOCUMENTATION PAGE OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 1 hour per response, including the time for reviewing instructions, searching existing data
sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other
aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information
Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other
provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number.
PLEASE DO NOT RETURN YOUR FORM TO THE ABOVE ADDRESS.
1. REPORT DATE (DD-MM-YYYY) 2. REPORT TYPE 3. DATES COVERED (From - To)
04-17-2018
4. TITLE AND SUBTITLE
I Technical Note
5a. CONTRACT NUMBER
Semi-Quantitative Risk Analysis Calculation Methodology
5b. GRANT NUMBER
14. ABSTRACT
This document summarizes the methodology to estimate total incremental risk, non-breach risk for dams, and
overtopping incremental and non-breach risk for levees for semi-quantitative risk analysis performed by the U.S.
Army Corps of Engineers.
16. SECURITY CLASSIFICATION OF: 17. LIMITATION OF 18. NUMBER 19a. NAME OF RESPONSIBLE PERSON
ABSTRACT OF
a. REPORT b. ABSTRACT c. THIS PAGE
PAGES
Timothy M. O’Leary
U U U UU 14 19b. TELEPHONE NUMBER (Include area code)
502-315-6599
Standard Form 298 (Rev. 8/98)
Prescribed by ANSI Std. Z39.18
SQRA Calculation Methodology
April 2018
Author
The results, findings, and recommendations provided in this document are technically sound and
consistent with current Corps of Engineers practice.
Reviewed
This report has been checked and reviewed and is believed to be in accordance with the
standards of the profession.
Approved
Contents
Executive Summary ......................................................................................................................... 1
Risks Posed by Dams and Levees .................................................................................................. 1
Overtopping Risk Posed by Levees ................................................................................................. 3
Non-Breach Risk ........................................................................................................................... 11
Levees ....................................................................................................................................... 12
Dams.......................................................................................................................................... 15
Figures
Figure 1 - Incremental Life Safety Risk Matrix for SQRA ................................................................. 2
Figure 2 - Incremental Economic Risk Matrix for SQRA .................................................................. 2
Figure 3 - Incremental Life Safety Risk Matrix Example .................................................................. 3
Figure 4 - Example Societal Risk Estimate based on Critical Overtopping Elevation ...................... 5
Figure 5 - Example Societal Risk Estimate Based on a Range of Overtopping Events ................... 7
Figure 6 - Divergent Consequence Example for Levees ................................................................. 8
Figure 7 - Incremental Risk Example for a Levee with Convergent Life Loss .................................. 9
Figure 8 - Incremental Risk Example for a Levee with Divergent Life Loss ................................... 11
Figure 9 - Non-Breach Risk Matrix for SQRA ................................................................................ 12
Figure 10 - Non-Breach Economic Risk Matrix for SQRA.............................................................. 12
Figure 11 - Non-Breach Risk Example for Levees ......................................................................... 14
Figure 12 - Refined Non-Breach Life Loss Relationship ................................................................ 15
Figure 13 - Non-Breach Life Safety Risk Matrix Example for Dams .............................................. 16
SQRA Calculation Methodology
Executive Summary
Each risk assessment includes estimates of the risk posed by the dam or levee (incremental risk),
the non-breach risk, and the flood risk (residual risk). The total risk posed by the dam or levee
from all potential failure modes is evaluated against the tolerable risk guideline for societal and
individual life safety risk. The Dam and Levee Senior Oversight Groups use estimates of total dam
and levee risk to classify each structure and recommend appropriate courses of action with
respect to the structure and the population at risk. The non-breach and flood risk are assessed,
considered, and communicated to provide more complete, transparent, and informed decisions.
This technical note describes the preferred methodology to calculate and portray the total risk
posed by a dam or levee, the risk posed by an overtopping potential failure mode, and the non-
breach risk. Risk analysts should use these methods to calculate and portray risks for Semi-
Quantitative Risk Analysis (SQRA). The concepts and methods can also be applied to
Quantitative Risk Analysis (QRA) when appropriate.
1
SQRA Calculation Methodology
1E-01 1E-01
Annual Probability of Failure
' ',
1E-03
', ,, 1E-03
'
1E-04
', 1E-04
1E-05
' ', 1E-05
I'' ,,
1E-06 ' 1E-06
The total failure probability and average consequences are calculated from individual PFM
estimates using the center of the order-of-magnitude box as a point estimate. Because risk
estimates are portrayed and evaluated in logarithmic space, a geometric mean is used to
calculate the point estimate at the center of a box. The total APF is calculated by summing the
APF point estimates for all of the individual PFMs. This calculation assumes the PFMs are
mutually exclusive.
APFtotal = ∑APFi
The total AALL is calculated by summing the AALL for all of the individual PFMs. Recall that AALL
is equal to the product of the failure probability and the average consequences.
AALLtotal = ∑AALLi = ∑(APFi x Ni)
The total average consequence estimate is calculated as the weighted average of the
consequences for all of the individual PFMs.
N = ∑(APFi x Ni) / ∑APFi = AALLtotal / APFtotal
An example is provided below.
Total Risk Posed by a Dam or Levee
Given:
• PFM 1: APF = SQRT(1E-02 * 1E-03) = 3E-03 and N = SQRT(1 * 10) = 3
• PFM 2: APF = 3E-04 and N = 300
2
SQRA Calculation Methodology
Solution:
• Total Individual Risk = Total APF = 3E-03 + 3E-04 = 3.3E-03
• Total Societal Risk = (3E-03)(3) + (3E-04)(300) = 9.9E-02
• N = 9.9E-02 / 3.3E-03 = 30
• APF: In log space, 3.3E-03 is closest to 3E-03. The total risk is portrayed as 1E-03 to
1E-02.
• Average Life Loss: In log space, 30 is the geometric mean of 10 and 100. The total average
life loss is portrayed as 10 to 100.
The risk estimate for this example is portrayed in Figure 3.
1E-01
Annual Probability of Failure
1E-02
~, PFM
1E-03
' ', ~, 1
Total
' ,,
PFM
2
1E-04
', ,,
'
1E-05
', ,,
1E-06 '
1 10 100 1,000
Average Life Loss
3
SQRA Calculation Methodology
estimate the overtopping risk posed by the levee. Estimating overtopping societal risk based on a
single critical elevation typically results in overestimation of the societal risk posed by the levee
and underestimation of the flood risk. When consequence information is available, overtopping
risk estimates need to consider how consequences change over a range of overtopping flood
events.
As an example, consider the information provided in Table 1. The levee overtops at a frequency of
about 1 in 250, and the critical overtopping depth is judged to be 2 feet of overtopping at a
frequency of about 1 in 280. For SQRA, the critical overtopping elevation approach assumes that
the levee will not breach below this level and will breach above this level. This is reflected in the
probability of breach values in the third column of Table 1. This is a reasonable simplifying
approximation for the purposes of an SQRA. At the critical overtopping depth, a life loss of 100 is
expected to occur if the levee does not breach. If the levee breaches, a life loss of 800 is
estimated resulting in an incremental life loss of 700 (800 – 100). Using a single point estimate for
the SQRA would result in an APF estimate of 3.5E-03, life loss of 700, and a societal risk estimate
of 2.5 (3.5E-03 * 700). This risk estimate is portrayed in Figure 4.
Table 1 - Flood scenarios with and without breach
Annual
Chance Probability of Life loss if the Life loss if the
Overtopping Incremental
Exceedance Breach Given Levee does Levee does
Depth (feet) Life Loss
of a Flood OT Depth not Breach Breach
Scenario
0.0038
1 0 0 0 0
(ACETOL)
0.0035
2 1.0 100 800 700
(ACEOTB)
0.0030 3 1.0 800 1,600 800
0.0025 6 1.0 2,000 2,400 400
0.0020 10 1.0 3,100 3,100 0
4
SQRA Calculation Methodology
1E-01
5
SQRA Calculation Methodology
Table 2 – Calculating Risk Posed by the Levee for an Overtopping Potential Failure Mode
Annual
Probability
Chance Average
of Breach Incremental
Exceedance Calculation Annual
Given OT Life Loss
of a Flood Life Loss
Depth
Scenario
0.0038
0 0 (0.0038 – 0.0035) * 0 * (0 + 700)/2 0
(ACETOL)
0.0035
1.0 700 (0.0035 – 0.003) * 1 * (700 + 800)/2 0.38
(ACEOTB)
0.0030 1.0 800 (0.003 – 0.0025) * 1 * (800 + 400)/2 0.30
0.0025 1.0 400 (0.0025 – 0.002) * 1 * (400 + 0)/2 0.1
0.0020 1.0 0 0.002 * 1 * 0 0
The estimate of APF is the same as the previous estimate of 3.5E-03. The estimate of AALL is
based on the product of the flood interval probability, the system response, and the average
consequences over the flood interval. In this calculation, the system response is implicitly
assumed to be a step function. The probability of breach is 0 below the critical overtopping depth
and 1 above the critical overtopping depth. This is typically a reasonable and sufficient assumption
for SQRA. The total AALL is calculated by summing the values in the last column of Table 1.
AALL = 0 + 0.38 + 0.30 + 0.1 + 0 = 0.8
The average life loss is calculated by dividing the AALL by the APF.
N = 0.8 / 3.5E-03 = 230
The improved risk estimate is portrayed in Figure 5. Notice that the revised risk estimate is one
order of magnitude less than the estimate based on a single critical overtopping elevation. This
demonstrates the impact consequences can have on overtopping risk estimates. When
consequence information is available or can be estimated by judgment, this is the preferred
approach for estimating and portraying overtopping risk for SQRA. The approach can also be
used for QRA. Refinements can be made to the system response and other inputs as needed to
achieve the desired precision and accuracy needed for the risk estimate.
6
SQRA Calculation Methodology
1E-01
7
SQRA Calculation Methodology
Jtl J _ _ J _ J __ 1 ____
900
800 -- -- Breach
-- Non-Breach ,,
-- - - -Incremental
L"
Average Life Loss (lives)
700
600
500 ~
,r
/'
~
400
300 /
200
100
0
0.001 ACEOT ACEOTB 1E-4 ACEult 1E-5
Annual Chance Exceedance, ACE (floods/year)
8
SQRA Calculation Methodology
Solution:
• Average incremental life loss = average breach life loss – average non-breach life loss
OT Depth Incremental Life Loss
Overtopping Event ACE
(ft) Day Night Average
Top of levee (TOL) 0.0 3.70E-03 596 897 777
1-ft overtopping (OTB) 1.0 3.51E-03 593 889 771
1.5-ft overtopping 1.5 3.33E-03 697 1,076 924
6.0-ft overtopping 6.0 2.00E-03 4 2 3
1E-01
Annual Probability of Failure
1E-02
~,
OT
1E-03
' ', ~,
' ,,
1E-04
', ,,
'
1E-05
', ,,
1E-06 '
1 10 100 1,000
Average Life Loss
Figure 7 - Incremental Risk Example for a Levee with Convergent Life Loss
9
SQRA Calculation Methodology
Solution:
• Average incremental life loss = average breach life loss – average non-breach life loss
OT Depth Incremental Life Loss
Overtopping Event ACE
(ft) Day Night Average
Top of levee (TOL) 0.0 6.59E-04 216 331 285
1.0-ft overtopping 0.5 2.89E-04 216 331 285
1.4-ft overtopping (OTB) 1.4 1.60E-04 420 602 529
2.0-ft overtopping 2.0 7.14E-05 685 955 847
10
SQRA Calculation Methodology
1E-01
Figure 8 - Incremental Risk Example for a Levee with Divergent Life Loss
Non-Breach Risk
Dams and levees use a consistent approach for estimating non-breach risk. The ACE when the
public would begin to experience flooding due to levee overtopping or dam spillway release and
the ACE when life loss would start to occur are important to communicate flood risk to the public.
For levees, the ACE for flooding is typically when the levee begins to overtop. For dams, the ACE
for flooding is typically at the top of active storage pool elevation. The ACE when life loss would
start to occur depends on the specific situation but is typically less than the ACE for flooding.
Example matrices for portraying the non-breach risk are shown in Figure 9 and Figure 10.
11
SQRA Calculation Methodology
1E-01 1E-01
1E-02 1E-02
1E-03 1E-03
1E-04 1E-04
1E-05 1E-05
1E-06 1E-06
Levees
USACE does not typically consider interior flooding scenarios where water flowing into the leveed
area from the landside of the levee exceeds the available pumping capacity; therefore, the ACE
associated with the top of levee is used to estimate the likelihood of flooding. The annual
probability of inundation due to overtopping without breach (APINB) is estimated as the ACE at the
top of the levee. The estimated ACE when life loss begins to occur (≥ 1) depends on the available
consequence information. For levees, it is likely that the ACE for overtopping and the ACE for life
loss are similar enough to be considered equivalent. However, this is not necessarily true for
every levee.
The estimation of non-breach risk assumes that consequences are constant for flood events less
frequent than the ultimate overtopping flood. Recall that this event is selected so that most of the
risk is captured in the estimate. This flood event is typically greater in magnitude (less frequent)
than the flood event for initial overtopping and greater than the flood event for the critical
overtopping depth. Releases from upstream dams can also have a significant effect on the non-
breach risk estimate for the leveed area. Failure to consider these larger flood events results in an
underestimation of the non-breach and flood risk. It is important that the ultimate overtopping flood
reflect a plausible maximum scenario. Available consequence information and judgment should be
used to select an ultimate overtopping load for non-breach risk estimates.
12
SQRA Calculation Methodology
Solution:
• In the previous example, a slight extrapolation was performed to estimate the flood with
zero incremental life loss. This estimate is used in this example for the ultimate overtopping
event. The ACE is 1.997E-3 and the life loss is 3,126.
OT Depth Non-Breach Life Loss
-----
Overtopping Event ACE
(ft) Day Night Average
Ultimate overtopping flood 6.01 1.997E-03 3,126
13
SQRA Calculation Methodology
1E-01
NB
1E-03 Levee
Overtops
1E-04 at 1 in 270
1E-05
1E-06
1 10 100 1,000
Average Life Loss
14
SQRA Calculation Methodology
Dams
The standard inundation scenarios for USACE include Top of Active Storage (TAS) and Maximum
High Pool (MHP) elevations. The MHP elevation corresponds to the Probable Maximum Flood
(PMF) for high hazard potential projects. For an uncontrolled spillway, TAS would typically be the
elevation of the spillway crest. For a gated spillway, this would typically be an elevation near the
top of the spillway gates. This elevation is sometimes referred to as the “top of flood control pool.”
The water control manual and water management staff should be consulted for the official TAS
elevation.
The methodology for estimating non-breach risk for dams is similar to levees. The ACE for
flooding is defined by the top of active storage which is when surcharge operations (spillway
releases) would typically initiate. The ACE when life loss begins to occur is estimated based on
the available consequence information and judgment. For dams, it is likely that the ACE for life
loss is less than the ACE for flooding. However, this is not necessarily true for every dam. An
assessment of the dam outflow required to pose a threat to life safety or to cause extensive
flooding or damage can inform the ACE estimate. Moderate or major flood stages published by
the National Weather Service (http://water.weather.gov/ahps/) may provide additional insights.
The concepts are illustrated in Figure 12 using available consequence information to estimate the
ACE for initiation of life loss. In this example, the ACE of flooding is about 1 in 200 and the ACE
for initiation of life loss is about 1 in 1,000.
TAS N>0 MHP
40
35
Average Life Loss (lives)
30
/f -
25 ,,,,
20
~ . ~
V
.... ~
15
..... ~~ -
/.
_, 1~" -
~'I
10
V
/
5 ,..,, . ,,, ~ -
~
0
0.01 0.001 1E-4 1E-5
Annual Chance Exceedance, ACE (floods/year)
15
SQRA Calculation Methodology
Solution:
• APINB = ACEN>0 = 1.00E-03
• ACE for flooding is 5E-03
• AALLNB = (1.00E-03 – 1.00E-04)(0 + 30)/2 + (1.00E-04)(30) = 1.65E-02
• NNB = (1.65E-02 lives) / (1.00E-03) = 17
• Non-Breach Life Safety Risk Matrix:
o Likelihood of Flooding: between 3E-04 and 3E-03
o Average Life Loss: between 3 and 30
The risk estimate for this example is portrayed in Figure 13.
1E-01
Annual Probability of Life Loss
1E-02
Top of
1E-03 NB
Active
1E-04
Storage
is 1 in 200
1E-05
1E-06
1 10 100 1,000
Average Life Loss
16