5608 - Manpower Loading Progress
5608 - Manpower Loading Progress
1 INDIRECT MANPOWER
a) Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 26
d) Contracts Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 26
e) QA/QC Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 26
f) HSE Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 26
h) Commissioning Engineer 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 12
a) Engineering Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 13
b) Project Manager 0 0 0 0 0 0 0 0 0 0 0
c) Process Engineer 1 1 1 1 1 1 1 1 1 1 9
d) Piping Engineer 1 1 1 1 1 1 1 1 1 1 1 10
g) Pipeline Engineer 0 0 0 0 0 0 0 0 0 0 0
h) Electrical Engineer 1 1 1 1 1 1 1 1 1 1 1 10
i) Instr. Engineer 1 1 1 1 1 1 1 1 1 1 1 1 11
k) HSE Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 13
l) QA/QC Engineer 1 1 1 1 1 1 1 1 1 1 1 1 11
m) CAD Operator 0 0 0 0 0 0 0 0 0 0 0 0 0
n) Draftsman 4 4 4 4 4 4 4 4 4 4 3 2 41
a) Civil Surveyor 2 2 2 2 2 2 2 12
2 DIRECT MANPOWER
1) General
a) Construction Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 18
b) Project Engineers 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 18
c) Planning Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 18
776395771.xlsx 1 of 17
INSTALLATION OF ESD VALVES IN TRAIN 1 & 2 TANKS
PROJECT NO. 5608
FEES REF NO.: FEES-AUH-Q-0510 REV-B
ATTACHMENT– 3
Manpower Deployment Schedule (Appendix - 04)
Monthwise Quantity
Planned to be Mobilised (Nos.)
Total Est.
Peak
SR No Designation / Title 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 (Man-
(Nos)
months)
Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20
d) HSE Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 18
e) QA /QC Engineer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 18
g) Supervisors / Formen 3 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 1 49
a) Fabrication Manager 1 1 1 1 3
b) Supervisor 2 2 2 2 6
Non-supervisory Staff
2.2 (CONTRACTOR to indicate Details separately 0
against each discipline)
1) MainContractor Manpower 0
a) Permit Holder 4 1 2 2 4 4 4 4 4 4 4 4 4 2 2 1 46
b) HSE Officer 2 1 1 1 2 2 2 2 2 2 2 2 2 1 1 1 24
c) Logistice Co-ordinator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15
d) Material Co-ordinator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15
e) Store Keeper 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15
f) Site Administrator 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 15
g) Piping Foreman 2 1 1 1 2 2 2 2 2 2 2 2 2 1 1 23
h) E&I Foreman 2 1 1 1 2 2 2 2 2 2 2 2 2 1 1 23
i) Civil Foreman 1 1 1 1 1 1 1 1 1 1 1 1 1 12
j) Pipe Fitter 8 4 4 4 8 8 8 8 8 8 8 8 8 4 4 92
k) Pipe Welder 8 4 4 4 8 8 8 8 8 8 8 8 8 4 4 92
l) Rigger 8 4 4 4 8 8 8 8 8 8 8 8 4 4 4 88
m) Scaffolders 0 0
p) NDT Technician 1 1 1 1 1 1 1 1 1 1 1 1 11
q) Hydrotest Technician 1 1 1 1 1 1 1 1 1 1 1 1 11
r) Piping Helpers 8 4 4 4 8 8 8 8 8 8 8 8 8 4 4 92
r) Insulation Technician 2 2 2 2 2 2 2 2 2 2 18
s) Mason 0 0
t) Steel Fixer 0 0
u) Carpenter 0 0
v) Civil Helpers 0 0
w) E&I Technician 4 2 4 4 4 4 4 4 4 4 4 4 4 46
x) Tube Fitter 4 2 4 4 4 4 4 4 4 4 4 4 4 46
y) QA/QC Insopectors 2 1 2 2 2 2 2 2 2 2 2 1 1 21
z) Crane Operator 0 0
776395771.xlsx 2 of 17
INSTALLATION OF ESD VALVES IN TRAIN 1 & 2 TANKS
PROJECT NO. 5608
FEES REF NO.: FEES-AUH-Q-0510 REV-B
ATTACHMENT– 3
Manpower Deployment Schedule (Appendix - 04)
Monthwise Quantity
Planned to be Mobilised (Nos.)
Total Est.
Peak
SR No Designation / Title 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 (Man-
(Nos)
months)
Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20
2) Subcontractor Manpower 0
a) Fitter 4 2 2 2 4 4 4 18
b) Welder 4 2 2 2 4 4 4 18
c) Helper 4 3 3 3 4 4 4 21
d) Rigger 2 2 2 2 2 2 2 12
e) NDT Technician 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 16
f) Civil Mason 4 2 2 2 2 4 4 4 4 4 4 4 4 4 4 4 4 56
g) Carpenter 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 32
h) Steel Fixer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 32
j) Crane Operator 1 1 1 1 1 1 1 1 1 1 1 1 1 12
k) Hiab Operator 1 1 1 1 1 1 1 1 1 1 1 1 1 12
l) HDD Driver 2 2 2 2 2 2 2 2 2 2 2 2 2 24
m) LDD Driver 4 4 4 4 4 4 4 4 4 4 4 4 4 48
n) Scaffolders 6 6 6 6 6 6 6 6 6 6 6 6 6 72
Sub-Total (2) 119 0 0 0 0 0 0 0 0 29 29 58 62 87 119 105 109 110 110 110 110 110 105 87 9 88 14 1451
Grand Total (Monthwise) 126 21 21 22 22 22 22 20 20 49 47 72 71 96 126 113 117 117 117 117 117 117 112 94 16 95 20 1783
776395771.xlsx 3 of 17
SD VALVES IN TRAIN 1 & 2 TANKS
OJECT NO. 5608
.: FEES-AUH-Q-0510 REV-B
Deployment Schedule
Total Est.
Man-days
(Note-E)
572
572
550
572
572
572
308
264
3982
286
198
220
220
220
242
242
286
242
902
264
3322
7304
468
468
468
776395771.xlsx 4 of 17
SD VALVES IN TRAIN 1 & 2 TANKS
OJECT NO. 5608
.: FEES-AUH-Q-0510 REV-B
Deployment Schedule
Total Est.
Man-days
(Note-E)
468
468
468
1274
78
156
1196
624
390
390
390
390
598
598
312
2392
2392
2288
572
572
286
286
2392
468
1196
1196
546
776395771.xlsx 5 of 17
SD VALVES IN TRAIN 1 & 2 TANKS
OJECT NO. 5608
.: FEES-AUH-Q-0510 REV-B
Deployment Schedule
Total Est.
Man-days
(Note-E)
234
468
468
546
312
416
1456
832
832
3536
312
312
624
1248
1872
234
234
37726
45030
776395771.xlsx 6 of 17
RUWAIS - INSTALLATION OF ESD VALVES IN TRAIN 1 & 2 TANKS
(PROJECT NO. 5608)
ATTACHMENT– 8
Manpower Deployment Schedule
Monthwise Quantity
Planned to be Mobilised (Nos.) & Forecast Plan from Oct-2020 to May-2021
Total Est. Total Est.
Peak
SR No Designation / Title P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P F P F F F F F F F F F (Man- Man-days
(Nos)
months) (Note-E)
Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21
1 INDIRECT MANPOWER
e) Contracts Engineer 0 0 0
f) QA/QC Manager 0 0 0
g) HSE Manager 0 0 0
b) Project Manager 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
g) Pipeline Engineer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
m) CAD Operator 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
n) Draftsman 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 3 3 3 3 2 3 3 1 1 1 1 1 1 1 1 1 1 1 44 968
a) Civil Surveyor 0 0
2 DIRECT MANPOWER
1) General
c) Planning Engineer 0 0 0
a) Fabrication Manager 1 1 1 2 52
b) Supervisor 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 20 520
Non-supervisory Staff
2.2 (CONTRACTOR to indicate Details separately 0 0
against each discipline)
1) MainContractor Manpower 0 0
l) Rigger 8 4 4 4 1 8 1 8 1 8 1 8 1 8 1 8 1 8 1 8 1 8 8 92 2392
m) Scaffolders 0 0 0
s) Mason 0 0 0
t) Steel Fixer 0 0 0
u) Carpenter 0 0 0
v) Civil Helpers 0 0 0
z) Crane Operator 0 0 0
2) Subcontractor Manpower 0 0
a) Fitter 4 4 4 4 4 4 4 4 4 1 4 4 4 4 4 4 4 2 2 2 2 2 2 2 2 27 702
b) Welder 4 4 4 4 4 4 4 4 4 1 4 4 4 4 4 4 2 4 4 4 4 4 4 4 4 37 962
c) Helper 6 4 4 4 4 4 4 4 4 2 4 4 4 4 6 6 4 4 2 2 2 2 2 2 2 28 728
d) Rigger 2 2 2 2 2 2 2 2 2 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 14 364
g) Carpenter 4 4 4 4 2 4 2 4 2 4 2 2 2 2 2 2 2 2 2 2 1 2 1 2 1 2 2 2 44 1144
k) Hiab Operator 0 0 0
n) Scaffolders 6 6 6 2 6 2 6 2 6 2 6 2 6 2 6 2 6 2 6 6 4 6 4 4 4 4 4 88 2288
Grand Total (Monthwise) 108 16 16 16 16 16 16 16 16 16 16 16 16 17 16 17 17 17 17 16 16 40 16 40 16 53 52 85 54 99 55 105 65 108 65 108 59 104 59 104 58 104 58 104 58 101 48 102 28 97 46 95 49 50 49 49 6 6 49 21 6 1848 46952
ATTACHMENT–8
MANPOWER HISTOGRAM
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Total Man-
Months
Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21 Apr-21 May-21
months
INDIRECT
MANPOWER
16 16 16 16 16 16 17 17 17 16 12 8 6 4 4 4 5 5 5 5 5 5 4 5 5 5 3 3 3 3 3 3 3 3 274
DIRECT
MANPOWER
- - - - - - - - - - 28 32 47 81 95 101 103 103 99 99 99 99 97 97 92 90 47 46 46 3 3 46 18 3 1,574
Total (Nos) 16 16 16 16 16 16 17 17 17 16 40 40 53 85 99 105 108 108 104 104 104 104 101 102 97 95 50 49 49 6 6 49 21 6 1,848
Attachment No. 09
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Name of Plant / P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P A P F P F P P P P P P P P
S. No. Remarks
Equipment
Total
May-19
May-20
May-21
Aug-18
Aug-19
Aug-20
Nov-18
Nov-19
Nov-20
Sep-18
Dec-18
Sep-19
Dec-19
Sep-20
Dec-20
Feb-19
Mar-19
Jun-19
Feb-20
Mar-20
Jun-20
Feb-21
Mar-21
Jan-19
Jan-20
Jan-21
Apr-19
Apr-20
Apr-21
Oct-18
Oct-19
Oct-20
Jul-19
Jul-20
1 Front End Loaders / Shovels 0
2 Trench Compacters 2 2 2 2 2 2 2 2 2 2 2 2 1
3 Rollers / Compactors 1 1 1 1 1 1 1 1 1 1 1 1
4 Diesel Welding Machines 8 2 4 8 8 2 8 2 6 2 6 2 6 4 6 4 6 4 6 4 6 4 4 4 4 4 4 4 4
5 Automatic Welding Machines 0
6 Cranes 1 1 1 1 1 1 1 1 1 1 1 1
7 Air Compressor with Dryer 2 1 2 2 2 2 2 1 2 1 2 1 2 1 1 1 1 1 1 1 1
8 Generators 2 1 1 1 2 2 2 2 2 2 2 2 2 2
9 Water Tankers 1 1 1 1 1 1 1 1 1 1 1 1
10 Dumpers / Dump Turcks 0
11 Fuel Trucks / Diesel Trucks 0
12 Tractor / Trailer 0
13 Pipe Trucks 0
14 NDT Equipments 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
15 De-watering Pumps 0
16 Concrete mixers 1 1 1 1 1 1 1 1 1
17 Sand Blasting & Painting Equipment 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
18 Stress Relieving / PWHT Equipment 1 1 1 1 1 1 1 1 1 1 1 1 1
19 Calibration Equipment 0
20 Survey Equipments 1 1 1 1 1 1 1 1 1 1 1 1 1
21 Boom Truck 1 1 1 1 1 1
22 Passenger Bus (66 Seeater) 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 1 1 1 1 1 1 1 1
23 Pick-up 2 1 2 1 2 1 2 1 2 1 2 1 2 1 2 2 2 2 2 2 2 1 2 2 2 2 2 2 2 2 2 2 2
24 Light Vehicle 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
25 Hydraulic Jack 2 2 2 2 2 2 2 2 2 2 2 2
26 Loop Calibrator 2 2 2 2 2 2 2 2 2 2 2 2
27 Multimeter 2 2 2 2 2 2 2 2 2 2 2 2
1 INDIRECT MANPOWER
d) Contracts Engineer 0 0
e) QA/QC Manager 0 0
f) HSE Manager 0 0
b) Project Manager 0 0 0 0 0 0 0 0 0 0 0 0
g) Pipeline Engineer 0 0 0 0 0 0 0 0 0 0 0 0
m) CAD Operator 0 0 0 0 0 0 0 0 0 0 0 0 0 0
n) Draftsman 4 2 4 4 4 4 4 4 4 4 3 2 39 858
a) Civil Surveyor 0 0 0
2 DIRECT MANPOWER
1) General
c) Planning Engineer 0 0 0
a) Fabrication Manager 0 0 0
b) Supervisor 1 1 1 1 1 1 1 1 7 182
776395771.xlsx 11 of 17
Attachment No. 08
Non-supervisory Staff
2.2 (CONTRACTOR to indicate Details separately against
each discipline)
1) MainContractor Manpower 0 0
d) Material Co-ordinator 0 0 0
h) E&I Foreman 0 0 0
i) Civil Foreman 0 0 0
l) Rigger 4 4 4 4 4 4 4 4 4 4 4 4 4 48 1248
m) Scaffolders 0 0 0
s) Mason 0 0 0
t) Steel Fixer 0 0 0
u) Carpenter 0 0 0
v) Civil Helpers 0 0 0
z) Crane Operator 0 0 0
2) Subcontractor Manpower 0 0
a) Fitter 4 2 4 4 4 1 15 390
b) Welder 4 2 4 4 4 2 16 416
c) Helper 4 2 4 4 4 14 364
d) Rigger 2 2 2 2 2 8 208
g) Carpenter 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 30 780
776395771.xlsx 12 of 17
Attachment No. 08
k) Hiab Operator 0 0 0
n) Scaffolders 4 4 4 4 4 4 4 4 4 4 4 4 44 1144
776395771.xlsx 13 of 17
Attachment No. 08
MANPOWER HISTOGRAM
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Total Man-
Months
months
Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20
INDIRECT
14.00 16.00 16.00 16.00 16.00 16.00 17.00 17.00 16.00 13.00 10.00 5.00 5.00 4.00 5.00 5.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 3.00 230.00
MANPOWER
DIRECT
- - - - - - - - - - 9.00 12.00 23.00 34.00 58.00 72.00 74.00 73.00 74.00 74.00 74.00 73.00 72.00 72.00 65.00 50.00 909.00
MANPOWER
Total (Nos) 14.00 16.00 16.00 16.00 16.00 16.00 17.00 17.00 16.00 13.00 19.00 17.00 28.00 38.00 63.00 77.00 78.00 77.00 78.00 78.00 78.00 77.00 76.00 76.00 69.00 53.00 1,139.00
776395771.xlsx
Contrcator's Postions Status Company's Postions
Issue Company Contractor
CTN No. Rev Description
Date refernce Refernce
Cost (US
Cost (US $) Schedule C/P/A/R/W Schedule Date
$)
Remarks
CTN
Company Decision TA Decision DCA Status CTN Ref.
Status
Implemented
Raise to TA
SN DCA No
Raise o TA
Over ruled
Approved
Date Details RANK Cost Impact
Remarks
Rejected
Approve
Approve
Division
Reject
Reject
Date
Date
TA
TE TE
1 HSE
HSE
EU
TE TE
2 HSE
HSE
EU
TE TE
3 HSE
HSE
EU