Check List - Raft Concrete Works
Check List - Raft Concrete Works
LOCATION / AREA:
2.0 FORMWORK
2.1 Ensure that all temporary & permanent formworks are placed as per the
approved drawing, inspected & verified by the surveyors
Check that all openings / provision for other services have been retained
2.2
as per the drawings
Embedded items if any are installed as per the approved drawings and
2.3
are properly supported.
2.4 Check & ensure that Setting out, Alignment, elevation and dimensions are
as per latest approved drawing.
3.0 REINFORCEMENT
3.1 Verify that approved Steel bars are delivered to site & all test results are
available for the supplied bars.
3.2 Check Reinforcing bars are cut to sizes, tied to correct spacing and placed
as per drawing.
3.3 Check all embedded items (H.D.Bolt, Sleeves, Conduits etc & Concrete
covers are in place as per spec and drawing.
3.4 Check that all starter bars are in place for the verticals.
3.5 Check that all lap locations are as per the approved drawing & sufficient
lap length is provided at all places.
3.7 Check that the reinforcement is cleaned from rust, dust etc before
proceeding with the concrete.
Checklist Rev 00
4.0 PRE-POUR CHECK
4.3 Check & ensure that sufficient work space is available for concrete pump
set out & concrete mixer movement.
4.4 Check and ensure that concrete placing & compacting equipments are
available at site with stand by.
4.5 Check & ensure that all concrete testing equipments (slump cone,
thermometer, cube moulds etc) are available at site.
4.6 Check & ensure that Polythene sheets, Hessian cloth & portable water are
available at site for concrete curing
5.1 Check that the arrived Concrete is in accordance with the Design mix.
Ensure the Concrete Temperature is less than 30-degree C.
5.2
Check that concrete slump is as per the approved mix design-
5.3
5.5 Check the batching time of the concrete. & ensure that sufficient time left
for pouring.
5.6 Check & ensure that cubes samples are taken for compressive strength
test & durability test as per the method statement.
5.7 Ensure that Concrete is placed as specified & consolidated with proper
vibrator.
5.9 Check that the Concrete finishes are as per specification and drawing.
6.1 Check that curing is on progress as per the approved method statement.
6.2 Check any Cracks, pour holes, Honey Combs exist in the concrete.
6.4 Check that the Formwork is removed upon Concrete attains sufficient
strength.
Signed by Contractor QA/QC: Signed by Engineer (MIRAGE)
Checklist Rev 00