Culverts Lecture
Culverts Lecture
&
DESIGN
CONSIDERATIONS
LECTURE
Instructor:
Zahid Mahmood, P.E., PMP
Email: [email protected]
Page 1 of 47
Table of Contents
Page 2 of 47
Units and Formulas
Manning’s Equation:
Q = (1.49/n)* A * (Rh)2/3 * (S)1/2
Q = Discharge (CFS)
n = Hydraulic roughness coefficient (barrel roughness)
A = Area of the pipe (ft 2)
Rh = Hydraulic radius (ft )
S = Slope of the culvert
he = ke (V 2 / 2g)
Where:
he =entrance head loss (ft)
ke = Entrance loss coefficient
V = the flow velocity just inside the barrel inlet (ft/ sec)
g = gravitational constant of 32.2 ft / sec 2
Rational Method:
Q = C*I*A
Where:
Q = Peak discharge on the runoff hydrograph (CFS)
C = A runoff coefficient
I = Rainfall intensity for a particular frequency (in/hr)
A = Area of the watershed (Acres)
Outlet Velocity:
Vout = Q/A
Where “A” is the full cross-section area of the barrel
Friction Loss:
hf = (Q2 n 2 ) (L) / ( z 2 A2 R4 / 3 ), from TxDOT HDM
Where:
hf = friction loss through the culvert
Q = discharge
L = length of pipe
z = 1.486 (US customary units only!)
A = area of the pipe
R = hydraulic radius (recall: R = A / Wp - area divided by the wetted perimeter)
Note: For mitered inlets use +0.7 S instead of -0.5 S as the slope correction factor
Once H is computed, the elevation of the headwater at the inlet when the entire culvert is
in outlet control is then computed as:
ELho = ELo + H + Do …See Figures on next page for the culvert locations at
which the terms are applied.
Where:
ELho = headwater elevation at the inlet due to outlet control
ELo = flowline elevation at the outlet, and H and Do are computed as previously
described above
Page 5 of 47
Page 6 of 47
Coefficients Used
Page 7 of 47
Page 8 of 47
*Note: The designer must use judgment to select the appropriate "C" value within the range.
Generally, larger areas with permeable soils, flat slopes and dense vegetation should have the
lowest "C" values. Smaller areas with dense soils, moderate to steep slopes, and sparse
vegetation should assigned the highest "C" values.
Page 9 of 47
Table – Symbols, Definitions and Units
Page 10 of 47
Theoretical Overview Questions
1. What is a culvert and used for?
7. How does the roughness coefficient affect the flow capacity in a culvert?
Page 11 of 47
Theoretical Overview Answers
1. Culverts are structures used to convey surface runoff through embankments. In addition
to the hydraulic function, a culvert must also support the embankment and roadway for
traffic conveyance, and protect the traveling public and adjacent property owners from
flood hazards to the extent practicable and in a reasonable and prudent manner
3. These are three – Open Channel Flow, Full Barrel Flow, or a Combination of Partial and
Open Channel Flow.
4. Bridges are more expensive and need more area including freeboard. At some locations,
they are not feasible at all.
5. The velocity of flow upstream, within the culvert barrel, and downstream of the culvert
is important for sediment transport (minimum velocity of 2 to 3 ft/sec is usually quoted
to minimize deposition within the culvert). The outlet velocity is important for the
consideration of erosion control downstream of an outlet. The maximum culvert
velocity allowable at a culvert outlet is dependent on the downstream channel conditions
and susceptibility of the channel to erosion
6. The barrel size, shape, material (roughness) and slope can influence the culvert
hydraulics
7. Roughness value is inversely proportional to the flow capacity (See Manning’s Equation
and Coefficient Table above)
8. Culvert end treatments serve as the transitions from the culvert barrel to the upstream and
downstream channel (Include: channel transitions, headwalls, wing walls depressed inlets
with “improved inlets.” – See Entrance Loss Coefficient Table above)
Page 12 of 47
10. The following:
o IF WATER CAN FLOW THROUGH AND OUT OF THE CULVERT FASTER
THAN IT CAN ENTER, THE CULVERT IS UNDER INLET CONTROL
o Inlet control occurs when the culvert barrel is capable of conveying more flow
than the inlet will accept
o The control section of a culvert operating under inlet control is located just inside
the entrance
o Critical depth occurs at or near this location, and the flow regime immediately
downstream is supercritical
o With inlet control, the culvert capacity depends on headwater depth, barrel shape,
cross-sectional area, and entrance conditions
o The entrance can be either submerged or unsubmerged. With the entrance
unsubmerged, the weir flow equation may be applied. If the entrance is
submerged, the discharge can be computed using the orifice equation
o A figurative representation is given below:
Page 13 of 47
Figure-A depicts a condition where neither the inlet nor the outlet end of the culvert are
submerged. The flow passes through critical depth just downstream of the culvert
entrance and the flow in the barrel is supercritical. The barrel flows partly full over its
length, and the flow approaches normal depth at the outlet end.
Figure-B shows that submergence of the outlet end of the culvert does not assure outlet
control. In this case, the flow just downstream of the inlet is supercritical and a hydraulic
jump forms in the culvert barrel.
Figure-C is a more typical design situation. The inlet end is submerged and the outlet
end flows freely. Again, the flow is supercritical and the barrel flows partly full over its
length. Critical depth is located just downstream of the culvert entrance, and the flow is
approaching normal depth at the downstream end of the culvert.
Figure-D is an unusual condition illustrating the fact that even submergence of both the
inlet and the outlet ends of the culvert does not assure full flow. In this case, a hydraulic
jump will form in the barrel. The median inlet provides ventilation of the culvert barrel. If
the barrel were not ventilated, sub-atmospheric pressures could develop which might
create an unstable condition during which the barrel would alternate between full flow
and partly full flow.
Page 14 of 47
TYPES OF OUTLET CONTROL
Condition-A represents the classic full flow condition, with both inlet and outlet
submerged. The barrel is in pressure flow throughout its length. This condition is often
assumed in calculations, but seldom actually exists.
Condition-B depicts the outlet submerged with the inlet unsubmerged. For this case, the
headwater is shallow so that the inlet crown is exposed as the flow contracts into the
culvert.
Condition-C shows the entrance submerged to such a degree that the culvert flows full
throughout its entire length while the exit is unsubmerged. This is a rare condition. It
requires an extremely high headwater to maintain full barrel flow with no tailwater. The
outlet velocities are usually high under this condition.
Condition-D is more typical. The culvert entrance is submerged by the headwater and
the outlet end flows freely with a low tailwater. For this condition, the barrel flows partly
full over at least part of its length (subcritical flow) and the flow passes through critical
depth just upstream of the outlet.
Condition-E is also typical, with neither the inlet nor the outlet end of the culvert
submerged. The barrel flows partly full over its entire length, and the flow profile is
subcritical.
Page 15 of 47
12. The table below describes:
13. A performance curve is a plot of headwater depth or elevation versus flow rate. A
performance curve is also important is determining type of flow control for a culvert. The
resulting graphical depiction of culvert operation is useful in evaluating the hydraulic
capacity of a culvert for various headwaters. See below:
DESIGN FLOWCHART
Page 17 of 47
16. The following design criteria should be considered for all culvert designs as
applicable:
Engineering aspects
Flood frequency
Velocity limitation
Buoyancy protection
Site criteria
Length and slope
Debris control
Design limitations
Headwater
Tailwater conditions
Storage
Design options
Culvert inlets
Inlets with headwalls
Wingwalls and aprons
Improved inlets
Material selection
Culvert skews
Culvert sizes
Related designs
Weep holes
Outlet protection
Erosion and sediment control
Environmental considerations
Safety considerations
Loading requirements
Page 18 of 47
Culvert and Bridge Photos
PHOTO NO. 1: Low head culvert or slab-span bridge? (TxDOT DES 604)
PHOTO NO. 2: The outlet velocities of this culvert are almost 20 ft/ sec.
Erosion damage is minimal.
Page 19 of 47
PHOTO NO. 3: Rip rap erosion protection was required below this culvert.
PHOTO NO. 4: A simple energy dissipator at a culvert outlet. (TxDOT DES 604)
Page 20 of 47
PHOTO NO. 5: Sediment accumulation in a box culvert. (TxDOT Photo)
PHOTO NO. 6: “Projected” barrel end treatments with sharp edges present some of the
highest entrance head loss conditions for inlets; Ce = 0.9. (TxDOT DES 604)
Page 21 of 47
PHOTO NO. 7: Flared wingwall end treatment with grooved edge treatments tend to result
in lower losses through the inlets; Ce = 0.2 (TxDOT DES 604)
Page 22 of 47
Important Definitions
1. Design Discharge – The “hydraulic load” for a culvert design is analogous to
the structural load for a structural component design. The design discharge is
usually a “peak discharge” or momentary maximum discharge on a typical storm
runoff hydrograph.
9. When normal depth is less than critical depth, Supercritical Flow results.
11. Tailwater level may be influential on both the headwater and the outlet
velocity characteristics of the culvert flow.
12. The Potential Scour or other damage at the downstream end of the culvert
is at its highest. This is because the constriction in flow represented by the
culvert barrel(s) causes an increase in velocity over the unconstricted velocity for
an unchanged discharge rate.
Page 23 of 47
13. Culvert Installation Types consist of:
a) Trench
b) Embankment and
c) Jacked or Bored (Trenchless)
14. Vast majority of culverts do not fail hydraulically or structurally, but rather they
wear out from the effects of corrosion and/or abrasion.
15. HEADWATER. Energy is required to force flow through a culvert. This energy
takes the form of an increased water surface elevation on the upstream side of
the culvert. The depth of the upstream water surface measured from the invert at
the culvert entrance is generally referred to as headwater depth. Figure V shows
performance curve for a culvert.
17. OUTLET VELOCITY. Since a culvert usually constricts the available channel area, flow
velocities in the culvert are likely to be higher than in the channel. These increased
velocities can cause streambed scour and bank erosion in the vicinity of the culvert outlet.
Minor problems can occasionally be avoided by increasing the barrel roughness.
Page 24 of 47
CULVERT CONCEPTS
Page 25 of 47
Concept No. 1 – Manning’s Equation
GIVEN:
Contributing Flow for a 36” RCP
Q = 67 CFS
Pipe Invert in = 100.0’
Pipe Invert out = 98.0’
Pipe Length = 100’
n = 0.013
FIND:
Culvert Capacity; is it adequate for contributing flow?
Page 26 of 47
Concept No. 2 – Head Loss
The velocity in a culvert barrel flowing full is 8 ft/sec just inside the barrel
entrance. Consider the following entrance loss coefficient “ke” or “Ce” values
(different end treatments)
What are the head losses for the above-mentioned end treatments?
Page 27 of 47
Concept No. 3a – Rational Method
(Contribution & Flow Type)
Water from a 175-Acre light industrial watershed is collected and drained by a
trapezoidal open channel. The channel (Manning’s roughness coefficient n =
0.022) has a 4.5-ft wide bottom and 1:1 sides. The channel direction is
perpendicular to a road where twin, side-by-side 54-inch diameter corrugated metal
pipe (CMP) culverts take the water under the roadway. The average slope of the
channel and culverts is 0.75% (0.0075 ft/ft). The time for runoff from the farthest
part of the watershed to begin contributing to the flow is 35 minutes.
FIND:
2. Using the rational method and assuming the intensity after 35 min. is 2 in/hr,
what is the runoff?
Page 28 of 47
Concept No. 3b – Rational Method
(Size Analysis)
On a rural section of a primary road there is a 36” concrete pipe cross-drain at a
location where a property owner claims his property is being flooded during heavy
rains due to the cross-drain being inadequate. Suppose you are employed as a
consultant to check this out and prove his point. In your investigation, you find that
the drainage area the pipe is to drain is 25 Acre extending 1000 feet back from the
right of way. It is farm land with a coefficient of imperviousness of 0.25. Rainfall
records indicate that the design rainfall intensity should be 4 in/hr. The pipe is laid
on the natural slope of 0.3%. It is a concrete pipe with a Manning’s n value of
0.012.
Page 29 of 47
Concept No. 4 – Capacity
(Unsubmerged Inlet)
A box culvert with an unsubmerged inlet (the flow is below the top of the culvert
inlet) functions as a weir. The culvert has a bottom width of 4 feet. The tailwater
does not back through culvert, so the “weir” can also be assumed to be
unsubmerged. The “ponded” water elevation immediately upstream of the inlet is
1.6 feet above the inlet flowline. Assume the approach is short and the velocity in
the “pond” is zero. Use Cw value of 3.1.
What is the maximum estimated discharge that will pass through the inlet?
Page 30 of 47
Concept No. 5 – Capacity
(Submerged Inlet)
The depth of water above the centroid of the inlet of a pipe culvert is 4.46 feet. The
downstream side of the culvert is unsubmerged and the discharge coefficient is
Co=0.6. The pipe has a diameter of 2 ft.
Page 31 of 47
Concept No. 6 – Critical Depth
[Critical depth of a hydraulic section (treated as an open channel) must be found
through iterative procedures for most shapes; however, for rectangular sections,
critical depth has a straightforward formula]
What is the critical depth in a 9 foot wide box culvert for a flow of 1374 cfs?
Page 32 of 47
Concept No. 7 – Use of Nomographs
(from TxDOT DES 604)
Compute the “inlet” control headwater depth and elevation using the nomographs.
The headwater needs to be determined for a discharge of 25 cfs through a 4 ft by 4
ft concrete box culvert. The culvert has an entrance coefficient “Ke” of 0.2 (use
Scale 1 on the nomograph). The barrel has an upstream flowline elevation of 100
feet at the inlet. This inlet elevation will be the reference point for the headwater
elevation (elevation = reference elevation + depth).
The PE exam may provide superfluous data on the barrel, but recall that the
question is asking for an inlet control headwater depth so only the culvert
inlet is of interest.
Page 33 of 47
Page 34 of 47
Page 35 of 47
Page 36 of 47
Concept No. 8 – Headwater
(Submerged Inlet - Orifice)
The inlet of a 24-inch (2-ft) diameter reinforced concrete pipe (RCP) is submerged
by a flow of 31.9 cfs. The inlet has a square-edge treatment and headwall
(ke = 0.5). What is the inlet control headwater depth above the inlet invert/
flowline?
Page 37 of 47
Concept No. 9 – Outlet Control
(Submerged Tube – w/o Nomograph)
A 4 ft by 4 ft concrete box culvert has a length of 100 feet, an entrance loss
coefficient Ke of 0.2, and a roughness coefficient of 0.012. The inlet flowline
elevation “Eli” is 100.0 feet. The outlet flowline elevation “Elo” is 99.0 feet.
The tailwater depth at the outlet is 8.8 feet and submerges the outlet.
Calculate the outlet control headwater elevation “ELho” and depth for a flow of
200 cfs.
Page 38 of 47
Concept No. 10 – Manning’s Table
(Capacity-Change Analysis)
A 24-in diameter pipe (n = 0.013) was installed 30 years ago on a 0.001 slope.
Recent tests indicate that the full flow capacity of the pipe is 6.0 CFS.
FIND:
a) The original full flow capacity
b) The original full flow velocity
c) The current full flow velocity
d) The current Manning’s coefficient
Page 39 of 47
Concept No. 11 – n Varying with Depth
(Circular Pipe)
A circular sewer is to be installed on a .5% grade. Its Manning coefficient is 0.013.
The maximum full-flow capacity is to be 7.4 CFS. Assume n is varying with depth.
FIND:
a) The pipe size
b) The full-flow capacity if an 18” pipe size is chosen
c) The full-flow velocity
d) Using the chart provided, flow depth for 0.85 CFS flow
e) Minimum velocity that will prevent solids from settling out in the sewer
Page 40 of 47
Concept No. 12 – Design for Peak Flow
(Circular Pipe)
a. A circular storm sewer with n = 0.012 is being designed to carry a peak flow
of 5 CFS. To allow for excess capacity, the depth at peak flow is to be 75%
of the sewer diameter. The sewer is to be installed in a bed with a slope of
2%. What is the required sewer diameter? Use the chart provided.
n = 0.013
Peak Flow = 7 CFS
Flow depth = 80%
Slope = 1%
Page 41 of 47
Concept No. 13 – Types of Flow
A 42” diameter concrete culvert is 250 Linear Feet long and is laid at a slope of
0.006. The culvert entrance is flush and square-edged. The Tailwater level at the
outlet is just above the crown of the barrel, and the headwater is 5.0 feet above the
crown of the culvert’s inlet.
Page 42 of 47
Concept No. 14 – Flow Rate under Inlet &
Outlet Controls
Determine the flow rate through a 50-ft. long, 18-in. diameter steel culvert with a 1
percent slope if HW = 5-ft. and TW = 2.5-ft. Assume n = 0.015, the entrance loss
coefficient CL = 0.5, and the orifice coefficient Cd = 0.65
Page 43 of 47
Concept No. 15 – Graphs with Inlet and
Outlet Controls
Using the given graph for 54” pipe and for the following scenario,
Page 44 of 47
Thickness of Pipe Culverts (RCP)
Equation/Formulae:
Page 45 of 47
References
Culvert Analysis and Design by Reagan Engineering
Associates.
http://www.HyperDictionary.com
Page 47 of 47