Final Thesis Final
Final Thesis Final
Cable stayed bridges date back many centuries; the system was used by Egyptians for their sailing ships.
In 1955 he built the Stralsund bridge, located in Sweden, which is considered the first modern cable stayed bridge.
Another important factor in the evolution of cable-stayed bridges was the employment of superstructure sections that act as a continuous girder
along the longitudinal axis. With these improvements, modern cable-stayed bridges became very popular in the last thirty years.
Significant illustrated milestones are the Theodor Heuss bridge in 1958, the Schiller-Steg footbridge which was constructed in Germany in 1961,
the Maracaibo Bridge constructed in Venezuela in 1962.
A cable-stayed bridge is a cable supported bridge in which one or multiple pylons are installed in the middle of the bridge and girder segments are
connected to the pylons by a cable.
In cable-stayed bridges, the shape of pylons, the shape of girders, and the cable arrangement can be freely designed; therefore, various structural
systems can be applied. (For example, adjusting the tension of the cable forces can reduce the size of the bending moment of the girder).
Today, the emergence of high-strength cables, the advancement of structural analysis software, the establishment of wind-resistant design
methods through wind tunnel tests, and the development of construction technology have placed cable-stayed bridges, alongside with suspension
bridges, responsible for the future of long-span bridges.
Edong China
CASE STUDY AND LITERATURE REVIEW
1) Naini Bridge-
The New Yamuna Bridge is a cable-stayed bridge located in Allahabad (Prayagraj). The bridge was constructed by the end of 2004 with the aim of minimizing the traffic over the Old
Naini Bridge. The bridge runs north–south across the Yamuna River connecting the city of Prayagraj to its neighborhood of Naini. The construction was consulted by COWI, a Danish
consulting company in joint venture with SPAN. Main construction was done by Hyundai and
was successfully completed in 2004.
BridgeSpecifications
Dimensions
Main Span 260 mt
Total Length 610 mt
Girder depth 1.4 mt
Deck width 26 mt
Deck Slab Thickness 250mm
Using prestressed concrete in segmental launches of span supported by cables and
semi fan system pylon of 90 mt.
BridgeSpecifications
A specially designed crane of 45-ton capacity was used to erect
Dimensions the pylons of the bridge. The structural steel used in the bridge weighs
Main Span 457.20 mt about 13,200 tones. The pylons, which are 128 meters (420 ft) in
Total Length 823mt height, are designed as free-standing portals. They are provided with
Girder depth 1.4 mt two cross portal members, one at the bottom and another at the top,
Deck width 35 mt
below the pylon head. The deck is connected to the end piers by bolts
embedded in the chambers of the piers. Pylons made of 4 m × 4 m (13
Deck Slab Thickness 230 mm ft × 13 ft) steel boxes of riveted construction were raised on the two
Pylon height 127.62 mts side spans of the bridge; one set is on the Calcutta side and the other is
Number of lanes 3 lanes and 1.2 mt footpath on each on the Howrah side.
side
Longest Span 457.27mt
Total Length 822.96
Main Span 457.2
Type of foundation Well foundation
World's Highest Rail bridge, a cable suspension over river Chenab in J&K,
India as per railway officials and DRDO, INDIA (Height is taller than Eiffel
tower in Paris) Under construction image of BWSL
Under construction picture of Arch-cable suspension bridge over Chenab. Conceptual image of BWSL
'
Determine the initial shape
(Final stage)
•
'
ConstructionStage
+ + +
Static analysis Dynamic analysis Stability check
Analysis
• Construction stage • moving load analysis • Seismic analysis (3D Model) • Cable replacement check
determination (Influence line analysis) • Wind resistance analysis • Buckling eigenvalue analysis
• Construction • Dead load (Eigenvalue analysis) (Stiffening girder, pylon)
load analysis • Wind tunnel test
determination (Temperature,
manufacturing and
• Construction Stage analysis
construction errors)
(Construction phase analysis)
I I I I
Design member forceand aggregate reaction force
and displacement
Load transfer
Deck Pylon
Tension
Cables
pylons
Stay Cable
Pile cap
Deck
Compression
Piles Pile cap
Piles
soil
15
Analysis
Steps of cable stayed bridge analysis
Dynamic
analysis
Static
analysis
16
Pylons
Height of the pylon is dictated by the stability analysis and economics of the bridge. A tall pylon will
minimize the compression introduced into the steel deck system, but may increase the length of cable used
while a short pylon will introduce undesirable compressive forces into the steel deck structure.
The cross section is sized for not only strength and deflection requirements, but also to accommodate
a stressing and inspection route.
The cable-stayed bridge is to be analyzed for its dead-load static response and then to two loadings
corresponding to earthquakes.
The cable is considered to have no stiffness in compression. An initial strain is applied to the cable
elements to provide the necessary pre stress needed to keep the deck from sagging under the dead load
using finite element analysis software creating a 3D model of the structure and carrying out its modal
analysis in STAAD Pro V8i/ Midas Civil/ Larsa4D.
17
STAAD MODEL REPRESENTATION
18
DESIGN OF GIRDERS AND SUPER STRUCTURE
19
Cable
A cable may be composed of one or more structural ropes, structural strands, locked coil strands
or parallel wire strands.
A strand is an assembly of wires formed helically around center wire in one or more symmetrical
layers.
A strand can be used either as an individual load-carrying member, where radius or curvature is
not a major requirement, or as a component in the manufacture of the structural rope.
A rope is composed of a plurality of strands helically laid around a core. In contrast to the strand,
a rope provides increased curvature capability and is used where curvature of the cable becomes
an important consideration
20
Cables Continued
Cables are made of high-strength steel, usually encased in a plastic or steel covering that is filled
with grout , a fine grained form of concrete, for protection against corrosion.
21
Selection of cable configuration
22
Efficiency and Economy
Greater stiffness that suspension bridge , so deformation of deck under live load is reduced
Symmetrical bridge, the horizontal forces are balance hence no large ground anchorage needed
25
The main system disadvantages are:
1. Still inferior to suspension bridges for super-long spans
FACES
Table 4.13
700
600
500
100
Graph 4.13
Results and Interpretations (Design Bending moment output)
Bending Moment { ULS (kN - m) }
FACES
Table 4.14
700
600
500 Blending
Moment { ULS (kN - m) } D
400 provider
300 Blending
Moment { ULS (kN - m) }
200 FACES Top
Blending
100 Moment { ULS (kN - m) }
FACES Bottom
Graph 4.14
Results and Interpretations (Minimum area of steel required)
Ast reqd
FACES
Section 1 255 52 2
Section 2 409 88 0
Table 4.16
3500
3000
2500
Graph 4.16
Results and Interpretations (Area of steel provided)
Ast min
FACES
Table 4.17
1200
1000
800
Ast
600 min D provider
Ast
400 min FACES Top
Ast
200 min FACES Bottom
Graph 4.17
Results and Interpretations (SLS check as per IRC:-6 Table:-B3)
300
250
200
150
50
Wk 0.022 0.002 0.041 0 0.171 0 0 0.155 0.067 0 0.062 0 0.057 0 0.12 0.067
FACE Top Bottom Top Bottom Top Bottom Top Bottom Top Bottom Top Bottom Top Bottom Inner
Outer
deff 172 256 379 255 601 447 449 395
Graph 4.21
Results and Interpretations (Box section Load analysis)
Figure 4.3: Loading on Box Girder - SIDL Figure 4.4: Loading on Box Girder - Wearing Coat
Conclusion
Cable-stayed bridges are usually thought of as long span bridges of above 200m spans for better
cost ratio of concrete than other types cantilever bridges. In many circumstances, cable-stayed
bridges can provide benefits at a relatively moderate increase in cost. Some of the benefits
include the following:
the minimization of environmental impacts and construction schedule limitations for river
crossings
enhanced appearance
In addition, greater use of this form of construction would allow our contactors to perfect
methods of construction that would drive down the cost for future cable-stayed bridges. However
cable stay bridges cannot be suggested for short to midspan bridges as it would round up too
expensive for short spans.
33
References
1) https://en.wikipedia.org/wiki/List_of_longest_cable-stayed_bridge_spans
2) https://www.slideshare.net/jigars7/cable-stayed-ppt-acp?qid=da69c352-
636a-4c74-a026-b558fcf82b10&v=&b=&from_search=12
3) https://failures.wikispaces.com/Cable+Bridge+Failures+Overview
4) http://www.bridgesofdublin.ie/bridge-building/types/cable-stayed
5) https://s3.amazonaws.com/ppt-download/cablen-140328072240-
phpapp01.pdf?response-content-
disposition=attachment&Signature=re98rzdUuZ4B%2B6YytC0%2F3PU1t1s
%3D&Expires=1488544787&AWSAccessKeyId=AKIAJ6D6SEMXSASXHDAQ
34