3-Process Description
3-Process Description
رﻗم اﻟﻣﺷروع
PROJECT NO.
EXPANSION OF AL KHOBAR SEWAGE TREATMENT
701230311 PLANT PROJECT
استشاري التصميم
DESIGN
CONSULTANT
Document Title:
PROCESS DESCRIPTION
Sheet Rev.
Document No.:
701230311-KHR-PAS-010GEN-HYD-RE-00001 Page 1 of 60 01
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
TABLE OF CONTENTS
ABBREVIATIONS .................................................................................. 5
1. Introduction ..................................................................................... 7
1.1 GENERAL .....................................................................................................................7
1.2 PLANT LOCATION AND FOOTPRINT ......................................................................7
1.3 INTERFERENCE WITH OTHER EXISTING PLANTS ...............................................................9
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
List of Figures
List of Tables
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
ABBREVIATIONS
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
1. INTRODUCTION
1.1 GENERAL
The scope of this project includes design, supply, construction and testing & commissioning of
the new expansion of Al Khobar Sewage Treatment Plant (STP), which will be capable to treat
an average daily flow of 200,000 m3/d. The new plant will be located in the same plot area of
existing Al Khobar STPs and Ajyal STP.
Generally, the design criteria will be based on the Employer Requirements (National Water
Company (NWC) Design Manual) according to the German Association for Water, Wastewater
and Waste (DWA) guide lines (former ATV) and implementing same process treatments and
technologies as Ajyal STP as requested by the Employer.
The STP will have biological nutrient removal process to achieve organic matter, nitrogen and
phosphorus removal, with secondary clarifiers. Sludge stabilization will be achieved by
anaerobic sludge digestion process.
The plant will have a total area of approximately 176,000 m2 (500m x 352m).
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
The new Expansion of Al Khobar STP will interfere with other existing plants, which are located
on the same plot area:
• As part of the expansion of Al Khobar STP’s scope, a new Sea Outfall Pumping Station
and pipeline will be provided, which will serve all the plants; existing Al Khobar STP,
existing Ajyal STP and the new expansion of Al Khobar STP.
• As part of the expansion of Al Khobar STP’s scope, a new disinfection plant (Electro-
chlorination plant) will be provided for existing Al Khobar STP.
• Treated effluent from the new Expansion of Al Khobar STP will be discharged to the
existing Irrigation Pumping Station.
2. DESIGN STANDARD
The proposed sewage treatment plant will comprise a biological treatment stage with a design
capacity of around 888,889 PE based on 225 l/(E*d).
The STP is designed in accordance with the Tender specifications and published standards.
Most references applied in our design can be found in the following literature:
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
1. Preliminary Treatment
• Coarse Screens
• Fine Screens
2. Primary Treatment
3. Biological Treatment
• Filter Station
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
5. Sludge Treatment
6. Biogas Systems
• Biogas Desulphurization
• Gas Flare
• Gas Holder
• Co-generation Unit
• Boiler Unit
7. Odor Treatment
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Table 2 shows pollution concentrations that is used for Process Design Calculation of
Expansion of Al Khobar STP.
TKN mg/L 50 36 32
* Concentrations under "Concentrations (Design Maximum)": are taken from NWC Design
Manual, Table 6-1 according to tender clarifications, dated on 10.01.2023.
*** Concentrations under "Concentrations (Actual Minimum)": are lowest organic load day
of existing Al-Khobar STP in 2023.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Note: Since the wastewater received will be municipal type wastewater and will not contain
any toxic substance for the biomass, therefore, its confirmed that these effluent characteristics
will be achieved with the proposed treatment process.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
6. PROCESS DESCRIPTION
6.1 GENERAL
The process of the wastewater treatment consists of mechanical treatment stage, primary
treatment stage, biological treatment stage, tertiary treatment stage, sludge treatment stage
and odour treatment. For further detailed information, refer to the process design calculation,
hydraulic calculation, hydraulic profile, site layout drawing, general arrangement drawings,
process flow diagram, mass balance and piping & instrumentation diagrams.
Function
Faecal sludge unloading and discharging to the inlet works of the plant
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Clear opening 10 mm
Explanatory Remarks
The facility mainly consists of three (3) sewage tanker truck unloading stations including flow
and quality monitoring (pH and conductivity), a sewage collection system, a screen for
removing large objects from the sewage and a pumping station for conveying the screened the
external septages delivered by trucks and other internal drainages to the Inlet Chamber
upstream of the screening facility.
The screenings from the trucked sewage screen will be thrown off into a container. The trucked
sewage transfer pumps will be controlled by the level measurement of the pump sump.
Function
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Bar spacing 20 mm
Explanatory Remarks
A bar screen is a mechanical filter used to remove large objects, such as rags and plastics,
from wastewater. It is part of the physical treatment and typically is the first being installed at
the influent to a wastewater treatment plant.
Six mechanical coarse screens (4 duty + 2 standby), which are designed for the maximum
hourly waste water flow-rate during rainy weather, will be provided for the protection of the fine
screens downstream.
The screens will be cleaned automatically and controlled by a water level difference measuring
on each screen. The cleaning system will start to operate when the level difference reaches to
a set point. Moreover, even if the level difference stays below the set point, the cleaning system
will also start to operate after the adjusted time interval.
Screened materials from the coarse screens will be discharged into screw conveyors and then
into wash presses where they will be exposed to powerful introduction of wash water. The
washing achieves perfect separation of organic particles and thus effective screenings
washing. After the screenings are compacted, they shall be directly disposed in to containers.
The conveyors and wash presses will be automatically switched on and off according to the
operation of the coarse screens.
Coarse screening channels, coarse screens, conveyors and screening wash presses will be
closed and collected air will be transferred to odour treatment unit.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Function
Opening’s size 6 mm
Explanatory Remarks
Perforated plate screens will be provided after the coarse screens inside the screen building.
The screenings are kept by the perforated plates. As the endless perforated chain is rotating
in the channel, the screenings are slowly separated from the water stream.
Six mechanical fine screens (4 duty + 2 standby), which are designed for the maximum hourly
waste water flow-rate during rainy weather, will be provided for the protection of the
downstream facilities.
The screens will be cleaned automatically and controlled by a water level difference measuring
on each screen. The cleaning system will start to operate when the level difference reaches to
a set point. Moreover, even if the level difference stays below the set point, the cleaning system
will also start to operate after the adjusted time interval.
Screened materials from the fine screens will be discharged into screw conveyors and then
into wash presses where they will be exposed to powerful introduction of wash water. The
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
washing achieves perfect separation of organic particles and thus effective screenings
washing. After the screenings are compacted, they shall be directly disposed in to containers.
The conveyors and wash presses will be automatically switched on and off according to the
operation of the fine screens.
Fine screening channels, fine screens, conveyors and screening wash presses will be closed
and collected air will be transferred to odour treatment unit.
Explanatory Remarks
An automatic sampler will be installed after pre-treatment to collect and store water samples
from the influent. Influent quality control for pH value, conductivity and temperature will be also
located at the same location. The automatic sampler can take flow proportional 24-hour-
composite samples. All the necessary equipment will be provided.
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Grit shall be removed in order to reduce risk of damage to the mechanical equipment in the
following treatment units and grease shall be removed to avoid non-aesthetic conditions
caused by the volatile organics and malodorous floating sludge.
After the fine screens, the wastewater will flow to four aerated grit and grease removal
chambers (longitudinal aerated grit chamber type with separate grease removal compartment
along the side). The purpose of these units is to remove the sand particles larger than 0.20
mm from the waste water with an efficiency of 90%.
An aerated grit chamber consists of a standard spiral flow aeration tank provided with air
diffusion tubes placed on one side of the tank. The grit particles tend to settle down to the
bottom of the tank at rates dependent upon the particle size and the bottom velocity of roll of
the spiral flow, which in turn depends on the rate of air diffusion through diffuser tubes and
shape of aeration tank. The heavier particles settle down whereas the lighter organic particles
are carried with roll of the spiral motion. The settled grit from the bottom of the channel will be
transferred to the grit channels and then transferred by gravity to the grit classifiers. Grit
classifiers will separate water from grit; water (supernatant) will flow to the sump pump of
trucked sewage receiving station, while grit will be stored in containers.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
The floated grease and oil will be pushed by grease blades to a grease chamber, which is
placed at the head of each grit and grease removal chamber. On the scrapers way back to the
head, the grease will be pushed into the grease chambers via motorized penstocks. The
grease is collected in the two grease collection chambers and then pumped to the anaerobic
sludge tanks (seeding mixers) by grease pumps.
Positive displacement type blowers will be provided for the air supply to the grit chambers.
Grit and grease chambers and grit classifiers will be closed and collected air will be transferred
to odour treatment unit.
Local control panels will control the moving drives and shields of the scrapers of grit and grease
removal chambers.
In order to achieve a maximum operation flexibility during start up and operation, primary
sedimentation tanks by-pass will be provided to be directly transferred to the Activated Sludge
Tanks. This will give more operational flexibility during operation of the plant, if its needed.
Explanatory Remarks
Influent wastewater flow will be measured by means of two electromagnetic flow meters,
monitored, controlled and registered via the SCADA system. All accessories for the proper
flow measurement will be provided.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Distribution chambers of PSTs will receive the wastewater from Bypass Chamber PST and
distribute it evenly to the Primary Sedimentation Tanks.
Distribution Chambers PST will be equipped with agitator to prevent separation of sludge and
water and to guarantee equal distribution of MLSS.
Number of tanks 4
Diameter of tank 30 m
Explanatory Remarks
From the Distribution Chambers PST, wastewater passes to four Primary Sedimentation
Tanks. In the PSTs, primary sludge will be separated from the wastewater by sedimentation.
Pollutant removal rates are dependent on the retention time according to ATV-DVWK-A 131E,
Table 1. Al-Khobar wastewater treatment plant primary sedimentation tank has been designed
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
to remove 50% of the suspended solid, 25% of organic pollutant (COD, BOD), 9.1% of nitrogen
(TKN) and 11.1% of phosphorous (P).
Four circular tanks with shield scrapers and scum removal system are foreseen. Velocities of
the inlet flow are kept slow to minimise the turbulence of the inlet. Due to the retention time
and calming down of stream, the primary sludge deposit on the bottom of the tank. Via a shield
scraper, the sludge on the bottom will be transported to the central sludge hopper of the tanks.
A pipeline connects each central sludge hopper to the primary sludge pumping station. The
sludge pumping stations will be equipped with eccentric pumps and primary sludge will be
pumped to the Sludge Mixing Tanks prior to further sludge treatments (i.e., anaerobic
digestion).
The waste water flows radially to the periphery of the primary sedimentation tanks and
discharge over a weir system to pass over into a collection channel and then into a Bypass
Collection Chamber PST from where it will gravitate to the Return Sludge Mixing Chamber.
The scum of PSTs will be collected by a surface shield scrapers scum into the collecting
chamber and pumped to the Sludge Mixing Tanks.
Primary sedimentation tanks will be fully closed with cover and collected air will be transferred
to odour treatment unit.
Local control cabinet of each primary sedimentation scraper bridge controls the system.
In order to achieve a maximum operation flexibility during start up and operation, primary
sedimentation tanks by-pass will be provided to be directly transferred to the Activated Sludge
Tanks. This will give more operational flexibility during operation of the plant, if its needed.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Receiving wastewater from PSTs, dirty filters’ backwash and return liquors, and mix with return
activated sludge.
Explanatory Remarks
This chamber will receive wastewater from PSTs, dirty filters’ backwash and return liquors, and
mix with return activated sludge. The chambers will be equipped with agitator to prevent
separation of sludge and water and to guarantee equal distribution of MLSS.
After receiving, mixed wastewater will be transferred to Distribution Chambers AST by pipes.
Manually operated penstocks to isolate the lines will be provided.
These distribution chambers will receive the wastewater from Return Sludge Mixing Chamber
and distribute it evenly to the Activated Sludge Tanks. Distribution Chambers AST will be
equipped with agitators to prevent separation of sludge and water, and to guarantee equal
distribution of MLSS.
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
wastewater and return activated sludge (RAS) enter the front end of the aeration tank and are
mixed by diffused air system. During the aeration period (Oxic Zone) adsorption, flocculation
and oxidation of organic matter occur. Activated-sludge solids are separated in a secondary
settling tank.
Explanatory Remarks
Eight anaerobic tanks will be provided. The reactor configuration utilized for phosphorus
removal is comprised of an anaerobic tank having 0.5 to 1.0 hours. The phosphorus necessary
for built-up heterotrophic biomass is calculated as 1% of inlet BOD concentration while excess
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
In order to prevent sludge sedimentation, the anaerobic tanks will be equipped with
submersible agitators.
Explanatory Remarks
The biological phosphorus removal process will be supported by a chemical phosphorus
removal system (FeCl3 dosing) in order to remove any excess phosphorus to meet the required
effluent discharge concentrations.
The precipitant solution will be pumped to the outlet chambers of the Activated Sludge Tanks
by means of dosing pumps. The phosphate-measurements of the outlet samples (Automatic
Samplers) are used for determination of the required amount of precipitants. The operator
calculates and provides the amount of precipitants which is required to reduce the phosphate
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
concentration below the allowed concentration of the effluent standards and accordingly the
pumps are adjusted.
In addition, Ferric Chloride will be dosed to Sludge Mixing Tanks in order to control Struvite
(Magnesium Ammonium Phosphate (MAP)) and upstream of the Primary Sedimentation Tanks
to allow Chemically Enhanced Primary Treatment (CEPT) in case needed.
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Eight activated sludge tanks are designed for organic matter (organic carbon, COD, BOD5)
removal as well as nitrification/de-nitrification (Kjeldahl-N and NO3-N) process. The tanks will
be designed as plug flow reactor with separate de-nitrification and aeration tanks and internal
circulation in order to provide the de-nitrification process.
In order to provide an operational flexibility to the biological system; part of the reactor volume
could be operable as aerobic as well as anoxic volume (swing zone). Additionally, the
anaerobic tank could be included in the volume of denitrification as the internal recirculation
pumps are designed to return the mixed liquor to both zones.
Nitrification: Conversion of ammonia into nitrite and nitrate by othotrophic bacteria via
biological oxidation.
2NH4 + 3O2 → (nitrosomonas) 2NO2 + 2H2O + 4H + new cell
2NO2 + O2 → (nitrobacter) 2NO3 + new cell
De-nitrification: Conversion of nitrate into nitrogen gas (N2) by facultative hetetrophic bacteria.
NO3 + CH3OH → 3N2 + 5CO2 + 7H2O + 6OH
The designed age of the sludge for the process will be 6 days at the minimum temperature of
20°C and the concentration of dry solids in the tank will be 3.5 kg/m3.
The de-nitrification tanks will be equipped with submersible agitators in order to ensure an
efficient mixing of sludge and water and to avoid settling of sludge in the tanks. No flow maker
or agitator will be required for aeration tank because the bottom of the aeration tank will be
covered with diffuser grit and fine bubble aeration will be sufficient to keep the biomass
suspended. The swing zone will have both agitator and fine bubble aeration.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
The process application will be re-denitrification with internal circulation. In this system
nitrification and carbon removal is achieved in the aeration zone, where the dissolved oxygen
concentration is maintained and de-nitrification is achieved in the anoxic zones prior to the
aeration zone. For the process efficiency considering the nitrate degradation, the activated
sludge will be recycled via internal pumps, which are located at the end of aeration zone and
the mixed liquor will be pumped back to the top of de-nitrification zone.
The applied biological wastewater treatment is based on the activated sludge process with fine
bubble aeration. For the intake of the necessary oxygen, the aeration tanks will be equipped
with fine bubble aeration, air distribution system as well as air blowers. Aeration will be
automatically regulated by electrically actuated valves based on on-line measurement of the
oxygen concentration in the individual tanks.
The blowers will be regulated with frequency controllers. Blowers will be operated
automatically based on a preset oxygen value (2 mg/l) and hence directly based on the air
pressure in the common air pressure pipe monitored in the activated sludge tanks.
Wastewater will be overflowed from each aeration basin to the outlet collecting channels. Pipes
located at the other side of collecting channel will transfer flow to Distribution Chamber SST.
Explanatory Remarks
This distribution chamber will receive the wastewater from the outlet collection channels of
Activated Sludge Tanks and distribute it evenly to the Secondary Sedimentation Tanks.
Distribution Chamber SST will be equipped by agitator to prevent separation of sludge and
water, and to guarantee equal distribution of MLSS.
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Separation of water and sludge, temporary sludge storage and sludge thickening.
Number of tanks 8
Explanatory Remarks
The SSTs will be constructed as circular tanks with sloping towards hoppers located in the
centre of the tanks.
Eight circular concrete tanks with sludge scraper mechanism for the removal of sludge and
scum will be constructed.
The settled sludge is scraped into hoppers in the center of tanks by scraper blades that are
mounted to the scraper bridge. From hoppers, sludge is piped to return and surplus sludge
pumping stations by pipes.
The floating scum will be scraped by scum blades into scum collection pits and from there
scum will be pumped to the SAS Balancing Tanks.
Peripheral scum baffles and peripheral weir plates will be provided on each final clarifier to be
retained within the process stream. The weir plate will utilize V notch design and shall be sized
to accommodate the maximum flow rate without overtopping.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Tertiary filtration will be designed to receive secondary effluent and to allow effective polishing
of the secondary effluent to achieve TSS effluent values of < 10 mg/L. Filtered water will be
conveyed to tertiary disinfection/Chlorine Contact Tanks via pipes. Captured solids, contained
in the filter backwash water, will be returned to the Return Sludge Mixing Chamber.
The whole Filter Station will consist of 8 filter units each located in a separate filter chamber (2
units will be standby).
The backwash water will be collected in the central backwash water channel from where it
gravitates to the Dirty Backwash Pumping Station.
The Disc Filter works on the basis of the well-proven drum filter principle. The screen consists
of horizontally arranged rotating filter discs installed on a central hollow shaft. The wastewater
to be treated enters the Disk Filter a rectangular inlet box and then flows via the central hollow
shaft into the individual disc segments. The solids are kept on the inside of the disc while the
clear filtrate passes through the mesh into the tank from where it discharges via an overflow
weir at the end of the tank.
The filter discs remain in rest position during the filtration process which is a continuous
process. The (suspended) solids settle by gravity on the inner disc surface, which leads to
gradual blinding of the filter mesh with the retained solids as the filtration process progresses,
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
resulting in an increases pressure difference between the flow inside the disc towards the clear
water level in the tank. When the predefined maximum internal pressure difference of typical
100 mm has been reached, the solids are removed from the filter surfaces by a slow rotation
of the filter discs combined with a backwash of the filter mesh. The backwash pumps feeding
the spray bar / nozzles are an integral part of the Disk Filter unit and do use the filtered water
from the tank. The backwash process goes on until the pressure difference has dropped again.
The removed solids are washed into a trough situated below the segment openings prior to
being drained off. The filtration process runs on continuously whilst the filter discs are being
cleaned.
Explanatory Remarks
There will be three submersible pumps (2 duty and 1 standby) of the same size installed within
the dirty backwash pumping station. They will have the task to forward the collected dirty
backwash which is produced by the filter station to the Return Sludge Mixing Chamber.
The duty backwash pumps will be switched on and off by a level sensor which is installed
within the dirty backwash pumping station, which will be also used for prevention overfilling
and dry running protection.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Effluent treated sewage flowrate will be measured by means of two electromagnetic flow
meters, monitored, controlled and registered via the SCADA system. All accessories for the
proper flow measurement will be provided.
On site generation of Sodium Hypochlorite (NaOCl) solution from Sodium Chloride (NaCl) and
potable water
Main Design Data
Capacity of each NaOCl dosing pump - new Expansion Al Khobar STP 7 m3/hr at 20 mWC
Type of NaOCl dosing pump - new Expansion Al Khobar STP Eccentric screw
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Capacity of each NaOCl dosing pump - Existing Al Khobar STP 3.5 m3/hr at 20
mWC
Explanatory Remarks
Complete disinfection plants will be provided for both new expansion of Al Khobar plant and
also for existing Al Khobar plant to inactivate pathogens in the treated effluent and to provide
a residual chlorine concentration in the treated effluent. Disinfection will be affected by a
sodium hypochlorite (NaOCl) solution generated on site from sodium chloride (NaCl) and
potable water by adopting an electrolysis process.
In the new expansion of Al Khobar STP, the dosing points for the effluent disinfection will be
situated in the Chlorine Contact Tank feed pipes. The Disinfection facility will be designed to
be capable to provide a continuous dosage of NaOCl solution into the effluent of 8 mgCl2/L.
The two dosing points downstream of the filter station will be served by a pump set operating
in a 2+1 operation mode. The chlorine dosing rate will automatically be adjusted proportionally
to the plant inflow (feed forward control) supported by residual chlorine measurements at the
outlet of the Chlorine Contact Tank.
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
In order to allow a complete reaction of chlorine upstream of the effluent measuring point,
Chlorine Contact Tanks will to be provided. The tanks will be made of concrete and will be
completely covered. The Chlorine Contact Tanks will be equipped with sufficient flow baffles
in order to guarantee a proper plug flow pattern.
The effluent sampling point for the automatic sampling device and the online monitoring for the
parameter residual chlorine, pH and turbidity will be located in the outlet chamber of the
Chlorine Contact Tanks.
Service water will be withdrawn from the tank outlet shaft by means of pipes.
Usage of treated effluent for Screening Building, Sludge Thickening & Dewatering Building,
Odour Control Units and other consumers.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
For the service water supply, service water will be withdrawn from the outlet chamber of the
Chlorine Contact Tanks by means of pipes.
A compressed air reservoir tank, which will reduce the number of operations of these pumps,
is included within the Service Water Pumping Station.
The demand for service water will mainly be in the screening plant (screenings wash press,
grit classifiers), sludge thickening and dewatering building and odour control units.
The cut in and cut out of the service water pumps will be controlled by pressure measurement
on the pumping main.
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Treated effluent from Chlorine Contact Tanks will gravitate to Treated Effluent Storage Tanks,
which will be completely covered and equipped with an outlet overflow for the discharge of
treated water.
Discharged treated effluent will be via an overflow to a chamber, which will be connected to
the existing Irrigation Pumping Station (main consumer of treated effluent). In case of excess
treated effluent, it will overflow to the new Sea Outfall Pumping Station for discharge to the
sea.
Explanatory Remarks
Sea outfall pumps and pipeline will be provided in order to pump excess treated wastewater
into the Gulf.
This new pumping station will serve also other existing plants e.g., Khobar STP and Ajyal STP
as well as the new expansion of Al Khobar STP.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Sex progressive cavity pumps (two as stand by) will pump primary sludge in to sludge mixing
tanks. Two electromagnetic flow measurements will be provided on discharge line of primary
sludge pumps to measure the quantity of the primary sludge.
The scum that is taken from the primary sedimentation tanks will be transferred from scum
collection chambers to Sludge Mixing Tanks by PST scum pumps (2 duty + 2 standby).
The primary sludge pumps operate in time intervals (Control by timer and flow meter on the
pumping main) throughout the day depending on the dynamic solids load to the STP and
depending on the sludge concentration which is required to be achieved.
6.6.2 Return & Surplus Sludge and Secondary Scum Pumping Stations
Function
Pumping of return sludge to the Return Sludge Mixing Chamber and pumping of surplus
activated sludge and secondary scum to the SAS Balancing Tanks
Main Design Data
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Sludge collected from the Secondary Sedimentation Tanks flows via pipes to the RAS/SAS
pumping station by gravity.
Each pipeline enters the return sludge pumping station through separate reservoirs and the
inlet flow to the pump’s sump is controlled by adjustable motorized weir penstocks. Controlling
of the opening/ closing of these penstocks is provided via ultrasonic flow measurements that
are placed in the inlet reservoirs of the pump sump. According to the signals from plant’s inlet
flow measurement and selected rate of recirculation, ultrasonic flow measurements supervise
the adjustable motorized weir penstocks.
Operation of RAS pumps will be controlled by ultrasonic level measurement instruments in the
pump sumps, which also provide protection of the pumps from dry running.
Submersible pumps will be provided for pumping the surplus activated sludge to SAS
Balancing Tank. The SAS pumps shall be fixed-speed and shall operate until a set daily volume
is pumped out in order to maintain the design sludge age. A flowmeter is installed on the
discharge pipe of the WAS pumps for this purpose.
The SST scum that is taken from the SSTs is transferred from scum pits to SAS Balancing
Tanks by progress cavity SST scum pumps (2 duty + 2 standby).
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Surplus sludge will be pumped to SAS Balancing Tanks in order to store and homogenize the
surplus sludge before thickening. Furthermore, scum from the secondary sedimentation tanks
will be pumped into the SAS Balancing Tanks as well.
The tanks will be equipped with submersible agitators in order to ensure an efficient mixing
and to avoid settling of sludge in the tanks. Also, level in the tanks will be measured to control
the pumps and mixers.
The tanks will be covered with GRP and forced ventilated. The extracted foul air will be treated
by the odour control unit.
Function
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Capacity of polymer preparation unit 9.91 kg/hr polymer (1982 l/hr @ 0.5%)
Explanatory Remarks
Surplus sludge and scum from secondary sedimentation tanks will be mechanically thickened
by means of four mechanical thickeners (one as standby). For this purpose, the sludge will be
delivered by four feed pumps (one as standby) to the belt thickeners.
Belt thickeners are continuous gravity filters with a screening belt which runs between two
rollers and onto which the sludge to be thickened is fed. Filtrate of the thickening process will
flow to the Return Liquor Pumping Station via gravity pipe line. Thickened sludge flows into the
suction line of the thickened sludge pumps, which pump direct the thickened sludge to the
Sludge Mixing Tanks.
In order to improve the sludge characteristic regarding to its thickening capability, it is planned
to apply coagulant aids (polymers) to the thin sludge directly. The sludge will be thickened up
to about up to 6 % DS and one polymer preparation & dosing station will be installed which
serves for pre-conditioning of the thin sludge prior to the four belt thickeners. Four frequency
converter controlled positive displacement pumps will be used for polymer dosing and each
pump will be associated with one belt thickener. The polymer preparation plant will be a
package plant coming with its own local control cabinet.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
The belt thickeners will be fully closed for the provision of odour control and extracted foul air
will be transferred into the odour treatment unit. The start and stop signal of the thickening
machine will be given manually by the operator via HMIs, after that the machines will be
operated in full automation.
Thickening units, polymer preparation & dosing station and all relevant equipment will be
located in Sludge Thickening & Dewatering Building.
Storage and mixing of SAS and SST scum (after thickening) with the primary sludge and scum
Explanatory Remarks
Sludge Mixing Tanks will be provided to store thickened surplus sludge & SST scum and
primary sludge & PTS scum prior to feed to the anaerobic digesters. Tanks will be equipped
with agitators. Also, level measurements will be provided for control purposes.
The tanks will be equipped with submersible agitators in order to ensure an efficient mixing
and to avoid settling of sludge in the tanks. Also, level in the tanks will be measured to control
the pumps and mixers.
The tanks will be covered with GRP and forced ventilated. The extracted foul air will be treated
by the odour control unit.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Mixed sludge will be pumped to the anaerobic digesters with six eccentric screw pumps (two
as standby). For each two digesters, two duty eccentric screw pumps will be provided as
digester feed pumps and one common standby pump. Each digester feed line will be equipped
with an electromagnetic flow meter to monitor the flowrate inlet to digesters.
Sludge feeding to the digesters will be started and stopped by the level measurement within
the Sludge Mixing Tanks. One adjustable feeding timer controls whether digesters will be fed
or not. Therefore, the duration for sludge feeding will be set by the operator. Several interlocks
will be existed for the feeding pumps such as level measurements in the Sludge Mixing Tanks
& Digesters, sludge re-circulation pumps, heating system, etc.
6.6.7.1 Introduction
Anaerobic sludge digestion was developed decades ago and today is an integral part of most
sophisticated disposal concepts. ARTELIA has experience
with more than 1,500 sludge digesters worldwide and is a leader in the design and optimization
of this process. In fact, the anaerobic sludge digestion process was meanly developed in our
company (former “Roediger – Anlagenbau”) and the well-known manual guide for sludge
digestion which is an essential work book for experts for waste water treatment plants was
written by us. So our company has an experience of more than 74 years in design, build,
commissioning and operation of digestion plants.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
In view of the above, ARTELIA would like to incorporate its obtained expertise from the
supply, installation, commissioning and maintenance of more than 1,500 plants worldwide into
the design of Expansion of Al Khobar STP:
• The offered Equipment has been successfully implemented around the globe.
The sludge digestion system will consist of four mesophile anaerobic digesters with associated
mixing, heating and biogas storage & utilisation equipment. The digestion system is based on
ARTELIA’s established processes and wealth of experience gained from many installations
worldwide.
DIGESTION EQUIPMENT
1 Manhole
2 Heat Exchanger
3 Seeding Mixer
4 Scum Removal
5 Recirculation Pumps
6 Scum-Breaker
7 Gas Hood
10 Gravel Filter
11 Ceramic Filter
12 Condensate Drain
15 Supernatant Discharge
16 Boiler
17 Gas Storage
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
The mixed thickened sludge from the Sludge Mixing Tanks will be pumped to the inject points
of the heating exchanger prior to the digester.
In the inoculation mixer the sludge is mixed together with the recirculation sludge, so that
seeding with the recirculation sludge, which is already undergoing digestion, as well as pre-
heating, is achieved at the same time.
The raw sludge and seeding sludge are transported from the inoculation mixer via the heat
exchangers, construction by ARTELIA, where the sludge is indirectly heated counter
currently by heating water. The heated sludge mixture is transported via the feeding line into
the digester.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
During the feeding process with raw sludge, digested sludge from the hopper is displaced via
the rising pipeline by the discharge device. Digested sludge is discharged in a separate outside
shaft and from there digested sludge flows to the Digested Sludge Storage Tanks.
Digester Recirculation Pumps switched on and off by digester feed pumps operation or by heat
demand (temperature measurement within digesters).
Capacity of gas compressors (Gas Lance Mixing) 240 Nm3/h at 2.5 bar
Explanatory Remarks
The gas injection serves for intensified re-circulation of the digester contents. The system is
patented for ARTELIA (CH - Pat. Nr. 671 885). There are 12
hanging lances in each digester, the distributors of which are arranged at a low level above
the bottom of the digester. The lances are operated according to a special scheme in order to
achieve an optimal mixing of the raw sludge into the digester content. The digester gas is taken
out of the digester hood, construction by ARTELIA and is discharged into a separate
circulation. At first the gas is sucked via the suction line out of the digester, then it flows through
a ceramic filter (constructed by ARTELIA) which serves for pre -filtering, then it is
compressed in the gas compressor. The compressed gas from the gas compressor is delivered
via a liquid separator and the pressure line to the gas lances. The gas injection can be affected
automatically.
The gas injection System ARTELIA uses special inje ction heads
which hang at flexible special hoses (lances); the system is conceived in a manner that no
sludge can penetrate into the gas lines when the gas compressors are cut off and that the
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
lances can be pulled out of the digester without interruption of the operation of the digester. By
the utilization of special gas compressors for the compression of the gas damages because of
corrosion are prevented. Besides, all parts coming into contact with the gas are made of special
alloys.
Digester mixing system is a timer-controlled system with mixing time and break time for the
various segments of the digester.
In order to protect the digester against an over-pressure (over 0.05 bar = 500 kp/m³) or sub-
pressure a special combined protection device for gas over-pressure and sub-pressure
(constructed by ARTELIA), is installed in the gas hood with a hydraulic seal. The
construction of the device is made in such manner that the sealing liquid (usually water) does
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
not run out of the device. When the original conditions are restored, the sealing liquid flows
back again. In case of very strong pressure blasts, smaller loss of sealing liquids is possible.
Therefore, the device is equipped with a level indicator which has to be checked daily. Since
the device is immerged in the digester roof (in the gas room) and is continuously heated by the
temperature being present in this area, there is no danger of freezing.
There is a gas withdrawal dome (constructed by ARTELIA) installed on the gas hood,
which serves for the withdrawal of the biogas for the further utilisation. The gas dome is
equipped with a foam trap. This foam trap shall prevent the penetration of the foam into the
gas system.
• Monitoring and control of the digester contents (level measurement). The measurement
according to the hydrostatic pressure principle by pressure sensors.
• Monitoring and control of the temperature of the digester at three measurement points
in each digester.
• Monitoring and control of the pH-value of the fresh feed sludge. A measurement point
is located at the circulation-pipe line. The electrode takes continuously the pH-value
and gives it to the indication instrument. Therewith the pH-value of the sludge is
controlled in the digester.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
• Monitoring and control of the gas production with one measurement point in the main
line. The entire gas unit is continuously measured via an orifice gauge, indication and
addition is made.
• Monitoring and control of the gasometer level. This measurement point is located at
the gasholder and is showing the actual level and also some contacts with which the
flare is switched on and off, resp. alarm is taken off or release statement for the heating
boiler or the power plant is given. Since the gasometer has an optic indication, this
measuring point is connected to the mechanic indication instrument.
• Flow Measurement of utilisation gas with each measurement point in front of boiler and
of gas engine.
Explanatory Remarks
The biogas is withdrawn via the gas withdrawal dome out of the head of the digester with a
pipeline. The gas flows into the gravel filter (constructed by ARTELIA) which serves for the
pre-dewatering and pre-filtering (coarse filtering) of the biogas. The condense water is
separated at the surface of the filling material (gravel) and is collected on the bottom of the
filter. There it is discharged via a siphon.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
After gravel filter, biogas will flow to desulphurization plant for further treatment. The purpose
of the plant is to reduce the amount of hydrogen sulphide of the biogas. The removal of the
Sulphur in the biogas is done with the help of Bacteria. The desulphurization plant is package
unit and controlled by its own control panel. The sulphate waste stream produced at the
Desulphurisation Unit is discharged to the Return Liquor Pumping Station.
Type Double-Membrane
Volume 4,500 m3
Gas line goes to the low-pressure gasholders with a usable volume of 4500 m³. These gas
meters serve for storage and pressure compensation resp. pressure maintenance in the gas
system and will be designed for a storage capacity of about 12-hour production.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
After the desulphurization plant, the biogas flows to two low pressure gasholders (tanks). The
gas production by the anaerobic sludge digestion is not constant during the whole day. There
is a peak gas production expected especially after the feeding of the digester with raw sludge.
The task of the gas holder is to store intermediately the peak gas production during the day so
that the biogas consumers e.g., Combined Heat & Power (CHP) units or boiler can be fed with
biogas also in times when the biogas production is low.
Each Gasholder consists of a double Membrane. Air is blown into between the two membranes
through the blowers. This creates the pressure in the Biogas System. The gasholders are
directly integrated in the main gas pipe. There will be an automatic condensate trap installed
prior to and right after each gas tank. These condensate traps are placed in a small chamber
directly at the gas tanks. The removed and collected condensate flows into a pump sump which
is equipped with a condensate pump.
The gas holders will be equipped with level measurements. This is required for the control of
the gas holders, gas flare, gas boiler as well as CHP units. Therefore, several pre-set values
have to be created and adjusted to ensure a proper operation of the gas utilization plant.
Explanatory Remarks
If the gasholder is filled up to a maximum level, a certain quantity of the gas is burnt off
automatically by a gas flare which is connected with the gas system via a branch line (through
Biogas Booster Blowers). The control of the gas flare and the protection is fully automatic in
dependence on the level of the gasholder (the gas flare is switched on and off by the level
measurement within gas storage tank (e.g. high-high level))
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
The biogas used in the CHP units and/or dual fuel burner flows to the gas filtering devices.
This plant consists of a ceramic filter (constructed by ARTELIA), which serve for fine -
purification; in these filters a number of fine-pored filter candles is arranged, through which the
gas is flowing from the inside to the outside. During this process fine polluted matter and the
remaining moisture is filtered out of the gas and fall from the outside of the filter candles into
the collection chamber of the filter, while the purified gas is flowing on to the biogas consumers.
In addition, prior to the biogas consumers, the biogas will pass through Siloxane removal
system (using granular activated carbon filters) in order to remove the undesirable silicon
components.
Function
Main Parameters
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
Stored biogas in the gasholders doesn’t have enough pressure to flow to the consumers i.e.,
CHPs and/or boiler, therefore, booster blowers will be provided to increase pressure of biogas
upto required level for the final consumers as recommended by the manufacturers. The
blowers will have variable speed and will be controlled based on the level of the gasholders
(switch-off function for Biogas booster blowers will be provided in dependence with the filling
level of the gas holders and operation command of the consumers (i.e. CHPs, and/or boiler)).
Explanatory Remarks
CHP-units are installed for energy recovery purposes. The power plant consists of combined
heat and power units. It is heated with combined full automatic digester gas excess pressure
burners. The burner is equipped with special safety and regulation armatures. The heated
water flows through the lines from the boilers to the distributor battery. Heating circulating
pumps deliver a part of this water to the heat exchangers, construction (constructed by
ARTELIA . Power is produced when the digester gas is burnt and
the waste heat from cooling and waste gas is used for heating of water. The water has normally
a temperature of 70°C when it is used for the motor and is heated up to 90°C. The hot water
is delivered over the heat distributors to the heating circuit.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Produced biogas will be primarily utilized in four CHP units to produce required head demand
in the plant and production of electricity. Furthermore, a dual fuel boiler that has capacity of
plant’s head demand will be provided to be used for the start-up period when produced biogas
is insufficient and also as back-up when the CHP unit is not in operation.
The CHP units will be installed for energy recovery purposes. The power plant consists of
combined heat and power units. It is heated with combined fully automatic digester gas excess
pressure burners. The burner is equipped with special safety and regulation armatures.
Heating circulating pumps deliver a part of this water to the heat exchangers. Power is
produced when the digester gas is burnt and the waste heat from cooling and waste gas is
used for heating of water. The water has normally a temperature of 70°C when it is used for
the motor and is heated up to 90°C. The hot water is delivered over the heat distributor to the
heating circuit.
For start-up of operation and emergency cases, sufficient boiler capacity will be provided. The
boiler will be of the dual fuel type capable to be operated whether with biogas or light fuel oil.
Biogas Consumers (CHP and Dual Fuel Boiler) will be switched on and off by level
measurement within gas storage tank according to the heat demand by the plant.
Gas rooms, heating room and CHP room will be provided with emergency fans. The fans will
switch on automatically when the gas detectors indicate a high gas level within above
mentioned rooms.
Number of tanks 2
Diameter of tank 20 m
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Explanatory Remarks
There will be two storage tanks for digested sludge from anaerobic digestion process. The
tanks will be circular and equipped with submersible mixers for avoiding sedimentation of
sludge, as well as level measurements for monitoring and controlling the dewatering feed
pumps. The task of the Digested Sludge Storage Tanks is to store the digested sludge prior to
the sludge dewatering plant. The tanks will be covered with GRP and forced ventilated. The
extracted foul air will be treated by the odour control unit.
The mixers will operate with the operation of dewatering plant (centrifuges), when the
centrifuges are not in operation, then mixer’s control will be a timer (operation/break timer).
Function
Explanatory Remarks
Digested sludge will be pumped to the dewatering machines via eccentric screw pumps with
frequency convertors. An electromagnetic flow measurement will be provided at the discharge
lines of the dewatering feed pumps to measure its quantity.
For control purpose there will be installed level measurements within each Digested Sludge
Storage Tanks, which will be also used for dry-run protection of the pumps.
Starting and stopping of each dewatering feed pump will be done in accordance with the
command signal received from control panel of corresponding dewatering machine (i.e.,
centrifuge).
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Function
Capacity of polymer preparation unit 21.35 kg/hr polymer (4271 l/hr @ 0.5%)
Explanatory Remarks
Digested sludge from the Digested Sludge Storage Tank will be pumped by sludge dewatering
feed pumps to four Centrifuges (one as standby) in order to reduce the amount of sludge. The
dewatered sludge will contain approx. 22% solid substances.
Before the entering of the sludge to the Centrifuges, polymer is dosed into the feeding pipe in
order to condition the sludge accordingly. The polymer preparation unit will allow the use of
polymers in both granular and liquid form. The polymer preparation units prepare 0.5% solution
with potable water. The 0.5% solution is then post diluted with service water to 0.1% solution
prior to mixing with sludge, to improve blending and flocculation. Diluted polymer will be dosed
by four (one pump for each line) frequency-controlled eccentric screw pumps before the
Centrifuges. The polymer preparation unit will be a stand-alone unit and will be automatically
controlled locally by a local control panel. The flow on the polymer line will be measured with
electromagnetic flow meter.
The designed load conditions will be daily operating period of 16 hours and 7 days a week.
The filtrate from the Centrifuges will flow by gravity to the Returns Liquor Pumping Station
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
where it will be pumped back to the plant. Dewatered sludge will be taken into the conveyor
and transferred to sludge cake storage area. Dewatering units, polymer preparation and dosing
station and all relevant equipment will be located in Sludge Thickening & Dewatering Building.
A crane will be provided to the building in case any maintenance requirement is occurred.
The sludge dewatering machines and the polymer preparation and dosing plant are package
units coming with their own local control panels.
Function
Explanatory Remarks
After the solids content in the sludge is increased to 22%, stabilized and dewatered sludge will
be transported to the Sludge Storage Area for an intermediate storage.
Function
Explanatory Remarks
Return liquors/supernatant from thickening and dewatering processes and drainage from other
units will be collected in supernatant pumping station and pumped by submersible pumps to
Return Sludge Mixing Chamber.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
The pumps will be switched on and off by a level measurement which will be installed within
the sump pump. Water elevation will be controlled by to start/stop mechanism for prevention
overfilling and dry running. The sump pump will be covered with GRP and forced ventilated.
The extracted foul air will be treated by the odour control unit.
Document Title:
PROCESS DESCRIPTION
Project Title:
EXPANSION OF AL KHOBAR SEWAGE TREATMENT PLANT PROJECT
Number of OCU 2
Explanatory Remarks
The odorous air will be collected from Inlet Chamber, Screening units, Trucked Sewage
Receiving Station, Grit & Grease Chambers, PST, Returns Liquor Pumping Station, Sludge
Mixing Tanks, SAS Balancing Tanks, Digested Sludge Storage Tanks and Sludge Thickening
& Dewatering Plant. The Bio-Trickling Filters are of a counter current design, where the gas
will enter the filter via the gas inlet at the bottom of the filter. The gas moves upward and passes
through the packing beds in vertical direction while the bed will be irrigated from above by
water through the spray nozzle situated immediately above the bed.
The odour treatment plant is a package plant, which will have its own local control panels.
-END OF DOCUMENT-