Complete 420E Standard Manual July 2010
Complete 420E Standard Manual July 2010
INSTALLATION, OPERATION,
MAINTENANCE AND
SPARE PARTS MANUAL
Copyright (C) 2010, Weir Minerals Australia Ltd trading as Weir Minerals Multiflo. All rights reserved. MULTIFLO, VACTRONIC
and HYDRAU-FLO are registered trademarks of Weir Minerals Australia Ltd. This document contains information which is confi-
dential to Weir Minerals Australia Ltd. It should not be disclosed in whole or in part to parties other than the recipient without
the express written permission of Weir Minerals Australia Ltd authorized personnel.
Introduction
Contact Details for O.E.M.
O.E.M. Introduction
General Safety
Shaft Lock Removal
Performance Curve
Weir Minerals Australia General Conditions of Sale
Caterpillar Warranty Conditions
Part 1 Installation
Part Page
Section 1.1 Pump Unit Delivery & Storage Procedures I 1
1.1.1 Storage Procedures I 1
1.1.1.1 General Storage I 1
Section 1.2 Safety Warnings I 2
1.2.1 Bare Shaft Pump Safety I 2
1.2.2 Vacuum Pump Safety I 3
Section 1.3 Unit Lifting Points (Total Unit Mass) I 4
Section 1.4 Assembly Instructions I 6
1.4.1 Assembly of Pump and Skid I 6
1.4.2 Assembly of Pontoon I 8
1
Multiflo Model MF-420E – Master Index
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
2
Multiflo Model MF-420E – Master Index
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
3
Multiflo Model MF-420E – Master Index
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
4
Multiflo Model MF-420E – Master Index
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
5
Multiflo Model MF-420E – Master Index
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
6
Multiflo Model MF-420E – Master Index
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
7
Multiflo Model MF-420E – Master Index
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
Part Page
Suction Components
Suction Assembly IV 40
Discharge Components
Discharge Assembly 41
Non Return “Vooom” Valve 43
Discharge Inspection Tee Assembly 44
Standard Options
Worklights 45
Fire Extinguisher 46
Washdown Hose 47
Strobe Light 48
Unit Data
Unit Mass & Dimensions
Specific Spare Parts
Wiring Diagram
List of Accompanying Manuals
8
Multiflo Model MF-420E – Master Index
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
1
Multiflo Model 420E – List of Figures
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
2
Multiflo Model 420E – List of Figures
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
3
Multiflo Model 420E – List of Figures
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
4
Multiflo Model 420E – List of Figures
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
ISO CERTIFICATIONS
Introduction
Weir Minerals Multiflo
In Indonesia:-
Or
(Always Quote Unit Model and Serial Number when Requesting Information and when Ordering Parts)
Weir Minerals Multiflo
In Australia:-
Queensland (Bowen Basin)
Weir Minerals Multiflo Authorised Dealer
For Service, Repair and
Spare Parts Supply
NQ Water Services
319 Nebo Road Mackay Qld.
Ph: 07 4952 2252
Fax: 07 4952 2126
Email: [email protected]
Or
Rockhampton Authorised Service Provider
Weir Minerals Service Centre
80 McLaughlin Street
North Rockhampton QLD 4701
Ph:
Ph: 07 4924 7700
Fax:
ax: 0 7 4924 7799
[email protected]
Or
Head Office
Weir Minerals Multiflo
15 Dacmar Road
Coolum Beach Qld 4573
Ph: 07 5449 3032
Fax: 07 5446 4304
Email: [email protected]
(Always Quote Unit Model and Serial Number when Requesting Information and when Ordering Parts)
Weir Minerals Multiflo
Introduction
The purpose of this Manual is to advise and instruct installers, operators and
repairers of the Weir Minerals Multiflo Pump Unit in the recommended installation,
operation and maintenance of this equipment. You have purchased a quality product
which has been manufactured with utmost care and the finest materials, reflecting
many years of engineering knowledge and design.
The following information will aid you in the installation, operation and maintenance
of your new Weir Minerals Multiflo Pump Unit. To ensure long life and trouble-free
operation, you should read and understand these instructions and provide regular,
periodic maintenance.
1
Introduction
Weir Minerals Multiflo
MULTIFLO PUMPS
EXCELLENCE THROUGH DESIGN
EXCELLENCE THROUGH ENGINEERING
EXCELLENCE THROUGH PERFORMANCE
2
Introduction
Weir Minerals Multiflo
Safety
1
Weir Minerals Multiflo – Pump Unit General Safety
Weir Minerals Multiflo
Safety Symbols
Fatal or crippling
DANGER ! Imminent risk of Persons
injuries likely to
fatal or crippling
result from any
injuries
exposure
Application
INFORMATION ! Hints and other Nil Nil
useful
Information
2
Weir Minerals Multiflo – Pump Unit General Safety
Weir Minerals Multiflo
WARNING!
(Always quote Model and Serial Number of Unit when Ordering Parts)
WEIR MINERALS AUSTRALIA LTD
ABN 69 009 701 802
4.2 The due date for payment shall not be postponed on account of 8. AMENDMENT AND CANCELLATION
damage, non delivery or additions, alterations, minor omissions or The Purchaser shall not, after acceptance of order, cancel or amend it in
defects to, from or in the Goods which do not substantially affect the any way without the written approval of Weir. Weir may, on consenting to
commercial use of the Goods. Payments must be made without an amendment, revise its price and delivery schedule and amend the terms
setoffs, counter-claim or deduction. and conditions to reflect such change. In the event of an amendment or
cancellation, the Purchaser shall reimburse Weir for all costs and expenses
5. PRICES & TAXES
already incurred by Weir or for which Weir has or will become liable, and for
5.1 GST All prices quoted are exclusive of GST. In addition to the
any additional costs and expenses resulting from the amendment or
payment of the prices quoted, Purchaser must pay to Weir an
cancellation.
amount equal to any GST imposed on Taxable Supplies made by
Weir to the Purchaser. Weir must give the Purchaser a Tax Invoice The specification by Weir of any particular personnel, in any quotation or
in respect of each such Taxable Supply. “Taxable Supply”, “GST” tender, is subject to availability of those personnel and Weir reserves the
and “Tax Invoice” have the same meanings as in the A New Tax right to substitute any nominated personnel at any time.
System (Goods and Services Tax) Act 1999. If the Purchaser
9. DEFAULT
intends to export the Goods, so that Weir will be exempt from GST
If the Purchaser makes default in payment or fails to carry out any part of
in respect of its supply of the Goods, it must provide Weir with
any contract of which these General Conditions of Sale form part or shall
copies of the shipping documents, and such other documentation as
become bankrupt or commit any act of bankruptcy or compound with its
Weir may reasonably require, within 60 days after the date of Weir’s
creditors or have judgment entered against it in any court or, being a
invoice, otherwise an amount equal to the GST will be payable by
company, have a provisional liquidator, receiver or manager appointed or
the Purchaser to Weir.
enter into any other form of insolvency administration, Weir may at its option
5.2 Unless otherwise specified in writing by Weir, all prices quoted are and without prejudice to any of its rights and remedies under the contract,
ex works (the location specified by Weir in its tender or quotation), suspend or terminate the contract or require payment in cash before or on
unpacked, and all costs of freight and delivery from Weir works, and delivery notwithstanding any other terms of payment specified in the
packing, will be to the Purchaser’s account. contract. If Weir terminates the contract pursuant to this clause, all amounts
payable for work performed up to the date of termination, whether or not
5.3 Where Goods or raw materials or components for Goods are to be
otherwise then due for payment, will become immediately due and payable.
imported:
Weir will not be liable to the Purchaser for any loss or damage the
(a) the quoted prices for those Goods are based on the foreign
Purchaser suffers because Weir has exercised its rights under this clause.
currency rate of exchange disclosed in Weir’s quotation and if
no rate of exchange is disclosed, are based on the 10. RETURN OF GOODS
Commonwealth Bank of Australia Foreign Exchange Rates, Weir may, at its absolute discretion, agree to accept the return of any of
published on the date of the quotation. Goods which have not been made or purchased specifically for the
Purchaser and credit the Purchaser with the invoice value of the Goods
(b) unless otherwise specified in writing by Weir, the quoted prices
provided the Goods is returned in “as purchased” condition and the prior
shall be adjusted upwards or downwards as the case may be
written approval of Weir has been obtained by the Purchaser for the return
to reflect the difference between the base rate of exchange
of the Goods. Weir reserves the right to charge a restocking fee for the
referred to in (a) and the actual rate of exchange prevailing on
return of Goods to stock.
the day Weir remits the foreign currency amount for the Goods
or raw materials or components, or if Weir hedges the order for 11. WARRANTIES
the Goods or raw materials or components, the rate hedged by 11.1 New Goods If within a period of 12 months from the date of delivery
Weir and advised to the Purchaser in writing prior to Weir’s (or in the case of diesel-operated pumps, within the first 1,000 hours
remitting the foreign exchange currency amount. of operation, whichever first expires) (“warranty period”) any new
Goods sold by Weir (other than purchased equipment as referred to
5.4 Any increases in the rate of GST, any increases in customs duty on
in Clause 11.4) are found to be defective in materials or
imported Goods or raw materials or components for Goods (whether
workmanship, or do not conform to any applicable drawings and
because of a change in the Customs Tariff Classification and/or
specifications approved in writing by Weir, or (in the case of Goods
rate), and any new carbon trading or emissions trading or other
which are Weir-manufactured pumps) do not perform in accordance
levies, imposts, duties or taxes, applicable to or impacting on the
with the current applicable water performance curves supplied as
cost to Weir of the Goods or Services, between the date of Weir’s
part of the Weir quotation or published by Weir as at the date of the
tender or quotation and the date of invoice, will be to Purchaser’s
quotation (within the tolerances specified in applicable Australian
account, and will be payable by Purchaser within 30 days from the
Standards), then Weir will, at its option, either repair or provide
date of Weir’s invoice.
replacement parts or Goods provided that:
6. DELIVERY & STORAGE (a) the Purchaser has given written notice to Weir of any alleged
6.1 Delivery shall be deemed to occur when the Purchaser is informed defect within the warranty period;
by Weir that the Goods are ready for collection at Weir’s works. (b) the Purchaser has provided Weir a reasonable opportunity to
perform all appropriate tests on the Goods;
April 2009 Page 1 of 3
WEIR MINERALS AUSTRALIA LTD
ABN 69 009 701 802
Installation
Weir Minerals Multiflo
PART 1
INSTALLATION
1.1 Pump Unit Delivery
Each order or shipment is double checked before leaving the factory. All parts,
pieces and components are listed item by item on our packing list, which
accompanies each order. The number and description of each item, package,
container, skid, etc., is listed on the bill of lading. IN SIGNING THE BILL OF LADING,
THE CARRIER ASSUMES FULL RESPONSIBILITY FOR SAFE DELIVERY OF ALL
GOODS TO DESTINATION IN THE SAME ORDER A CARRIER AS TENDERED BY
THE SHIPPER. In the event of damage or shortage, have the transportation
company note the same on the freight bill.
You will find a packing list attached to one of the items in the shipment. Check each
item against the list. Check by description, specification, quantity, count, etc. Should
there be any discrepancies, notify Multiflo immediately. Small parts and items such
as bolts, washers, bushings and keys are just as important to an installation as the
larger parts. Make sure these are located and checked before disposing of any
containers or packing. We cannot be responsible for loss of items that are listed and
included on our packing list.
1.2 Warnings
(Regarding Installation &
Pre-Operational Procedures)
Pump unit to be locked and tagged before
DANGER ! any maintenance or service is performed.
Do not operate the pump at low or zero flow conditions for prolonged periods, or
under any circumstance that could cause the pumping liquid to vaporize. Personnel
injury and equipment damage could result from the pressure created.
Do not apply heat to impeller boss or nose in an effort to loosen the impeller thread
prior to impeller removal. Personnel injury and equipment damage could result from
the impeller shattering or exploding when the heat is applied.
Do not feed very hot or very cold liquid into a pump which is at ambient temperature.
Thermal shock may cause the pump casing to crack.
Tapped holes (for eye bolts) and lugs (for shackles) on Warman Parts are for lifting
individual parts only.
Shaft Locks (If Fitted) must be removed from the bare shaft pump before the unit is
started.
FIGURE 1
UNIT LIFTING POINTS
FIGURE 2
SKID CHASSIS
LIFTING POINTS
1.4.1.1 Using suitable lifting equipment, lift pump base over high lift skid.
1.4.1.2 Make sure the skid is clean of all rocks and debris.
1.4.1.3 When pump base is suspended over skid, gently lower base into
skid. Be sure that base moves into position freely and does
interfere with skid sides.
FIGURE 3
INSTALLING PUMP
ONTO SKID CHASSIS
1.4.1.4 Make sure the pump unit is sitting flat in the skid.
1.4.1.5 When base is sitting on skid frame, on one side only, insert
spacers between the skid and the pump unit (approximately
6mm). Fit the bolts and tighten that side. Repeat with the other
side fitting the required shim for the gap left between the skid and
pump unit.
PONTOON
CENTRE SECTION
RIGHT HAND SIDE
PONTOON
CENTRE
SECTION LEFT
HAND SIDE
PONTOON
FRONT
(PUSH BAR)
END
FIGURE 4
PONTOON CENTRE
HULL IDENTIFICATION
1.4.2.1 Using a crane, lift the left hand side pontoon into position as
shown in the diagram below.
LOCATING PIN
MOUNTING
PEDESTAL
FIGURE 5
LEFT HAND PONTOON HULL
WITH LOCATING PIN &
MOUNTING PEDESTAL
IDENTIFICATION
FIGURE 6
LEFT HAND PONTOON
HULL BOLTING POINTS
1.4.2.2 Align the bolt holes at either end of the pontoon and install the
appropriate bolts as shown.
1.4.2.3 Using a crane, lift the right hand side pontoon into position as
shown in the diagram below.
ACCESS STEPS
FIGURE 7
RIGHT HAND PONTOON
HULL WITH LOCATING
PIN & MOUNTING
PEDESTAL
IDENTIFICATION
1.4.2.4 Align the bolt holes at either end of the pontoon and install the
appropriate bolts as shown in the diagram below.
FIGURE 8
RIGHT HAND PONTOON
HULL BOLTING POINTS
1.4.2.5 There are a number of mounting pads welded onto the pontoon
deck to which the pump unit base is bolted. These are marked
on the diagram below.
BOLT HOLE
PUMP BASE
MOUNTING PAD
FIGURE 9
PUMP UNIT BASE
MOUNTING PAD
INDICATION POINTS
FIGURE 10
POSITIONING THE PUMP
SET OVER THE
MOUNTING PADS
1.4.2.6 Carefully align the bolt holes on the pump set with the mounting
pad holes on the pontoon.
BOLT NOT
REQUIRED IN
THIS
LOCATION
FIGURE 11
ALIGNMENT OF PUMP
SET BOLT HOLES WITH
MOUNTING PAD BOLT
HOLES
1.4.2.7 Now the discharge pipe work can be fitted to the pump unit. If
not already done, firstly install the Non Return Valve to the pump
discharge elbow.
FIGURE 12 - LEFT
NON RETURN VALVE
WITH INSPECTION
PLATE IN THE ‘UP’
POSITION
FIGURE 13 - ABOVE
WHERE TO INSTALL THE
NON RETURN VALVE
1.4.2.8 The Non Return Valve must be fitted as shown in the diagram
below, with the inspection plate in the “UP” position and the
green arrow showing the direction of water flow through the
valve.
FIGURE 14
NON RETURN VALVE
INSTALLED ON THE
PUMP SET
FIGURE 15A
FITTING THE SUCTION
BOOM
FIGURE 15C
FIGURE 15B INSERTION OF BOOM
FITTING THE REDUCER LOCKING BOLTS
AND THE HOSE
1.5.1 With boom lying flat, insert boom locking bolts in boom and
pump base. Tighten bolts. As shown in Figure 15C.
1.5.2 If not already done so, attach winch to pump base winch mount.
1.5.3 With boom lying flat, run winch rope through boom pulley.
Removal of the pulley may be necessary. As shown in Figure 16
on the right.
FIGURE 16
ATTACHING WINCH
ROPE TO BOOM PULLEY
FIGURE 17
FITTING THE WINCH
ROPE
FIGURE 18A
FITTING THE BOOM
CHAINS
FIGURE 18B
FITTING THE SUCTION
STRAINER
1.5.5 Using suitable lifting device, pick up boom and lift into a position
that will allow the boom chains to reach the boom chain mounting
points on the pump. Refer Figure 18A.
FIGURE 19
FIT THE LEFT HAND SIDE
HANDRAIL
FIGURE 20
FIT THE RIGHT HAND SIDE
HANDRAIL
Multiflo Pumps are mounted on a skid base chassis. A robust push beam assembly
and towing brackets are attached to the skid base to enable the unit to be pushed or
pulled.
For long term pumping operations in deep water or in high rain fall areas, the pump,
complete with skid base, can be mounted on a floating pontoon. Skids are also
provided at the base of the pontoon.
Before preparing the pump site, consideration must be given to the best pumping
location, with the aim at positioning the pump as near as possible to the deepest part
of the water catchment area.
For skid mounted pumps, the site should be prepared as close to the water as
possible and the final resting place of the pump should be reasonably level.
Operating the pump at an incline of over 10° is not recommended.
Moving or relocating a pump unit within the pit is normally done by a wheel
dozer or small track dozer. A small excavator can also be used especially for
launching pontoon units.
Obviously, the proper way to move a pump unit is by towing, using appropriate
tow chains. Pushing the pump unit over long distances or over uneven ground
is to be avoided.
1. Ensure the pipes or hoses are disconnected from the wet end pump
discharge.
2. Stow any loose items of pump hardware, such as clamps, connectors,
lengths of pipe etc. that be may be lying around the deck.
3. Raise and secure the suction strainer and suction hose well clear of the
ground. The suction boom can remain in its normal suspended
position.
4. If not already fitted, attach appropriate towing chains to the towing
brackets at the front of the pump unit skid base, or at the towing
brackets at the front end of the pontoon. The front end is the engine
end of the pump unit.
5. Connect towing chains to the draw bar of the towing vehicle.
Towing should be kept at a reasonable safe speed and extra caution should be taken
when towing along haul roads, keeping as close as possible to the left side. Don't
tow or push the pump over rough, uneven ground. Unhitch the dozer and level the
way.
Final positioning will usually involve pushing the pump down a ramp at a maximum
grade of 15°, either with the dozer blade or the excavator bucket. For launching
pontoon pumps, an excavator may be the best tool. Pushing must be done with
extreme caution and only on the push beam assembly provided. Pontoon pumps are
pushed on the pontoon push bar only and not on the base chassis push beam.
Under no circumstances should any pump unit be pushed on the sides or at the
suction end (rear).
Before launching a pontoon pump, consideration should be given to the best method
of connecting up the discharge line. (It is extremely difficult to connect up hoses and
pipes in deep water). If layflat hose is to be connected to the initial discharge pipe,
then this connection can be made before the pump is launched. If polypipe is used,
one or two lengths can be connected to the pump discharge before launching and
the final connection made on land when the pontoon is floating.
To assist in positioning the pontoon when it is in the water, a rope tag line long
enough to reach the bank should be attached to it.
Use When
Whenever pumps have to be moved, located and/or launched at a pump site.
Purpose
To minimise the risk of damage to equipment and injury to personnel when
moving and/or locating pumps at a pump site.
Before Starting
Before preparing a pump site, consideration must be given to the best
pumping location, with the aim of positioning the pump as near as possible to
the deepest part of the water catchment area.
1. Ensure appropriate towing chains are available for the particular pump
type.
2. Ensure that pipes and hoses are disconnected from the wet end pump
discharge.
7. When towing, travel at a safe speed and keep as close as possible to the
left hand side of the road.
4. The operator of the dozer or excavator must be able to see the point at
which the blade or bucket is making contact with the pump. The pushing
operation must be directed by a person on the ground. The equipment
operator and person directing must be clear on the hand signals being
used by the person directing. Skid mounted pumps must only be pushed
on the push beam assembly provided.
As well, a rope tag line long enough to reach the bank should be fitted to assist
in final pontoon positioning.
FIGURE 21
BLADE CONTACT POINT ON
PUMP PUSH BAR
FIGURE 22
BLADE CONTACT POINT ON
PONTOON PUSH BAR
FIGURE 23 EXAMPLES OF
INCORRECT
PUMP UNIT POSITIONING
FIGURE 24
EXAMPLES OF CORRECT
PUMP UNIT POSITIONING
Ensure the hose couplings at the wet end pump, both suction and discharge, are
completely sealed.
Ensure the pump unit is positioned as close as possible to the level of the fluid being
pumped. (If the height of the wet end pump is above 8 metres from the level of fluid,
the pump will not pump).
Ensure that the suction strainer is free from blockages and fully submerged in the
fluid.
Ensure that the largest possible pipe diameter, both at suction and discharge, is
being used.
Ensure that the vacuum tank gauge reading is within the normal range (depending on
suction height).
Ensure that the engine is set at the correct speed (RPM) to give maximum pump
efficiency.
When using "layflat" hose, ensure that it is free from kinks and sharp turns.
Ensure that the vacuum prime indicator light on the “First Out” panel goes out once
the unit is primed. If the light stays illuminated, then a fault has occurred. Refer to
the priming section of the Trouble Shooting guide in the Maintenance Manual.
Ensure that the pump unit is situated in a safe position and not operating at an angle
of more than 10°.
Ensure that there is a good rate of liquid flow coming from the end of the discharge
line.
Alignment
All units are assembled, aligned and test run at Weir Minerals Multiflo
Caloundra Factory before they are despatched. This alignment may be affected
during transportation, therefore should be checked before the unit is used on
site.
Operation
Weir Minerals Multiflo
PART 2
OPERATION
2.1 Introduction
The Weir Minerals Multiflo MF-420E pump unit has been designed to
provide a safe working environment for operators, maintenance
personnel and others.
Application
INFORMATION ! Hints and Nil Nil
other useful
Information
The automatic prime system consists of the vacuum tank, vacuum pump and
fluid level control.
A vacuum gauge which is mounted in the vacuum tank indicates, while the
pump unit is operating, dynamic head loss in the suction system. As this
reading will vary with different pumping conditions, i.e. varying lengths of
suctions hose, height of pump unit above fluid, quantity of fluid being pumped
etc., it is impractical to predict a general vacuum gauge operating reading.
2.1.3.1 Operation
1. As the unit uses vacuum to prime the Bare Shaft Pump, it is necessary
to ensure that the hose couplings to the Bare Shaft Pump, both suction
and discharge, are completely sealed.
4. Always use a large diameter hose for the suction, and use the correct
size pipe on the discharge to obtain maximum performance from the
unit.
PUMP UNIT
RIGHT SIDE
FIGURE 25
PUMP UNIT ORIENTATION
GUIDE
Operation
2.2.1.7 Battery
Maintain level in range above plates and filler bridge (if applicable).
2.2.1.12 Probes
Clean probes.
2.2.2.3 Cavitation
FIGURE 26
RESULTING EFFECTS OF
CONTINUOUS CAVITATION
2.2.3 To Shutdown
1. When pumping heavy mediums it is advisable to raise the pumps
strainer into clean water prior to shutting down to prevent slurry from
settling in the pumps casing.
2. Decrease engine RPM slowly to idle.
3. Allow the engine to idle for 3 minutes on turbo charged units prior to
shutting down.
4. Turn the ignition key anti clockwise to stop the engine.
5. Turn the battery isolation key to the “off” position.
The bare Shaft Pump protection system consists of probes fitted to the
vacuum tank and a Vactronic System which connects to the engine shutdown.
The Vactronic System has an inbuilt six minute timer which activates when the
water level in the vacuum tank falls below the probe. The orange indicating
light will flash. The unit will remain in this mode for six minutes before
activating the engine shutdown. Once this has occurred, the red indicating
light will stay on.
Should the pump pick up water within the six minutes after being activated, the
unit will automatically reset.
This feature is designed to prevent damage to the pump from dry running.
The pump discharge can be orientated in almost any position through 360°
depending on mounting.
The wet end parts are cast from Ultrachrome A49/A48 and the impeller is
constructed from H7A stainless steel. These long wearing materials have
been developed for abrasion and corrosion resistance and to give a long life in
slurry pumping applications.
FIGURE 27
BARE SHAFT PUMP
WETTED PARTS
FIGURE 28
BARE SHAFT PUMP
BEARING HOUSING
FIGURE 29
BARE SHAFT PUMP
PEDESTAL ASSEMBLY
FIGURE 30
PISTON TYPE
VACUUM PUMP
MAJOR COMPONENTS
Torque Settings
Cylinder Head 35 NM + 3 25FT LB + 2
Cylinder to Crankcase 30 NM + 3 20FT LB + 2
Bearing Cap 35 NM + 3 25FT LB + 2
Conrod Big Cap 35 NM + 3 25FT LB + 2
Valve Retainer Cap 35 NM + 3 25FT LB + 2
Krundimendt Safety
Check Valve
FIGURE 31
VACUUM TANK
The high lift vacuum tank is manufactured from 6mm material incorporating a
vacuum and air separator chamber designed to give maximum air separation
and allowing an uninterrupted capacity flow to the bare shaft pump. The
vacuum tank is also complete with a vacuum water trap and back up
Krundimendt Safety Check Valve to give maximum protection to the vacuum
pump under all operating conditions.
FIGURE 32
VACUUM GAUGE
1. As the unit uses vacuum to prime the Bare Shaft Pump, it is necessary
to ensure that the hose couplings to the Bare Shaft Pump, both suction
and discharge, are completely sealed.
4. Always use a large diameter hose for the suction, and use the correct
size pipe on the discharge to obtain maximum performance from the
unit.
FIGURE 33
NON RETURN “VOOOM” VALVE,
FLAP IN CLOSED POSITION
FIGURE 34
NON RETURN “VOOOM” VALVE,
FLAP IN OPEN POSITION
In the event of this non-return valve sticking and failing to close when pumping
stops, fluid would then drain back and flood the vacuum tank. If such a case
occurred, fluid will be prevented from entering the vacuum pump by closing of
the vacuum valve by the action of the float rising to close off the vacuum pump
intake port.
Upon start up of the pump unit, the electric clutch engages drive and the
vacuum pump pulls a vacuum which lifts the water into the vacuum tank and
bare shaft pump.
When the water reaches the bare shaft pump, the pump primes and the water
level rises in the vacuum tank and covers the probe. Once this occurs, the
electric clutch disengages and the vacuum pump will not run. The vacuum
pump will remain in this mode under normal pumping conditions.
Should the water level drop below the probe, the vacuum pump will
automatically restart and run until the level in the vacuum tank is restored.
The krundimendt valve, fitted to the top of the vacuum tank, acts as a check
valve. In the event of a shutdown, when the discharge line non-return valve
fails and floods the vacuum tank, the ball will rise in the krundimendt valve and
stop water from entering the vacuum pump. The one way check valve fitted in
the vacuum line stops air being pulled back into the vacuum tank from the
vacuum pump.
FIGURE 35
VACTRONIC CIRCUIT
DIAGRAM
General
Keep the unit as clean as possible.
Replace the gland packing at regular intervals or as required, replace
all of the packing when doing so. A gradual loss of performance or
difficulty priming is an indicator of worn packing, although these
symptoms may have other causes.
Set up the unit as close to level as practicable.
Periodically check the discharge for adequate flow.
Don’t run the pump for extended periods when it is cavitating.
Maximum rpm must not be exceeded; vibration from impeller imbalance
will lessen bearing life.
FIGURE 36
“FIRST OUT”
INDICATION PANEL
FIGURE 37
FUEL FILTER / WATER
SEPARATOR
Shop Towels
Diesel Fuel (about 1 gallon)
Thread Sealant (no thread tapes)
Parker Super –O Lube (or equivalent)
Fuel Hose (see Fuel Hose Chart)
Mounting Hardware (3/8” or M10 Fasteners)
Inlet/Outlet Fittings (see Fitting Chart)
V
10° 10°
90°
FIGURE 38
FUEL FILTER / WATER
SEPARATOR
MOUNTING
INSTRUCTIONS
FH filter assemblies should be installed on the vacuum side of the fuel transfer
pump for optimum water separating efficiency. (See ‘Installation Diagram’ on
the next page.)
Keep fuel line restrictions to a minimum. Locate the FH filter assembly
between the horizontal planes of the bottom of the fuel tank and the inlet of the
fuel pump, if possible. If the FH filter assembly is installed in an application
where the fuel tank is higher than the filter, a shut-off valve must be installed
between the tank and the FH filter assembly INLET. This will be used when
servicing the replacement element.
Completely remove any vacuum side filters in the fuel line between the fuel
tank and the fuel pump. This is where the FH filter assembly will mount.
Leaving these filters in place will add to the fuel line restriction. Filter heads
cast into the engine or that are non-removable or hard piped should be
serviced with a new element and left in place.
Keep fuel flow restriction valves to a minimum. Always use the maximum size
fuel hose possible. Do not make sharp bends with flexible fuel hose as kinks
may occur. Avoid the use of two 45° elbow fittings where one 90° elbow will
work.
When routing hose, avoid surfaces that will move, sharp edges, or will get hot
(such as exhaust piping).
FIGURE 39
FUEL FILTER / WATER
SEPARATOR
INSTALLATION
INSTRUCTIONS
1. Remove the ‘T’ handle and lid from top of filter assembly.
2. Fill the filter assembly with clean fuel.
3. Lubricate lid gasket and ‘T’ handle O’ring with clean fuel or motor oil.
4. Replace the lid and ‘T’ handle and tighten snugly by hand only –
do not use tools.
5. If applicable, refer to the equipment operator’s service manual to
complete the fuel priming procedure.
6. Start engine and check for fuel system leaks.
7. Correct as necessary with engine off and pressure relieved from filter
assembly.
2.4 Electrical
2.4.1 Electrical Drawings/Schematics
Pump unit to be locked and tagged before
WARNING ! any maintenance or service is performed.
Maintenance
Weir Minerals Multiflo
PART 3
MAINTENANCE
3.1 Normal Maintenance Procedures
3.1.1 Safety Procedures
Engine and bare shaft pump parts and all
DANGER ! fluids may be at extremely high
temperatures when the pump unit is
stopped and may cause serious burns.
Ensure pump unit has cooled down before
any checks or maintenance are carried out.
FIGURE 40
BARE SHAFT PUMP
FRAME ASSEMBLY
Gland Assembly - Fitting Stuffing Box, Neck and Lantern Rings, Packing, Gland,
Shaft Sleeve, Shaft Spacer and Shaft Sleeve ‘O’ Ring.
1. Insert ADAPTOR PLATE (032) for BASE (003), making certain that the
adaptor spigot has engaged with the corresponding base recess.
FIGURE 41
BARE SHAFT PUMP
GLAND ASSEMBLY
5. Stand SHAFT SLEEVE (075) on end and slide through neck ring.
8. Fit shaft ‘O’ RING (109) to shaft, followed by SHAFT SLEEVE SPACER
(179) and second SHAFT ‘O’ RING (109).
9. Insert assembled stuffing box in adaptor plate and tap into position with
a soft faced mallet. Locate stuffing box with threaded connection at
top. The shaft sleeve will probably remain forward. It should be
pushed back to the shaft sleeve spacer on the shaft. Check that ‘O’
Rings are correctly positioned in grooves.
10. Fit the SHAFT SPACER (117) and the final SHAFT ‘O’ RINGS (109).
Fitting Back Liner, Impeller, Bowl, Door, Clamp Rings, Stuffing Box, Bowl Seals,
Intake and Discharge Flanges
1. Fitting SEAL RING (122). The seal is an ‘O’ Ring. Fit into the groove on
the rim of the stuffing box.
2. Fitting BACK LINER (041) and impeller. In the back liners, provision is
made to accommodate studs for mounting back liners on adaptor plates.
Proceed as follows;
FIGURE 42
BARE SHAFT PUMP
IMPELLER & BOWL
ASSEMBLY
a) Screw and tension STUD (026) into tapped holes provided in back
liner.
c) Fit SHAFT KEY (070) in key way and bolt SHAFT WRENCH (306) over
key. Check that CLAMP BOLTS (012) on side B of base are nipped up
just enough to hold the bearing assembly horizontal but not to lock it.
d) Check that ‘O’ RING (109) is correctly seated in groove in shaft spacer.
e) Obtain correct type of impeller. Apply grease to thread, lift impeller with
hoist using a chain or wire sling and screw it onto shaft. Use a bar
between vanes and hold shaft with wrench to tighten impeller. Ensure
that the various ‘O’ Rings on the shaft are not damaged during
assembly and that they are fully covered by the various parts.
FIGURE 43
BARE SHAFT PUMP
BEARING ASSEMBLY
(a) Pump bowls are provided with three lifting lugs around the periphery.
Lift BOWL (131) with hoist using one or two lugs to obtain discharge
position required. Pass it over the impeller and fit it over the tapered
rim on the back liner. Check that the bowl seal has not moved.
(Bowl discharge can be orientated in any position through 360°).
FIGURE 44
BARE SHAFT PUMP
VOLUTE ASSEMBLY
FIGURE 45
BARE SHAFT PUMP
SECTIONAL DRAWING
Fit the INTAKE JOINT RING (132) and the DISCHARGE JOINT RING (132)
as shown in Figure 51.
FIGURE 46
BARE SHAFT PUMP
COMPLETE ASSEMBLY
FIGURE 47
BARE SHAFT PUMP
COMPLETE SECTIONAL
ASSEMBLY
Recommended Procedure:
a) On initial fit up, adjust the impeller so it “just touches” the door.
b) Re-adjust the impeller to “just touch” the door after 50-100 hours.
c) Re-adjust a further two or three times at regular intervals during the
wear life of the pump.
d) After adjustment of the impeller, it is important to tighten the
bearing housing clamp to 185Nm.
Impeller Removal
To gain access to the impeller generally the BOWL (131) and the DOOR
(013) can be withdrawn from the pump by removing the CLAMP RING (135)
securing the bowl to the ADAPTOR PLATE (032).
3.1.3.1 Gland
The Multiflo Pumps' oil feed system provides lubrication and sealing of the
gland packing under snore and high vacuum conditions.
This system requires the use of "Flurograph 193" or equivalent packing, which
has been found, through experience, capable of providing excellent service
under the harsh conditions under which it may be called upon to operate.
The gland should be adjusted regularly to prevent excess leakage. The gland
must not be over tightened as this will lead to over heating of the gland area
and short life of the sealing components.
The pumps will require repacking when the gland follower is tight against the
stuffing box. It is imperative that all packing rings are replaced when
repacking. Replacement of only the first few sets of packing will lead to
premature wear of the shaft and priming difficulties.
Each ring of packing should be inserted separately and pushed in place into
the stuffing box. The split opening of the successive packing rings are to be
positioned at 180° intervals. A slight leak is des irable from the newly packed
gland to allow the packing time to bed in. Excessive tightening at this period
will result in burning of the packing and scoring of the shaft.
All these pumps utilise five rows of ¾ gland packing. The part number for the
set of packing is PAK-DWF193.
Remove the two gland adjustment nuts and withdraw the gland follower from
the stuffing box. Remove the two gland follower securing bolts then remove
both halves of the follower from the shaft.
Using the appropriate packing removal tool, (PAK 2) remove all packing rings
from stuffing box and clean out any remaining residue.
FIGURE 48
PACKING REMOVAL TOOL
Fit gland follower to shaft and nip gland nuts up to pack gland packing.
Ensure front face of gland follower has entered the stuffing box housing. If
after tightening the gland nuts the packing has compressed enough to allow
space for another ring, remove gland follower, fit extra packing ring, re-
assemble follower and nip gland nuts up again. Back nuts off and leave finger
tight until pump is started.
After pump has been started, the glands must be adjusted to provide
reasonable leakage. When water pressure is at a minimum the gland should
leak slightly, therefore when this pressure rises, leakage will necessarily be
excessive. If the gland is adjusted to provide optimum leakage at higher pump
rpm (high pressure), insufficient leakage will occur when the rpm falls or is less
from the point of adjustment.
As well as lubricating and cooling the gland, the water escaping from the gland
also prevents the ingress of air when the pressure at the shaft falls below
atmospheric. E.g. when a vacuum is required.
If one of the following conditions apply, air may be induced into the pump
through the gland. This may prevent the pump “picking up” its prime or cause
it to loose its prime during operation.
Inspection of the gland will reveal if any of the above faults are occurring.
As stated before the glands are designed for water lubrication and some
leakage is necessary during operation to lubricate and cool the packing and
shaft sleeve, however the oil feed system is used to assist with lubricating the
gland and shaft when the presence of water is limited.
Gland leakage at all times must be clean and free from as much abrasive
material as possible. If there is any sign of excess slurry leaking from a gland
then one of the following must be occurring:
3.1.3.2 Impeller
The performance of the pump can change with excessive clearance between
the impeller and the front wear plate/door. For best performance it may be
necessary to occasionally stop the pump and move the impeller forward. The
procedure is:-
The wet end bearings are pressure fed via a hydraulic pump and reservoir.
The reservoir level must be checked daily, keep the level of oil in the top sight
glass.
FIGURE 49
BARE SHAFT PUMP
BEARING HYDRAULIC
OIL FILTER AND
PRESSURE RELIEF
VALVE
1. Drain the hydraulic oil tank by removing the hydraulic oil tank drain
plug. Once empty re-fit the plug to the tank. Remove and clean the
strainer located under the hydraulic oil cap. Refit the clean strainer to
the oil cap assembly.
2. Remove the old oil filter from the tank and replace with a new oil filter.
Check that the new oil filter seal is in place on top of the filter and lightly
coat the seal with clean hydraulic oil before fitting to the filter housing.
3. Refill the hydraulic oil tank with clean new hydraulic oil. Fill to bottom of
the strainer ensuring that oil is evident in tank. Sight glass.
FIGURE 50
BARE SHAFT PUMP
BEARING HYDRAULIC
OIL TANK
MAIN COMPONENTS
SUCTION
FEED
FIGURE 51
BARE SHAFT PUMP
BEARING HYDRAULIC
OIL HOSES
NON-RETURN VALVE
RELIEF VALVE
SETTING 100PSI ORIFICE SIZE .045" (1.40mm)
SUCTION FILTER
PUMPSET 1
FIGURE 52
BARE SHAFT PUMP
HYDRAULIC CIRCUIT
FIGURE 53
ELECTRO-LUBER
COMPONENT
IDENTIFICATION
Starting Procedures
Select the dispensing time and
amount of lubricant required,
then click the appropriate
switch or switches. This
action closes a circuit and the
gas generation begins.
FIGURE 54
ELECTRO-LUBER
STARTING &
PROGRAMMING
FIGURE 55
ELECTRO-LUBER TIMER
SETTINGS FOR 420E
LABYRINTH
FIGURE 56
ELECTRO-LUBER
3.1.4 Maintenance
Model 57 Piston Vacuum Pump
Pump unit to be locked and tagged before
WARNING ! any maintenance or service is performed.
It is advisable that the ridge be removed from the top of worn cylinders prior to
removing the piston. Failure to do so may result in cracked or broken piston
ring lands.
The ring sets are designed to bed in on both new bores and worn bores.
Honing is not essential but it is recommended to give the optimum result.
However, it is essential if one of the following conditions are present:-
Excessive wear;
Bore distortion;
Polishing or Glazing;
Scuffing;
Scratching.
Poor cleaning after honing accounts for most of today’s wear out / oil
consumption problems. Petrol and kerosene are not suitable. Soap and hot
water with a nylon scrubbing brush are best. Check with a clean white cloth
which should not come out grey. Finally, swab with a light engine oil to
prevent corrosion.
Always check the gap clearance of new rings in the lower unworn portion.
The gap should not be less that 0.003mm per mm of cylinder diameter.
Ensure piston rings and pin are thoroughly clean and then lubricate rings,
skirt, pin bores and bearings with engine oil. Use a good quality ring
compressor held firm against the engine block at the time of entry of the rings
into the cylinder.
• Wind on expander.
FIGURE 57
WINDING ON PISTON OIL
RING EXPANDER
• Hold the expander end in place with thumb. Wind on lower rail then wind
on upper rail.
FIGURE 58
UPPER & LOWER RAIL
OF EXPANDER
• Both ends of the expander should be visible and not over lapped.
FIGURE 59
UPPER
&
LOWER
RAIL GAP
• Align all gaps as per the diagram above (gaps must not be lined up).
Check the assembly can rotate in the groove.
• When fitting the compression rings, make sure they are fitted the correct
way up as per the diagram on the following page.
FIGURE 60
CORRECT FITMENT OF
COMPRESSION RINGS
X FIGURE 61
INCORRECT FITMENT OF
COMPRESSION RINGS
• Use a ring expander or expand with the thumbs before placing in piston
grooves.
FIGURE 62
CORRECT EXPANSION
METHOD FOR
COMPRESSION RINGS
• All rings must have clearance between the back of the ring and the back
of the groove. To check this, push the rings against the bottom of the
groove on the thrust side of the piston, then place a straight edge against
the skirt of the piston. The minimum clearance between rings and edge
should be 0.3mm for compression rings and 0.15mm fir oil rings.
FIGURE 63
CORRECT RING
BACK CLEARANCE
Put the belts around the pulleys, set them to the appropriate tension value
stated in the "Tensioning Forces" Table (using the Belt Tension Indicator as
shown), run the drive under load for 30 minutes, stop the drive, check the
tension, re-setting to catalogue value if necessary. On a properly designed
drive for the application there will be no need for any further attention during
the life of the drive.
FIGURE 64
BELT TENSIONING
INDICATOR OPERATION
2. Set the lower marker ring at the deflection distance required in mm on the
lower scale.
3. Set the upper marker ring against the bottom edge of the top tube.
4. Place the belt tension indicator on top of the belt at the centre of span, and
apply a force at right angles to the belt deflecting it to the point where the
lower marker ring is level with the top of the adjacent belt.
For single belt drives a straight edge
INFORMATION ! should be placed across the two pulleys
to act as a datum for measuring the
amount of deflection. If the measured
force falls within the values given, the
drive should be satisfactory. A measured
force below the lower value indicates
under-tensioning. A new drive should be
tensioned to the higher value to allow for
the normal drop in tension during the
running-in period. After the drive has
been running for 30 minutes, the tension
should be checked and re-adjusted to the
higher value, if necessary.
5. Read off the force value indicated by the top edge of the upper marker ring.
6. Compare this force to the kgf value shown in the attached table.
FIGURE 65
BELT TENSIONING
INDICATOR
Pulley Installation
Before assembling the drive, check the pulley grooves are free from scores or
sharp edges and all dimensions conform to the relevant standard. The
Taperlock Bush is the starting point when it comes to assembly and
installation. Drive installation is a straight forward job with Taperlock, but the
stages set out on the installation leaflet provided with every Taperlock bush
should be followed closely.
Alignment
A. B. C. D.
FIGURE 66
BELT ALIGNMENT
Belts
When the pulleys have been correctly positioned on the shafts, the belts can
be installed to complete the drive. The drive centre distance should be
reduced prior to the installation of the belts so that they may be fitted without
the use of force. Under no circumstances must belts be forced into the
grooves. Belts and pulley grooves can be easily damaged by using sharp
tools to stretch the belts over the pulley rim.
The installation allowance given in the table on the following page is the
minimum recommended reduction in centre distance for the various belt
section and lengths to allow for correct fitting. The take-up allowance given in
the same table should be added on to the calculated centre distance to allow
for belt stretch.
Installation Take-Up
Belt Allowances (mm)
Pitch Length
SPZ
(mm)
2030 20 30
FIGURE 67
TAPERLOCK BUSH
REMOVAL
1. Insert Bush
Remove the protective coating from the bore and outside of bush, and
bore of hub. After ensuring that the mating tapered surfaces are
completely clean and free from oil or dirt, insert bush in hub so that
holes line up.
FIGURE 68 LEFT
INSERTING
TAPERLOCK BUSH
TO HUB
FIGURE 69 BELOW
LOCATING
TAPERLOCK ONTO
THE SHAFT
2. Insert Screws & Locate on Shaft
Sparingly oil thread and point of grub screws, or thread and under head
of cap screws. Place screws loosely in holes threaded in hub, shown in
diagram below.
Screw Qty 3
FIGURE 72
TAPERLOCK FLANGE
Dimensions of Fenaflex Flanges Types F & H DIMENSION CHART
F180 F H
Bush No. 4535 4535 Notes
Max Bore mm 125 125
§: G is the amount by which
L 112 112 clamping screws need to be
E 89 89 withdrawn to release tyre
J† 89 89
A 470 470 †: J is the spanner clearance
to allow for tightening the
C 398 398 bush on the shaft and the
D 205 205 clamp ring screws
F 94 94 ¶: M is half the distance
between flanges. Shaft ends
G§ 19 19 (normally Mx2) can project
M¶ 23 23 beyond the flanges. In this
Mass Kg 42.2 42.2 event allow sufficient space
between shaft ends for end
Inertia kgm² 0.847 0.847 float misalignment.
Installation Instructions
2. Fit flanges to the shafts after placing the external clamp rings on the
shafts. (Where Taper Lock Flanges are used, see separate fitting
instructions supplied with the Taper Lock Bushes.) Locate flanges to that
dimension ‘M’ is obtained (see para 3). Flanges with internal clamping
rings should then have the clamping rings fitted, engaging only two or
three of the threads of the screws at this time.
3. Bring shafts into line until dimension ‘M’ is obtained (Refer Figure 73 &
Table 1, Page 43). If shaft end float is to occur, locate the shafts at mid-
position of end float when checking dimension ‘M’. Note that shaft ends
may project beyond the faces of the flanges if required. In this event,
allow sufficient space between shaft ends for end float and mis-
alignment. Flanges should be fitted flush with the end of the shaft when
used with Mill-Motor flanges.
5. Open out tyre and fit over coupling flanges ensuring that the tyre beads
seat properly on the flanges and/or clamping rings. To ensure proper
seating, it may be necessary to strike the outside diameter of the tyre with
a small mallet. When seated, there should be a gap between the ends of
the tyre as shown in Figure 74 & Table 2, Page 44.
6. Tighten clamping ring screws alternately and evenly (half turn at a time)
working round each flange until the required screw torque is achieved
(Table 1).
FIGURE 73 TABLE 1
INTERNAL CLAMP RING TORQUE
Table 1
FIGURE 74 TABLE 2
INTERNAL CLAMP RING TORQUE
Table 2
Draining Water:
Frequency of water draining is determined by the contamination level of the
fuel. Inspect or drain the collection bowl of water daily or as necessary. The
collection bowl must be drained before contaminants reach the top of the
turbine or when the Water Detection Module (optional) indicates it’s time to
‘drain water’.
Vacuum Application/Installations:
1. Close the inlet valve (or valve#1) and open the self-venting drain on
the bottom of the bowl.
2. Close the drain after all the water and contaminants have been
evacuated – DO NOT leave the drain open too long as it will eventually
completely drain the entire filter assembly of water AND fuel.
3. Follow ‘Priming Instructions’.
Pressure Applications/Installations:
1. Open the self-venting drain on the bottom of the bowl to evacuate water
and contaminants with a suitable collection container in place. Head
pressure will push any water and contaminants out of the drain while
keeping the filter primed.
2. Close the drain after all the water and contaminants have been
evacuated – DO NOT leave the drain open too long as it will eventually
completely drain the entire filter assembly of water AND fuel, and
possibly drain the entire tank.
Element Replacement:
Frequency of element replacement is determined by the contamination level of
fuel. Replace the elements every 10,000 miles, every 500 hours, every other
oil change, when the vacuum gauge (optional) reads between 6 to 10 inches
of mercury (inHg), if power loss is noticed, or annually, whichever comes first.
All Applications:
1. Bypass filter assembly with bypass valves, if applicable.
2. Remove the ‘T’ handle and lid.
3. Remove the element by holding the bail handles and slowly pulling
upward with a twisting motion. Dispose of properly.
4. Replace old lid gasket and ‘T’ handle O’ring with new seals (supplied
with new element). Lubricate both seals with motor oil or diesel fuel
before installation.
5. Refer to ‘Priming Instructions”, otherwise, fill the unit with clean fuel,
then replace the lid and ‘T’ handle and tighten snugly – by hand only –
do not use tools.
Replacement Parts
Racor Additives
Coolant Level Maintain level in range above baffle plate and filler neck.
(Engine Stopped and Cold)
Fuel Tank Fill as required.
Vacuum Tank Probes Inspect and remove and clean the probes.
(Vactronic & Waterloss)
Mounting Bolts Check all bolts on Engine, Bare Shaft Pump and Vacuum
Pump. Tighten if necessary.
3.2 Troubleshooting
3.2.1 Finding and Diagnostic Guide
(Including Details of Normal
Readings)
3.2.1.1 Pump Unit
Failure to Prime
Check Vacuum Gauge Reading.
FIGURE 76
VACUUM GAUGE –
HIGH READING
FIGURE 77
VACUUM GAUGE –
LOW READING
FIGURE 78
VACUUM GAUGE
NORMAL OPERATING
RANGE
If Vacuum Pump Dirty probes – fault in probe Clean probes & check
Electromagnetic wiring. probe wiring.
clutch fails to
engage. Faulty vactronic module. Repair or replace
vactronic module.
Faulty clutch. Repair or replace clutch
Faulty clutch relay. Repair or replace clutch
relay.
If the pump fails to prime after all the above conditions have been checked,
remove the suction hose from the vacuum tank inlet and the delivery hose
from the pump discharge. Seal the vacuum tank inlet and the pump
discharge. Start the engine and check the vacuum gauge reading. The
reading should be within 80 KPA to 100 KPA.
Sticking valves, inlet and exhaust, or both are visually evident by a popping
noise emitted from the vacuum pump exhaust, or uneven exhaust pulses or
no emission from exhaust pipe.
Remove inlet and exhaust caps from top of cylinder head. Remove valves.
Clean valves in solvent and check for broken springs, worn valve plates and
faces. Replace faulty components where necessary.
Replace copper washer between valve and valve seat in the cylinder head.
Retention mounting bolts as per specifications.
FIGURE 79
CORRECT REPLACEMENT OF
VACUUM PUMP CRANK SEAL
Worn Rings
For conventional rings, the gap should be 0.1mm when assembled. Where
one groove of segmental is being used with one groove of a conventional oil
ring, the latter is in the lowest groove. The segments in the centre groove,
and the compression in the upper. Segmental rings, when fitted should be
paired.
Gaps should be fitted initially over the end of the gudgeon pin alternating
sides, but they will tend to move around during operation.
The piston ring groove should have a minimum of 0.25mm clearance behind
the rings.
Symptom Remedy
Small cracks on ‘V’ Belt Generally caused by shortage of belt tension but
side and base. excessive heat and/or chemical fumes can also
give same failure.
Fuel nozzle not Float valve not closing Check operation of float
shutting off. capillary line. ensuring it does not hit
internal walls of fuel tank.
Check valve seat for
damage or obstruction.
Piston stuck open. Check piston operation is
smooth and unrestricted.
Leakage in capillary line. Check line and fittings for
leaks or damage.
Fuel weeping from Float level set too high, not Lower float level setting.
breather after tank has allowing enough air space
been filled. for fuel expansion due to
rise in temperature.
New filter installations must be filled with fuel and the fuel system must be
adequately primed following the engine manufacturer’s recommendations, if
applicable. Existing installation difficulties are usually associated with
improper priming procedures or damage to the unit or fuel system. The result
is either internal air suction or external fuel leakage. Diagnosis should be in
the following steps:
1. Check the fuel level and make sure any fuel delivery valves are in the
open position as applicable.
2. Ensure the T-handle, bowl fasteners and fuel fittings are tight. Also
verify that the bowl drain is closed.
3. If the Racor element is new, check potential restrictions at the fuel tank
draw tube. An in-tank strainer may be plugged.
4. Review some of the workings of the units below to possibly uncover the
solutions.
Correct Application
It is very important that the RH filter assembly is not ‘under specified’ for the
application. The maximum fuel flow rating of the FH filter assembly must not
be exceeded. Doing so will reduce efficiency and de-gas (pull air from) the
fuel.
Filter Elements
Replacement elements are available in 2, 10 and 30 micron ratings. Filtration
needs are based on application, fuel quality, maintenance schedules and
operating climates. A simple rule to remember is – the finer the filtration, the
more frequent the filter change. Always carry extra replacement elements with
your equipment as one tank full of excessively contaminated fuel can plug an
element. When clogged to the maximum capacity, elements will have a brown
to black colour or tar like contaminants may be present – this is normal. An
appearance of a multi-coloured slime (which may have a foul odour) is an
indication of microbiological contamination. This condition must be treated
immediately. Severe conditions must be corrected by a repair facility.
All Racor FH filter assemblies are 100% tested to ensure a leak-proof, quality
product.
FIGURE 80
FUEL FILTER / WATER
SEPARATOR
TROUBLESHOOTING
HINTS
Copyright (C) 2010, Weir Minerals Australia Ltd trading as Weir Minerals Multiflo. All rights reserved. MULTIFLO, VACTRONIC
and HYDRAU-FLO are registered trademarks of Weir Minerals Australia Ltd. This document contains information which is confi-
dential to Weir Minerals Australia Ltd. It should not be disclosed in whole or in part to parties other than the recipient without
the express written permission of Weir Minerals Australia Ltd authorized personnel.
1
Multiflo Model MF-420E – Parts Index
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
Part Page
Fuel Filters IV 39
Suction Components
Suction Assembly IV 40
Discharge Components
Discharge Assembly 41
Non Return “Vooom” Valve 43
Discharge Inspection Tee Assembly 44
Standard Options
Worklights 45
Fire Extinguisher 46
Washdown Hose 47
Part 4A – Unit Specifics
If Fitted
2
Multiflo Model MF-420E – Parts Index
Rev 04.10
(Always quote Model and Serial Number of Unit when Ordering Parts)
Weir Minerals Multiflo
9
6
5
6
7
6 3
7
6 3
MAJOR COMPONENTS
ITEM DESCRIPTION PART NUMBER QTY
1 CANOPY CA0420Z0001 1
2 CABLE COVER BA0000Z0001 1
3 STEP TREADS WA0420Z0017 2
4 LADDER MCT420A035 1
5 WALKWAY PLATFORM (RIGHT SIDE) WA0420Z0003 1
6 WALKWAY PLATFORM MOUNTS (RIGHT SIDE) MCLAPB420A 4
7 HANDRAIL (SET OF 2) WA0420Z0007 1
8 PRECLEANER PBHOO-2224 2
9 MESH PANEL WA0420Z0015 1
10 THERMO BLANKETS - MUFFLER (NOT SHOWN) EX0027Z0001 2
11 THERMO BLANKETS - TURBO (NOT SHOWN) EX0027Z0002 2
12 THERMO BLANKETS - PIPE (NOT SHOWN) EX0027Z0003 2
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 1
Weir Minerals Multiflo
4
3
2
1
5
8
7
MAJOR COMPONENTS
ITEM DESCRIPTION PART NUMBER QTY
1 CATERPILLAR C27 POWER PACK CAC27 1
2 EXHAUST REFER CAT MANUAL 2
3 RAINCAP REFER CAT MANUAL 2
4 STROBE LIGHT - AMBER LENS (STANDARD) PRE3414SL A/R
STROBE LIGHT - BLUE LENS (OPTIONAL) BR95QBS A/R
5 WALKWAY PLATFORM (LEFT SIDE) WA0420Z0004 1
6 WALKWAY PLATFORM MOUNTS (LEFT SIDE) MSS000N001 5
7 HANDRAIL (SET OF 2) WA0420Z0008 1
8 MESH PANEL WA0420Z0015 1
9 THERMO BLANKET KIT RH & LH (NOT SHOWN) 102750 1
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 2
Weir Minerals Multiflo
1
3 5
Revised 08.09
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 3
Weir Minerals Multiflo
8
10
12
3
5
7
9
11
13
6 9
5
6
8
7
4
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 4
Weir Minerals Multiflo
16 14
15
17
21
22
18
19
14 20
23
24
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 5
Weir Minerals Multiflo
6
7
3 5
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 6
Weir Minerals Multiflo
11
10
9
8
6
1
4
7
3
12
1
2
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 7
Weir Minerals Multiflo
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 8
Weir Minerals Multiflo
6 5
3
2
PRIMING ASSEMBLY
ITEM DESCRIPTION PART NUMBER QTY
1 VACUUM TANK (BARE) VT0420Z0001 1
2 VACUUM TANK MOUNT VT0420Z0002 1
3 BOLTS & NUTS BLTM16050G8SA 8
4 WASHERS BLTSQ50506-16 16
5 KRUNDIMENDT VALVE (C/W BOLTS & O'RING) VT2002-02 1
6 WATER TRAP 200-0345 1
7 GASKET VRA150-20 1
8 BOLTS BLTM10040SS6 8
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 9
Weir Minerals Multiflo
1 1
PROBES
ITEM DESCRIPTION PART NUMBER QTY
1 PROBE VT2002-01 2
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 10
Weir Minerals Multiflo
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 11
Weir Minerals Multiflo
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 12
Weir Minerals Multiflo
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 13
Weir Minerals Multiflo
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 14
Weir Minerals Multiflo
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 15
Weir Minerals Multiflo
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 16
Weir Minerals Multiflo
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 17
Weir Minerals Multiflo
Weir Minerals Multiflo
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 19
Weir Minerals Multiflo
1 3
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 20
Weir Minerals Multiflo
12
11
1
10
10
7
4
5 6 8
3 9
2
13
DRIVE ASSEMBLY
ITEM DESCRIPTION PART NUMBER QTY
1 COUPLING GUARD (3 PIECE) GU0420Z0001 1
2 FENAFLEX COUPLING TYPE H (2 PIECE) F180H 1
3 FENAFLEX ELEMENT F180ST 1
4 FENAFLEX COUPLING TYPE F (2 PIECE) F180F 1
5 TAPERLOCKS TL4535-120 2
6 STUBSHAFT MPT420A017 1
7 KEY MPT420A235 1
8 DRIVE PLATE MPT420A018 1
9 BOLTS BLTMF24080B 8
10 WASHER BLTW24G 16
11 SPRING WASHERS BLTSW24G 8
12 NUTS BLTMFNN24 8
13 BELTS VB2030SPZ 2
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 21
Weir Minerals Multiflo
10
4
9 2
7
3
2
BATTERY BOX
ITEM DESCRIPTION PART NUMBER QTY
1 BATTERY BOX EL0420Z0003 1
2 BATTERY BATCENTN200 2
3 BATTERY MAT BM1 2
4 BATTERY BOX GAS STRUT BB24V6B-07 1
5 HOLD DOWN BRACKET EL0420Z0004 1
6 HOLD DOWN TIE FA0000Z0001 2
7 HOLD DOWN ROD FA0000Z0002 2
8 BATTERY CABLE (BRIDGE) BC2101Z0380 1
9 BATTERY CABLE (BATTERY-ISOLATOR +) BC1102Z2300 1
10 BATTERY CABLE (BATTERY-ISOLATOR -) BC2102Z2450 1
11 BATTERY CABLE (ISOLATOR-STARTER +) (NOT SHOWN) BC1105Z2180 1
12 BATTERY CABLE (ISOLATOR-STARTER -) (NOT SHOWN) BC2105Z2150 1
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 22
Weir Minerals Multiflo
1 2
5,6,7,8,9 & 10
5,6,7,8,9 & 10
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 23
Weir Minerals Multiflo
2 1
4
3
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 24
Weir Minerals Multiflo
ELECTRICAL COMPONENTS
ITEM DESCRIPTION PART NUMBER QTY
1 FUSE HOLDER 5442BL A/R
2 FUSE (1AMP) 302-9219-01AMP A/R
3 FUSE (2AMP) 302-9219-02AMP A/R
4 FUSE (4AMP) 302-9219-04AMP A/R
5 FUSE (5AMP) 302-9219-05AMP A/R
6 FUSE (10AMP) 302-9219-10AMP A/R
7 FUSE (15AMP) 302-9219-15AMP A/R
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 25
Weir Minerals Multiflo
ELECTRICAL COMPONENTS
ITEM DESCRIPTION PART NUMBER QTY
1 CIRCUIT BREAKER (2AMP) CB-02K A/R
2 CIRCUIT BREAKER (3AMP) CB-03K A/R
3 CIRCUIT BREAKER (4AMP) CB-04K A/R
4 CIRCUIT BREAKER (5AMP) CB-05K A/R
5 CIRCUIT BREAKER (10AMP) CB-10K A/R
6 CIRCUIT BREAKER (15AMP) CB-15K A/R
7 CIRCUIT BREAKER (20AMP) CB-20K A/R
8 CIRCUIT BREAKER (30AMP) CB-30K A/R
9 CIRCUIT BREAKER (40AMP) CB-40K A/R
10 CIRCUIT BREAKER (50AMP) CB-50K A/R
11 CIRCUIT BREAKER (60AMP) CB-60K A/R
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 26
Weir Minerals Multiflo
ELECTRICAL COMPONENTS
ITEM DESCRIPTION PART NUMBER QTY
1 RELAY CHANGEOVER R24VCOAS-01 A/R
2 RELAY BLOCK H4973 A/R
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 27
Weir Minerals Multiflo
ELECTRICAL COMPONENTS
ITEM DESCRIPTION PART NUMBER QTY
1 C.B. BOX RS282-1152M 1
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 28
Weir Minerals Multiflo
EMERGENCY STOP
ITEM DESCRIPTION PART NUMBER QTY
1 EMERGENCY STOP ES-03-01 1
NC CONTACT (IF REQUIRED) ES-03-02 1
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 29
Weir Minerals Multiflo
2
1
ISOLATORS
ITEM DESCRIPTION PART NUMBER QTY
1 BATTERY LOCKOUT LS11003-01 1
2 STARTER LOCKOUT (IF FITTED) LS11003-02 1
3 ISOLATOR 341003004 A/R
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 30
Weir Minerals Multiflo
9 3
4
10 8
2
6 1
11 7
9
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 31
Weir Minerals Multiflo
1 14
12
13
3
2
5 13
4
6
9
11
7
10 8
10 6
4
4(New Pn:101495)
3
7 2
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 33
Weir Minerals Multiflo
7
10
6
11
5
4 9
3
12
420E (04.10)+B46 PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 34
Weir Minerals Multiflo
HYDRAU-FLO
ITEM DESCRIPTION PART NUMBER QTY
1 WIGGINS RECEIVER + CAP AUS23L + AUS23C 1
2 VALVE ASSEMBLY FBS-03A 1
3 ELBOW HF807-0609 2
4 HOSE HH1J061062J06-6020 1
5 HOSE HH1J061062J06-0610 1
6 MOUNTING PLATE FBS-08A 2
7 ELBOW HFS8-0409 2
8 FLOAT ASSEMBLY FBS-66-110 2
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 35
Weir Minerals Multiflo
1 3 2
8
5
6
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 36
Weir Minerals Multiflo
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 37
Weir Minerals Multiflo
2 5
6
3 4
1
FUEL FILLERS
ITEM DESCRIPTION PART NUMBER QTY
1 VALVE ASSEMBLY BLACK FBS-03A 1
2 RECEIVER FUEL BANLAW AUS23L 1
3 ALUMINIUM CAP AUS23C 1
4 FUEL GAUGE 62200-A-250 1
5 MANUAL FILL CAP KL50-DC 1
6 MANUAL FILL FITTING KL50-A 1
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 38
Weir Minerals Multiflo
1 1
FUEL FILTERS
ITEM DESCRIPTION PART NUMBER QTY
1 RACOR 1000 FUEL FILTER 1000FH2 2
REPLACEMENT ELEMENTS 2020SM-OR A/R
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 39
Weir Minerals Multiflo
10
2 12 7
5
11
1
3 6
10 9
6
SUCTION ASSEMBLY
ITEM DESCRIPTION PART NUMBER QTY
1 SUCTION REDUCER MFL300X200ERSS 1
2 BOOM MFB8 1
3 BOOM CHAINS CH80ZP13-06600 2
4 WINCH (INCLUDES GUARD) F11650C 1
5 SPREADER BAR H250JSB-3000 1
6 SUCTION HOSE H25002204JL 2
7 STRAINER MFS300-40SS 1
8 WIRE ROPE WR10-25SASA 1
9 INTERMEDIATE CLAMP UN31-273LE 1
10 HAMMERLOK HL13 4
11 INTERMEDIATE CHAIN CH80ZP10-02200 1
12 D SHACKLE DS-S-13 1
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 40
Weir Minerals Multiflo
2 1
4 8
3
8
8 6
DISCHARGE ASSEMBLY
ITEM DESCRIPTION PART NUMBER QTY
1 DISCHARGE PIPEWORK 1 PW0420Z0019 1
2 DISCHARGE PIPEWORK 2 PW0420Z0020 1
3 DISCHARGE PIPEWORK 3 PW0420Z0021 1
4 DISCHARGE PIPEWORK 4 PW0420Z0022 1
5 DISCHARGE PIPEWORK 5 PW0420Z0023 1
6 DISCHARGE PIPEWORK 6 MFL300X200ER 1
7 RUBBER HOSE H20002200.90JL 1
8 DISCHARGE SUPPORT MCJ000N006 5
9 RUBBER HOSE 1.5M LONG (NOT SHOWN) H30002201.5JL 1
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 41
Weir Minerals Multiflo
2
1
5 4
6
5
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 42
Weir Minerals Multiflo
14
6
13
3
5
11
4
9
12
10 2
1
NON-RETURN VALVE
(STAINLESS STEEL)
ITEM DESCRIPTION PART NUMBER QTY
COMPLETE VALVE NRV150-01SS 1
1 BODY NRV150-02SS 1
2 O'RING NRV150-03 1
3 DOWEL PIN NRV150-24 1
4 STUD NRV150-17 8
5 GASKET NRV150-20 1
6 INSPECTION LID NRV150-13 1
7 BAR, FIXING NRV150-07 1
8 STUD NRV150-19 3
9 STUD NRV150-18 16
10 FLAP NRV150-06 1
11 SEAT NRV150-04SS 1
12 NYLOC NUT NRV150-08 3
13 WASHER NRV150-14 8
14 NUT NRV150-15 8
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 43
Weir Minerals Multiflo
13
12
11
5 10
1
11
4
7
7
3
6
3
2
8
9
WORKLIGHTS
ITEM DESCRIPTION PART NUMBER QTY
1 LIGHT BODY 9150901 6
2 LIGHT BEAM (24 VOLTS) 1096 6
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 45
Weir Minerals Multiflo
FIRE EXTINGUISHER
ITEM DESCRIPTION PART NUMBER QTY
1 MOUNTING PLATE FEP-1 1
2 FIRE EXTINGUISHER FEQ9KGC-70 1
3 MOUNTING BRACKET FEHDVMBC9KG 1
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 46
Weir Minerals Multiflo
WASHDOWN HOSE
ITEM DESCRIPTION PART NUMBER QTY
1 ELBOW BSPEMF-1SS6 1
2 REDUCING BUSH BSPRB-50X25SS6 1
3 NIPPLE BSPN 1-0SS6 1
4 BALL VALVE BVF 1-0SS6 1
5 HOSE CLAMP RSC-3437 1
6 HOSE TAIL S21-025 1
7 BRACKET MSLWH42001 1
8 SAFETY HOSE MSLWH42001-01 1
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 47
Weir Minerals Multiflo
STROBE LIGHT
ITEM DESCRIPTION PART NUMBER QTY
1 AMBER STROBE LIGHT 101078 1
420E (04.10) PLEASE QUOTE MODEL AND SERIAL NUMBER OF PUMP WHEN ORDERING SPARE PARTS 48
Weir Minerals Multiflo Document Page
TB-2010-06 1 of 8
Technical Bulletin
8/6 FFY-HX BEARING ASSEMBLY SEAL UPGRADE Rev. Date Rev.
Feb 2010 0
1. Applies To
All 8/6 FFY-HX Bare Shaft pumps delivered prior to March 2010.
2. Purpose
Improve the end cap seals to eliminate oil leakage from the bearing assembly.
3. Parts Required
Qty Part Number Description
2 203095 RADIAL OIL SEAL
1 203191 LABYRINTH DRIVE END
2 203193 BEARING CAP END
2 203194 V SEAL
1 203195 LABYRINTH WET END
2 203196 ORING
2 203199 GASKET
2 203214 GREASE LUBRICATING NIPPLE (SAP#5AA-07)
Weir Minerals Multiflo Document Page
TB-2010-06 4 of 8
Technical Bulletin
8/6 FFY-HX BEARING ASSEMBLY SEAL UPGRADE Rev. Date Rev.
Feb 2010 0
4. Procedure
The following procedure describes the process to upgrade a typical 8/6 FFY-HX Bare Shaft Pump. Please
contact Weir Minerals Multiflo if you have questions regarding your specific unit.
i. Remove the bare shaft pump from the pump unit.
ii. Remove the bearing assembly from the bare shaft pump.
iii. Remove the components as illustrated from the bearing assembly.
Accompanying
Manuals