0% found this document useful (0 votes)
27 views

MCL Schedule

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views

MCL Schedule

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

ID Task Task Name Duration Start Finish Predecessors

11 Jul '22 19 Sep '22 28 Nov '22 06 Feb '23 17 Apr '23
Mode S F T W T M S S F
1 MCL 50MW Solar Project 151 days Thu 27-10-22 Sun 26-03-23
2 Boundary wall 124 days Thu 17-11-22 Mon 20-03-23
3 Supply of Columns & Slabs 70 days Thu 17-11-22 Wed 25-01-23
4 Supply of Barbed Wire 10 days Sat 17-12-22 Mon 26-12-22 3SS+30 days
5 Supply of Concerntina coil 10 days Sat 17-12-22 Mon 26-12-22 4SS
6 Installation of Columns & Slabs 90 days Fri 18-11-22 Wed 15-02-23 3SS+1 day
7 Installation of Barbed Wire 90 days Sun 18-12-22 Fri 17-03-23 4SS+1 day
8 Installation Of Concerntina Coil 90 days Sun 18-12-22 Fri 17-03-23 5SS+1 day
9 Finishing Works 3 days Sat 18-03-23 Mon 20-03-23 8
10
11 DC Works 124 days Thu 27-10-22 Mon 27-02-23
12 Supply Requirement for 50MW 65 days Thu 10-11-22 Fri 13-01-23
13 Supply of Column post 30 days Thu 10-11-22 Fri 09-12-22
14 Supply of MMS 50 days Fri 25-11-22 Fri 13-01-23 13SS+15 days
15 Supply of DC Cables(300sqmm,400sqmm) 35 days Fri 25-11-22 Thu 29-12-22 14SS
16 Supply of String cables 35 days Fri 25-11-22 Thu 29-12-22 15SS
17 Supply of SCB 35 days Fri 25-11-22 Thu 29-12-22 16SS
18 Supply of Inverters 7 days Fri 30-12-22 Thu 05-01-23 17
19
20 Vendor Finalisation 124 days Thu 27-10-22 Mon 27-02-23
21 Column post 15 days Thu 27-10-22 Thu 10-11-22
22 MMS&Module 15 days Thu 27-10-22 Thu 10-11-22 21SS
23 DCCable laying & SCB Erection 15 days Tue 01-11-22 Tue 15-11-22 22SS+5 days
24
25 Block-1 92 days Thu 10-11-22 Thu 09-02-23
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary

Project: NCL Schedule Milestone Inactive Milestone Start-only


Date: Sat 29-10-22 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
ID Task Task Name Duration Start Finish Predecessors
11 Jul '22 19 Sep '22 28 Nov '22 06 Feb '23 17 Apr '23
Mode S F T W T M S S F
26 Installation of Column post 50 days Thu 10-11-22 Thu 29-12-22 13SS
27 Installation of MMS 60 days Fri 25-11-22 Mon 23-01-23 26SS+15 days
28 Installation of Modules 60 days Fri 02-12-22 Mon 30-01-23 27SS+7 days
29 Installation of DC 60 days Fri 25-11-22 Mon 23-01-23 26SS+15 days
Cables(300sqmm,400sqmm)
30 Installation of String cables 60 days Mon 12-12-22 Thu 09-02-23 29SS+17 days
31 Installation of SCB 40 days Fri 02-12-22 Tue 10-01-23 17SS+7 days
32 Installation of Inverters 15 days Fri 06-01-23 Fri 20-01-23 18
33
34 Block-2 92 days Thu 17-11-22 Thu 16-02-23
35 Installation of Column post 50 days Thu 17-11-22 Thu 05-01-23 26SS+7 days
36 Installation of MMS 60 days Fri 02-12-22 Mon 30-01-23 35SS+15 days
37 Installation of Modules 60 days Fri 09-12-22 Mon 06-02-23 36SS+7 days
38 Installation of DC 60 days Fri 02-12-22 Mon 30-01-23 35SS+15 days
Cables(300sqmm,400sqmm)
39 Installation of String cables 60 days Mon 19-12-22 Thu 16-02-23 38SS+17 days
40 Installation of SCB 40 days Mon 12-12-22 Fri 20-01-23 31SS+10 days
41 Installation of Inverters 15 days Fri 13-01-23 Fri 27-01-23 32SS+7 days
42
43
44 Block 3 87 days Fri 25-11-22 Sun 19-02-23
45 Installation of Column post 40 days Fri 25-11-22 Tue 03-01-23 26SS+15 days
46 Installation of MMS 50 days Sat 10-12-22 Sat 28-01-23 27SS+15 days
47 Installation of Modules 50 days Sat 17-12-22 Sat 04-02-23 28SS+15 days

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: NCL Schedule Milestone Inactive Milestone Start-only


Date: Sat 29-10-22 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2
ID Task Task Name Duration Start Finish Predecessors
11 Jul '22 19 Sep '22 28 Nov '22 06 Feb '23 17 Apr '23
Mode S F T W T M S S F
48 Installation of DC 60 days Sat 10-12-22 Tue 07-02-23 29SS+15 days
Cables(300sqmm,400sqmm)
49 Installation of String cables 55 days Tue 27-12-22 Sun 19-02-23 30SS+15 days
50 Installation of SCB 40 days Tue 27-12-22 Sat 04-02-23 31SS+25 days
51 Installation of Inverters 15 days Tue 31-01-23 Tue 14-02-23 32SS+25 days
52
53 Block 4 75 days Thu 15-12-22 Mon 27-02-23
54 Installation of Column post 40 days Thu 15-12-22 Mon 23-01-23 26SS+35 days
55 Installation of MMS 50 days Fri 30-12-22 Fri 17-02-23 27SS+35 days
56 Installation of Modules 50 days Fri 06-01-23 Fri 24-02-23 28SS+35 days
57 Installation of DC Cables(300sqmm,400sqmm)60 days Fri 30-12-22 Mon 27-02-23 29SS+35 days
58 Installation of String cables 55 days Tue 27-12-22 Sun 19-02-23 30SS+15 days
59 Installation of SCB 40 days Tue 27-12-22 Sat 04-02-23 31SS+25 days
60 Installation of Inverters 15 days Tue 31-01-23 Tue 14-02-23 32SS+25 days
61
62
63 AC Works 99 days Tue 15-11-22 Tue 21-02-23
64 Supply of AC Cables 45 days Fri 25-11-22 Sun 08-01-23 15SS
65 Supply of ICOG 10 days Thu 15-12-22 Sat 24-12-22 64SS+20 days
66 Supply of IDT 10 days Thu 15-12-22 Sat 24-12-22 65SS
67 Supply of UPS,Battery,Chargers 10 days Thu 15-12-22 Sat 24-12-22 65SS
68 Supply of ACDB 10 days Thu 15-12-22 Sat 24-12-22 65SS
69 Supply of Auxilary Transformers 10 days Thu 15-12-22 Sat 24-12-22 65SS
70 Supply of SCADA panels 20 days Thu 15-12-22 Tue 03-01-23 65SS
71

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: NCL Schedule Milestone Inactive Milestone Start-only


Date: Sat 29-10-22 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 3
ID Task Task Name Duration Start Finish Predecessors
11 Jul '22 19 Sep '22 28 Nov '22 06 Feb '23 17 Apr '23
Mode S F T W T M S S F
72 Block 1&2 95 days Tue 15-11-22 Fri 17-02-23
73 Inverter Foundation 45 days Tue 15-11-22 Thu 29-12-22
74 Construction of Prefab building 25 days Fri 30-12-22 Mon 23-01-23 73
75 Installation of ICOG 10 days Fri 30-12-22 Sun 08-01-23 73
76 Installation of IDT 10 days Fri 30-12-22 Sun 08-01-23 73
77 Installation of UPS,Battery,Chargers 10 days Tue 24-01-23 Thu 02-02-23 74
78 Installation of ACDB 10 days Tue 24-01-23 Thu 02-02-23 74
79 Installation of Auxilary Transformers 10 days Tue 24-01-23 Thu 02-02-23 74
80 Installation of SCADA panels 10 days Tue 24-01-23 Thu 02-02-23 74
81 Cable laying & Precommissioning 70 days Sat 10-12-22 Fri 17-02-23 64SS+15 days
82
83 Block 3&4 89 days Fri 25-11-22 Tue 21-02-23
84 Inverter Foundation 45 days Fri 25-11-22 Sun 08-01-23 73SS+10 days
85 Construction of Prefab building 25 days Mon 09-01-23 Thu 02-02-23 84
86 Installation of ICOG 10 days Mon 09-01-23 Wed 18-01-23 84
87 Installation of IDT 10 days Mon 09-01-23 Wed 18-01-23 84
88 Installation of UPS,Battery,Chargers 10 days Fri 03-02-23 Sun 12-02-23 85
89 Installation of ACDB 10 days Fri 03-02-23 Sun 12-02-23 85
90 Installation of Auxilary Transformers 10 days Fri 03-02-23 Sun 12-02-23 85
91 Installation of SCADA panels 10 days Fri 03-02-23 Sun 12-02-23 85
92 Cable laying & Precommissioning 70 days Wed 14-12-22 Tue 21-02-23 81SS+4 days
93
94 Main control Room Civil 90 days Sun 27-11-22 Fri 24-02-23
95 Excavation 10 days Sun 27-11-22 Tue 06-12-22
96 Column up to roof 40 days Wed 07-12-22 Sun 15-01-23 95
Task External Milestone Manual Summary Rollup
Split Inactive Task Manual Summary

Project: NCL Schedule Milestone Inactive Milestone Start-only


Date: Sat 29-10-22 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 4
ID Task Task Name Duration Start Finish Predecessors
11 Jul '22 19 Sep '22 28 Nov '22 06 Feb '23 17 Apr '23
Mode S F T W T M S S F
97 Roof 28 days Mon 16-01-23 Sun 12-02-23 96
98 Brick works 65 days Mon 12-12-22 Tue 14-02-23 96SS+5 days
99 Plastering & painting 40 days Mon 16-01-23 Fri 24-02-23 98SS+35 days
100 Main control Room Electrical 83 days Fri 25-11-22 Wed 15-02-23
101 Supply of Switchgear 7 days Fri 20-01-23 Thu 26-01-23
102 Supply of SCADA panels 7 days Thu 15-12-22 Wed 21-12-22 70SS
103 Supply of Auxilary Transformers 7 days Thu 15-12-22 Wed 21-12-22 69SS
104 Supply of CRP,RELays 7 days Sat 14-01-23 Fri 20-01-23 103SS+30 days
105 Supply of Battery,UPS,Chargers 10 days Thu 15-12-22 Sat 24-12-22 67SS
106 Supply of Cables 10 days Fri 25-11-22 Sun 04-12-22 64SS
107
108 Installation of Switchgear 20 days Fri 27-01-23 Wed 15-02-23 101
109 Installation of SCADA panels 10 days Tue 31-01-23 Thu 09-02-23 108SS+4 days
110 Installation of Auxilary Transformers 10 days Tue 31-01-23 Thu 09-02-23 109SS

111 Installation of CRP,RELays 10 days Tue 31-01-23 Thu 09-02-23 109SS


112 Installation of Battery,UPS,Chargers 10 days Tue 31-01-23 Thu 09-02-23 109SS

113 Installation of Cables 15 days Tue 31-01-23 Tue 14-02-23 109SS


114
115 Road & Drain 110 days Thu 01-12-22 Mon 20-03-23
116
117 TL 114 days Wed 30-11-22 Thu 23-03-23
118 Supply of Material 90 days Wed 30-11-22 Mon 27-02-23
119 Foundation 90 days Fri 02-12-22 Wed 01-03-23 118SS+2 days

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: NCL Schedule Milestone Inactive Milestone Start-only


Date: Sat 29-10-22 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 5
ID Task Task Name Duration Start Finish Predecessors
11 Jul '22 19 Sep '22 28 Nov '22 06 Feb '23 17 Apr '23
Mode S F T W T M S S F
120 Erection of Tower 90 days Sat 17-12-22 Thu 16-03-23 119SS+15 days
121 Stringing 90 days Sat 24-12-22 Thu 23-03-23 120SS+7 days
122
123
124 Switchyard works & Commisioni ng 127 days Sun 20-11-22 Sun 26-03-23
125 Foundation for switchyard & Power transformer 75 days Sun 20-11-22 Thu 02-02-23
126 Supply of Power transformer & switchyard 30 days Wed 04-01-23 Thu 02-02-23 125SS+45 days
equipments
127 Erection of Power Transformer & Switch yard 45 days Fri 03-02-23 Sun 19-03-23 126
activities
128 Precommisioning 75 days Tue 10-01-23 Sat 25-03-23
129 Commisioning 3 days Fri 24-03-23 Sun 26-03-23 121

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: NCL Schedule Milestone Inactive Milestone Start-only


Date: Sat 29-10-22 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress