0
0
Respected Sir,
We are pleased and honored to submit our best Revised offer for Construction,
Completion and handing over to the defect’s liability period of the said project,
subject to the following conditions:
AED 3,530,765.00
(UAE Dirham’s Three Million Five Hundred Thirty Thousand Seven Hundred Sixty Five
Dirham Only).
Note:
Included All Items As Per BOQ.
Exclusions:
6. Vat tax or any other taxes that may be imposed by Government Authorities.
We hope that our offer gets your satisfaction and acceptance, and looking forward to
working with your esteemed firm in due course.
A ) Mobalisation
1 L.S 1.00 65000.00 65,000.00
B ) Providing a Watchman and Generator and Scaffolding for the site until the completion
of the work in the site And everything that the site requires
3 Super structure
4 Block Work
1/5
S.No. Description Unit Quantity Offer rate Amount
5 Plaster works
1 L.S 1.00 65000.00 65,000.00
Plaster for all internal walls for building includid ( OTS - Parpet ) M2 4,450 28 124,600
Stone Cladding WORKS 60 dhs / m2 (Supply and fix by Contractor) M2 198 120 23,760
Stone Cladding WORKS 30 dhs / l.m (Supply and fix by Contractor) L.M
GRANITE ( 150 dhs / M2 supply ) (Supply and fix by Contractor) M2 18 200 3,600
Stone Finish Paint For external wall for building M2 1,232 30 36,960
Epoxe Finish Paint For Parpet and OTS ( Inside ) M2 188 30 5,640
Granite & Marble & Ceramic for ( Entrance - Ramp - LOBBY - Lift floor ) G.F
M2 20 180 3,600
(Granite supply 120/m2)
Granite & Marble Steps for Main entracnce ( G.F ) (Granite supply 110/lm) L.M 3 150 450
Ceramic tiles for ( bath rooms - kitchens - Garbage room ) G.F - T.F (ceramic tile supply 25/m2) M2 198 70 13,860
Granite Ceramic tiles for All halls & bed rooms, balcony ( GF - TF ) (ceramic tile supply 25/m2) M2 544 70 38,080
ceramic tiles for service rooms ( GF - TF ) (ceramic tile supply 25/m2) M2 92 70 6,440
ceramic tiles Watch man room ( G.F ) (ceramic tile supply 25/m2) M2 9 70 630
Ceramic tiles for Shops ( G.F ) (ceramic tile supply 25/m2) M2 80 70 5,600
Granite & Marble & Ceramic for tiles for Corridors between apartments ( T.F )
M2 55 150 8,250
(Marble supply 100/m2)
Granite & Marble & Ceramic tiles for All staircase ( G F - TF ) (Marble supply 100/lm) L.M 135 150 20,250
Granite & Marble & Ceramic tiles for All staircase ( G F - TF ) landing (Marble supply 100/m2) M2 34 150 5,100
2/5
S.No. Description Unit Quantity Offer rate Amount
Granite & Marble & Ceramic for tiles for Corridors between apartments ( T.F )
M2 150 85 12,750
(ceramic tile supply 30/m2)
Emulsion paint for All internal walls of the building As to drawings & specifications. M2 2,274 20 45,480
NATIONAL HITEC M2 0
600x600*12mm PVC Vinyl Coated gypsum tile for shops ( G.F ) M2 80 80 6,400
Gypsum Board 12mm thickM2 including bulk head for entrance , lobby , corridor ( G.F ) M2 23 95 2,185
600x600*12mm PVC Vinyl Coated gypsum tile for bathroom , kitchen ( GF - TF ) M2 190 80 15,200
Gypsum Board 12mm thickM2 including bulk head for Corridors between apartments ( TF ) M2 55 95 5,225
Supply and installation of Corniche for All room and halls ( GF - TF ) L.M 510 30 15,300
Main door for FLATS 2000 Dhs / door (supply & fix price) Nos 12 2,000 24,000
All bed room + halls door 1500 Dhs /door (supply & fix price) Nos 17 1,500 25,500
Kitchen door 1500 dhs/door (supply & fix price) Nos 12 1,500 18,000
Bathroom door 1500 dhs/door (supply & fix price) Nos 29 1,500 43,500
stair case door 2000 Dhs/door (supply & fix price) Nos 7 2,000 14,000
wathc man door 1500 dhs/door (supply & fix price) Nos 1 1,500 1,500
12 Kitchen Cabinet
Bottom (Bottom & top)= 600 dhs / L.M supply L.M 60 850 51,000
3/5
S.No. Description Unit Quantity Offer rate Amount
Iron staircase For Service rooms on the roof of the building L.S 1 1,850 1,850
Hand rail for stair case = 0 dhs / L.M supply L.M 36 680 24,480
Railing Works In The Elevations = 0 dhs / L.M supply L.M 40 680 27,200
water proofing sys.for the External walls ( bitumen paint ) M2 198 13 2,574
water proofing for bath & kitchen & balcony L.S 1 15,000 15,000
water proofing forunder grounf water tank ( Membrane from the outside ) L.S 53 90 4,770
G.R.P ling for under grounf water tank L.S 108 80 8,640
15 Garbage chute
16 Lift works
Civil work For Lift + With the provision of services to the subcontractor L.S 1.00 7,000.00 7,000
Civil work for CCTV & Satellite & intercom for all floors L.S
Light Fittings = 20,000 dhs ( Buying price ) L.S 1.00 20,000.00 20,000
Transformer & Main Cable & Generato & Camera cctv & intercom (CCTV
PS 1.00 10,000.00 10,000
and Intercome only)
Supply and installation Fire Fighting & Fire Alarm Work L.S 1 140,000 140,000
Civil work For Fire Fighting & Fire Alarm + With the provision of services to the subcontractor L.S 1 20,000 20,000
4/5
S.No. Description Unit Quantity Offer rate Amount
Supply and installation Water tanks (G.R.P) 2 Tank L.S 1 17,500 17,500
Supply and installation manholes works ( Including civil works and covers ) L.S 1 18,000 18,000
All Sanitary Fittings ( Large bathroom ) Including Accessories& Mixers & Laundry counters ( supply
L.S 1 3,000 3,000
by owner - fixing by contracting )
All Sanitary Fittings ( Small bathroom ) Including Accessories& Mixers & Laundry counters ( supply
L.S 1 3,000 3,000
by owner - fixing by contracting )
All Sanitary Fittings ( For Shops ) Including Accessories& Mixers & Laundry counters ( supply by
L.S 1 1,200 1,200
owner - fixing by contracting )
Civil work for A/C work + With the provision of services to the subcontractor L.S 1 15,000 15,000
22 Gas System
Cleaning & Hand over & Levelling Work L.S 1 4,000 4,000
TOTAL 3,530,765
The contractor should add any item if it is not mentioned in the table of quantities or the price will be included if it is not mentioned
5/5