MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
A External Panels
1 Panel No. 01 & 39
Wall 1 4.750 83.100 394.725 1.025+0.78+2.58+0.38-0.015=4.750
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.580 0.300 41.796
D/d for Chajja Joint -54 0.300 0.150 -2.43
TOTAL :- 349.041
Total No.of Same Pannel :- 2.000
Total Qty. of Panel :- 698.082 Sqm
2 Panel No. 02, 05, 11, 29, 35 & 38
Wall 01 1 3.850 83.100 319.935 2.63+0.4+0.83-0.01=4.395
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.580 0.300 41.796
D/d for Chajja Joint -27 0.300 0.150 -1.215
D/d for Chajja Joint 27 0.300 0.150 1.215
TOTAL :- 276.681
Total No.of Same Pannels :- 6.000
Total Qty. of Panels :- 1660.086 Sqm
3 Panel No. 03 & 37
Wall 1 7.235 83.100 601.229 1.85+1.85+1.97+1.57-0.005=7.235
D/d for Perapit -1 3.820 1.350 -5.157 0.75+3*27+1.35=83.100
D/d for Opening -26 3.820 2.600 -258.232
D/d for Opening -1 3.820 3.000 -11.460
Add Balcony Parapit 27 1.910 0.450 23.207
TOTAL :- 349.586
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 699.172 Sqm
4 Panel No. 04 & 36
Wall 1 4.682 83.100 389.074 0.98+0.78+2.58+0.37-0.028=4.682
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.580 0.300 41.796
D/d for Chajja Joint -54 0.300 0.150 -2.43
TOTAL :- 343.390
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 686.780 Sqm
5 Panel No. 06 & 34
Wall 1 10.040 83.100 834.324 1.7+6.98+1.37-0.01=10.040
D/d for Perapit -1 6.980 1.350 -9.423 0.75+3*27+1.35=83.100
D/d for Opening -1 6.780 3.000 -20.340 6.98-0.200=6.780
D/d for Opening -26 6.780 2.600 -458.328
Add Balcony Parapit 54 1.755 0.450 42.647
TOTAL :- 388.880
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 777.759 Sqm
6 Panel No. 07 & 33
Page 1 of 9
External MS
MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
Wall 1 3.525 83.100 292.928 0.83+0.08+2.63-0.015=3.525
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.775 0.300 44.955
Add for Chajja Sides Joint 54 0.300 0.150 2.43
TOTAL :- 255.263
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 510.525 Sqm
7 Panel No. 08
Wall 1 5.025 83.100 417.578 0.37+3.35+0.08+1.23-0.005=5.025
D/d for Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.730 0.300 44.226
Add for Chajja Sides Joint 27 0.230 0.150 0.9315
D/d for Chajja Sides Joint -27 0.300 0.150 -1.215
TOTAL :- 376.470
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 376.470 Sqm
8 Panel No. 09
Wall 1 9.500 83.100 789.450 0.25+0.8+1.5+0.8+2.8+0.8+1.5+0.8+0.25=4.310
Wall abive Parapit Wall of Staircase/OHWT 1 6.300 6.775 42.683 0.25+1.5+2.8+1.5+0.25=6.300
Ceiling asbove of Windows 2 0.800 1.500 2.400 0.75+3*27+1.35=83.100
D/d for Window -55 1.500 1.250 -103.125
Add chajja Top & Bottom 110 1.500 0.300 49.500
D/d for Chajja Sides Joint -110 0.300 0.150 -4.950
TOTAL :- 775.958
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 775.958 Sqm
9 Panel No. 10
Wall 1 1 7.775 83.100 646.1025 2.11+3.82+1.85-0.005=7.775
D/d for Perapit -1 3.820 1.350 -5.157 0.75+3*27+1.35=83.100
D/d for Opening -26 3.820 2.600 -258.232
D/d for Opening -1 3.820 3.000 -11.460
Add Balcony Parapit 27 1.910 0.450 23.207
TOTAL :- 394.460
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 394.460 Sqm
10 Panel No. 12 & 28
Wall 1 4.700 83.100 390.57 0.980+0.78+2.58+0.38-0.020=4.700
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.580 0.300 41.796
D/d for Chajja Joint -54 0.300 0.150 -2.43
TOTAL :- 344.886
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 689.772 Sqm
11 Panel No. 13 & 27
Page 2 of 9
External MS
MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
Page 3 of 9
External MS
MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
Add Shaft Slab Openings Sides 27 1.500 0.150 6.075
D/d Ventilators - 2Nos/Floor -54 0.750 0.900 -36.450
TOTAL :- 680.195
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 1360.389 Sqm
17 Panel No.19, 21, 42 & 44
Wall 1 3.720 83.100 309.132 2.77+0.75+0.2=3.720
Add Shaft Slab 54 2.770 0.750 112.185 0.75+3*27+1.35=83.100
D/d Shaft Slab Both Sides Joint -54 0.750 0.150 -6.075
D/d Shaft Slab Openings -54 0.650 0.300 -10.530
Add Shaft Slab Openings Sides 27 1.250 0.150 5.063
D/d W2 -27 1.500 1.050 -42.525
TOTAL :- 367.250
Total No.of Same Pannels :- 4.000
Total Qty. of Panels :- 1468.998 Sqm
Page 4 of 9
External MS
MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
18 Panel No. 20
Wall - 01 1 10.650 83.100 885.015 4.5+1.65+4.5=10.650
D/d Passage Opening -27 1.650 1.050 -46.778 0.75+3*27+1.35=83.100
Add Chajja Top & Bottom 54 1.650 0.300 26.730
D/d Chhja Joint -54 0.300 0.150 -2.430
TOTAL :- 862.538
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 862.538 Sqm
19 Panel No. 30
Wall 1 5.015 83.100 416.747 1.85+1.85+1.07+0.25-0.005=5.015
D/d for Perapit -1 3.820 1.350 -5.157 0.75+3*27+1.35=83.100
D/d for Opening -26 3.820 2.600 -258.232
D/d for Opening -1 3.820 3.000 -11.460
Add Balcony Parapit 27 1.910 0.450 23.207
TOTAL :- 165.104
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 165.104 Sqm
20 Panel No. 31
Wall 1 11.219 83.100 932.299 1.48+1.5+0.8+2.8+0.8+1.5+2.36-0.021=11.219
Wall abive Parapit Wall of Staircase/OHWT 1 5.800 6.775 39.295 0.25+1.5+2.8+1.5+0.25=6.300
Ceiling asbove of Windows 2 0.800 1.500 2.400 0.75+3*27+1.35=83.100
D/d for Window -55 1.500 1.250 -103.125
Add Chajja Top & Bottom 110 1.500 0.300 49.500
D/d for Chajja Sides Joint -110 0.300 0.150 -4.950
TOTAL :- 915.419
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 915.419 Sqm
21 Panel No. 32
Wall 1 4.045 83.100 336.140 0.37+3.35+0.08+1.23-0.005=5.025
D/d for Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.730 0.300 44.226
Add for Chajja Sides Joint 27 0.230 0.150 0.9315
D/d for Chajja Sides Joint -27 0.300 0.150 -1.215
TOTAL :- 295.032
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 295.032 Sqm
22 Panel No. 40 & 46
Wall 1 7.500 83.100 623.250 0.75+3*27+1.35=83.100
TOTAL :- 623.250
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 1246.500 Sqm
Page 5 of 9
External MS
MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
23 Panel No. 41 & 45
Wall 1 6.520 83.100 541.812 0.2+0.75+5.01+0.75=6.710
Add Shaft Slab 54 4.820 0.750 195.210 0.75+3*27+1.35=83.100
D/d Shaft Slab Both Sides Joint -54 0.750 0.150 -6.075
D/d Shaft Slab Front Side Joint -27 0.750 0.150 -3.038
D/d Shaft Slab Openings -54 0.750 0.300 -12.150
Add Shaft Slab Openings Sides 27 1.350 0.150 5.468
D/d Shaft Slab Openings -54 1.810 0.300 -29.322
Add Shaft Slab Openings Sides 27 2.410 0.150 9.761
D/d Shaft Slab Openings -54 0.900 0.300 -14.580
Add Shaft Slab Openings Sides 27 1.500 0.150 6.075
D/d Ventilators - 2Nos/Floor -54 0.750 0.900 -36.450
TOTAL :- 656.711
Total No.of Same Pannel :- 2.000
Total Qty. of Panel :- 1313.421 Sqm
24 Panel No. 43
Wall - 01 1 10.650 83.100 885.015 4.5+1.65+4.5=10.650
D/d Passage Opening -27 1.650 1.050 -46.778 0.75+3*27+1.35=83.100
Add Services Slab Top & Bottom 54 1.650 1.100 98.010
D/d Shaft Slab Both Sides Joint -54 0.200 0.150 -1.620
D/d Shaft Slab Openings -108 0.900 0.300 -29.160
Add Shaft Slab Openings Sides 54 1.500 0.150 12.150
TOTAL :- 917.618
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 917.618 Sqm
B Shaft Panels
1 Flat No. 01/02 & 03/04
Wall 1 16.740 83.100 1391.094 4.82+3.55+4.82+3.55-.01=16.750
D/d for Opening of Passage (Stilt) -1 4.770 1.950 -9.302 0.75+3.9+3*27+1.35=87.0
D/d for Opening of Passage (Stilt) -1 4.770 1.950 -9.302 3.9-(0.75+1.2)=1.950
D/d for Opening of Wall (Stilt) -1 2.680 3.900 -10.452
Add Beam 1 2.680 1.150 3.082
D/d for Opening of Passage -27 3.320 1.050 -94.122 0.75+3*27+1.35=83.100
Add Chajja 56 3.320 0.300 55.776 28*2=56
D/d for Window - W2 -27 1.500 1.050 -42.525
D/d for Ventilator - V -81 0.750 0.900 -54.675
Add Service Slab Top & Bottom 108 2.800 0.750 226.800
D/d for Service Slab Joint -108 0.750 0.150 -12.150
D/d Shaft Slab Openings -54 0.650 0.300 -10.530
Add Shaft Slab Openings Sides 27 1.250 0.150 5.063
D/d Shaft Slab Openings -54 0.730 0.300 -11.826
Add Shaft Slab Openings Sides 27 1.330 0.150 5.387
D/d Shaft Slab Openings -54 0.820 0.300 -13.284
Add Shaft Slab Openings Sides 27 1.420 0.150 5.751
D/d Shaft Slab Openings -54 1.160 0.300 -18.792
Add Shaft Slab Openings Sides 27 1.760 0.150 7.128
Add Service Slab Top & Bottom 54 4.820 0.750 195.210
Page 6 of 9
External MS
MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
Page 7 of 9
External MS
MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
2 Flat No. 05 & 10
Wall 1 16.220 87.000 1411.14 4.82+3.55+4.82+3.55=16.750
D/d for Opening of Passage (Stilt) -1 2.830 1.950 -5.519 0.75+3.9+3*27+1.35=87.0
D/d for Opening of Passage (Stilt) -1 4.630 1.950 -9.029 3.9-(0.75+1.2)=1.950
D/d for Opening of Wall (Stilt) -1 2.530 3.900 -9.867
Add Beam 1 2.530 1.150 2.910
D/d for Opening of Passage -27 2.130 1.050 -60.386
Add Chajja 56 2.130 0.300 35.784 28*2=56
D/d for Window - W2 -27 1.500 1.050 -42.525
D/d for Ventilator - V -54 0.750 0.900 -36.450
Add Service Slab Top & Bottom 54 2.750 0.750 111.375
D/d for Service Slab Joint -54 0.750 0.150 -6.075
D/d Shaft Slab Openings -54 0.650 0.300 -10.530
Add Shaft Slab Openings Sides 27 1.250 0.150 5.063
Add Service Slab Top & Bottom 54 4.680 0.750 189.540
D/d for Service Slab Joint -81 0.750 0.150 -9.113
D/d Shaft Slab Openings -54 0.650 0.300 -10.530
Add Shaft Slab Openings Sides 27 1.250 0.150 5.063
D/d Shaft Slab Openings -54 1.630 0.300 -26.406
Add Shaft Slab Openings Sides 27 2.230 0.150 9.032
D/d Shaft Slab Openings -54 0.850 0.300 -13.770
Add Shaft Slab Openings Sides 27 1.450 0.150 5.873
TOTAL :- 1535.580
Total No.of Same Pannel :- 2.000
Total Qty. of Panel :- 3071.159 Sqm
3 Flat No. 06 & 09
Wall 1 16.270 87.000 1415.49 4.82+3.55+4.82+3.55=16.750
D/d for Opening of Passage (Stilt) -1 2.830 1.950 -5.519 0.75+3.9+3*27+1.35=87.0
D/d for Opening of Passage (Stilt) -1 4.630 1.950 -9.029 3.9-(0.75+1.2)=1.950
D/d for Opening of Wall (Stilt) -1 2.530 3.900 -9.867
Add Beam 1 2.530 1.150 2.910
D/d for Opening of Passage -27 2.080 1.050 -58.968
Add Chajja 56 2.080 0.300 34.944 28*2=56
D/d for Window - W2 -27 1.500 1.050 -42.525
D/d for Ventilator - V -54 0.750 0.900 -36.450
Add Service Slab Top & Bottom 54 3.500 0.750 141.750
D/d for Service Slab Joint -81 0.750 0.150 -9.113
D/d Shaft Slab Openings -108 0.650 0.300 -21.060
Add Shaft Slab Openings Sides 54 1.250 0.150 10.125
Add Service Slab Top & Bottom 54 2.980 0.750 120.690
D/d for Service Slab Joint -54 0.750 0.150 -6.075
D/d Shaft Slab Openings -54 0.650 0.300 -10.530
Add Shaft Slab Openings Sides 27 1.250 0.150 5.063
Add Service Slab Top & Bottom 54 0.900 0.950 46.170
D/d for Service Slab Joint -81 0.750 0.150 -9.113
D/d Shaft Slab Openings -54 0.850 0.300 -13.770
Add Shaft Slab Openings Sides 27 1.450 0.150 5.873
TOTAL :- 1550.997
Page 8 of 9
External MS
MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
Total No.of Same Pannel :- 2.000
Total Qty. of Panel :- 3101.993 Sqm
Page 9 of 9