0% found this document useful (0 votes)
10 views9 pages

Panel MS - 093121

Uploaded by

Santanu Das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views9 pages

Panel MS - 093121

Uploaded by

Santanu Das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

External MS

MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
A External Panels
1 Panel No. 01 & 39
Wall 1 4.750 83.100 394.725 1.025+0.78+2.58+0.38-0.015=4.750
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.580 0.300 41.796
D/d for Chajja Joint -54 0.300 0.150 -2.43
TOTAL :- 349.041
Total No.of Same Pannel :- 2.000
Total Qty. of Panel :- 698.082 Sqm
2 Panel No. 02, 05, 11, 29, 35 & 38
Wall 01 1 3.850 83.100 319.935 2.63+0.4+0.83-0.01=4.395
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.580 0.300 41.796
D/d for Chajja Joint -27 0.300 0.150 -1.215
D/d for Chajja Joint 27 0.300 0.150 1.215
TOTAL :- 276.681
Total No.of Same Pannels :- 6.000
Total Qty. of Panels :- 1660.086 Sqm
3 Panel No. 03 & 37
Wall 1 7.235 83.100 601.229 1.85+1.85+1.97+1.57-0.005=7.235
D/d for Perapit -1 3.820 1.350 -5.157 0.75+3*27+1.35=83.100
D/d for Opening -26 3.820 2.600 -258.232
D/d for Opening -1 3.820 3.000 -11.460
Add Balcony Parapit 27 1.910 0.450 23.207
TOTAL :- 349.586
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 699.172 Sqm
4 Panel No. 04 & 36
Wall 1 4.682 83.100 389.074 0.98+0.78+2.58+0.37-0.028=4.682
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.580 0.300 41.796
D/d for Chajja Joint -54 0.300 0.150 -2.43
TOTAL :- 343.390
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 686.780 Sqm
5 Panel No. 06 & 34
Wall 1 10.040 83.100 834.324 1.7+6.98+1.37-0.01=10.040
D/d for Perapit -1 6.980 1.350 -9.423 0.75+3*27+1.35=83.100
D/d for Opening -1 6.780 3.000 -20.340 6.98-0.200=6.780
D/d for Opening -26 6.780 2.600 -458.328
Add Balcony Parapit 54 1.755 0.450 42.647
TOTAL :- 388.880
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 777.759 Sqm
6 Panel No. 07 & 33

Page 1 of 9
External MS

MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
Wall 1 3.525 83.100 292.928 0.83+0.08+2.63-0.015=3.525
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.775 0.300 44.955
Add for Chajja Sides Joint 54 0.300 0.150 2.43
TOTAL :- 255.263
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 510.525 Sqm

7 Panel No. 08
Wall 1 5.025 83.100 417.578 0.37+3.35+0.08+1.23-0.005=5.025
D/d for Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.730 0.300 44.226
Add for Chajja Sides Joint 27 0.230 0.150 0.9315
D/d for Chajja Sides Joint -27 0.300 0.150 -1.215
TOTAL :- 376.470
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 376.470 Sqm
8 Panel No. 09
Wall 1 9.500 83.100 789.450 0.25+0.8+1.5+0.8+2.8+0.8+1.5+0.8+0.25=4.310
Wall abive Parapit Wall of Staircase/OHWT 1 6.300 6.775 42.683 0.25+1.5+2.8+1.5+0.25=6.300
Ceiling asbove of Windows 2 0.800 1.500 2.400 0.75+3*27+1.35=83.100
D/d for Window -55 1.500 1.250 -103.125
Add chajja Top & Bottom 110 1.500 0.300 49.500
D/d for Chajja Sides Joint -110 0.300 0.150 -4.950
TOTAL :- 775.958
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 775.958 Sqm
9 Panel No. 10
Wall 1 1 7.775 83.100 646.1025 2.11+3.82+1.85-0.005=7.775
D/d for Perapit -1 3.820 1.350 -5.157 0.75+3*27+1.35=83.100
D/d for Opening -26 3.820 2.600 -258.232
D/d for Opening -1 3.820 3.000 -11.460
Add Balcony Parapit 27 1.910 0.450 23.207
TOTAL :- 394.460
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 394.460 Sqm
10 Panel No. 12 & 28
Wall 1 4.700 83.100 390.57 0.980+0.78+2.58+0.38-0.020=4.700
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.580 0.300 41.796
D/d for Chajja Joint -54 0.300 0.150 -2.43
TOTAL :- 344.886
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 689.772 Sqm
11 Panel No. 13 & 27

Page 2 of 9
External MS

MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark

Wall 1 4.370 83.100 363.147 2.99+1.380=4.370


Wall @ Beam & Perapit For Bed Balcony 14 3.100 0.850 36.89 0.75+3*27+1.35=83.100
TOTAL :- 400.037
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 800.074 Sqm
12 Panel No. 14 & 26
Wall 01 1 5.685 83.100 472.4235 4.41+1.28-0.005=5.685
D/d for Perapit -1 4.210 1.350 -5.684 0.75+3*27+1.35=83.100
D/d for Opening -26 4.210 2.600 -284.596
D/d for Opening -1 4.210 3.000 -12.630
Add Balcony Parapit 27 2.105 0.450 25.576
TOTAL :- 195.090
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 390.180 Sqm
13 Panel No. 15 & 25
Wall 01 1 3.650 83.100 303.315 2.43+0.4+0.83-0.01=3.650
Add Bed Balcony Parapit Beam/Wall(Left Side) 1 1.180 0.850 1.003 2.43+0.4+0.83-0.01=3.650
D/d for Passage Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.430 0.300 39.366
D/d for Chajja Joint -27 0.300 0.150 -1.215
D/d for Chajja Joint 27 0.300 0.150 1.215
TOTAL :- 258.634
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 517.268 Sqm
14 Panel No. 16 & 24
Wall (Front Side) 13 3.800 0.850 41.990
TOTAL :- 41.990
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 83.980 Sqm
15 Panel No. 17 & 23
Wall 1 7.130 83.100 592.503 0.75+3*27+1.35=83.100
Add Bed Balcony Parapit Beam/Wall(Rifht Side) 13 0.780 0.850 8.619
TOTAL :- 601.122
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 1202.244 Sqm
16 Panel No.18 & 22
Wall 1 6.710 83.100 557.601 0.2+0.75+5.01+0.75=6.710
Add Shaft Slab 54 5.010 0.750 202.905 0.75+3*27+1.35=83.100
D/d Shaft Slab Both Sides Joint -54 0.750 0.150 -6.075
D/d Shaft Slab Front Side Joint -27 0.750 0.150 -3.038
D/d Shaft Slab Openings -54 0.750 0.300 -12.150
Add Shaft Slab Openings Sides 27 1.350 0.150 5.468
D/d Shaft Slab Openings -54 1.810 0.300 -29.322
Add Shaft Slab Openings Sides 27 2.410 0.150 9.761
D/d Shaft Slab Openings -54 0.900 0.300 -14.580

Page 3 of 9
External MS

MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
Add Shaft Slab Openings Sides 27 1.500 0.150 6.075
D/d Ventilators - 2Nos/Floor -54 0.750 0.900 -36.450
TOTAL :- 680.195
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 1360.389 Sqm
17 Panel No.19, 21, 42 & 44
Wall 1 3.720 83.100 309.132 2.77+0.75+0.2=3.720
Add Shaft Slab 54 2.770 0.750 112.185 0.75+3*27+1.35=83.100
D/d Shaft Slab Both Sides Joint -54 0.750 0.150 -6.075
D/d Shaft Slab Openings -54 0.650 0.300 -10.530
Add Shaft Slab Openings Sides 27 1.250 0.150 5.063
D/d W2 -27 1.500 1.050 -42.525
TOTAL :- 367.250
Total No.of Same Pannels :- 4.000
Total Qty. of Panels :- 1468.998 Sqm

Page 4 of 9
External MS

MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
18 Panel No. 20
Wall - 01 1 10.650 83.100 885.015 4.5+1.65+4.5=10.650
D/d Passage Opening -27 1.650 1.050 -46.778 0.75+3*27+1.35=83.100
Add Chajja Top & Bottom 54 1.650 0.300 26.730
D/d Chhja Joint -54 0.300 0.150 -2.430
TOTAL :- 862.538
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 862.538 Sqm

19 Panel No. 30
Wall 1 5.015 83.100 416.747 1.85+1.85+1.07+0.25-0.005=5.015
D/d for Perapit -1 3.820 1.350 -5.157 0.75+3*27+1.35=83.100
D/d for Opening -26 3.820 2.600 -258.232
D/d for Opening -1 3.820 3.000 -11.460
Add Balcony Parapit 27 1.910 0.450 23.207
TOTAL :- 165.104
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 165.104 Sqm
20 Panel No. 31
Wall 1 11.219 83.100 932.299 1.48+1.5+0.8+2.8+0.8+1.5+2.36-0.021=11.219
Wall abive Parapit Wall of Staircase/OHWT 1 5.800 6.775 39.295 0.25+1.5+2.8+1.5+0.25=6.300
Ceiling asbove of Windows 2 0.800 1.500 2.400 0.75+3*27+1.35=83.100
D/d for Window -55 1.500 1.250 -103.125
Add Chajja Top & Bottom 110 1.500 0.300 49.500
D/d for Chajja Sides Joint -110 0.300 0.150 -4.950
TOTAL :- 915.419
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 915.419 Sqm
21 Panel No. 32
Wall 1 4.045 83.100 336.140 0.37+3.35+0.08+1.23-0.005=5.025
D/d for Window -27 1.800 1.750 -85.05 0.75+3*27+1.35=83.100
Add chajja Top & Bottom 54 2.730 0.300 44.226
Add for Chajja Sides Joint 27 0.230 0.150 0.9315
D/d for Chajja Sides Joint -27 0.300 0.150 -1.215
TOTAL :- 295.032
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 295.032 Sqm
22 Panel No. 40 & 46
Wall 1 7.500 83.100 623.250 0.75+3*27+1.35=83.100
TOTAL :- 623.250
Total No.of Same Pannels :- 2.000
Total Qty. of Panels :- 1246.500 Sqm

Page 5 of 9
External MS

MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
23 Panel No. 41 & 45
Wall 1 6.520 83.100 541.812 0.2+0.75+5.01+0.75=6.710
Add Shaft Slab 54 4.820 0.750 195.210 0.75+3*27+1.35=83.100
D/d Shaft Slab Both Sides Joint -54 0.750 0.150 -6.075
D/d Shaft Slab Front Side Joint -27 0.750 0.150 -3.038
D/d Shaft Slab Openings -54 0.750 0.300 -12.150
Add Shaft Slab Openings Sides 27 1.350 0.150 5.468
D/d Shaft Slab Openings -54 1.810 0.300 -29.322
Add Shaft Slab Openings Sides 27 2.410 0.150 9.761
D/d Shaft Slab Openings -54 0.900 0.300 -14.580
Add Shaft Slab Openings Sides 27 1.500 0.150 6.075
D/d Ventilators - 2Nos/Floor -54 0.750 0.900 -36.450
TOTAL :- 656.711
Total No.of Same Pannel :- 2.000
Total Qty. of Panel :- 1313.421 Sqm
24 Panel No. 43
Wall - 01 1 10.650 83.100 885.015 4.5+1.65+4.5=10.650
D/d Passage Opening -27 1.650 1.050 -46.778 0.75+3*27+1.35=83.100
Add Services Slab Top & Bottom 54 1.650 1.100 98.010
D/d Shaft Slab Both Sides Joint -54 0.200 0.150 -1.620
D/d Shaft Slab Openings -108 0.900 0.300 -29.160
Add Shaft Slab Openings Sides 54 1.500 0.150 12.150
TOTAL :- 917.618
Total No.of Same Pannels :- 1.000
Total Qty. of Panels :- 917.618 Sqm

B Shaft Panels
1 Flat No. 01/02 & 03/04
Wall 1 16.740 83.100 1391.094 4.82+3.55+4.82+3.55-.01=16.750
D/d for Opening of Passage (Stilt) -1 4.770 1.950 -9.302 0.75+3.9+3*27+1.35=87.0
D/d for Opening of Passage (Stilt) -1 4.770 1.950 -9.302 3.9-(0.75+1.2)=1.950
D/d for Opening of Wall (Stilt) -1 2.680 3.900 -10.452
Add Beam 1 2.680 1.150 3.082
D/d for Opening of Passage -27 3.320 1.050 -94.122 0.75+3*27+1.35=83.100
Add Chajja 56 3.320 0.300 55.776 28*2=56
D/d for Window - W2 -27 1.500 1.050 -42.525
D/d for Ventilator - V -81 0.750 0.900 -54.675
Add Service Slab Top & Bottom 108 2.800 0.750 226.800
D/d for Service Slab Joint -108 0.750 0.150 -12.150
D/d Shaft Slab Openings -54 0.650 0.300 -10.530
Add Shaft Slab Openings Sides 27 1.250 0.150 5.063
D/d Shaft Slab Openings -54 0.730 0.300 -11.826
Add Shaft Slab Openings Sides 27 1.330 0.150 5.387
D/d Shaft Slab Openings -54 0.820 0.300 -13.284
Add Shaft Slab Openings Sides 27 1.420 0.150 5.751
D/d Shaft Slab Openings -54 1.160 0.300 -18.792
Add Shaft Slab Openings Sides 27 1.760 0.150 7.128
Add Service Slab Top & Bottom 54 4.820 0.750 195.210

Page 6 of 9
External MS

MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark

D/d for Service Slab Joint -108 0.750 0.150 -12.150


D/d Shaft Slab Openings -54 0.690 0.300 -11.178
Add Shaft Slab Openings Sides 27 1.290 0.150 5.225
D/d Shaft Slab Openings -54 1.680 0.300 -27.216
Add Shaft Slab Openings Sides 27 2.280 0.150 9.234
D/d Shaft Slab Openings -54 0.950 0.300 -15.390
Add Shaft Slab Openings Sides 27 1.550 0.150 6.278
TOTAL :- 1563.133
Total No.of Same Pannel :- 2.000
Total Qty. of Panel :- 3126.266 Sqm

Page 7 of 9
External MS

MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
2 Flat No. 05 & 10
Wall 1 16.220 87.000 1411.14 4.82+3.55+4.82+3.55=16.750
D/d for Opening of Passage (Stilt) -1 2.830 1.950 -5.519 0.75+3.9+3*27+1.35=87.0
D/d for Opening of Passage (Stilt) -1 4.630 1.950 -9.029 3.9-(0.75+1.2)=1.950
D/d for Opening of Wall (Stilt) -1 2.530 3.900 -9.867
Add Beam 1 2.530 1.150 2.910
D/d for Opening of Passage -27 2.130 1.050 -60.386
Add Chajja 56 2.130 0.300 35.784 28*2=56
D/d for Window - W2 -27 1.500 1.050 -42.525
D/d for Ventilator - V -54 0.750 0.900 -36.450
Add Service Slab Top & Bottom 54 2.750 0.750 111.375
D/d for Service Slab Joint -54 0.750 0.150 -6.075
D/d Shaft Slab Openings -54 0.650 0.300 -10.530
Add Shaft Slab Openings Sides 27 1.250 0.150 5.063
Add Service Slab Top & Bottom 54 4.680 0.750 189.540
D/d for Service Slab Joint -81 0.750 0.150 -9.113
D/d Shaft Slab Openings -54 0.650 0.300 -10.530
Add Shaft Slab Openings Sides 27 1.250 0.150 5.063
D/d Shaft Slab Openings -54 1.630 0.300 -26.406
Add Shaft Slab Openings Sides 27 2.230 0.150 9.032
D/d Shaft Slab Openings -54 0.850 0.300 -13.770
Add Shaft Slab Openings Sides 27 1.450 0.150 5.873
TOTAL :- 1535.580
Total No.of Same Pannel :- 2.000
Total Qty. of Panel :- 3071.159 Sqm
3 Flat No. 06 & 09
Wall 1 16.270 87.000 1415.49 4.82+3.55+4.82+3.55=16.750
D/d for Opening of Passage (Stilt) -1 2.830 1.950 -5.519 0.75+3.9+3*27+1.35=87.0
D/d for Opening of Passage (Stilt) -1 4.630 1.950 -9.029 3.9-(0.75+1.2)=1.950
D/d for Opening of Wall (Stilt) -1 2.530 3.900 -9.867
Add Beam 1 2.530 1.150 2.910
D/d for Opening of Passage -27 2.080 1.050 -58.968
Add Chajja 56 2.080 0.300 34.944 28*2=56
D/d for Window - W2 -27 1.500 1.050 -42.525
D/d for Ventilator - V -54 0.750 0.900 -36.450
Add Service Slab Top & Bottom 54 3.500 0.750 141.750
D/d for Service Slab Joint -81 0.750 0.150 -9.113
D/d Shaft Slab Openings -108 0.650 0.300 -21.060
Add Shaft Slab Openings Sides 54 1.250 0.150 10.125
Add Service Slab Top & Bottom 54 2.980 0.750 120.690
D/d for Service Slab Joint -54 0.750 0.150 -6.075
D/d Shaft Slab Openings -54 0.650 0.300 -10.530
Add Shaft Slab Openings Sides 27 1.250 0.150 5.063
Add Service Slab Top & Bottom 54 0.900 0.950 46.170
D/d for Service Slab Joint -81 0.750 0.150 -9.113
D/d Shaft Slab Openings -54 0.850 0.300 -13.770
Add Shaft Slab Openings Sides 27 1.450 0.150 5.873
TOTAL :- 1550.997

Page 8 of 9
External MS

MEASUREMENT SHEET
VTP PEGASUS R2_TOWER - 2
S.N Description Nos Length W/H Total Remark
Total No.of Same Pannel :- 2.000
Total Qty. of Panel :- 3101.993 Sqm