Contract Tender and Valuation
Contract Tender and Valuation
In this contract, contractor agrees to perform specified job for fixed sum.
In this contract both the parties try to fix the conditions of the work as precisely as
possible.
Owner is aware of the cost of the project before the project construction starts.
It avoids a lot of details and accounting by both owner and contractor.
Low risk on the owner, Higher risk to the contractor
If this contract is used with design-construct method of delivery, contractor gets
opportunity to use value engineering
This type of construction is usually followed in government sector for large infrastructure
construction.
This type of contract provides owner a competitive bid.
Item rate contract:
For this contract, contractors are required to quote rates for individual items of work on
the basis of schedule of quantities furnished by the client’s department.
EPC contract:
EPC stands for “Engineering, Procurement & Construction is a significant form of
contract in construction industries.
In EPC owner provides the basic engineering to contractor and contractor
Needs to perform detailed design based on the basis design received by owner
CLASSIFICATION OF TENDERS:
Tenders are broadly classified into:
1. Open or public tender: In this type of tender any contractor can enter into competition
and all formalities of giving opportunity to compete are to be fulfilled. It is compulsory
for public works and because of competition; it may result in low cost. But there are
chances of dispute as mistakes found out at a later stage are difficult to be adjusted. It is
also not suitable for complicated and specialized jobs.
2. Selected or limited tender: For this type of tender, the architect after consultation with
his client invites a limited number of contractors for filling up the tender of the project. It
results into competition on a small scale. But it proves to be useful for specialized and
skilled works. It also leads to early successful completion of the project.
3. Negotiated tender: This is the advanced form of selective tender and the contract is
given by negotiations with one or at the most two contractors . As such, there is no
competition in this type of tender and hence, it may prove to be costly. But when the
work is to be completed in target time without sacrificing for the quality, the negotiated
tender may prove to be the only alternative.
Invitation to tender:
An invitation to tender is a formal invitation to make an offer for the supply of goods or services.
An invitation to tender might be issued for a range of contracts, including:
1. Equipment supply
2. Design by contractors
3. Trade contractors
4. Main construction contractors
5. Demolition or enabling works
PREQUALIFICATION OF CONTRACTORS:
Under this procedure, the competency of the contractors is determined before the tenders
for the work are released. The tenders are then supplied to those contractors who are qualified for
the job. Normally, a contractor will be required to fill up a detailed questionnaire form.
Questionnaire may contain the following information
Contractors past experience
Present works on hand
Financial stability
Technical qualifications
Plants and equipment's etc.
Advantages of prequalification:
1. Facility for acceptance
2. Sufficient time for decision
3. Sound contract
4. Facilities for unqualified contractors
5. Better class of contractors
Disadvantages of prequalification:
1. No real competition
2. Doubt of favouritism
3. Complicated questionnaire form
3. Submission of bids and their scrutiny: After the tenders are received, they should be
properly scrutinized with respect to the following items:
1. A list of tenders which are received should be made with the details of the deposit
cheques.
2. It should be checked and verified that each tender is duly signed and it contains the
address of the contractor.
3. It should be seen that the contractor has not altered the terms and conditions of the tender
and at the same time, he has not mentioned some other terms and conditions.
4. The rates of each item should be entered in figures and words. The calculations showing
the amount of each item should be carefully checked.
5. The totaling of the amounts from page to page also should be done carefully in order to
arrive at the final cost of construction in each case.
6. After all the tenders are scrutinized, a comparative list should be made. The tender
showing the lowest amount should be placed first and the tender showing the highest
amount should be placed last.
4. Accceptance of tender: Generally, the tender with the lowest amount is accepted. But in
some cases, the rates of the lowest tender are so low that it becomes evident that the work will be
spoiled, if contract is given to such tenderer. In such cases, the owner decides for or negotiates
with the second lowest contractor.
VALUATION
TECHNICAL TERMS
1. EXPENDITURE
The whole amount can be spent during the financial year or not.
2. CAPITAL COST
Total cost including all the expenditure incurred from beginning to the completion of a work.
3. PROVISIONAL SUM
Estimate of bill quantities for some special work to be done by a specialist firm whose details are
known at the time of preparation of estimate.
4. RATE OF COST
The cost per unit of subhead which is arrived at by dividing the up-to-date final charges on a sub-
head by its up-to-date progress.
5. PREMIUM
The tendered percentage rate above the notified rates.
6. REBATE
The tendered percentage rate below the notified rates.
7. PLINTH AREA
It is a covered area of a building measured at floor level. It is measured by taking external
dimensions excluding plinth offset if any.
8. RATES
Rates followed are of sanctioned schedule of rates or non-scheduled, this fact is to be mentioned
under this sub – head.
9. CONTINGENCIES
Incidental expenses of miscellaneous character which cannot be classified approximately under
any distinct sub-head, but is added in the cost of construction necessarily.
10. VALUATION
Valuation is the technique of estimating or determining the fair price or value of a property such
as building, a factory, other engineering structure of various types, land…etc.
OBJECTS OF VALUATION
It is the technique of estimating and determining the fair price or value of a property such
as a building, a factory or other engineering structures of various types, land etc.
Market Value
The market value of a property is the amount which can be obtained at any particular time from
the open market if the property is put for sale. The market value will differ from time to time
according to demand and supply.
The market value also changes from time to time for various miscellaneous reasons such as
changes in industry, changes in fashions, means of transport, cost of materials and labour etc.
Book Value
Book value is the amount shown in the account book after allowing necessary depreciations. The
book value of a property at a particular year is the original cost minus the amount of depreciation
allowed per year and will be gradually reduced year to year and at the end of the utility period of
the property, the book value will be only scrap value.
Capital cost
Capital cost is the total cost of construction including land, or the original total amount required
to possess a property. It is the original cost and does not change while the value of the property is
the present cost which may be calculated by methods of Valuation.
And the cost of each part should first be worked out on the present day rates by detailed
measurements.
The present value of land and water supply, electric and sanitary fittings etc should be added to
the valuation of the building to arrive at total valuation of the property.
Depreciation is the gradual exhaustion of the usefulness of a property. This may be defined as
the decrease or loss in the value of a property due to structural deterioration, life wear and tear,
decay and obsolescence.