Ventajas de La Gestión de La Información - Demian and Walters 2013
Ventajas de La Gestión de La Información - Demian and Walters 2013
Items in Figshare are protected by copyright, with all rights reserved, unless otherwise indicated.
http://dx.doi.org/10.1080/01446193.2013.777754
PUBLISHER
VERSION
AM (Accepted Manuscript)
LICENCE
CC BY-NC-ND 4.0
REPOSITORY RECORD
Demian, Peter, and David Walters. 2019. “The Advantages of Information Management Through Building
Information Modelling”. figshare. https://hdl.handle.net/2134/12185.
This item was submitted to Loughborough’s Institutional Repository
(https://dspace.lboro.ac.uk/) by the author and is made available under the
following Creative Commons Licence conditions.
Information Modelling
Abstract
solution to the problems in the construction industry, research is needed into the benefits BIM actually confers.
The focus here is on the effectiveness of BIM as a medium for communicating information within a
construction team. A case study of an off-site precast concrete fabrication facility was conducted. At the time
of the study, the facility was supplying precast units for four public sector projects, and using four information
management systems: email, a construction project extranet tool, an Enterprise Resource Planning system
and a new BIM-based system. The flow of information through the four media was measured and visualised
as the projects progressed. This quantitative measurement of information flow was combined with qualitative
data from interviews with facility staff. It was found that the introduction of the BIM-based system diverted
information flow through the building model and away from the extranet system. The use of email was largely
unaffected. that BIM allowed considerably more accurate, on-time and appropriate exchange of information. It
is concluded it is possible to quantify some of the benefits of BIM to information management. This research
paves the way for future research into the management of more construction project information linked more
Keywords
1
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
1 Introduction
The emergence of Building Information Modelling (BIM) warrants a fresh look at information flows and
communication in building design and construction. A review of historical data (Teicholz 2001) showed that
while productivity in all non-farming industries had more than doubled over a 40-year period, construction
productivity had fallen by around 5%. Another study suggests that communication and data handling
accounts for between 75% and 90% of a project manager’s time in the construction industry (Fisher & Yin
1992). Although comparisons across different industrial sectors are difficult to make and interpret, such
published findings suggest that the recent innovations in information management and the level of
collaboration seen in other industries have not yet been fully realised in construction. Even within
construction, a more recent study (Eastman and Sacks 2008) implies that innovations such as BIM are
Whilst there is a consensus that construction is a low-performing sector in terms of innovation (Sexton and
Barrett 2003, Pries and Janszen 1995, Slaughter 1998), the reasons for this remain unclear; Reichstein et al.
(2005) identify six factors, unique to the industry, affecting the UK construction industry’s ability to innovate.
• Liability of projects
• Liability of immobility
• Liability of smallness
• Liability of separation
• Liability of assembly
These liabilities go some way to explaining why concepts from mass production and lean thinking have
never been particularly relevant to construction (Winch 2003), but ideas centred on information
management systems bear significantly more relevance to the project-driven nature of construction. In
particular, recent and ongoing developments in BIM hold the potential to bring significant benefits to the
transfer, storage and access of construction project information (Eastman et al. 2008, Huang et al. 2009).
The aim is to measure the benefits and challenges involved in the application of a BIM-based system for
construction information management, through analysis of primary data collected at an off-site precast
2
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
concrete fabrication facility. This is achieved by measuring the volumes of information and workflow rates
through BIM and other media. The off-site precast concrete fabrication facility was a subsidiary of the large
general contractor, but was run autonomously. The two organisations had independent information
management platforms, but the close relationship between the two facilitated some degree of coordination
between the various information systems, and allowed measurements to be taken for the purpose of this
research.
2 Literature Review
A number of studies have highlighted both the extent (Hendrickson and Au 2003) and importance (Howell
1999) of information management activities in construction. Despite significant research and investment,
studies formulating and applying new financial models to large-scale construction projects in the US have
shown that construction organisations are largely dissatisfied with their IT investments (Pena-Mora et al.
1999), from the perspective of managers monitoring return on investment. Jacobsson and Linderoth (2010)
find in a Swedish case study that the transient nature of project teams (“temporary organisations”) limits the
drive to deploy information management technologies. They report (2012) that the end users of these
technologies are generally “fairly satisfied”. Those studies seem to lean more towards qualitative data and
user perceptions as a research approach, in contrast to the research presented here which favours
In trying to propose new technologies and frameworks for information management, researchers have found
that information management and exchange within construction typically still takes place manually, with
individuals or organisations reformatting and manually distributing information (Dawood et al. 2002),
normally on a document level (Anumba et al. 2008). This leads to wasted time and cost through data loss
when information is exchanged or converted, inefficiencies through rework, further wasted time spent
identifying the useful information in a document (Anumba et al. 2008), and the late, incomplete,
uncoordinated and/or inappropriate exchange of information. The fragmented nature of the construction
industry frequently leads to incompatibilities in semantics, process and software between collaborating
organisations (clients, designers, contractors, suppliers, and so on), amplifying the waste mentioned above
3
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
Taken cumulatively, it is therefore clear that the key requirement in any improved information management
system is the co-ordination of information exchange. Dawood et al. (2002) discuss the challenges involved
in creating a system that will ‘meet the different views and needs of the multiple professional disciplines
involved in the construction process’. BIM is well positioned to meet these needs in construction. Sacks et
al (2010) have identified the synergies between the principles of BIM and lean construction, and observed
that information can be managed according to lean principles. However little work is published specifically
on measuring information flows through BIM to evaluate its impact on the challenge of information exchange
and co-ordination.
BIM means different things to different people and in different contexts. BIM is generally ‘a modelling
technology and associated set of processes to produce, communicate and analyse building models’
(Eastman et al. 2008). BIM builds upon the concepts of 3D modelling by incorporating non-graphical object
data into the model. Many studies define BIM through the benefits it confers, including parametric modelling
(Huang et al., 2009), detailed building analysis (Krygiel et al. 2008), 4D programming whereby the
construction programme is linked into the building model (Mahalingam et al. 2010), 5D modelling, whereby
cost data is also integrated into the building model (Goedert and Meadati, 2008) and more generally nD
modelling (Marshall-Ponting and Aouad, 2005). For the purposes of the research presented here, BIM is
construction and operation of a building, anchored to a geometric (2D/3D) model of the building (as such a
model emerges). The fundamental subtlety that makes a building model a BIM model (rather than, say, a
CAD model) is the object orientation and the symbolic information linked to the geometry. A 3D shape
might have the symbol “column” labelling it, enabling other information systems as well as human users to
BIM now constitutes a set of maturing technologies and work processes. BIM research has been widely
published in Construction Management and Economics (Fox and Hietanen, 2007, Li et al., 2011) and
elsewhere. BIM technology has already delivered benefits in building construction (Giel and Issa, 2010;
Aranda-Mena et al., 2008; Leicht and Messner, 2008; Lee et al 2012). However no studies could be found
4
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
which attempt to measure the volume of information flowing through a BIM model as a communication
Whilst the documented benefits are widespread and significant, sizeable research effort has also been
expended identifying the current barriers to implementing BIM more extensively. Eastman, et al (2008)
highlight that ‘BIM is not a thing or a type of software but a human activity that ultimately involves broad
process changes in construction.’ In order to gain the full benefits of BIM, these changes must be made
gradually and within multiple collaborating organisations, with decisions regarding the implementation made
on a project-by-project basis.
A broad category of process changes relates to the significant volume of training required. A relatively
steep learning curve is associated with a switch to BIM technologies, with the first employees to undergo
training likely to be unproductive, especially as they will need to customize tools for the company’s own uses
From a contractual standpoint, the increased collaboration between organisations employing BIM means an
increased entwining of fortunes. Current contract terms do not allow for this collective responsibility, nor do
current tools provide enough support for tracking and monitoring changes. The closer collaborative working
facilitated by BIM also highlights the problem of interoperability. In an evaluation of the interoperability issue
in BIM, Grilo and Jardim-Goncalves (2010) identify interoperability as a major barrier to BIM adoption. In
the US, studies suggest that inadequate interoperability within the capital facilities industry costs $15.8
billion each year (Gallaher et al., 2004). Standards are common throughout the construction industry
already (Björk and Laakso, 2010), but the implementation of BIM requires the development of new
Despite numerous research efforts identifying the benefits and barriers to the use of BIM, relatively few
studies have attempted to measure these in use. This study adapts the measurement techniques built by
Tribelsky and Sacks (2010), who took the concepts of lean thinking (Womack, Jones and Roos, 1990) and
leveraged them as a system of measuring and quantifying information flow in the detailed design phase of
5
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
construction projects. Based on Hicks’ (2007) definition of waste within information management, the study
analysed information flow during the design development phase of 14 construction projects, utilising 7
indices; action rate, package size, work in process, batch size, development velocity, bottlenecks, and
rework.
3 Method
3.1 Methodology
This research spans construction management and information management, a young field deserving
careful choice of research method(s) to address a particular type of research question. Researchers in
information systems (Fitzgerald and Howcroft 1998) have taken a humorous look at the tension between
“hard” and “soft” research in that field. Standard texts on construction research methods (e.g. Fellows and
Liu 2003) often implicitly map the friction between hard and soft research to the distinction between
collecting and analysing quantitative versus qualitative data. As part of measuring the benefits and
challenges of applying BIM, the research reported here attempts to quantify information flows through BIM
and other systems. This suggests taking a quantitative, positivist approach and is reflected in the method
adopted of measuring and visualising information flows. Still, it is recognised that such quantities are
context dependent; the world is sometimes best understood through an interpretivist lens, whereby reality is
socially constructed. The measurements of information flow were therefore accompanied by interviews with
staff from the fabrication facility to allow a holistic consideration of the projects studied, the systems used for
information management and the relationship between the fabrication facility and the other project
stakeholders.
A mixed methods approach was adopted, combining quantitative measurement of actual information flows
with qualitative recordings of perceptions of the quality of information flow. Measurement data consisted of
information flow logs exported from the four primary information systems used by an off-site fabrication
facility in the UK. This quantitative data was supplemented with interviews with five employees from the
1. Project 1 – a university project in the South-East of England, requiring the fabrication and delivery of
795 units.
6
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
2. Project 2 – a Building Schools for the Future scheme project in the South-East of England, requiring the
3. Project 3 – a Building Schools for the Future scheme project in the South-East of England, requiring the
4. Project 4 – a small hospital project in the South-West of England, requiring the fabrication and delivery
of 72 units.
These four projects were selected because they spanned the rollout of a new BIM-based workflow system,
and as such would provide a good opportunity for comparison, since Projects 1 and 2 would not be utilising
the new BIM-based workflow, whilst Projects 3 and 4 would. The window during which data was collected
was just after Project 1 was completed, with all units prefabricated and delivered. Projects 2, 3, and 4 were
“live” during data collection, with production and delivery on-going as weekly information flow logs were
exported. The figures for precast units quoted above give an indication of the scale and complexity of the
four projects; all four were public sector projects of moderate complexity and stakeholder team sizes, with
Project 4 significantly smaller than Projects 1, 2 and 3. The four projects selected form only a part of the
3. SAP – for transfer and storage of commercial information, used internally only,
4. PPManager – new BIM-based information management and co-ordination tool under continuing
development by Nemetschek, for the management and transfer of design and planning information
While other information flows were present within the facility (telephone calls, printed documents and face-
to-face discussion), the four primary flows above form the foundation for the majority of information
exchange, and as such provide as near to a comprehensive view of the information workflows as is
possible. A comprehensive study would quantitatively analyse the entire information flow through the
facility, through all channels, but time and resourcing constraints made this unrealistic.
7
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
Email remains a popular medium, despite the appearance of new technologies for information and
document exchange in construction. Many construction projects use an extranet to address the problems of
version control and co-ordination inherent in email. Asite is such an extranet system, whereby project
participants have controlled access to a central repository of project documents and project workflow forms
over the Internet. SAP is an enterprise application software package used to manage enterprise
information internally; in the projects studied for this research, SAP was used primarily to manage
commercial information such as cost estimates, formal price quotations, commercial approval documents
and formal order forms. PPManager (Precast Part Manager) is an object-oriented system which allows all
building information (such as cost data, production and delivery dates) to be linked to objects in the
graphical model, driven by an underlying database system. The database operates using a client-server
software architecture, allowing views of the central model to be retrieved over the internet. In this sense,
PPManager fits within the working definition of BIM adopted here as it is designed specifically to facilitate
information flow though models of precast concrete components. The interaction between the four systems
(Email, Asite, SAP and PP Manager) was only possible through documents. Report documents could be
exported from SAP, PPManager and Asite; these documents could be circulated through email and Asite,
In order to analyse the information flow measurement data in a structured way, a hierarchical information
paradigm was utilised (Tribelsky and Sacks, 2010, Tribelsky and Sacks, 2011), in which the fundamental
1. Information Object – A component or constituent part of a building or facility, about which information is
its dimensions, material type, supplier name, colour, price, etc. The value of an information attribute may
3. Information Package – A document used for the communication and transfer of information attributes.
This includes 2D drawings, spreadsheets, text documents or email exchanges, and ‘are the basic units
that are transferred between project team members’ (Tribelsky and Sacks, 2010).
8
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
4. Information Batch – A collection of information packages transferred by a project participant
simultaneously.
5. Project Action – a project participant performs an action in order to communicate information, either
These definitions were then used to formulate a number of visualisation and measurement tools, allowing
characteristic analysis of information flow over time, and at numerous levels of detail.
Table 1 summarises the information flow measurement metrics developed. The action rate allows analysis
of the total quantity of information being transferred either over the whole project, between two project
events, or between two arbitrary dates. To calculate the action rate between dates t1 and t2:
Where represents the cumulative number of project actions up to date t1, and represents the
The revision rate is a further extension of the action rate, and expresses the rate at which revised information
Revision Rate
Where represents the cumulative number of revised information packages transferred up to date t1,
The information iteration metric is a measure of the quantity of revised information packages, in relation to
Where represents the number of revised packages transferred on day , and denotes the
total number of information packages transferred on day . It should be noted that this metric includes for
9
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
multiple revisions of the same package; if a revision is issued of a previously revised package, both revised
The systems utilisation metric looks at the relative proportions of information attributes transferred through
Where denotes the number of information packages transferred on the th day through system ,
and indicates the number of information packages transferred on the th day through all systems.
The information inventory metric measures the time taken for information packages to be used when issued
to a team member; it measures the delay in information usage, whereby a higher result indicates poorer flow.
This can be measured overall for a project or in relation to a particular team member, whereby the
Where denotes the number of information packages uploaded by time , denotes the time at
which package was uploaded, and is equal to 1 if package has not been downloaded or viewed
The final metric, batching, measures the average size of information batches as defined above. Whilst
batching of information is commonplace within the industry, high levels of batching can indicate particularly
Where indicates the total number of information packages transferred through system , and
represents the total number of project actions carried out through system .
10
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
These metrics form the basis for the measurement of information flows across the four primary information
systems and the four projects. Alongside the visualisation measurements described above, they allow
comparison between projects as well as assessment of the impact of implementing the PPManager model-
Semi-structured interviews were conducted in parallel with quantitative data collection and analysis, allowing
one to inform the other. Four primary themes emerged, under which headings the subsequent analysis is
presented:
2. Information storage,
4. Information redundancy.
In Figure 2, information flow for Project 2 (which did not use PPManager) is visualised at three levels of
detail; at the project action level, the information package level and the information attribute level (as defined
above), whereby a project action includes one or more information packages, and an information package
conveys one or more information attributes. On each chart, the x-axis represents time, against the number
of items transferred on the primary y-axis. Information items are aggregated for the SAP, Asite and
PPManager and are categorised as either planning, design or commercial. Categorisation was manual, with
a small subset re-categorised by a second researcher to ensure validity of categorisation. A secondary bar
chart illustrates the number of project emails, providing further context to the information transfer data.
(Categorisation of emails transpired to be a practically impossible task because of the volume of emails and
the complexity of their contents.) Interviews suggested that these measurements are in line with the
11
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
It is evident that the programme is being used as a ‘live’ tracking tool. Planning actions took the form of
updating the project programme document and circulating it using Asite. The planning line in the project
actions chart in Figure 2 suggests that the project programme document was revised 10 times a week
during the production phase, involving the repeated transfer of one information package, containing a large
number of information attributes. Analysis of Asite data shows that the project programme has seen 129
revisions, and 199 downloads. The Action Rate metric reflects this, with a value of 11.2 planning packages
transferred per week during the production phase. This practice was corroborated through the interviews,
and creates challenges in access and interpretation of information, since large quantities of information are
Further data analysis demonstrates how the use of PPManager mitigates against this undesirable
information transfer process. Figure 3 compares the transfer of planning information attributes during the
Project 1 shows a dumbbell curve of i transfer over the production phase; at its peak, the project participants
were transferring nearly 90,000 information attributes in a week, with a weekly action rate for planning
packages of 9.65. This suggests that for Project 1, the programme was being revised twice a day. Such
huge data transfer is both largely redundant and difficult to access. There seems to be a rough correlation
between the flow of planning information through email and that through the other information systems (for
Project 1, this was predominantly Asite, but also included nominally SAP). This implies that uploading an
updated programme to Asite lacked richness, and necessitated supplemental email communication to
Project 3 used PPManager to distribute the majority of its planning data; after an initial large generation of
data, day-to-day changes were reflected within a ‘live’ planning view of the PPManager model accessible by
all users. This greatly improves information visibility, and drastically reduces the amount of redundant
information flow, and hence the amount of time spent searching and retrieving information. In Project 3, the
absolute quantities of information flow (through both PPManager and email) are much smaller, and there is
12
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
a weaker correlation between the two. When comparing absolute values of information flow, it must be
noted that the projects differed slightly in scale (with Project 1 requiring delivery of 795 precast units,
Contradicting impressions of email were inferred from the qualitative and quantitative data. Interviewees felt
that email was incorrectly and over-used, but measurement data suggests it is a highly relied upon tool; a
total of 3,322 emails were recorded across four projects, with a peak of 160 emails for one project within a
week.
It is hypothesised that the use of PPManager on a project increases the ease with which information is
transferred, thereby causing a drop in the use of and reliance on email. This hypothesis was supported by
the interviews, and theoretically manifests itself through a reduction in the systems utilisation metric for
Figure 4 displays the systems utilisation metric calculated using the equation given above, for the four
projects and systems. Projects 3 and 4 see a significant drop in the use of Asite, as the majority of the
planning and design information previously transferred through Asite is now maintained in PPManager; but
a drop of between 1% and 6% can be seen in the use of email between those projects using PPManager,
and those that did not. Analysis of email data showed there was no discernible change in the number of
planning-related emails transferred, thereby not supporting the hypothesis. This is possibly caused by a
‘legacy effect’ of the recent implementation of PPManager, since users were not yet entirely comfortable
The average size (in megabytes) of email messages dropped by 30% in those projects utilising PPManager.
This could be a reflection of reduced reliance on email to transfer large files, but could equally reflect
differences in project size and scope; it cannot therefore confirm or disprove the above hypothesis.
Figure 4. Interviewees noted a number of benefits associated with this change, most notably including a
reduction in the ‘significant amount of administration’ associated with using Asite for information storage, as
well as an easing of document control-related problems. Interviewees noted that Asite ‘can only cope with
quite a small number of file types’, inhibiting its use for storage of files of certain proprietary formats.
Interviewees noted document control as a central benefit of PPManager. A significant difference between
PPManager and Asite as information management tools is the storage structure they each employ. Whilst
Asite uses a folder and file metaphor, all PPManager data is linked to the building model. Since many
issues relating to use of incorrect or outdated information stem from information storage problems, the fact
that PPManager minimises the opportunity for human error helps to reduce these problems. Interviewees
noted that the current use of spreadsheets for planning information is ‘prone to human error’, suggesting
Interviewees observed that the greatest benefits of PPManager pertained to issues of accessibility.
Analysis of planning data for Projects 1 and 2 showed that a total of 28 hours and 15 minutes had been
spent editing the two programme spreadsheets, with between 22 and 33 minutes spent on each revision.
During this time, other project participants could not view the latest project information; considering that the
documents were viewed a combined total of 453 times, by up to 16 different project participants, there is a
reasonable chance that a project participant made use of incorrect or out-dated information. The key
problem with this practice however, is the difficulties involved in accessing and interpreting a package
containing up to 5,000 information attributes. By contrast, all interviewees praised the interface employed
PPManager utilises the building and unit models to convey all information. A further benefit noted by
interviewees was the depth of available information. Whilst the document-based system only allows access
to those information attributes stored within each document, the model-based system utilised by
PPManager means that all design and planning information attributes related to a particular unit are
14
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
4.5 Information Redundancy
Table 2 shows the metrics relevant to information redundancy calculated for the four projects. The projects
showed comparable action rates, with the relative differences in action rate corresponding roughly to the
differences in scale between the four projects (i.e. the number of precast units to be delivered for each
project). With regards to project revision rates data, whilst all projects showed a similar information iteration
metric, Projects 1 and 2 showed a higher revision rate during the production phase. This observation could
be caused by the change in process associated with PPManager; interviewees noted a contrast between
the ‘hand to mouth’ approach used before PPManager and the more timely access to data possible when
using PPManager. Interviewees discussed the increased emphasis on earlier and accurate project data
brought about by PPManager. This observation is manifested in the reduced in revision rates during the
Calculation of the information inventory metrics using Asite data allows inferences to be drawn regarding the
speed and demand for information flow within a project. The data suggests that information did not flow fast
enough for downstream receivers, particularly within the production project phase; this observation was
corroborated through interviews. Since Projects 3 and 4 did not make use of Asite in such a way, it was not
possible to draw conclusions regarding the benefits PPManager confers within this area.
A final interpretation of information redundancy concerns ‘positive redundancy’, or backup systems. It was
noted by an interviewee that the extent and availability of the data stored on PPManager would cause
significant problems if the system became unavailable, and the quality and availability of backup systems is
in no way clear.
The level of comparison between the four case study projects is constrained by the relative scope and size
of each; whilst the total quantity of information packages increases with the number of units to be fabricated,
the core process requirements applied to each project also lead to the generation of a significant quantity of
information packages unrelated to the project’s size. Therefore the number of information attributes only
15
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
loosely correlates to the project size, with additional influences such as the wider project nature and
5 Conclusions
The problems found in typical information management systems applied to building construction projects
have been pinpointed through measurement and visualisation of information flow, and correlated with
interview data. Whilst the benefits and challenges of implementing a BIM-based solution in such projects
have been identified qualitatively, it was only possible to measure some (but not all) of these benefits and
• For the time being, email is irreplaceable (from the data presented in Figures 2, 3 and 4). Given the
documented shortcomings of email, more research is needed to identify the flaws in alternative
actioned and revised. This is evident from Figure 3 and the observed practice of updating the
• The construction extranet stands to benefit the most from aligning information management to the
building model. From Figure 4, the introduction of PPManager reduced the use of Asite.
Many of the benefits identified here aligned with those reported in literature, notably including accessibility
and interpretation of large volumes of construction information. Taken in unison, the measurement of
information flows highlighted a number of key underlying trends. The BIM-based solution helped to foster
more accurate, on-time and appropriate exchange of information between project participants, as well as
promoting earlier creation of critical information relating to design detailing, programming, logistics and co-
ordination that help to generate significant value during the later production phases. These underlying
trends were noted by the interviewees, and highlight the core potential of BIM as a mechanism by which to
foster significantly greater collaboration between project participants, thus placing considerable emphasis on
its role in ‘a human activity that ultimately involves broad process changes in construction’ (Eastman, et al.
2008).
16
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
Of course caution must be exercised when interpreting and generalising the results reported here. The four
construction projects studied represent a particular type and scale of project: medium scale, public sector
projects. The volume of information traffic would be greater in larger scale projects, as would the
importance of systems to manage this information. The results presented here imply that BIM (in the form of
PPManager) is appropriate for projects of a relatively small scale, and this agrees with some other research
(Sebastian 2010); however, it is to be expected that the information management advantages might be
more significant for larger scale projects (Aranda-Mena et al., 2008). PPManager is only applicable to
precast concrete construction. The developers of that system do not prominently label it as a “BIM”
platform, even though it clearly appears to strive for integrated information management.
The use of PPManager was championed by the fabrication facility; the use of Asite and SAP was supported
by the general contractor. The use of email was of course universal. The combined use of the different
media, and the changes in information flow reported here, were only possible because of the close
relationship between the general contractor and its subsidiary, the fabrication facility. Considered
collectively, the four systems monitored for information flow offer a reasonable representation of the full
range of information management systems. However those four systems played limited and distinct roles in
the projects studied, and it must be acknowledged that information will have been communicated through
The research reported here paves the way for future research on measuring information flows and the value
of linking information do the graphical building model. Humans possess special cognitive strengths in
processing visual information: a fuller exploitation of those strengths can have fundamental implications for
17
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
References
Abukhder, J. and Munns, A.K. (2005) 'Attributing Management Problems on Construction Projects to Project
Anumba, C.J., Pan, J., Issa, R.R.A. and Mutis, I. (2008) 'Collaborative project information management in a
semantic web environment', Engineering, Construction and Architectural Management 15(1) 1-17.
Aranda-Mean, G., Crawford, J., Chevez, A. and Froese, T (2008) ‘Building Information Modelling
Demystified: Does it Make Business Sense to Adopt BIM?’, paper presented at CIB W78 conference,
Björk, B. and Laakso, M. (2010) 'CAD standardisation in the construction industry--A process view',
Dawood, N., Akinsola, A. and Hobbs, B. (2002) 'Development of automated communication of system for
managing site information using internet technology', Automation in Construction 11(5) 557-572.
stman, C. and Sacks, R. (2008). ”Relative Productivity in the AEC Industries in the United States for On-Site
Eastman, C.M., Teicholz, P., Sacks, R. and Liston, K. (2008) BIM Handbook: A guide to building information
modeling for owners, managers, designers, engineers, and contractors. New Jersey, USA: Wiley
Publishing.
Fellows, R., Liu, A, (2003). Research Methods for Construction. 2nd ed.. 2003.
Fisher, N. and Li Yin, S. (1992) Inforamation Management in a Contractor: A Model of The Flow of Project
Fitzgerald B and D Howcroft (1998). “Competing dichotomies in IS research and possible strategies for
resolution.” ICIS '98: Proceedings of the international conference on Information systems, pp 155-
Fox, S. and Hietanen, J. (2007) ‘Interorganizational use of building information models: potential for
25(3) 289-296.
Gallaher, M.P., O'Conor, A.C., Dettbarn, J.L. and Gilday, L.T. (2004) 'Cost Analysis of Inadequate
Interoperability in the U.S. Capital Facilities Industry', National Institute of Standards & Technology,
Aug, 1-210.
18
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
Giel, B., Issa, R.R.A. and Olbina, S. (2010) ‘Quantitative Benefits of Building Information Modeling
Measured in Construction’, Proceedings Innovation in AEC, Penn State, University Station, June 9-11
2010
Goedert, J. and Meadati, P. (2008) 'Integrating construction process documentation into building information
Grilo, A. and Jardim-Goncalves, R. (2010) 'Value proposition on interoperability of BIM and collaborative
Hendrickson, C. and Au, T.(2003) Project Management for Construction: Fundamental Concepts for
nd
Owners, Engineers, Architects and Builders, 22 edition, Pittsburgh: Prentice Hall.
Hicks, B. (2007) 'Lean information management: Understanding and eliminating waste', international Journal
Howell, G.A. (1999) 'What is Lean Construction - 1999', Seventh Annual Conference of the International
Huang, T., Li, H., Guo, H., Chan, N., Kong, S., Chan, G. and Skitmore, M. (2009) 'Construction virtual
Jacobsson M, HCJ Linderoth (2010). “The influence of contextual elements, actors’ frames of reference,
and technology on the adoption and use of ICT in construction projects: a Swedish case study.”
Jacobsson M, HCJ Linderoth (2012). “User perceptions of ICT impacts in Swedish construction companies:
‘it’s fine, just as it is’”. Construction Management and Economics 30(5), 339–357.
Krygiel, E., Nies, B. and McDowell, S. (2008) Green BIM: successful sustainable design with building
Lee, G., H. K. Park, J. Won. “D3 City project — Economic impact of BIM-assisted design validation.”
Li, H., Guo, H.L., Skitmore, M., Huang, T., Chan, K.Y.N. and Chan, G. (2011) ‘Rethinking prefabricated
construction management using the VP-based IKEA model in Hong Kong, Construction Management
Leicht, R. and Messner, J. (2008) ‘Moving toward an ‘intelligent’ shop modeling process’, IT in Construction
Mahalingam, A., Kashyap, R. and Mahajan, C. (2010) 'An evaluation of the applicability of 4D CAD on
Pena-Mora, F., Vadhavkar, S., Perkins, E. and Weber, T. (1999) 'Information Technology Planning
framework for large-scale projects', Journal of Computing in Civil Engineering 13(4) 226-237.
Pries, F. and Janszen, F. (1995) 'Innovation in the Construction Industry: the dominant role of the
Reichstein, T., Salter, A. and Gann, D. (2005) 'Last among equals: a comparison of innovation in
construction, services and manufacturing in the UK', Construction Management and Economics
23(6)631-644.
Rischmoller, L., Fischer, M., Fox, R. and Alarcon, L. (2001) '4D planning and scheduling (4D-PS): grounding
Sacks, R., Koskela, L., Dave, B., and Owen, R. (2010). ”Interaction of Lean and Building Information
Sebastian R (2010). “Integrated Design and Engineering using Building Information Modelling: A Pilot
Sexton, M. and Barrett, P. (2003) 'A literature synthesis of innovation in small construction firms: insights,
Shim, C.S., Lee, K.M., Son, W.S. and Moon, J.W. (2008) ‘Collaborative Design of High-speed Railway Lines
using 3D information models’, paper presented at IABSE Conference, IABSE in Helsinki, Finland.
Slaughter, E.S. (1998) 'Models of construction innovation', Journal of Construction Engineering and
Teicholz P (2001) “U.S. Construction Labor Productivity Trends, 1970-1998.” Journal of Construction
Tribelsky, E. and Sacks, R. (2010) 'Measuring information flow in the detailed design of construction
20
Peter Demian & David Walters (2013): “The advantages of information management through building
information modelling”, Construction Management and Economics, DOI:10.1080/01446193.2013.777754
Tribelsky E. and Sacks R (2011): “An Empirical Study of Information Flows in Multidisciplinary Civil
Engineering Design Teams using Lean Measures.” Architectural Engineering and Design
Winch, G. (2003) 'Models of manufacturing and the construction process: the genesis of re-engineering
Womack, J.P., Jones, D.T. and Roos, D. (1990) The machine that changed the world, Toronto: Collier
Macmillan.
21
Construction Management and Economics Page 48 of 53
1
2
3 Metric Description Units
4
Action Rate Rate of information transfer Actions/Time
5
6 Revision Rate Rate of revision transfer Revisions/Time
7
8 Information Iteration Proportion of revised information Percentage
9
10 Proportion of packages transferred through
Systems Utilisation Percentage
each information system
11
12 The number of available but unused
Information Inventory Information packages
13 information packages
14 Average number of packages transferred
Fo
15 Batching Information packages
simultaneously
16
17 Table 1: Information flow measurement metrics
18
rP
19
20
21
22
ee
23
24
25
26
rR
27
28
29
30
ev
31
32
33
34
ie
35
36
37
w
38
39
40
On
41
42
43
44
45
ly
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
URL: http://mc.manuscriptcentral.com/rcme
Page 49 of 53 Construction Management and Economics
1
2
3
4
5 Metric Description Units Project Project Project Project
6 1 2 3 4
7 Action Rate Rate of information Actions/Time 62,3 75.1 25.0 16.5
transfer
8
Revision Rate of revision transfer Revisions/Time 6.9 13.5 0.8 2.4
9
Rate
10
Information Proportion of revised Percentage 11% 18% 3% 14%
11 Iteration information
12 Information The average number of Information 5.2 21.0 N/A N/A
13 Inventory available but unused Packages
14 information packages
Fo
15 The average number of Days 3.1 2.3 N/A N/A
16 days taken to complete
17 an action
18
rP
19
20 Table 2: Metrics related to information redundancy
21
22
ee
23
24
25
26
rR
27
28
29
30
ev
31
32
33
34
ie
35
36
37
w
38
39
40
On
41
42
43
44
45
ly
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
URL: http://mc.manuscriptcentral.com/rcme
Construction Management and Economics Page 50 of 53
1
2
3 Information Attributes
Information Object
4 Cost, price, value
E.g. wall, door, Material, finish\components
5 column, floor, Order date, production date, delivery date
6 window Dimensions, area, volume, weight
Status, contact clauses, customer
7
8
9 TILE
………
10 ………
……… Information Package
………
2D Drawing
11 ………
……… 3D Model
………
12 ………
………
Email discussion
Spread sheet
13 ………
LOGO
Text document
14 Quotation
Fo
15
16
17 TILE
………TILE Information Batch
18 ………
………
………
………
TILE
rP
………
………
19 ………
………
………
………
………
………
……… Information System
………
20 ………
………
………
………
………
……… Information Action Asite, Email, PPManager, SAP
………………
21 ………………
LOGO
………
………
……… Team member communicates
………
or requests information
22 LOGO
………
LOGO
ee
23
24
25
26 Figure 1 - Illustration of the defined terms
rR
27
28
29
30
ev
31
32
33
34
ie
35
36
37
w
38
39
40
On
41
42
43
44
45
ly
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
URL: http://mc.manuscriptcentral.com/rcme
Page 51 of 53 Construction Management and Economics
ee
23 70000 160
27 100
40000
28 80
29 30000
60
30 20000 40
ev
31
32 10000 20
33 0 0
34 0 10 20 30 40 50
ie
35
Project Week Number
36
37
w
38
39 Email Commercial Design Planning
40
On
41 700 180
42 160
600
No. of emails sent
43
No. of Project Packages
140
44 500
45 120
ly
46 400 100
47 80
300
48
49 60
200
50 40
51 100 20
52
0 0
53
0 10 20 30 40 50
54
55 Project Week Number
56
57
58 Figure 2 - Information flows for Project 2 (without PPManager) measured by Project Actions (top),
59 Project Packages (middle) and Information Attributes (bottom)
60
URL: http://mc.manuscriptcentral.com/rcme
Construction Management and Economics Page 52 of 53
1
2
3
4 Project 1 (without PPManager)
5 100000 120
6
7 No. of planning information attributes 90000
8 Email 100
9 80000
10 Planning
70000
80
27
28 Project 3 (with PPManager)
29 2000 70
30
Email
ev
31 1800
No. of planning information attributes
32 Planning 60
33 1600
34 1400 50
ie
38 1000
39 30
800
40
On
41 600 20
42
400
43
10
44 200
45
ly
46 0 0
47 48 49 50 51 52 53 54 55 56 57
48 Projet 3 week number
49
50
51 Figure 4 - Planning information attributes transferred during the production phase - Projects 1 and 3
52
53
54
55
56
57
58
59
60
URL: http://mc.manuscriptcentral.com/rcme
Page 53 of 53 Construction Management and Economics
1
2
3
4
5 100%
6
7 90%
Percentage of Information Packages processed by each System
8
9 80%
10
70%
11
12 60% Asite
13
14 50% PPManager
Fo
15 SAP
16 40%
17 Email
18 30%
rP
19 20%
20
21 10%
22
ee
23 0%
24 Project 1 Project 2 Project 3 Project 4
25
26
rR
31
32
33
34
ie
35
36
37
w
38
39
40
On
41
42
43
44
45
ly
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
URL: http://mc.manuscriptcentral.com/rcme