Guidelines To Contractor For Project Documentation
Guidelines To Contractor For Project Documentation
DOCUMENT NUMBER:
4567-0-OTH-0001
(Where XXXX is the project
number and YYYY is the
sequence number)
Revision: 0
Date: 07/05/2024
FINAL APPROVAL
PSD
XXXX-0-OTH-0001 REV. 0
TABLE OF CONTENTS
Page No.
Page 2 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
1. PROJECT INFORMATION
2. OBJECTIVE
Provide a standard methodology for managing and controlling documents
throughout the Project lifecycle and an overview of the QatarEnergy Document
Control Process.
3. COMMUNICATIONS
All transmittal submissions and document related queries shall be addressed to
the QatarEnergy assigned PDC with CC to the QatarEnergy Project Engineer,
Project E-mail Database & QatarEnergy DC E-mail Database.
All E-mail communications must have the Project No. (XXXX) & Contract No
(GC23106300) on the subject as a “Prefix”
Email ID [email protected]
Page 3 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
DOCUMENT
REV DESCRIPTION
NUMBER
CORP-ENG-STD-021 * Standard for Engineering Data Coding System
CORP-ENG-STD-018 * Standard for Development of Technical Drawings
Standard for Compilation and Handover of Project
CORP-ENG-STD-022 *
Dossiers
*Latest revision shall be used
Page 4 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
be converted from original native file to pdf format for clarity purpose. "Zipped"
files are not acceptable.
b) Contractor shall ensure that all submissions are made as per approved MDR.
c) Due to file size restrictions, if Contractor is unable to upload the Document
through QatarEnergy PDMS portal, then Contractor shall use QatarEnergy
Enterprises File Sharing Management (EFSM) system to share the electronic
submissions with QatarEnergy to enable PDC to upload the same in PDMS
on behalf of Contractor. However, Contractor is required to ensure that they
populate the metadata in PDMS. (EFSM Access will be provided by
QatarEnergy PDC)
d) All Documents and Drawings from Rev-1 until final revision shall contain a
Comment Resolution Sheet (CRS) and it should be consolidated with the
‘PDF’ files as the first sheet.
e) Documents shall have their pages numbered to reflect the total number of
pages in the document (i.e., page 1 of 10, page 2 of 10, etc.). Each page,
including attachments, shall have a document number and revision number
along with the page number.
f) File names shall be as per QatarEnergy standard CORP-ENG-STD-021.
g) Multi-Sheet Document/Drawings of A4 and A3 size are numbered as one
document with a cover sheet and index sheet. While uploading in PDMS,
sheet number shall not be part of the document number. However, drawing
sizes above A3 shall be numbered as individual drawings.
h) Each drawing above A3 size to be registered as separate drawing with
appropriate sheet number. Drawing sizes above A3 may also be submitted as
multi sheet sets but don’t fall under the requirements of A4 & A3 i.e. No cover
sheet or revision record sheet is required. Examples of such drawings are
location orientated drawings (Area specific), UEFD’s, P&ID’s (Unit or System
Specific), Single Line Diagrams etc., where in cases the detail cannot be fully
arranged entirely on one sheet the subject will continue the next sheet with
proper cross references and demarcation points. The number of sheets
contained in these sets should be kept to a minimum.
i) Contractor shall confirm all QatarEnergy External Transmittals in PDMS as an
acknowledgement on the same day or next working day.
j) Contractor can obtain QatarEnergy Acknowledgement from the PDMS. If the
submission is not acceptable, Contractor will receive the “non-Acceptance”
notification from QatarEnergy PDC.
k) Cut of time for submissions is 12 noon, those submissions made later than 12
noon will be recorded as submissions done on the following working day.
Page 5 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Page 6 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
The example in above indicates a Civil Discipline produced Buried Line or Trench
drawing located at Mesaieed NGL/1 flare system.
Document sequence number shall be from 0001 and continue in the sequence for
the same type of data within the same discipline and subgroup.
File Naming Format: The complete Document/Drawing Number followed by the
Revision Indicator to be used as the file name format.
• Example: 1234-MIFS-1-67-0021-001-X (where ‘X’ stands for revision)
List of non-Deliverables
Document
Description Document Number Format
Type
Asset Capitalization
ACS XXXX-X-ACS-0001
Schedule
Page 7 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Document
Description Document Number Format
Type
Construction Document
CDR XXXX-X-CDR-0001
Register
Certificates (PCC,PTS
CRT XXXX-X-CRT-0001
/Lifting, Qualification etc.)
Engineering Deliverable
EDR XXXX-X-EDR-0001
Register
Engineering Information
EIR Request (Engineering Data XXXX-X-EIR-0002
Request)
Engineering Technical
ETQ XXXX-X-ETQ-0001
Query
Feeder Reservation
FRR XXXX-X-FRR-0001
Request
Mechanical Completion
MCC XXXX-X-MCC-0001
Certificate
Page 8 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Document
Description Document Number Format
Type
Page 9 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Document
Description Document Number Format
Type
Technical Deviation
TDR XXXX-X-TDR-0001
Request
Status /
Description Revision Sequence* Application
Code
0 & subsequent Used to indicate the Document status,
numerical as ready for comments, for all Rev 0
Issued for revisions (if documents as well as for subsequent
IFC
Comment responded by numerical revisions (if previously
QatarEnergy in responded by QatarEnergy with Code 3).
Code 3) It can be used at all Project Stages.
Used, after IFC, to indicate the
1, 2, 3 & etc. Document status, as ready for approval.
Issued for
IFA (Numerical It is also used for subsequent numerical
Approval
Revisions only) revisions. It can be used at all Project
Stages.
Approved Only Used, after IFC or IFA, to indicate the
for Alphabetical deliverable status, as ready for
AFC
Constructio Revisions, construction, during ECS, EPIC, EPC
n except “Z” and Construction Stages.
Approved Only Used, after IFC or IFA, to indicate the
for Alphabetical deliverable status, as ready for
ACH
Constructio Revisions, construction with “HOLD” items,
n (With except “Z” represented with inverted cloud(s),
Page 10 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Status /
Description Revision Sequence* Application
Code
Hold) during ECS, EPIC, EPC and
Construction Stages. [Note: All HOLD
items shall be confirmed before issuing
the final ADD/AFC/AFP Documents]
Approved Only Used, after IFC or IFA, to indicate the
for Alphabetical deliverable status, as ready for
AFP
Procureme Revisions, procurement during EPIC, EPC and
nt except “Z” Construction Stages.
Subsequent
“Alphabetical
Letter” after
“AFC” for Used, after AFC, to indicate the
Approved
ASB “Grass Root / deliverable status, as final during EPIC,
as As-Built
Green Field” EPC and Construction Stages.
Projects. “Z”
for “Brown
Field” Projects.
Only Used to indicate the Document status,
Approved
Alphabetical as Approved for Demolition. It can be
ADM for
Revisions used during Construction/Demolition
Demolition
except “Z” Stages.
Used to indicate the Document status,
Issued for Any Numerical
IFI as issued for information. It can be used
Information Revisions
at all Project Stages.
Used to indicate the Document status,
as final documentation for retention,
1, 2, 3 & Etc.
Issued for mostly used for Project Dossiers,
RET (Numerical
Retention Operation & Maintenance (O&M)
Revisions only)
Manuals, test certificates, etc. It can be
used at all Project Stages.
1, 2, 3 & etc. Used to indicate the Document status,
Issued for (Numerical issued for cancellation, to notify the
CAN Cancelatio Revisions) / Any reason for cancellation of the document
n Alphabetical from the project. It can be used at all
Revisions Project Stages.
1, 2, 3 & etc.
Issued for Used to indicate the Document status,
IFT (Numerical
Tender Issued for Tender, prior to AFC.
Revisions only)
1, 2, 3 & etc.
Issued for Used to indicate the Document status,
IFH (Numerical
HAZOP Issued for HAZOP.
Revisions only)
Page 11 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Issue
Description Revision Sequence* Application
Code
Used to indicate the reason for
0 & subsequent issue of the Document as issued
numerical revisions for comments, for all Rev 0
Issued for
IFC (if responded by Documents, as well as for
Comment
QatarEnergy in subsequent numerical revisions (if
Code 3) previously responded by
QatarEnergy with Code 3).
1, 2, 3, etc. Used to indicate the reason for
(numerical issue of the Document, as issued
revisions) as well for approval, for all numerical
IFA Issued for Approval
as A, B, C… Z. revisions, as well as alphabetical
(alphabetical revisions, after obtaining approval
revisions) on IFC status.
Used to indicate the reason for
1, 2, 3, etc.
issue of the Document, as issued
(numerical
for Stamping/ Signature, for all
Issued for revisions) as well
IFS numerical revisions, as well as
Stamping/Signature as A, B, C… Z.
alphabetical revisions, after
(alphabetical
obtaining approval on IFC or IFA
revisions)
status.
Used to indicate the reason for
issue of the Document, as issued
Issued for Any Numerical for information,
IFI
Information Revisions (A Document received with Issue
Code IFI, may be commented
upon by Reviewers, if necessary)
Used to indicate the reason for
issue of the Document, as issued
1, 2, 3 & Etc. for retention, to indicate the
Issued for
RET (Numerical issuance of final documentation
Retention
Revisions only) such as Project Dossiers,
Operation & Maintenance (O & M)
Manuals, test certificates, etc.
Used to indicate the reason for
Any Numerical / issue of the Document, issued for
Issued for
CAN Alphabetical cancellation, to indicate the reason
Cancelation
revisions for cancellation of the Document
from the project.
Page 12 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Issue
Description Revision Sequence* Application
Code
1, 2, 3 & etc.
Applicable for FS/CO, Pre-FEED,
IFT Issued for Tender (Numerical
FEED, ECS
Revisions only)
1, 2, 3 & etc.
Applicable for FEED, EPIC and
IFH Issued for HAZOP (Numerical
Construction Contracts
Revisions only)
Page 13 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Approval
Description Revision Sequence* Application
Code
Alphabetical revisions
except “Z” for non-
Approved refinery projects. Applicable for ECS, EPIC & Construction
AFC For
Any Numerical Contracts
Construction
revisions except 0 for
refinery projects.
Alphabetical revisions Applicable for ECS, EPIC & Construction
except “Z” for non- Contracts. Applicable for Documents that
Approved for refinery projects. are issued for construction with “HOLD”
ACH Construction
Any Numerical items, represented with inverted cloud(s).
(with Hold)
revisions except 0 for [Note: All HOLD items shall be confirmed
refinery projects. before issuing the final AFC Documents].
Alphabetical revisions
except “Z” for non-
Approved refinery projects. Applicable for Materials Related
AFP For
Any Numerical Documents
Procurement
revisions except 0 for
refinery projects.
Subsequent
“alphabetical letter”
Approved as Applicable for EPIC and Construction
ASB after latest “AFC” for
AS-Built Contracts
“Greenfield” (non-
refinery) projects.
Page 14 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Approval
Description Revision Sequence* Application
Code
“Z” for “Brownfield”
(non-refinery) projects.
Subsequent numerical
revision after latest
AFC for refinery
projects
Used to indicate the Document status,
Any Numerical /
Approved for as Approved for Demolition. It can be
ADM Alphabetical
Demolition used during Construction/Demolition
Revisions except “Z”
Stages.
Approved - Used for those Documents submitted by
Resubmission applicable for
Contractor which are not meant to become
10 not required numerical revisions
AFD/ADD/AFC/ADM/AFP e.g., CVs,
only
Organization Chart, TQs, TDR, etc..
Note:
1. Subsequent revisions of AFC should contain revision description as “Re-issued for Construction”
2. Subsequent revisions of ACH should contain revision description as “Re-issued for Construction
(with Hold)”
3. Subsequent revisions of AFP should contain revision description as “Re-issued for Procurement”
4. Subsequent revisions of ASB should contain revision description as “Re-issued as As-Built”
Page 15 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Page 16 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Page 17 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Page 18 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Document 2 (i.e., the new document) shall be issued at Rev 0 and the revision text
box endorsed as “Created from Document No: XXXX-X-XX-XXXX”.
Page 19 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Page 20 of 21
CLASSIFICATION: C1 - CONTROLLED
XXXX-0-OTH-0001 REV. 0
Note: For detailed process of project dossier creation through PDMS, refer to
PDMS Manual-External Contractor Module provided separately.
DISCLAIMER: If there are any contradictions in this guideline with QatarEnergy
Standards, it shall be notified to QATARENERGY Project Document Controller
(PDC) and precedence will be given to QatarEnergy Standards and Contractual
requirements.
Page 21 of 21